Text

ID Task Name Duration Start Finish Predecessors 1

Geologic Studies 388 days?

Mon 1/5/09 Wed 6/30/10 2

Additional Geologic Mapping along Coast (G1) 388 days Mon 1/5/09 Wed 6/30/10 12FF 3

Map and Evaluate Shear Zone (G2) 193 days?

Tue 4/7/09 Thu 12/31/09 4

Seismicity Studies 193 days?

Mon 1/5/09 Wed 9/30/09 5

EQ locations and focal mechanisms of '80-'87 and 3/07-12/08 data sets (S1) 127 days?

Mon 1/5/09 Tue 6/30/09 6

Independent Revew of J. Hardebeck data processing (S2) 127 days Mon 1/5/09 Tue 6/30/09 7

Analyze and Document Expanded Data Set (S3) 66 days?

Wed 7/1/09 Wed 9/30/09 5,6 8

Install Additional Seismic Stations (S4) 131 days?

Wed 4/1/09 Wed 9/30/09 9

Geophysical Studies 259 days?

Mon 1/5/09 Thu 12/31/09 10 High Resolution Marine Magnetics (GP1A) 133 days?

Mon 3/30/09 Wed 9/30/09 11 Marine Magnetics Data Integration (GP1B) 132 days?

Wed 7/1/09 Thu 12/31/09 10FF 12 Mult-beam Bathymetry 20m-5m (GP2A) 197 days?

Wed 4/1/09 Thu 12/31/09 13 LIDAR Bathymetry and Coastal Topography (GP2B) 193 days?

Mon 1/5/09 Wed 9/30/09 14 3D Seismic Survey Scoping Study (GP3) 62 days?

Mon 1/5/09 Tue 3/31/09 15 Shoreline Fault Source Characterization 454 days?

Mon 1/5/09 Thu 9/30/10 16 Compile Geology Data into GIS (SC1) 193 days?

Mon 1/5/09 Wed 9/30/09 17 Integrate Data Layers and Interpret Results and Develop Alternative Credible Source Models (SC2) 194 days?

Mon 1/4/10 Thu 9/30/10 16 18 Ground Motion Studies 454 days?

Mon 1/5/09 Thu 9/30/10 19 Dynamic Rupture Model to Evaluate Rupture Characteristics for Hosgri plus Shoreline Splay (GM1) 259 days?

Mon 1/5/09 Thu 12/31/09 20 Compute Ground Motions from Kinematic Sources (GM2) 128 days?

Mon 1/4/10 Wed 6/30/10 19 21 Parameterize Kinematic Ground Motions (GM3) 66 days?

Thu 7/1/10 Thu 9/30/10 20 22 Final Report 132 days?

Thu 7/1/10 Fri 12/31/10 17FF,21FF-4 wks Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec 1st Quarter 2nd Quarter 3rd Quarter 4th Quarter 1st Quarter 2nd Quarter 3rd Quarter 4th Quarter 2009 2010 Task Split Progress Milestone Summary Project Summary External Tasks External Milestone Deadline Figure 1 Page 1 Project: Shoreline Fault Characterizatio Date: Mon 12/15/08