MONTHYEARML0830403912008-11-10010 November 2008 October 21, 2008, Public Meeting: NRC Presentation Slides, NRC Topical Report (TR) Program Monthly Meeting Project stage: Meeting ML0830800482008-11-10010 November 2008 October 21, 2008 Public Meeting: NEI Handout 2, Presentation Slides Project stage: Meeting ML0830400492008-11-10010 November 2008 Summary of the October 21, 2008, Category 2 Public Meeting Between the U.S. Nuclear Regulatory Commission (NRC) and Industry Representatives Regarding the NRCs Topical Report (TR) Process (Tac No. MD4832) Project stage: Meeting ML0830800472008-11-10010 November 2008 October 21, 2008, Public Meeting: NEI Handout 1, LIC-500 Comments Project stage: Meeting ML0834301072008-12-29029 December 2008 Summary of the November 20, 2008, Category 2 Public Meeting Between the U.S. Nuclear Regulatory Commission (NRC) and Industry Representatives Regarding the NRCs Pical Report (TR) Process Project stage: Meeting ML0833903672008-12-29029 December 2008 November 20, 2008 Topical Report Monthly Public Meeting: Industry Handout Project stage: Meeting ML0902200952009-02-0404 February 2009 Draft Flowchart for Topical Report Reviews That Include Pilot LARs Project stage: Request ML0902200842009-02-0404 February 2009 Technical Champion Flow Diagram (Draft) Project stage: Request ML0902200972009-02-0404 February 2009 Summary of Category 2 Public Meeting Between the U.S. Nuclear Regulatory Commission (NRC) and Industry Representatives Regarding the NRCs Topical Report (TR) Process Project stage: Meeting ML0902200692009-02-0404 February 2009 NEI Handout: January 8, 2009 Monthly Topical Report Public Meeting Project stage: Request ML0906502422009-03-12012 March 2009 2/19/09 Public Meeting Handout: Draft Topical Report Prioritization Scheme ML0906502952009-03-12012 March 2009 Summary of the February 19, 2009, Category 2 Public Meeting Between the U.S. Nuclear Regulatory Commission and Industry Representatives Regarding the NRCs Topical Report Process Project stage: Meeting ML0906502752009-03-12012 March 2009 NEI Meeting Handout: 2/19/09 Public Topical Report Monthly Meeting Project stage: Meeting ML0906502852009-03-12012 March 2009 2/19/09 Public Meeting Handout: Technical Champion Flow Diagram Project stage: Meeting ML0912003602009-05-19019 May 2009 Summary of Category 2 Public Meeting Between NRC and Industry Representatives Regarding NRCs Topical Report Process Project stage: Meeting ML0921908882009-08-25025 August 2009 Meeting Slides, Current Status of the Topical Report Draft Prioritization Scheme ML0922301812009-08-25025 August 2009 Meeting Summary, Category 2 Public Meeting Between the U.S. Nuclear Regulatory Commission and Industry Representatives Regarding the NRCs Topical Report Process Project stage: Meeting ML0921908862009-08-25025 August 2009 Meeting Slides, Nrc/Nei Public Meeting TR Process Project stage: Meeting ML0921908872009-08-25025 August 2009 NRC Handout: Appendix C - Draft Topical Report Prioritization Scheme Project stage: Draft Other ML0934903872009-12-17017 December 2009 Summary of Category 2 Public Meeting Between NRC and Industry Representatives Regarding the NRCs Topical Report Process Project stage: Meeting 2009-02-04
[Table View] |
Text
DRAFT FLOWCHART FOR TOPICAL REPORT REVIEWS THAT INCLUDE PILOT LARs Challenges:
Revise LIC-101 timeliness metrics for LARs (1 year from the date of application)
Revise LIC-101 for BWN issuance goals (30 days from the date of application)
Review LIC-109 guidance on the use of unapproved TRs; current guidance may be adequate Coordination of technical resources (consistent reviewers throughout the project)
Submittal:
Topical Report with Pilot LAR LIC-109 Review for TR and Pilot LAR (60 days)
Review TR; Draft TR SE; Draft TR -
based SE input for LAR (up to 3 years)
Transmit TR SE to author for final review (20 day comment)
Complete technical review of TR-based LAR Issue -A version of TR Issue Pilot LAR Open TR review TAC Open LAR TAC Notice the Pilot LAR (60 day comment)