Letter Sequence Other |
---|
|
Results
Other: ML083540261, ML083540266, ML090690198, ML090700515, ML090700525, ML090700543, ML090720091, ML090720103, ML090720516, ML090820113, ML090820140
|
MONTHYEARML0907005152008-03-11011 March 2008 Email from Pacific Gas and Electric Company Re Summary of Conference Call Held on November 21, 2009 Project stage: Other ML0906901982008-11-20020 November 2008 Email from Pacific Gas & Electric Regarding Preliminary Data for Seismic Discussion Project stage: Other ML0907005252008-11-21021 November 2008 Summary of Conference Call Held on November 21, 2009 Prepared by Pacific Gas and Electric Company Project stage: Other ML0906902092008-11-21021 November 2008 Meeting Slides, Summary of Preliminary Findings from the Usgs/Pg&E Hazard Studies for the Central Coastal California Region, Diablo Canyon Power Plant, Unit Nos. 1 and 2, from Pacific Gas & Electric Project stage: Meeting ML0908201402008-11-26026 November 2008 Yong Li Preliminary Conclusions Regarding New Shoreline Fault Project stage: Other ML0835402662008-12-17017 December 2008 Shoreline Fault Study Project stage: Other ML0907205162008-12-17017 December 2008 Email from Pacific Gas and Electric Regarding Seismic Action Plan (ME0174 and ME0175) Project stage: Other ML0835402612008-12-17017 December 2008 Shoreline Fault Characterization Schedule Project stage: Other ML0908201132009-01-0505 January 2009 Email Regarding Seismic Action Plan Project stage: Other ML0907201032009-03-11011 March 2009 Additional Slides - Seismic Information Project stage: Other ML0907200912009-03-11011 March 2009 Email from Pacific Gas and Electric Company Enclosing Additional Seismic Slides Project stage: Other ML0907005432009-03-11011 March 2009 E-mail from Pacific Gas and Electric Company Regarding Preliminary Data for Seismic Discussion Project stage: Other ML0909304592009-04-0808 April 2009 NRC Review of Potential Shoreline Fault Project stage: Approval ML0930805082009-11-0505 November 2009 Review of Potential New Shoreline Fault Project stage: Approval 2008-03-11
[Table View] |
|
---|
Category:E-Mail
MONTHYEARML24285A1902024-10-0808 October 2024 Email - Diablo Canyon Independent Spent Fuel Storage Installation License Renewal Environmental Assessment ML24281A1062024-10-0202 October 2024 NRR E-mail Capture - (External_Sender) Public Letter to Petition Review Board Regarding the Diablo Canyon Seismic Core Damage Frequency 10 CFR 2.206 Petition - OEDO-24-00083 ML24250A0542024-09-0606 September 2024 LRA - Requests for Additional Information - Set 1 - Email from Brian Harris to Adam Peck ML24250A0502024-09-0606 September 2024 NRR E-mail Capture - Acceptance Review Diablo Canyon Revision to Technical Specification 5.5.16 for Permanent Extension of Type a and Type C Leak Rate Test Frequencies ML24291A1322024-09-0505 September 2024 E-mail to California Department of Public Health for Diablo Canyon ISFSI License Renewal Environmental Assessment ML24235A2032024-08-22022 August 2024 OEDO-24-00083 - 10 CFR 2.206 - Diablo Canyon Units 1 and 2 Seismic - Final Determination e-mail - EPID L-2024-CRS-0000 ML24205A0622024-07-23023 July 2024 NRR E-mail Capture - Acceptance Review - Diablo Canyon Request for Approval to Extend the Alternative for Use of Full Structural Weld Overlay ML24187A1382024-07-0202 July 2024 License Renewal Environmental Review: Summary of June 27 Clarification Call Regarding Pg&Es Response to RCI AQN-3 ML24184C0422024-07-0202 July 2024 NRR E-mail Capture - Request for Additional Information Diablo Canyon 50.69 risk-informed Categorization ML24149A0832024-05-28028 May 2024 Acceptance Review: Diablo Canyon Request for Alternative Security Measures and Exemption for the Early Warning System ML24145A0612024-05-22022 May 2024 