Letter Sequence Other |
|---|
|
|
MONTHYEARML0624902422006-08-29029 August 2006 Enclosure 1, E. I. Hatch Request to Implement an Alternative Source Term - AST Safety Assessment Project stage: Request ML0630700372006-11-14014 November 2006 Edwin I Hatch, Nuclear Plant Unit No. 1 & 2, Request for Additional Information for Alternate Source Term Review (TAC Nos. MD2934 & MD2935) Project stage: RAI ML0632800652006-11-14014 November 2006 Meeting Summary Handouts, Enclosure 2 (Tac Nos. MD2934 and MD2935) Project stage: Meeting ML0632401972006-12-11011 December 2006 Summary of November 14, 2006, Meeting with Southern Nuclear Operating Co., on Alternative Source Term Submittal Project stage: Meeting ML0704602852007-02-22022 February 2007 Request for Additional Information Regarding Alternate Source Term Application Project stage: RAI ML0706502982007-03-15015 March 2007 Edwin I Hatch Nuclear Plant, Units 1 and 2 (HNP) - Request for Additional Information Alternative Source Term Application Project stage: RAI ML0708902972007-04-10010 April 2007 RAI Regarding Alternative Source Term Application Project stage: RAI ML0710900392007-04-26026 April 2007 Request for Additional Information Alternate Source Term Application Project stage: RAI ML0710900572007-05-0808 May 2007 Request for Additional Information Alternate Source Term Application Project stage: RAI ML0712801262007-05-30030 May 2007 Request for Additional Information the Revision of the Licensing and Design Basis with a Full Scope Implementation of an Alternative Source Term Project stage: RAI NL-07-1308, Request to Implement an Alternative Source Term Response to Request for Additional Information Regarding the Unit 1 Main Steam Isolation Valve Alternate Leakage Treatment Path Seismic Evaluation2007-07-16016 July 2007 Request to Implement an Alternative Source Term Response to Request for Additional Information Regarding the Unit 1 Main Steam Isolation Valve Alternate Leakage Treatment Path Seismic Evaluation Project stage: Response to RAI ML0721904682007-08-16016 August 2007 Nos. Units 1 and 2, (Hnp), RAI, Request for Additional Information Regarding Alternate Source Term Application Project stage: RAI ML0726806972007-10-0303 October 2007 Request for Additional Information Regarding Alternate Source Term Application Project stage: RAI NL-07-0894, Request to Implement an Alternative Source Term Response to Request for Additional Information Regarding the Power Sources for the Turbine Building Ventilation System2007-10-18018 October 2007 Request to Implement an Alternative Source Term Response to Request for Additional Information Regarding the Power Sources for the Turbine Building Ventilation System Project stage: Response to RAI NL-07-1949, Request to Implement an Alternative Source Term Response to Request for Additional Information Regarding the Turbine Building Ventilation and Leakage Treatment Piping Seismic Evaluations2007-12-11011 December 2007 Request to Implement an Alternative Source Term Response to Request for Additional Information Regarding the Turbine Building Ventilation and Leakage Treatment Piping Seismic Evaluations Project stage: Response to RAI ML0800702622008-01-0909 January 2008 (Hnp), Request for Additional Information (RAI) Regarding Alternate Source Term Application Tac Nos. MD2934 and MD2935) Project stage: RAI ML0801100512008-01-30030 January 2008 Discussion of Review Schedule Regarding Alternate Source Term Application Project stage: Other NL-08-0035, Request to Implement an Alternative Source Term Response to Request for Additional Information Regarding the Unit 1 Main Steam Isolation Valve Alternate Leakage Treatment Seismic Evaluation2008-02-0404 February 2008 Request to Implement an Alternative Source Term Response to Request for Additional Information Regarding the Unit 1 Main Steam Isolation Valve Alternate Leakage Treatment Seismic Evaluation Project stage: Response to RAI ML0803801412008-02-13013 February 2008 E.I Hatch Nuclear Plant, Units 1 and 2 (Hnp), RAI Regarding Alternate Source Term Application Project stage: RAI NL-07-1389, Request to Implement an Alternative Source Term Response to Request for Additional Information Regarding the Radiological Consequences Analyses2008-02-25025 February 2008 Request to Implement an Alternative Source Term Response to Request for Additional Information Regarding the Radiological Consequences Analyses Project stage: Response to RAI NL-07-1532, Request to Implement an Alternative Source Term Response to Request for Additional Information Regarding the Turbine Building Ventilation and Standby Liquid Control Systems2008-02-27027 February 2008 Request to Implement an Alternative Source Term Response to Request for Additional Information Regarding the Turbine Building Ventilation and Standby Liquid Control Systems Project stage: Response to RAI NL-08-0351, Request to Implement an Alternative Source Term Response to Request for Additional Information Regarding the Power Sources for the Turbine Building Ventilation System2008-03-13013 March 2008 Request to Implement an Alternative Source Term Response to Request for Additional Information Regarding the Power Sources for the Turbine Building Ventilation System Project stage: Response to RAI NL-08-0524, Request to Implement an Alternative Source Term Response to Request for Additional Information Regarding Atmospheric Dispersion Factors2008-04-0101 April 2008 Request to Implement an Alternative Source Term Response to Request for Additional Information