ML091880344

From kanterella
Jump to navigation Jump to search

Environmental Project Manager Change for the License Renewal of Kewaunee Power Station
ML091880344
Person / Time
Site: Kewaunee Dominion icon.png
Issue date: 07/08/2009
From: David Pelton
License Renewal Projects Branch 1
To: Heacock D
Dominion Energy Kewaunee
LOPAS, S, DLR/RPB1- 415-1147
References
TAC MD9409
Download: ML091880344 (5)


Text

July 8, 2009 Mr. David A. Heacock President and Chief Nuclear Officer Dominion Energy Kewaunee, Inc.

Innsbrook Technical Center - 2SW 5000 Dominion Boulevard Glen Allen, VA 23060-6711

SUBJECT:

ENVIRONMENTAL PROJECT MANAGER CHANGE FOR THE LICENSE RENEWAL OF KEWAUNEE POWER STATION (TAC NO. MD9409)

Dear Mr. Heacock:

This letter is to inform you that effective immediately, the U.S. Nuclear Regulatory Commissions License Renewal Environmental Project Manager responsible for the Kewaunee Power Station (KPS) license renewal environmental review will be Ms. Vanice Perin.

All correspondence for the Environmental Project Manager associated with the environmental review for KPS license renewal should be sent to:

Ms. Vanice Perin, Environmental Project Manager Projects Branch 1 Division of License Renewal Office of Nuclear Reactor Regulation U.S. Nuclear Regulatory Commission Mail Stop O-11F1 Washington, DC 20555 Ms. Perin may be reached at 301-415-8143 or by e-mail at Vanice.Perin@nrc.gov.

Sincerely,

/RA/

David L. Pelton, Chief Projects Branch 1 Division of License Renewal Office of Nuclear Reactor Regulation Docket No. 50-305 cc: See next page

July 8, 2009 Mr. David A. Heacock President and Chief Nuclear Officer Dominion Energy Kewaunee, Inc.

Innsbrook Technical Center - 2SW 5000 Dominion Boulevard Glen Allen, VA 23060-6711

SUBJECT:

ENVIRONMENTAL PROJECT MANAGER CHANGE FOR THE LICENSE RENEWAL OF KEWAUNEE POWER STATION (TAC NO. MD9409)

Dear Mr. Heacock:

This letter is to inform you that effective immediately, the U.S. Nuclear Regulatory Commissions License Renewal Environmental Project Manager responsible for the Kewaunee Power Station (KPS) license renewal environmental review will be Ms. Vanice Perin.

All correspondence for the Environmental Project Manager associated with the environmental review for KPS license renewal should be sent to:

Ms. Vanice Perin, Environmental Project Manager Projects Branch 1 Division of License Renewal Office of Nuclear Reactor Regulation U.S. Nuclear Regulatory Commission Mail Stop O-11F1 Washington, DC 20555 Ms. Perin may be reached at 301-415-8143 or by e-mail at Vanice.Perin@nrc.gov.

Sincerely,

/RA/

David L. Pelton, Chief Projects Branch 1 Division of License Renewal Office of Nuclear Reactor Regulation Docket No. 50-305 cc: See next page DISTRIBUTION:

See next page ADAMS Accession Number: ML091880344 OFFICIAL RECORD COPY OFFICE PM:DLR LA:DLR BC:DLR NAME S. Lopas I. King D. Pelton DATE 07/07/09 07/07/09 07/08/09

Letter to David A. Heacock from David L. Pelton dated July 08, 2009

SUBJECT:

ENVIRONMENTAL PROJECT MANAGER CHANGE FOR THE LICENSE RENEWAL OF KEWAUNEE POWER STATION (TAC NO. MD9409)

DISTRIBUTION:

HARD COPY:

DLR RF E-MAIL:

PUBLIC RidsNrrDlr Resource RidsNrrDlrRpb1 Resource RidsNrrDlrRerb Resource RidsOpaMail Resource RidsOgcMailCenter Resource S. Hernandez S. Lopas P. Tam M. Kunowski S. Burton K. Barclay V. Mitlyng I. Couret, OPA S. Uttal, OGC R. Shane, OCA B. Keeling, OCA

Kewaunee Power Station cc:

Resident Inspectors Office U.S. Nuclear Regulatory Commission N490 Hwy 42 Kewaunee, WI 54216-9510 Mr. Chris L. Funderburk Director, Nuclear Licensing and Operations Support Dominion Resources Services, Inc.

Innsbrook Technical Center - 2SE 5000 Dominion Boulevard Glen Allen, VA 23060-6711 Mr. Thomas L. Breene Dominon Energy Kewaunee, Inc.

Kewaunee Power Station N490 Highway 42 Kewaunee, WI 54216 Mr. Michael J. Wilson, Director Nuclear Safety & Licensing Dominion Energy Kewaunee, Inc.

Kewaunee Power Station N490 Highway 42 Kewaunee, WI 54216 Mr. William R. Matthews Senior Vice President - Nuclear Operations Innsbrook Technical Center - 2SE 5000 Dominion Boulevard Glen Allen, VA 23060-6711 Mr. Alan J. Price Vice President - Nuclear Engineering Innsbrook Technical Center - 2SE 5000 Dominion Boulevard Glen Allen, VA 23060-6711 Mr. William D. Corbin Director - Nuclear Engineering Innsbrook Technical Center - 3NE 5000 Dominion Boulevard Glen Allen, VA 23060-6711 Mr. Paul C. Aitken Supervisor - License Renewal Project Innsbrook Technical Center - 3NE 5000 Dominion Boulevard Glen Allen, VA 23060-6711 Mr. David A. Sommers Supervisor - Nuclear Engineering Innsbrook Technical Center - 2SE 5000 Dominion Boulevard Glen Allen, VA 23060-6711 Ms. Lillian M. Cuoco, Esq.

Senior Counsel Dominion Resources Services, Inc.

120 Tredegar Street Riverside 2 Richmond, VA 23219 Mr. Stephen E. Scace Site Vice President Dominion Energy Kewaunee, Inc.

Kewaunee Power Station N490 Highway 42 Kewaunee, WI 54216 Mr. David R. Lewis Pillsbury Winthrop Shaw Pittman, LLP 2300 N Street, N.W.

Washington, DC 20037-1122 Mr. Ken Paplham E 4095 Sandy Bay Rd.

Kewaunee, WI 54216 Mr. Richard Gallagher Senior Scientist, License Renewal Dominion Resources Services, Inc.

Route 156, Rope Ferry Road Waterford, CT 06385

Kewaunee Power Station cc:

Mr. Ronald Kazmierczak Regional Director Wisconsin Department of Natural Resources Northeast Region Headquarters 2984 Shawano Avenue P.O. Box 10448 Green Bay, WI 54307-0448 Ms. Kathleen Angel Federal Consistency and Coastal Hazards Coordinator Wisconsin Coastal Management Program P.O. Box 8944 Madison, WI 53708-8944 Mr. Jeff Kitsembel, P.E.

Public Service Commission of Wisconsin P.O. Box 7854 Madison, WI 53707-7854 Mr. Steven Ugoretz Environmental Analyst - OE/7 Wisconsin Department of Natural Resource P.O. Box 7921 Madison, WI 53707-7921 Mr. David Siebert Director Office of Energy Wisconsin Department of Natural Resources 101 South Webster Street Madison, WI 53703