MONTHYEARML0624902422006-08-29029 August 2006 Enclosure 1, E. I. Hatch Request to Implement an Alternative Source Term - AST Safety Assessment Project stage: Request ML0630700372006-11-14014 November 2006 Edwin I Hatch, Nuclear Plant Unit No. 1 & 2, Request for Additional Information for Alternate Source Term Review (TAC Nos. MD2934 & MD2935) Project stage: RAI ML0632800652006-11-14014 November 2006 Meeting Summary Handouts, Enclosure 2 (Tac Nos. MD2934 and MD2935) Project stage: Meeting ML0632401972006-12-11011 December 2006 Summary of November 14, 2006, Meeting with Southern Nuclear Operating Co., on Alternative Source Term Submittal Project stage: Meeting ML0704602852007-02-22022 February 2007 Request for Additional Information Regarding Alternate Source Term Application Project stage: RAI ML0706502982007-03-15015 March 2007 Edwin I Hatch Nuclear Plant, Units 1 and 2 (HNP) - Request for Additional Information Alternative Source Term Application Project stage: RAI ML0708902972007-04-10010 April 2007 RAI Regarding Alternative Source Term Application Project stage: RAI ML0710900392007-04-26026 April 2007 Request for Additional Information Alternate Source Term Application Project stage: RAI ML0710900572007-05-0808 May 2007 Request for Additional Information Alternate Source Term Application Project stage: RAI ML0712801262007-05-30030 May 2007 Request for Additional Information the Revision of the Licensing and Design Basis with a Full Scope Implementation of an Alternative Source Term Project stage: RAI NL-07-1308, Request to Implement an Alternative Source Term Response to Request for Additional Information Regarding the Unit 1 Main Steam Isolation Valve Alternate Leakage Treatment Path Seismic Evaluation2007-07-16016 July 2007 Request to Implement an Alternative Source Term Response to Request for Additional Information Regarding the Unit 1 Main Steam Isolation Valve Alternate Leakage Treatment Path Seismic Evaluation Project stage: Response to RAI ML0721904682007-08-16016 August 2007 Nos. Units 1 and 2, (Hnp), RAI, Request for Additional Information Regarding Alternate Source Term Application Project stage: RAI ML0726806972007-10-0303 October 2007 Request for Additional Information Regarding Alternate Source Term Application Project stage: RAI NL-07-0894, Request to Implement an Alternative Source Term Response to Request for Additional Information Regarding the Power Sources for the Turbine Building Ventilation System2007-10-18018 October 2007 Request to Implement an Alternative Source Term Response to Request for Additional Information Regarding the Power Sources for the Turbine Building Ventilation System Project stage: Response to RAI NL-07-1949, Request to Implement an Alternative Source Term Response to Request for Additional Information Regarding the Turbine Building Ventilation and Leakage Treatment Piping Seismic Evaluations2007-12-11011 December 2007 Request to Implement an Alternative Source Term Response to Request for Additional Information Regarding the Turbine Building Ventilation and Leakage Treatment Piping Seismic Evaluations Project stage: Response to RAI ML0800702622008-01-0909 January 2008 (Hnp), Request for Additional Information (RAI) Regarding Alternate Source Term Application Tac Nos. MD2934 and MD2935) Project stage: RAI ML0801100512008-01-30030 January 2008 Discussion of Review Schedule Regarding Alternate Source Term Application Project stage: Other NL-08-0035, Request to Implement an Alternative Source Term Response to Request for Additional Information Regarding the Unit 1 Main Steam Isolation Valve Alternate Leakage Treatment Seismic Evaluation2008-02-0404 February 2008 Request to Implement an Alternative Source Term Response to Request for Additional Information Regarding the Unit 1 Main Steam Isolation Valve Alternate Leakage Treatment Seismic Evaluation Project stage: Response to RAI ML0803801412008-02-13013 February 2008 E.I Hatch Nuclear Plant, Units 1 and 2 (Hnp), RAI Regarding Alternate Source Term Application Project stage: RAI NL-07-1389, Request to Implement an Alternative Source Term Response to Request for Additional Information Regarding the Radiological Consequences Analyses2008-02-25025 February 2008 Request to Implement an Alternative Source Term Response to Request for Additional Information Regarding the Radiological Consequences Analyses Project stage: Response to RAI NL-07-1532, Request to Implement an Alternative Source Term Response to Request for Additional Information Regarding the Turbine Building Ventilation and Standby Liquid Control Systems2008-02-27027 February 2008 Request to Implement an