Information Notice 2010-12, Containment Liner Corrosion
| ML100640449 | |
| Person / Time | |
|---|---|
| Site: | Beaver Valley, Salem, Brunswick |
| Issue date: | 06/18/2010 |
| From: | Mcginty T, Tracy G Division of Construction Inspection and Operational Programs, Division of Policy and Rulemaking |
| To: | |
| Beaulieu, D P, NRR/DPR, 415-3243 | |
| References | |
| TAC ME3101 IN-10-012 | |
| Download: ML100640449 (4) | |
ML100640449 UNITED STATES
NUCLEAR REGULATORY COMMISSION
OFFICE OF NUCLEAR REACTOR REGULATION
OFFICE OF NEW REACTORS
WASHINGTON, DC 20555-0001
June 18, 2010
NRC INFORMATION NOTICE 2010-12:
CONTAINMENT LINER CORROSION
ADDRESSEES
All holders of an operating license or construction permit for a nuclear power reactor issued
under Title 10 of the Code of Federal Regulations (10 CFR) Part 50, Domestic Licensing of
Production and Utilization Facilities, except those who have permanently ceased operations
and have certified that fuel has been permanently removed from the reactor vessel.
All holders of or applicants for a standard design certification, standard design approval, manufacturing license, or combined license issued under 10 CFR Part 52, Licenses, Certifications, and Approvals for Nuclear Power Plants.
PURPOSE
The U.S. Nuclear Regulatory Commission (NRC) is issuing this information notice (IN) to inform
addressees of recent issues involving corrosion of the steel reactor containment building liner.
The NRC expects recipients to review the information for applicability to their facilities and to
consider actions, as appropriate, to avoid similar problems. The suggestions contained in this
IN are not NRC requirements; therefore, no specific action or written response is required.
DESCRIPTION OF CIRCUMSTANCES
Beaver Valley Power Station
On April 23, 2009, during a refueling outage at Beaver Valley Power Station, Unit 1, the licensee
performed a visual examination of the interior reactor containment building steel liner in
accordance with Subsection IWE, General Visual Examination, of American Society of
Mechanical Engineers (ASME)Section XI of the Boiler and Pressure Vessel Code, Rules for
Inservice Inspection of Nuclear Power Plant Components. At a containment elevation of
746 feet, the licensee identified an area approximately 3 inches in diameter that exhibited
blistered paint. The paint blister was intact at the time of discovery. Collapse of the blister
during further inspection revealed a protruding rust product underneath. The licensee then
cleaned this area to allow further evaluation. The cleaning activity uncovered a rectangular area
of approximately 1 inch (horizontal) x 3/8 inch (vertical) that penetrated through the entire liner
plate thickness. Ultrasonic testing (UT) of the surrounding area showed liner thinning within an
area of approximately 10 square inches. The licensee removed the corroded section of the liner
and discovered a partially decomposed piece of wood approximately 2 inches x 4 inches x
6 inches embedded in the concrete behind the section of the liner. The wood was left behind as a result of inadequate housekeeping and quality assurance practices during the original
construction of the containment wall in the early 1970s.
The licensee determined that the cause of the through-wall liner corrosion was a pitting-type
corrosion (rust) originating from the concrete side caused by foreign material (wood) that was in
contact with the containment carbon steel liner. Licensee corrective actions included removing
the embedded wood, grouting the concrete area that was displaced by the wooden debris, and
welding a new section of steel plate to replace the previously removed portion of the liner. The
licensee also scheduled an examination of the containment liner during the next refueling
outage at Beaver Valley Power Station Units, 1 and 2 to visually inspect 100 percent of the
accessible liner area. In addition, the licensee stated in its license renewal submittals that it
would perform: (a) supplemental volumetric examinations of 1-square-foot samples in at least
75 random locations of each units containment liner in order to statistically determine whether
the containment liner is unacceptably degraded by corrosion originating from the concrete side;
and (b) supplemental volumetric examinations of a minimum of eight one-foot square locations
in the accessible areas of liner plate at locations that operating experience shows are
susceptible to localized pitting corrosion.
Additional information is available in Beaver Valley Licensee Event Report 50-334/2009-003-00,
dated June 18, 2009, and Beaver Valley Power Station, Unit 1, NRC Routine Inspection
Report 05000334/2009006, dated July 6, 2009, which can be found on the NRCs public Web
site under Agencywide Documents Access and Management System (ADAMS) Accession
Nos. ML091740056 and ML091870328, respectively.
Brunswick Steam Electric Plant
During a refueling outage in 2008 at Brunswick Steam Electric Plant, Unit 1, the licensee
performed a VT-1 visual inspection of the primary containment penetration sleeve for the
personnel air lock and found two bulged areas. The discovery of thinned areas on the bulges
led the licensee to perform UT examinations of the entire Unit 1 personnel air lock penetration
sleeve. These additional UT inspections identified many discrete locations that were below the
minimum wall thickness established by the design-basis containment liner specification.
During construction, the outside diameter of the sleeve was wrapped with two layers of 1/4 inch
felt and the felt was covered with a layer of 60 mil ethylene propylene film. The felt was
intended to permit the sleeve to expand when subjected to thermal loading. The licensees
evaluation determined that the bulges were caused by corrosion product buildup between the
sleeve and the concrete backing. This corrosion was caused by the felt that wrapped the
outside of the containment penetration sleeve; which became wet during the original
construction.
Samples of the degraded areas of the sleeve and felt wrapping were sent to the licensees
center for evaluation of potential ongoing corrosion mechanisms. These evaluations identified
that the pitting and corrosion on the concrete side of the sleeve were caused by under-deposit
corrosion. Licensee corrective actions include installing a new concentric sleeve inside the personnel air
lock penetration to repair the existing containment penetration sleeve. Following this planned
modification, the new sleeve will become the primary containment liner for this penetration.
Salem Nuclear Generating Station
In October 2009, at Salem Nuclear Generating Station Unit 2, the licensee inspected the
containment moisture barrier (the silicone RTV [room temperature vulcanizing] seal between the
concrete floor and containment liner) and found heavy corrosion on the containment liner within
6 inches of the concrete floor. This area of the containment liner was considered inaccessible
because it was normally covered by an insulation package that consisted of a layer of sheet
metal, a layer of plastic sheeting, and a layer of insulation. The licensee had not inspected the
containment liner areas covered by this insulation because ASME Code Section XI allowed an
exemption for inaccessible areas. In response to this discovery, and as a conservative
approach to the license renewal process, the licensee decided to enhance inspections of the
containment liner above the moisture barrier within about 6 inches of the concrete floor and to
randomly inspect several other areas that were covered by the insulation package. To perform
the inspections, the licensee removed that portion of the insulation package that extended
below the lower leak detection channel for the entire containment liner circumference, and cut
through and removed the insulation package for four other randomly selected areas. Licensee
inspections in these four areas identified some corrosion but subsequent ultrasonic
measurements did not indicate significant wall loss.
To evaluate the effect of the identified general corrosion on the safety function of the
containment boundary and to meet the expanded inspection requirements of ASME Code
Section XI, the licensee performed ultrasonic testing of 440 locations on the bottom 6 inches of
the cylindrical portion of the containment liner. Based on the results of the measurements at
these locations, the licensee determined that the liner remained operable because the lowest
thickness measured was 0.677 inches, which was above the design-required minimum wall
thickness of 0.43 inches. The actual safety significance of this general corrosion was minor
because there was significant design margin for the liner in this area.
The licensee reviewed the circumstances that led to the identified areas of heavy corrosion on
the liner and determined that previous containment liner inspections were not performed
adequately. Specifically, examinations should have identified evidence of corrosion (rust on
floor) and prompted removal of lagging to determine the source of the corrosion products.
The licensee determined that the source of the moisture that caused the liner corrosion at the
joint between the containment liner and concrete floor was service water leakage from the
containment fan coil units and associated piping. Licensee corrective actions included
conducting frequent containment walk-downs to identify, isolate, and repair any identified
service water leaks; verifying that the leakage from existing service water leaks did not reach
the containment liner; and, until the base of the containment liner is re-coated during a future
refueling outage, revising procedures to ensure liner inspections were performed when
containment service water leaks were identified. In addition, the licensee stated in its license
renewal submittals that it would perform supplemental and augmented examinations of the liner
plates at random and non-random locations.
BACKGROUND
Related NRC communications include the following:
IN 2004-09, Corrosion of Steel Containment and Containment Liner, dated
April 27, 2004 (ADAMS Accession No. ML041170030)
IN 1997-10, Liner Plate Corrosion in Concrete Containments, dated March 13, 1997 (ADAMS Accession No. ML031050365)
DISCUSSION
This IN provides examples of containment liner degradation caused by corrosion. Concrete
reactor containments are typically lined with a carbon steel liner to ensure a high degree of leak
tightness during operating and accident conditions. The reactor containment is required to be
operable as specified in plant technical specifications to limit the leakage of fission product
radioactivity from the containment to the environment. The regulations at 10 CFR 50.55a, Codes and Standards, require the use of Subsection IWE of ASME Section XI to perform
inservice inspections of containment components. The required inservice inspections include
periodic visual examinations and limited volumetric examinations using ultrasonic thickness
measurements. The containment components include the steel containment liner and integral
attachments for the concrete containment, containment personnel airlock and equipment hatch, penetration sleeves, moisture barriers, and pressure-retaining bolting. The NRC also requires
licensees to perform leak rate testing of the containment pressure-retaining components and
isolation valves according to 10 CFR Part 50, Appendix J, Primary Reactor Containment
Leakage Testing for Water-Cooled Power Reactors, as specified in plant technical
specifications. This operating experience highlights the importance of good quality assurance, housekeeping and high quality construction practices during construction operations in
accordance with 10 CFR Part 50, Appendix B, Quality Assurance Criteria for Nuclear Power
Plants and Fuel Reprocessing Plants.
Operating experience shows that containment liner corrosion is often the result of liner plates
being in contact with objects and materials that are lodged between or embedded in the
containment concrete. Liner locations that are in contact with objects made of an organic
material are susceptible to accelerated corrosion because organic materials can trap water that
combined with oxygen will promote carbon steel corrosion. Organic materials can also cause a
localized low pH area when they decompose. Organic materials located inside containment can
come in contact with the containment liner and cause accelerated corrosion. However, corrosion that originates between the liner plate and concrete is a greater concern because
visual examinations typically identify the corrosion only after it has significantly degraded the
liner. In some cases, licensees identified such corroded areas by performing ultrasonic
examination of suspect areas (e.g., areas of obvious bulging, hollow sound).
The objects and materials that caused liner corrosion that licensees have found lodged between
or embedded in the containment concrete include both foreign material (e.g., wooden pieces, workers gloves, wire brush handles) and material that was deliberately installed as part of the
design such as the felt material described in the above example at Brunswick Steam Electric Plant, Unit 1. Although there is no regulatory requirement to do so, one or more licensees have
chosen to review design documents to identify locations where organic material was
intentionally installed between the liner or penetration sleeve and schedule additional
examinations of these areas to monitor for liner material loss.
GENERIC IMPLICATIONS
In response to the above through-wall corrosion at Beaver Valley Power Station, Unit 1, the
NRC Office of Nuclear Reactor Regulation requested the NRC Office of Regulatory Research to
begin an assessment to better understand the possible mechanisms responsible for through- wall corrosion of containment liners. The NRC staff has also engaged committee members for
ASME Section XI to devise a formal tracking mechanism to monitor industry experience and
events involving containment liner corrosion. Subsection IWE of ASME Section XI could then
be updated using insights from these events.
CONTACT
This IN requires no specific action or written response. Please direct any questions about this
matter to the technical contacts listed below or to the appropriate Office of Nuclear Reactor
Regulation (NRR) project manager.
/RA/ /RA by MShuaibi for/
Timothy McGinty, Director
Glenn Tracy, Director
Division of Policy and Rulemaking
Division of Construction Inspection and
Office of Nuclear Reactor Regulation
Operational Programs
Office of New Reactors
Technical Contacts: Mike Brown, NRR
William Jessup, NRR
301-415-4096
301-415-2972
E-mail: Michael.Brown@nrc.gov
E-mail: William.Jessup@nrc.gov
301-415-4030
E-mail: Paul.Klein@nrc.gov
Note: NRC generic communications may be found on the NRC public Web site, http://www.nrc.gov, under Electronic Reading Room/Document Collections.
ML100640449 TAC ME3101 OFFICE IOEB:DIRS
SCVB:DSS
Tech Editor
BC:SCVB:DSS
D:DSS
NAME
MBrown
JBettle
KAzariah-Kribbs
RDennig
WRuland
DATE
03/30/10
05/24/10 e-mail
05/21/10 e-mail
05/24/10 e-mail
5/27/10 e-mail
OFFICE BC:EMCB:DE
BC:CSGB:DCI
BC:SPCV:DSRA
BC:RASB:DLR
BC:IOEB:DIRS
NAME
MKhanna
RTaylor
JMcKirgan
RAuluck
JThorp
DATE
5/25/2010 e-mail
5/25/10 e-mail
5/27/10 e-mail
6/9/10 e-mail
5/25/10 e-mail
OFFICE LA:PGCB:NRR
PM:PGCB:NRR
(A)BC:PGCB:NRR
D:DCIP:NRO
D:DPR:NRR
NAME
CHawes
DBeaulieu
TAlexion
GTracy(MShuaibi
for)
TMcGinty
OFFICE 6/10/10
5/27/10
6/10/10
7/17/10
6/18/10