Written Limited Appearance Statement of Doris Nassiry ML24136A1622024-05-15015 May 2024 OEDO-24-00083 (E-Mail) 10 CFR 2.206 - Diablo Canyon Power Plant, Unit Nos. 1 and 2 Seismic - Initial Assessment ML24135A1562024-05-13013 May 2024 July 2024 Emergency Preparedness Exercise Inspection - Request for Information ML24134A1902024-05-10010 May 2024 Written Limited Appearance Statement of Shelley Hamilton ML24134A1872024-05-10010 May 2024 Written Limited Appearance Statement of Charlene M. Woodcock ML24122C6702024-04-29029 April 2024 Request from NRC Review of a Draft EA for an Exemption for the Limerick Generating Station ML24095A3172024-04-0404 April 2024 NRR E-mail Capture - Acceptance Review Diablo Canyon Request to Revise Technical Specification 5.6.6 for Pressure and Temperature Limits Report ML24088A2382024-03-28028 March 2024 10 CFR 2.206 - Diablo Canyon Units 1 and 2 OEDO-24-00083 - Screen-in e-mail L-2024-CRS-0000 ML24058A1032024-03-0808 March 2024 OEDO-23-00350-NRR - Initial Assessment - 10 CFR 2.206 Petition from Mothers for Peace and Friends of the Earth Regarding Diablo Canyon ML24071A1762024-03-0707 March 2024 Email - (External Sender) NRC Proceeding on Diablo Canyon 50-275 and 50-323 LR-2 ML24067A0892024-03-0505 March 2024 Email Response from Diane Curran to Office of the Secretary, Assistant for Rulemaking and Adjudications, Russell Chazell ML24067A0902024-03-0505 March 2024 Email to Diane Curran from the Office of the Secretary, Assistant for Rulemaking and Adjudications, Russell Chazell ML24067A0882024-03-0404 March 2024 Email Hearing Request from San Luis Obispo Mothers for Peace, Friends of the Earth, and Environmental Working Group ML24060A0022024-02-28028 February 2024 (External Sender) Pre-Sub Mittal EWS Participants List E-mail ML24045A1972024-02-0606 February 2024 Tribal Consultation Request ML24033A3062024-02-0101 February 2024 Dcisc 2-1-2024 Email: Comments by Mr. Bruce Severance at This Mornings Public Meeting Re Scope of Review for DCPP License Extension ML23334A0912023-11-30030 November 2023 NRR E-mail Capture - Diablo Canyon 1 and 2 - Audit Questions for License Amendment Associated with TSTF-505, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b ML23335A1012023-11-0606 November 2023 OEDO-23-00350-NRR - Screen-in Email - 10 CFR 2.206 Petition from Mothers for Peace and Change.Org Regarding Diablo Canyon ML23306A0422023-11-0202 November 2023 NRR E-mail Capture - Acceptance Review Diablo Canyon Request to Adopt 10 CFR 50.69, risk-informed Categorization and Treatment of SSCs ML23230A0702023-08-18018 August 2023 NRR E-mail Capture - Acceptance Review - Diablo Canyon Request to Revise Technical Specifications to Adopt TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times – RITSTF Initiative 4b ML23165A2702023-06-14014 June 2023 NRR E-mail Capture - Acceptance Review - Diablo Canyon Revision to the Unit 1 Reactor Vessel Material Surveillance Program Withdrawal Schedule ML23157A2392023-06-0505 June 2023 Limited Appearance Statement from Nina Babiarz in the Matter of the Diablo Canyon ISFSI License Renewal Application ML23096A1792023-04-0606 April 2023 NRR E-mail Capture - Request for Additional Information Diablo Canyon Exemption Request Regarding Senior Reactor Operator License Application ML23094A1032023-04-0404 April 2023 NRR E-mail Capture - Acceptance Review - Diablo Canyon Exemption Request Regarding Senior Reactor Operator License Application ML23076A0932023-03-16016 March 2023 16-2023 Email - Estimate of Spent Nuclear Fuel in Tons ML23067A0202023-03-0808 March 2023 NRR E-mail Capture - Diablo Canyon Nuclear Power Plant Evacuation Time Estimate Analysis Review ML23046A1042023-02-13013 February 2023 Transmittal Email, Diane Curran to Gibson, 2/13/23, Filing of