Alternative Source Term Response to Request for Additional Information Regarding the Turbine Building Ventilation and Standby Liquid Control Systems Project stage: Response to RAI NL-08-0351, Request to Implement an Alternative Source Term Response to Request for Additional Information Regarding the Power Sources for the Turbine Building Ventilation System2008-03-13013 March 2008 Request to Implement an Alternative Source Term Response to Request for Additional Information Regarding the Power Sources for the Turbine Building Ventilation System Project stage: Response to RAI NL-08-0524, Request to Implement an Alternative Source Term Response to Request for Additional Information Regarding Atmospheric Dispersion Factors2008-04-0101 April 2008 Request to Implement an Alternative Source Term Response to Request for Additional Information Regarding Atmospheric Dispersion Factors Project stage: Response to RAI NL-08-0634, Request to Implement an Alternative Source Term Response to Request for Additional Information Regarding the Radiological Consequences Analyses2008-05-0505 May 2008 Request to Implement an Alternative Source Term Response to Request for Additional Information Regarding the Radiological Consequences Analyses Project stage: Response to RAI ML0814201722008-05-30030 May 2008 Request for Additional Information Regarding Alternative Source Term Application Project stage: RAI NL-08-0903, Request to Implement an Alternative Source Term Response to Request for Additional Information Regarding the Turbine Building Ventilation Exhaust System Fans2008-06-25025 June 2008 Request to Implement an Alternative Source Term Response to Request for Additional Information Regarding the Turbine Building Ventilation Exhaust System Fans Project stage: Response to RAI NL-08-1022, Request to Revise the Unit 1 and Unit 2 Operating Licenses to Extend the Interim Period for the Use of Potassium Iodide2008-07-0202 July 2008 Request to Revise the Unit 1 and Unit 2 Operating Licenses to Extend the Interim Period for the Use of Potassium Iodide Project stage: Request ML0819001752008-07-0909 July 2008 Request for Additional Information, Alternate Source Term Application Project stage: RAI ML0819003312008-07-14014 July 2008 Transmittal of Notice of Consideration of Issuance of Amendments for Alternate Source Term Application Project stage: Other ML0819003382008-07-14014 July 2008 Notice of Consideration of Issuance of Amendments for Alternate Source Term Application Project stage: Other ML0819703922008-07-14014 July 2008 Transmittal of Responses to Request for Additional Information Addition of License Conditions to Operating Licenses for Request to Implement an Alternative Source Term Project stage: Response to RAI NL-08-1269, Request to Implement an Alternative Source Term Response to Requests for Additional Information Regarding Turbine Building Ventilation Exhaust Systems and Operating License Changes2008-08-14014 August 2008 Request to Implement an Alternative Source Term Response to Requests for Additional Information Regarding Turbine Building Ventilation Exhaust Systems and Operating License Changes Project stage: Response to RAI ML0817700752008-08-28028 August 2008 Issuance of Amendment Nos. 256 and 200, Alternate Source Term Project stage: Approval ML0819600452008-08-28028 August 2008 Tech Spec Pages for Amendment Nos. 256 and 200, Alternate Source Term Project stage: Other 2008-01-30
[Table View] |
Similar Documents at Hatch |
|---|
|
Text
May 30, 2008 Mr. Dennis R. Madison Vice President - Hatch Edwin I. Hatch Nuclear Plant 11028 Hatch Parkway North Baxley, GA 31513
SUBJECT:
EDWIN I. HATCH NUCLEAR PLANT, UNIT NOS. 1 AND 2, REQUEST FOR ADDITIONAL INFORMATION REGARDING ALTERNATE SOURCE TERM APPLICATION (TAC NOS. MD2934 AND MD2935)
Dear Mr. Madison:
By letter to the U.S. Nuclear Regulatory Commission (NRC) dated August 29, 2006, Southern Nuclear Operating Company, Inc. (SNC, the licensee), proposed to revise the Edwin I. Hatch Nuclear Plant, Units 1 and 2 licensing and design-basis with a full scope implementation of an alternative source term. The NRC staff reviewed SNCs letter dated February 27, 2008 and identified a need for additional information as set forth in the Enclosure.
The NRC staff discussed the above-referenced issue with SNCs staff on May 29, 2008. In consideration of the previous correspondence on this issue, and the schedular issues as addressed in the NRC staffs letter of January 30, 2008, we are requesting that SNC provide a response to this letter within fifteen (15) days, if possible, but no later than thirty (30) days of receipt of this letter.
Sincerely,
/RA/
Robert E. Martin, Senior Project Manager Plant Licensing Branch II-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos. 50-321 and 50-366
Enclosure:
Request for Additional Information cc w/encl: See next page
ML081420172 OFFICE NRR/LPL2-1/PM NRR/LPL2-1/LA NRR/SCVB/BC NRR/ITSB/BC NRR/LPL2-1/BC NAME RMartin:nc GLappert RDennig RElliot MWong DATE 05/ 29 /08 05/30 /08 05/28/08 05/30 /08 05/ 30 /08
Enclosure REQUEST FOR ADDITIONAL INFORMATION BY THE OFFICE OF NUCLEAR REACTOR REGULATION EDWIN I. HATCH NUCLEAR PLANT, UNIT NOS. 1 AND 2 SOUTHERN NUCLEAR OPERATING COMPANY, INC.
DOCKET NOS. 50-321 AND 50-366 OPERATING LICENSE NOS. DPR-57 AND NPF-5 In a request for additional information dated April 26, 2007, concerning the implementation of an Alternative Source Term application; the U.S. Nuclear Regulatory Commission (NRC) staff asked whether Southern Nuclear Operating Company, Inc. (SNC) considered adding a Limiting Condition for Operation (LCO) to the Technical Specifications (TS) for the turbine building ventilation system (TBVS), including surveillance requirements (SR). SNCs reply dated February 27, 2008, stated that:
SNC intends to add the TB HVAC exhaust systems to the scope of the HNP Maintenance Rule program, in accordance with 10 CFR 50.65, and to the scope of license renewal, in accordance with 10 CFR 54.37(b). and After due consideration, SNC has concluded that the addition to HNP TS of a LCO, including surveillance requirements, to assure the lowest functional capability or performance levels, as stated in 10 CFR 50.36 titled Technical Specifications, is not warranted for the new credited function of the TB HVAC exhaust systems. Contrary to the vast majority of safety functions in the TS, the capability to perform the Alternative Source Term credited function of purging the turbine building is demonstrated continuously during Edwin I. Hatch Nuclear Plant operation.
As discussed with SNC staff on May 29, 2008, the NRC staff requests that SNC provide a detailed evaluation of whether the TBVS is equipment required for safe operation of the facility as required by 10 CFR 50.36(d)(2)(ii)( C), Criterion 3, A structure, system or component that is part of the primary success path and which functions or actuates to mitigate a design-basis accident or transient that either assumes the failure of or presents a challenge to the integrity of a fission product barrier, or 10 CFR 50.36(d)(2)(ii)(D), Criterion 4, A structure system, or component which operating experience or probabilistic risk assessment has shown to be significant to public health and safety and therefore requires a limiting condition for operation.
The NRC staff may pursue, in the future as needed, further details on the addition of the TB HVAC exhaust systems to the scope of the HNP Maintenance Rule program.
Edwin I. Hatch Nuclear Plant, Units 1 & 2 cc:
Laurence Bergen Oglethorpe Power Corporation 2100 E. Exchange Place P.O. Box 1349 Tucker, GA 30085-1349 Mr. R. D. Baker Manager - Licensing Southern Nuclear Operating Company, Inc.
P.O. Box 1295 Birmingham, AL 35201-1295 Resident Inspector Plant Hatch 11030 Hatch Parkway N.
Baxley, GA 31531 Harold Reheis, Director Department of Natural Resources 205 Butler Street, SE., Suite 1252 Atlanta, GA 30334 Steven M. Jackson Senior Engineer - Power Supply Municipal Electric Authority of Georgia 1470 Riveredge Parkway, NW Atlanta, GA 30328-4684 Mr. Reece McAlister Executive Secretary Georgia Public Service Commission 244 Washington St., SW Atlanta, GA 30334 Arthur H. Domby, Esq.
Troutman Sanders Nations Bank Plaza 600 Peachtree St, NE, Suite 5200 Atlanta, GA 30308-2216 Chairman Appling County Commissioners County Courthouse Baxley, GA 31513 Mr. Jeffrey T. Gasser Executive Vice President Southern Nuclear Operating Company, Inc.
P.O. Box 1295 Birmingham, AL 35201-1295 General Manager Edwin I. Hatch Nuclear Plant Southern Nuclear Operating Company, Inc.
U.S. Highway 1 North P.O. Box 2010 Baxley, GA 31515 Mr. K. Rosanski Resident Manager Oglethorpe Power Corporation Edwin I. Hatch Nuclear Plant P.O. Box 2010 Baxley, GA 31515