ML090700515
| ML090700515 | |
| Person / Time | |
|---|---|
| Site: | Diablo Canyon |
| Issue date: | 03/11/2008 |
| From: | Parker L Pacific Gas & Electric Co |
| To: | Wang A Plant Licensing Branch IV |
| Wang, A B, NRR/DORL/LPLIV, 415-1445 | |
| Shared Package | |
| ML090700508 | List: |
| References | |
| TAC ME0174, TAC ME0175 | |
| Download: ML090700515 (1) | |
Text
From: Parker, Larry M [LMP1@pge.com]
Sent: Wednesday, March 11, 2009 12:17 PM To:
Alan Wang Cc:
Ketelsen, Stan C
Subject:
RE: DCPP Seismic Conference Call Summary, November 21 Attachments:
20081121.doc
- Alan, Here are the final minutes.
Larry
Original Message-----
From: Parker, Larry M Sent: Tuesday, March 10, 2009 10:30 AM To: 'Alan.Wang@nrc.gov'
Subject:
Re: DCPP Seismic Conference Call Summary, November 21 Alan I'm across the street at the ric. There was a minor comment I wanted to incorporate before it goes on the docket. I should get it to you tomorrow.
Larry 805 441 5526
Original Message -----
From: Alan Wang <Alan.Wang@nrc.gov>
To: Parker, Larry M Sent: Tue Mar 10 10:15:22 2009
Subject:
RE: DCPP Seismic Conference Call Summary, November 21 Larry, have the minutes been finalized? If they have I have been asked to place it in ADAMS as this was when slides regarding your findings were presented to us. Alan From: Parker, Larry M [1]
Sent: Monday, December 08, 2008 4:13 PM To: Becker, James; Peters, Kenneth; Welsch, James; Guldemond, Bill; Cluff, Lloyd; Abrahamson, Norman; Klimczak, Richard; Ketelsen, Stan C; Grebel, Terence; Strickland, L Jearl Cc: Alan Wang; Tony Brown; Michael Peck
Subject:
DCPP Seismic Conference Call Summary, November 21 Attached are draft minutes of the conference call on November 21 when PG&E briefed the NRC of the new potential seismic fault.
<<20081208124817948.pdf>> <<20081121.doc>> Any comments/corrections are welcome.
Larry Parker
Regulatory Services Supervisor PG&E, Diablo Canyon Power Plant 805-545-3386 (work) 805-441-5526 (cell)
LMP1@pge.com E-mail Properties Mail Envelope Properties (855985CB2A096741901904980FD8CB6C01CE0441)
Subject:
RE: DCPP Seismic Conference Call Summary, November 21 Sent Date:
3/11/2009 12:17:21 PM Received Date:
3/11/2009 12:17:21 PM From:
Parker, Larry M Created By:
LMP1@pge.com Recipients:
Alan.Wang@nrc.gov (Alan Wang)
Tracking Status: None SCK3@pge.com (Ketelsen, Stan C)
Tracking Status: None Post Office:
exchange18.Utility.pge.com Files Size Date & Time MESSAGE 58542 3/11/2009 20081121.doc 54336 Options Expiration Date:
Priority:
olImportanceNormal ReplyRequested:
False Return Notification:
False Sensitivity:
olNormal Recipients received: