MONTHYEARML24031A6432023-12-20020 December 2023 Independent Spent Fuel Storage Installation (ISFSI) - Nuclear Liability Insurance Coverage ML23341A0222023-11-15015 November 2023 Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation ML23192A0612023-06-14014 June 2023 Possession-Only License DPR-45 - Formal Announcement of New ISFSI Manager ML23192A1082023-06-14014 June 2023 Possession-Only License DPR-45 - New Chief Nuclear Officer Selected ML23130A1202023-05-0202 May 2023 Transmittal of Financial Statement and Auditors' Report ML23137A1552023-05-0202 May 2023 Possession-Only License DPR-45 - Financial Statement and Auditors' Report ML23115A1712023-04-0404 April 2023 ISFSI - Nuclear Liability Insurance Coverage ML23115A1742023-04-0303 April 2023 Independent Spent Fuel Storage Installation, Adoption of Amendment 7 of NAC MPC Certificate of Compliance No. 72-1025 and Canister Registration ML23074A0552023-03-13013 March 2023 Decommissioning Funding Status Report for Shutdown Reactor ML23076A0402023-03-0606 March 2023 Notification of License Transfer Date from Lacrossesolutions, LLC to Dairyland Power Cooperative ML23060A0732023-02-27027 February 2023 Annual Radiological Environmental Operating Report ML23055A0282023-02-24024 February 2023 Completion of License Termination Activities and Release of Remaining Class 1 Survey Units from Possession Only License No. DPR-45 ML22361A1022023-02-24024 February 2023 Reactor Decommissioning Branch Project Management Changes for Some Decommissioning Facilities and Establishment of Backup Project Manager for All Decommissioning Facilities ML23024A0122023-01-26026 January 2023 Letter to Energysolutions Transmitting Threshold Determination for Merger/Restructuring ML23033A0682023-01-26026 January 2023 Proof of Financial Protection IR 05000409/20220012022-12-27027 December 2022 NRC Inspection Report No. 05000409/2022001(DRSS) ML22321A3132022-12-0808 December 2022 LACBWR License Transfer Order Fifth Extension Letter ML22335A0852022-11-23023 November 2022 Request for Extension of Order Approving Transfer of the License for the La Crosse Boiling Water Reactor from Lacrossesolutions, LLC, to Dairyland Power Cooperative ML22297A0042022-10-20020 October 2022 Response to October 14, 2022 Request for Additional Information for Class 1 Excavation and Basement Survey Units ML22285A0782022-10-13013 October 2022 NRC Analysis of Energy Solutions' Decommissioning Funding Status Report Docket No. 50-409 ML22278A0282022-10-12012 October 2022 Request for Confirmatory Information Letter Re to the Review of the Class 1 Survey Units ML22269A3902022-09-0707 September 2022 Response to July 5, 2022 Request for Additional Information for Class 1 Excavation and Basement Survey Units ML22230A8012022-08-16016 August 2022 Request for Extension of Order Approving Transfer of the License for the La Crosse Boiling Water Reactor from Lacrossesolutions, LLC, to Dairyland Power Cooperative ML22223A0712022-07-28028 July 2022 Response to June 5, 2022 Request for Additional Information for Class 1 Survey Areas ML22224A1172022-07-14014 July 2022 Possession-Only License DPR-45 Chief Nuclear Officer Selected ML22224A1372022-07-12012 July 2022 Quality Assurance Program Description (Oapd), Revision 31 ML22203A0932022-07-11011 July 2022 Changes to the La Crosse Boiling Water Reactor (LACBWR) ISFSI Physical Security Plan IR 07200046/20224012022-06-0101 June 2022 (Decommissioning) - Independent Spent Fuel Storage Installation Security Inspection Report 07200046/2022401 ML22122A2302022-05-24024 May 2022 Approval to Release Class 2 and Class 3 Survey Units from the Part 50 License ML22146A2002022-05-24024 May 2022 Submittal of Quality Assurance Program Changes ML22123A0822022-04-25025 April 2022 Possession-Only License DPR-45 - Financial Statement and Auditors' Report ML22068A2102022-04-20020 April 2022 Issuance of Amendment No. 77 Approving Independent Spent Fuel Storage Installation Emergency Plan, Revision 40 ML22108A0562022-03-28028 March 2022 Decommissioning Funding Plan for Independent Spent Fuel Storage Installation ML22084A0092022-03-22022 March 2022 Annual Property Insurance Status Report ML22077A0132022-03-15015 March 2022 Report on Status of Decommissioning Funding for Shutdown Reactor ML22069A1282022-03-0808 March 2022 Lacrossesolutions, LLC, La Crosse Boiling Water Reactor (LACBWR) Annual Radiological Environmental Operating Report, Supplemental Letter ML22062B0362022-02-28028 February 2022 Annual Radiological Environmental Operating Report ML22031A1162022-01-26026 January 2022 CFR 50.59 I 10 CFR 72.48 Report of Changes, Tests, and Experiments ML22033A1472022-01-26026 January 2022 Submittal of Decommissioning Plan and Post-Shutdown Decommissioning Activities Report, and License Termination Plan Changes IR 05000409/20210012022-01-0707 January 2022 NRC Inspection Report No. 05000409/2021-001 La Crosse Boiling Water Reactor ML22010A0862022-01-0505 January 2022 Proof of Financial Protection ML21235A1212021-09-0303 September 2021 EPA Phase 2 Closure Letter to B. Lowery, EPA from P. Holahan ML21228A0682021-09-0202 September 2021 Request for Additional Information Related to the ISFSI-Only Emergency Plan ML21228A1062021-08-30030 August 2021 LACBWR License Transfer Order Third Extension Letter ML21230A3302021-08-17017 August 2021 Lacrossesolutions, LLC, Request for Extension of Order Approving Transfer of the License for the La Crosse Boiling Water Reactor ML21131A0852021-04-26026 April 2021 Financial Statement and Auditors' Report ML21126A2152021-04-13013 April 2021 Changes to and Biennial Review of the La Crosse Boiling Water Reactor (LACBWR) ISFSI Physical Security Plan ML21067A3052021-04-0707 April 2021 DFP Close-out Letter for La Crosse ML21084A2172021-03-23023 March 2021 Report on Status of Decommissioning Funding for Shutdown Reactor ML21084A2192021-03-22022 March 2021 Annual Property Insurance Status Report 2023-06-14
[Table view] |
Text
CHARLES V. SANS CRAINTE, P.E.
Vice President, Generation DAIRYLAND POWER C 0 0 P E R A T I V E April 30, 2010 In reply, please refer to LAC- 14115 DOCKET NO. 72-46 Document Control Desk Director, Division of Spent Fuel Storage and Transportation Office of Nuclear Material Safety and Safeguards US Nuclear Regulatory Commission Washington, DC 20555-0001
SUBJECT:
Dairyland Power Cooperative (DPC)
La Crosse Boiling Water Reactor (LACBWR)
Possession-Only License No. DPR-45
REFERENCE:
(1) Letter of June 19, 2008, DPC to NRC, Affirmation of Need for Dry Cask Certificate of Compliance Amendment (2) Letter of June 3, 2009, NRC to DPC, and attached Order for Additional Security Measures at the La Crosse Boiling Water Reactor Independent Spent Fuel Storage Installation, EA-09-118 (3) Letter of June 22, 2009, DPC to NRC, and attached response to EA-09-118, containing the Additional Security Measures (ASM) for physical protection of the Independent Spent Fuel Storage Installation (ISFSI) and access authorization and fingerprinting (4) Letter of November 2, 2009, DPC to NRC, Supplemental Response to Order of June 3,2009, Modifying Licenses (5) Letter of November 24, 2009, DPC to NRC, Relaxation of Scheduled Analysis Delivery Date and Notification of Scheduled Fuel Loading (6) Letter of February 18, 2010, NRC to DPC, Relaxation of Schedule for Implementing Requirements of order for Implementation of ASM and Fingerprinting Unescorted Access to LACBWR ISFSI In References 3, 4 & 5, DPC committed to providing an analysis to the NRC by May 1, 2010.
The analysis completes the LACBWR response to the Order for Additional Security Measures at the La Crosse Boiling Water Reactor Independent SpentFuel Storage Installation, EA-09-118.
The results of the analysis are contained in the Attachment 1. 0J k5_-9T A Touchstone Energy Cooperative ,bbT 3200 East Ave. S.
- PO Box 817 - La Crosse, WI 54602-0817
- 608-787-1233 ° 608-787-1462 fax
Document Control Desk Page 2 April 30, 2010 It is anticipated that construction of the vehicle barrier system will begin on August 1, 2010. We would appreciate a response prior to this date in order to remain on schedule.
If you have any questions, please call Michael Brasel of my staff at (608) 689-4220.
Sincerely, DAIRYLAND POWER COOPERATIVE Charles V. Sans Crainte Vice President, Generation CVS:MAB:two:krm G:\GnrAdmin\Letters 2010\LAC-14115 NRC Letter 043010-cvs-mab043010.doc
Attachment:
ISFSI Additional Security Measures Analysis Results (SAFEGUARDS INFORMATION) cc w/att: Kristina Banovac Project Manager U.S. Nuclear Regulatory Commission Washington, DC 20555 Douglas Garner Security Specialist Office of Nuclear Security and Incident Response Mail Stop T4-F25M U.S. Nuclear Regulatory Commission Washington, DC 20555-0001 Mark Satorius Regional Administrator, Region III 2443 Warrenville Rd.
Lisle, IL 60532 Raynard Wharton Division of Spent Fuel Storage and Transport Office of Nuclear Material Safety and Safeguards Mail Stop E-3-D-2M U.S. Nuclear Regulatory Commission Washington, DC 20555 cc w/o att: Paul Schmidt Manager, Radiation Protection Section State of Wisconsin PO Box 2659 Madison, WI 53701-26459