Letter Sequence Draft Other |
|---|
|
|
MONTHYEARML0823410392008-08-12012 August 2008 Applicant’S Environmental Report, Operating License Renewal Stage Project stage: Other ML0825207742008-10-0202 October 2008 Notice of Intent to Prepare an Environmental Impact Statement and Conduct Scoping Process for License Renewal for Kewaunee Power Station Project stage: Other ML0831907342008-10-22022 October 2008 Transcript of Kewaunee License Renewal Afternoon Scoping Meeting Afternoon Session, October 22, 2008 Project stage: Meeting ML0831907442008-10-22022 October 2008 Transcript of Kewaunee License Renewal Evening Scoping Meeting Evening Session, October 22, 2008 Project stage: Meeting ML0831000922008-10-22022 October 2008 Written Comment Submitted by State Representative Jim Soletski Supporting the Kewaunee Power Station License Renewal Project stage: Other ML0831005862008-10-22022 October 2008 Comment (1) of Bob Ziegelbauer on Behalf of the State of Wi, Supporting Dominion Energy Kewaunees Application for License Renewal Project stage: Request ML0831000942008-10-22022 October 2008 Written Comment from Bob Ziegelbauer, Manitowoc County Executive, Regarding Kewaunee Power Station License Renewal Project stage: Other ML0831000932008-10-22022 October 2008 Written Comment Submitted by Nancy Crowley, Manitowoc Emergency Services Coordinator, Regarding Kewaunee Power Station License Renewal Project stage: Other ML0830505892008-10-22022 October 2008 License Renewal Public Meeting Presentation Slides Project stage: Meeting ML0825605582008-10-27027 October 2008 Request for Additional Information Regarding the Review of the License Renewal Application for Kewaunee Power Station Project stage: RAI ML0833804552008-11-0505 November 2008 Comments of Greg Veith in Support of Kewaunee Power Station License Renewal Project stage: Other ML0830904522008-11-17017 November 2008 Summary of Public License Renewal Overview and Environmental Scoping Meeting Related to the Review of the Kewaunee Power Station License Renewal Application Project stage: Meeting ML0832507192009-01-0808 January 2009 Request for Additional Information Regarding Severe Accident Mitigation Alternatives for Kewaunee Power Station Project stage: RAI ML0902902872009-02-0303 February 2009 Summary of Conference Call with Dominion Energy Kewaunee, Inc., to Discuss the Severe Accident Mitigation Alternatives Requests for Additional Information for Kewaunee Power Station Project stage: RAI ML0906904582009-03-0909 March 2009 Response to Request for Additional Information Regarding Severe Accident Mitigation Alternatives for Kewaunee Power Station License Renewal Application Project stage: Response to RAI ML0907708802009-04-0808 April 2009 Issuance of Environmental Scoping Summary Report Associated with the Staffs Review of the Application by Dominion Energy Kewaunee, Inc., for Renewal of the Operating License for Kewaunee Power Station Project stage: Approval ML0907507202009-04-11011 April 2009 Environmental Site Audit Regarding Kewaunee Power Station License Renewal Application Project stage: Other ML0911000932009-04-20020 April 2009 Reissuing of the Environmental Scoping Summary Report Associated with the Staffs Review of the Application by Dominion Energy Kewaunee, Inc., for Renewal of the Operating License for Kewaunee Power Station Project stage: Approval ML0910603652009-04-22022 April 2009 Summary of Conference Call with Dominion Energy Kewaunee, Inc., to Discuss Responses to Severs Accident Migration Alternatives Request for Additional Information for Kewaunee Power Station Project stage: RAI ML0906700032009-07-0606 July 2009 Forthcoming Meeting to Discuss the Status of the License Renewal Review for the Kewaunee Power Station License Renewal Application Project stage: Meeting ML0919705162009-07-0606 July 2009 Response to Request to Docket Information Related to the Environmental Site Audit, Enclosure F, Archaeological and Cultural Resources Project stage: Request ML0918205652009-07-0808 July 2009 Summary of Conference Calls with Dominion Energy Kewaunee, Inc., to Discuss Response to Follow-Up Question Regarding Severe Accident Mitigation Alternatives Request for Additional Information for Kewaunee Power Station Project stage: RAI ML0918803442009-07-0808 July 2009 Environmental Project Manager Change for the License Renewal of Kewaunee Power Station Project stage: Other ML0918900172009-07-10010 July 2009 RAI Regarding the Environmental Review of the License Renewal Application for Kewaunee Power Station Project stage: RAI ML0920902772009-07-27027 July 2009 Response to Request for Additional Information Regarding the Environmental Review of the KPS License Renewal Application Project stage: Response to RAI ML0920501442009-08-12012 August 2009 Summary of Site Audit Related to the Review of the License Renewal Application for Kewaunee Power Station Project stage: Approval ML0921801372009-08-12012 August 2009 Summary Site Audit Related to the Review of the License Renewal Application for Kewaunee Power Station Project stage: Approval ML0932807992010-01-29029 January 2010 Notice of Availability of the Draft Plant-Specific Supplement 40 to the Generic Environmental Impact Statement for License Renewal of Nuclear Plants Regarding Kewaunee Power Station Project stage: Draft Other ML0932400142010-01-29029 January 2010 Notice of Availability of the Draft Plant-Specific Supplement 40 to the Generic Environmental Impact Statement for License Renewal of Nuclear Power Plants Regarding Kewaunee Power Station Project stage: Draft Other ML1005502102010-03-0101 March 2010 Environmental Project Manager Change for the License Renewal Project for Kewaunee Power Station Project stage: Other ML1012410612010-03-24024 March 2010 Transcript of Kewaunee Power Station on License Renewal Draft Environmental Issues Public Meeting, Evening Session, March 24, 2010, Pages 1-16 ML1012410602010-03-24024 March 2010 License Renewal Public Meeting Afternoon Session Project stage: Meeting ML1013104192010-05-18018 May 2010 Draft Supplement Environmental Impact Statement Meeting Slides March 24, 2010 ML1012601102010-05-18018 May 2010 Summary of Public Meetings Conducted to Discuss the Draft Supplement Environmental Impact Statement Related to the Review of the Kewaunee Power Station License Renewal Application ML1021504642010-08-24024 August 2010 Final Supplement 40 to the Generic Environmental Impact Statement for License Renewal of Nuclear Plants Regarding Kewaunee Power Station Project stage: Other 2009-04-22
[Table View] |
Text
[7590-01-P]
NUCLEAR REGULATORY COMMISSION DOMINION ENERGY KEWAUNEE, INC.
KEWAUNEE POWER STATION NOTICE OF AVAILABILITY OF THE DRAFT SUPPLEMENT 40 TO THE GENERIC ENVIRONMENTAL IMPACT STATEMENT FOR LICENSE RENEWAL OF NUCLEAR PLANTS AND PUBLIC MEETINGS FOR THE LICENSE RENEWAL OF KEWAUNEE POWER STATION DOCKET NO. 50-305
[NRC-2010-0041]
Notice is hereby given that the U.S. Nuclear Regulatory Commission (NRC or Commission) has published a draft plant-specific supplement to the Generic Environmental Impact Statement for License Renewal of Nuclear Plants (GEIS), NUREG-1437, regarding the renewal of Operating License No. DPR-43 for an additional 20 years of operation for Kewaunee Power Station (KPS). KPS is located in Kewaunee County, Wisconsin, on the west-central shore of Lake Michigan. Possible alternatives to the proposed action (license renewal) include no action and reasonable alternative energy sources.
The draft Supplement 40 to the GEIS is publicly available at the NRC Public Document Room (PDR), located at One White Flint North, 11555 Rockville Pike, Rockville, Maryland 20852, or from the NRC=s Agencywide Documents Access and Management System (ADAMS).
The ADAMS Public Electronic Reading Room is accessible at http://adamswebsearch.nrc.gov/dologin.htm. The Accession Number for the draft Supplement 40 to the GEIS is ML100240002. Persons who do not have access to ADAMS, or who encounter problems in accessing the documents located in ADAMS, should contact the NRC=s PDR reference staff by telephone at 1-800-397-4209, or 301-415-4737, or by e-mail at pdr.resource@nrc.gov. In addition, a copy of the draft supplement to the GEIS is available to local residents near the site at the Kewaunee Public Library, 822 Juneau Street, Kewaunee, Wisconsin 54216.
Any interested party may submit comments on the draft supplement to the GEIS for consideration by the NRC staff. To be considered, comments on the draft supplement to the GEIS and the proposed action must be received by April 23, 2010; the NRC staff is able to ensure consideration only for comments received on or before this date. Comments received after the due date will be considered only if it is practical to do so. Written comments on the draft supplement to the GEIS should be sent to: Chief, Rulemaking and Directives Branch, Division of Administrative Services, Office of Administration, Mailstop TWB 5B01, U.S. Nuclear Regulatory Commission, Washington, DC 20555-0001.
Electronic comments may be submitted to the NRC by e-mail at KewauneeEIS.Resource@nrc.gov. All comments received by the Commission, including those made by Federal, State, local agencies, Native American Tribes, or other interested persons, will be made available electronically at the Commission=s PDR in Rockville, Maryland, and through ADAMS.
The NRC staff will hold a public meeting to present an overview of the draft plant-specific supplement to the GEIS and to accept public comments on the document. The public meeting will be held on March 24, 2010, at the City of Carlton Town Hall, N1296 Town Hall Road, Kewaunee, WI 54216. There will be two sessions to accommodate interested parties. The first session will convene at 1:30 p.m. and will continue until 4:30 p.m., as necessary. The second session will convene at 7:00 p.m. and will continue until 10:00 p.m., as necessary. Both meetings will be transcribed and will include: (1) a presentation of the contents of the draft plant-specific supplement to the GEIS, and (2) the opportunity for interested government agencies, organizations, and individuals to provide comments on the draft report. Additionally, the NRC staff will host informal discussions one hour prior to the start of each session at the same location. No comments on the draft supplement to the GEIS will be accepted during the informal discussions. To be considered, comments must be provided either at the transcribed public meeting or in writing. Persons may pre-register to attend or present oral comments at the meeting by contacting Ms. Vanice Perin, the NRC Environmental Project Manager at 1-800-368-5642, extension 8143, or by e-mail at Vanice.Perin@nrc.gov, no later than Tuesday, March 16, 2010. Members of the public may also register to provide oral comments within 15 minutes of the start of each session. Individual, oral comments may be limited by the time available, depending on the number of persons who register. If special equipment or accommodations are needed to attend or present information at the public meeting, the need should be brought to Ms. Perins attention no later than March 16, 2010, to provide the NRC staff adequate notice to determine whether the request can be accommodated.
FOR FURTHER INFORMATION, CONTACT: Ms. Vanice Perin, Projects Branch 1, Division of License Renewal, Office of Nuclear Reactor Regulation, U.S. Nuclear Regulatory Commission, Mail Stop O-11F1, Washington, DC 20555-0001. Ms. Perin may be contacted at the aforementioned telephone number or e-mail address.
Dated at Rockville, Maryland, this 29th day of January, 2010.
FOR THE NUCLEAR REGULATORY COMMISSION
/RA/
Bo M. Pham, Chief Projects Branch 1 Division of License Renewal Office of Nuclear Reactor Regulation