Formal Opposition to PG&E Exemption Request ML23046A1132023-02-13013 February 2023 Transmittal Email, Paul Bessette to Gibson, 2/13/23, Filing of Formal Opposition to PG&E Exemption Request ML23052A2042023-01-10010 January 2023 E-mail from Paul Bessette Dated 01/10/2023 Regarding Diablo Canyon ML22326A1632022-11-21021 November 2022 Licensee Comment Email on Post-Shutdown Emergency Plan Amendment ML22266A0012022-09-22022 September 2022 (External Sender) E-Mail Diablo Canyon Power Plant, Unit Nos. 1 and 2 - Total Amount of Spent Nuclear Fuel Stored in Tons ML22241A1142022-08-29029 August 2022 NRR E-mail Capture - Acceptance Review - Diablo Canyon Application to Revise Technical Specifications to Adopt TSTF-569, Revision of Response Time Testing Definitions ML22194A8872022-07-11011 July 2022 September 2022 Emergency Preparedness Exercise Inspection - Request for Information Email ML22187A2652022-07-0606 July 2022 NRR E-mail Capture - Request for Additional Information: Diablo Canyon Exemption Request for Part 73 force-on-force Training Due to COVID-19 ML22105A0702022-04-15015 April 2022 NRR E-mail Capture - Acceptance Review - Diablo Canyon Request to Revise Technical Specifications to Adopt TSTF 577, Revised Frequencies for Steam Generator Tube Inspections ML22090A0832022-03-31031 March 2022 NRR E-mail Capture - Acceptance Review - Diablo Canyon Request for Approval of a Certified Fuel Handler Training and Retraining Program ML22089A1672022-03-29029 March 2022 Email - Acknowledgement of NRC Receipt of Diablo Canyon ISFSI Renewal Application ML22087A0412022-03-25025 March 2022 NRR E-mail Capture - Acceptance Review - Diablo Canyon Request for Approval of Alternative Security Measures for Early Warning System ML22061A2192022-03-0202 March 2022 NRR E-mail Capture - Request for Additional Information - Diablo Canyon Proposed Changes to Emergency Plan for post-shutdown and Permanently Defueled Condition ML21323A0652021-11-19019 November 2021 NRR E-mail Capture - Acceptance Review - Diablo Canyon Revision of Emergency Plan for post-shutdown Condition 2024-09-06
[Table view] |
Text
From: Ketelsen, Stan C [SCK3@pge.com]
Sent: Wednesday, March 11, 2009 10:06 PM To: Alan Wang Cc: Guldemond, Bill; Sharp, Loren; Cluff, Lloyd; Abrahamson, Norman; McLaren, Marcia K; Parker, Larry M
Subject:
Additional Seismic Information Attachments: CEC_ 1-29-09.pdf Alan -
Bill Guldemond asked that I forward the attached slide file to you. It was used as the basis for discussions with Assemblyman Blakeslee and the CEC, Commissioner Boyd and staff. The meetings were held on January 29, 2009 in Sacramento. There is some duplication with respect to the previous slides transmitted to you prior to our conference call on November 21, 2008..
<<CEC_ 1-29-09.pdf>>
Stan Ketelsen Manager - Regulatory Services Diablo Canyon Power Plant (805) 545-4720 8-691-4720 104/5/536 E-mail Properties Mail Envelope Properties (C7F97EAA3DB12743A56ED3B2C25D69980183AB31)
Subject:
Additional Seismic Information Sent Date: 3/11/2009 10:06:12 PM Received Date: 3/11/2009 10:06:12 PM From: Ketelsen, Stan C Created By: SCK3@pge.com Recipients:
Alan.Wang@nrc.gov (Alan Wang)
Tracking Status: None WGG4@pge.com (Guldemond, Bill)
Tracking Status: None LDSL@pge.com (Sharp, Loren)
Tracking Status: None LSC2@pge.com (Cluff, Lloyd)
Tracking Status: None NAA2@pge.com (Abrahamson, Norman)
Tracking Status: None
MKM2@pge.com (McLaren, Marcia K)
Tracking Status: None LMP1@pge.com (Parker, Larry M)
Tracking Status: None Post Office:
exchange18.Utility.pge.com Files Size Date & Time MESSAGE 2415138 3/11/2009 CEC_ 1-29-09.pdf 2411705 Options Expiration Date:
Priority: olImportanceNormal ReplyRequested: False Return Notification: False Sensitivity: olNormal Recipients received: