Information Notice 2010-08, Welding and Nondestructive Examination Issues

From kanterella
Jump to navigation Jump to search
Welding and Nondestructive Examination Issues
ML091670177
Person / Time
Issue date: 04/09/2010
From: Dan Dorman, Mcginty T, Tracy G
NRC/NMSS/FCSS, Division of Construction Inspection and Operational Programs, Division of Policy and Rulemaking
To:
Herrera T, NRO/DCIP/CCIB, 301-415-7138
References
IN-10-008
Download: ML091670177 (5)


ML091670177 UNITED STATES

NUCLEAR REGULATORY COMMISSION

OFFICE OF NUCLEAR REACTOR REGULATION

OFFICE OF NUCLEAR MATERIAL SAFETY AND SAFEGUARDS

OFFICE OF NEW REACTORS

WASHINGTON, DC 20555-0001

April 9, 2010

NRC INFORMATION NOTICE 2010-08:

WELDING AND NONDESTRUCTIVE

EXAMINATION ISSUES

ADDRESSEES

All holders of an operating license or construction permit for a nuclear power reactor issued

under Title 10 of the Code of Federal Regulations (10 CFR) Part 50, Domestic Licensing of

Production and Utilization Facilities, except those who have permanently ceased operations

and have certified that fuel has been permanently removed from the reactor vessel.

All holders of or applicants for an early site permit, standard design certification, standard

design approval, manufacturing license, or combined license issued under 10 CFR Part 52, Licenses, Certifications, and Approvals for Nuclear Power Plants.

All holders of or applicants for a license for a fuel cycle facility issued pursuant to

10 CFR Part 70, Domestic Licensing of Special Nuclear Material.

PURPOSE

The U.S. Nuclear Regulatory Commission (NRC) is issuing this information notice (IN) to alert

addressees of recent operating experience involving welding and nondestructive examination.

The NRC expects recipients to review the information for applicability to their planned activities

and to consider actions to avoid similar problems. However, the suggestions contained in this

IN are not NRC requirements; therefore, no specific action or written response is required.

DESCRIPTION OF CIRCUMSTANCES

Prairie Island Inservice Inspection

On October 1, 2008, at Prairie Island Nuclear Generating Plan (Prairie Island), NRC inspectors

reviewed the weld control records of the licensee contractor that performed machine gas

tungsten arc welding of the structural weld overlay on a pressurizer surge nozzle dissimilar

metal weld. The NRC inspectors noted that the documented weld speed on several weld

control records had not changed as would be expected and as required by procedure. To

control the weld heat input (an essential welding variable), it is necessary to control the weld

head travel speed. The operating instruction specified that welders would use the values for

piping/nozzle radius and the desired travel speed to determine the appropriate travel speed

setting for the welding machine. In this case, contrary to welding procedure specifications, the welders did not determine and enter a new speed into the welding machine as the piping/nozzle

radius increased as weld layers were added. Notwithstanding, a subsequent engineering

evaluation determined that based on the travel speeds recorded in the weld control record, the

resulting heat inputs were within the acceptable range.

While evaluating this weld speed issue, the welding contractor discovered that incorrect welding

parameters had been used to apply the first layer of the temper bead weld over a section of the

ferritic nozzle adjacent to a stainless steel butter interface. Specifically, the welders had failed

to change temper bead welding parameters when transitioning from the butter to the nozzle, a

requirement which was not delineated in the operating instruction. The resulting heat input on

the ferritic nozzle exceeded that allowed by the welding procedure specifications. As a result, the weld had to be removed (ground out) and rewelded. An extent of condition review showed

that other structural weld overlays performed were applied correctly.

Additional information is available in Prairie Island Nuclear Generating Plant, Units 1 and 2, NRC Integrated Inspection Report (IR) 05000282/2008005; 05000306/2008005, dated February

10, 2009, and can be found on the NRCs public website in the Agencywide Documents Access

and Management System (ADAMS) under Accession No. ML090420033.

Welding Issues at Louisiana Energy Services, National Enrichment Facility

In May 2009, the NRC inspectors identified welding issues involving the construction of the

Louisiana Energy Services, National Enrichment Facility (LES NEF). The following are three

examples of failure to implement American Society of Mechanical Engineers (ASME) B31.3

"Process Piping" requirements for welding and nondestructive examination.

(1)

Progressive radiography sampling was not proceduralzed to comply with the

requirements of ASME B31.3. The NRC inspectors reviewed weld records and identified

examples where a designated lot of random radiography samples was not expanded

when results revealed a weld defect for work performed by a welder/welding operator in

Category M Fluid Service. Corrective actions included performing additional radiography

of production welds.

(2)

Welders were not qualified in accordance with ASME Section IX for manual tack welding

of pipes, as required by ASME B31.3. Corrective actions included additional

radiography of field welds with fused tacks that were not previously selected for random

radiography and requalification of all welders to perform manual tack welding.

(3)

Weld reinforcement height exceeding the maximum allowed by ASME B31.3 for

circumferential butt welds on pipe. LES NEF corrective actions included re-inspecting all

welds to ensure compliance with the ASME B31.3 maximum height of weld

reinforcement and correction of any welds that exceeded the maximum criteria.

Additionally, NRC inspectors identified examples where LES NEF did not meet requirements

regarding commercial grade dedication of cascade component welds. Additional information

regarding the above examples is available in NRC IR 70-3103/2009-002, dated June 26, 2009, at ADAMS Accession No. ML091770643 and NRC IR 70-3103/2009-007, dated January 27,

2010, at ADAMS Accession No. ML100271177. Subcontractor Welding Issues at Flamanville-3 in France

On October 22, 2008, inspectors for the French regulatory authority, Autorité de Sûreté

Nucléaire, inspected the welding records of Societ delle Fucine (SdF), a subcontractor under

AREVA who in turn is the primary contractor for the construction of Flamanville-3. The

inspectors reviewed documentation and quality assurance measures applied to the weld test

samples to support the manufacturing of an intermediate collar ring for a pressurizer. The

inspectors found that the subcontractor used welding rods that were not qualified and did not

conform to the American Society for Testing and Materials (ASTM) E208, the International

Organization for Standardization (ISO) 9001, and subcontractors own procedures. The welding

rods were considered unqualified because they were not tested before performing drop-weight

testing.

The inspectors found that the subcontractor SdF was aware that unqualified weld rods were

used for the test samples and decided to not generate a nonconformance report, which is

contrary to ASTM E208, ISO 9001, and the subcontractors own procedures. The subcontractor

only generated a nonconformance report following unsuccessful tests of the samples taken from

the intermediate collar ring of the pressurizer.

The French regulators determined that without the necessary documentation to demonstrate

conformance with the French nuclear construction code, it did not have the assurance that the

subcontractor manufactured the pressurizer components in accordance with specified

requirements. Also noted was that the primary contractor AREVA had not prevented the

nonconformances by its subcontractor. The French regulators required AREVA to perform the

following three actions:

(1)

Propose a way to demonstrate that the three pressurizer intermediate collar rings

already manufactured conformed completely to the required specifications. This

approach will not rely on subcontractors quality assurance (QA) program.

(2)

Implement a more effective surveillance of AREVAs supplier, such that these QA issues

do not repeat themselves.

(3)

Describe measures that AREVA will implement before any additional orders are placed

with the subcontractor SdF for the manufacture of pressure-boundary components, destined for French nuclear power plants.

BACKGROUND

NUREG-1425, Welding and Nondestructive Examination Issues at Seabrook Nuclear Station:

An Independent Review Team Report, dated July 28, 1990, describes lessons learned

regarding licensee radiographic and welding programs. (Agencywide Documents Access and

Management Systems (ADAMS) Accession No. ML090300351).

DISCUSSION

This IN provides examples of welding issues that illustrate the importance of licensee oversight

of contractors or subcontractors, including direct observation of welding activities while in

progress when possible, to ensure welders adhere to welding procedure specifications and QA

requirements. Specifically, 10 CFR Part 50, Appendix B, Quality Assurance Criteria for Nuclear

Power Plants and Fuel Reprocessing Plants: (1) Criterion VII requires that measures be

established to adequately control contractor materials and services, (2) Criterion IX requires a

licensee to establish adequate measures to ensure the control of special processes, including

welding, heat treating, and nondestructive testing. and (3) Criterion XVI requires that measures

be established to assure that conditions adverse to quality be promptly identified and

corrected.

CONTACT

This IN requires no specific action or written response. Please direct any questions about this

matter to the technical contacts listed below.

/RA/

/RA/

Timothy J. McGinty, Director

Daniel H. Dorman, Director

Division of Policy and Rulemaking

Division of Fuel Cycle Safety and Safeguards

Office of Nuclear Reactor Regulation

Office of Nuclear Material Safety and Safeguards

/RA/

Glenn Tracy, Director

Division of Construction Inspection

and Operational Programs

Office of New Reactors

Technical Contacts: Omid Tabatabai

Alain Artayet

(301) 415-6616

(404) 562-0533

Omid.Tabatabai@nrc.gov

Alain.Artayet@nrc.gov

Tomas Herrera

(301) 415-7138

Tomas.Herrera@nrc.gov

Note: NRC generic communications may be found on the NRC public Web site, http://www.nrc.gov, under Electronic Reading Room/Document Collections..

ML091670177

ME0879 OFFICE

CCIB:DCIP:NRO Tech Editor

CTSB:DCIP:NRO

BC:CTSB:DCIP:NRO BC:FFLD:NMSS

NAME

THerrera

KAzariah-Kribbs

OTabatabai

MKowal

BSmith

DATE

06/05/09

06/12/09 via e-mail 02/26/10 via e-mail 06/18/09

02/26/10 via e-mail

OFFICE

BC:OIP

BC:CIB3:DCI:RII

BC:CVIB:NRR

LA:PGCB:NRR

NAME

CAbrams

JMoorman

MMitchell

CHawes CMH

DATE

01/12/2010

02/26/10 via email 03/10/10 via e-mail 03/15/10

OFFICE

PM:PGCB:NRR

BC:PGCB:NRR

D:NMSS:DFCSS

D:DCIP:NRO

D:DPR:NRR

NAME

DBeaulieu

MMurphy

DDorman

GTracy

TMcGinty

OFFICE

03/10/10

03/15/10

04/07/10

03/25/10

04/09/10