Regarding Atmospheric Dispersion Factors Project stage: Response to RAI NL-08-0634, Request to Implement an Alternative Source Term Response to Request for Additional Information Regarding the Radiological Consequences Analyses2008-05-0505 May 2008 Request to Implement an Alternative Source Term Response to Request for Additional Information Regarding the Radiological Consequences Analyses Project stage: Response to RAI ML0814201722008-05-30030 May 2008 Request for Additional Information Regarding Alternative Source Term Application Project stage: RAI NL-08-0903, Request to Implement an Alternative Source Term Response to Request for Additional Information Regarding the Turbine Building Ventilation Exhaust System Fans2008-06-25025 June 2008 Request to Implement an Alternative Source Term Response to Request for Additional Information Regarding the Turbine Building Ventilation Exhaust System Fans Project stage: Response to RAI NL-08-1022, Request to Revise the Unit 1 and Unit 2 Operating Licenses to Extend the Interim Period for the Use of Potassium Iodide2008-07-0202 July 2008 Request to Revise the Unit 1 and Unit 2 Operating Licenses to Extend the Interim Period for the Use of Potassium Iodide Project stage: Request ML0819001752008-07-0909 July 2008 Request for Additional Information, Alternate Source Term Application Project stage: RAI ML0819003312008-07-14014 July 2008 Transmittal of Notice of Consideration of Issuance of Amendments for Alternate Source Term Application Project stage: Other ML0819003382008-07-14014 July 2008 Notice of Consideration of Issuance of Amendments for Alternate Source Term Application Project stage: Other ML0819703922008-07-14014 July 2008 Transmittal of Responses to Request for Additional Information Addition of License Conditions to Operating Licenses for Request to Implement an Alternative Source Term Project stage: Response to RAI NL-08-1269, Request to Implement an Alternative Source Term Response to Requests for Additional Information Regarding Turbine Building Ventilation Exhaust Systems and Operating License Changes2008-08-14014 August 2008 Request to Implement an Alternative Source Term Response to Requests for Additional Information Regarding Turbine Building Ventilation Exhaust Systems and Operating License Changes Project stage: Response to RAI ML0817700752008-08-28028 August 2008 Issuance of Amendment Nos. 256 and 200, Alternate Source Term Project stage: Approval ML0819600452008-08-28028 August 2008 Tech Spec Pages for Amendment Nos. 256 and 200, Alternate Source Term Project stage: Other 2008-01-30
[Table View] |
Similar Documents at Hatch |
|---|
|
Text
July 14, 2008 Mr. Dennis R. Madison Vice President - Hatch Edwin I. Hatch Nuclear Plant 11028 Hatch Parkway North Baxley, GA 31513
SUBJECT:
EDWIN I. HATCH NUCLEAR PLANT, UNIT NOS. 1 AND 2, REGARDING NOTICE OF CONSIDERATION OF ISSUANCE OF AMENDMENTS FOR ALTERNATE SOURCE TERM APPLICATION (TAC NOS. MD2934 AND MD2935)
Dear Mr. Madison:
The U.S. Nuclear Regulatory Commission (NRC) has forwarded the enclosed Notice of Consideration of Issuance of Amendments to Facility Operating Licenses, Proposed No Significant Hazards Consideration Determination, and Opportunity for a Hearing to the Office of the Federal Register for publication.
This notice relates to your application dated August 29, 2006, as supplemented on November 6, November 27, 2006, January 30, June 22, July 16, August 13, October 18, December 11, 2007, January 24, February 4, February 25 (two letters, nos. 1389 and 0175), February 27, March 13, April 1, May 5, June 25, July 2, and July 14, 2008. The proposed amendment would approve a revised licensing and design basis for analysis of certain design basis accidents and would extend the required dates for implementation of such revised licensing and design basis by modifying license condition 2.C of the Edwin I. Hatch Nuclear Plant, Unit Nos. 1 and 2, Operating Licenses.
Sincerely,
/RA/
Robert E. Martin, Senior Project Manager Plant Licensing Branch II-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos. 50-321 and 50-366
Enclosure:
Federal Register Notice cc w/encl: See next page
July 14, 2008 Mr. Dennis R. Madison Vice President - Hatch Edwin I. Hatch Nuclear Plant 11028 Hatch Parkway North Baxley, GA 31513
SUBJECT:
EDWIN I. HATCH NUCLEAR PLANT, UNIT NOS. 1 AND 2, REGARDING NOTICE OF CONSIDERATION OF ISSUANCE OF AMENDMENTS FOR ALTERNATE SOURCE TERM APPLICATION (TAC NOS. MD2934 AND MD2935)
Dear Mr. Madison:
The U.S. Nuclear Regulatory Commission (NRC) has forwarded the enclosed Notice of Consideration of Issuance of Amendments to Facility Operating Licenses, Proposed No Significant Hazards Consideration Determination, and Opportunity for a Hearing to the Office of the Federal Register for publication.
This notice relates to your application dated August 29, 2006, as supplemented as November 6, November 27, 2006, January 30, June 22, July 16, August 13, October 18, December 11, 2007, January 24, February 4, February 25 (two letters, nos. 1389 and 0175), February 27, March 13, April 1, May 5,June 25, July 2, and July 14, 2008. The proposed amendment would approve a revised licensing and design basis for analysis of certain design basis accidents and would extend the required dates for implementation of such revised licensing and design basis by modifying license condition 2.C of the Edwin I. Hatch Nuclear Plant, Unit Nos. 1 and 2, Operating Licenses.
Sincerely,
/RA/
Robert E. Martin, Senior Project Manager Plant Licensing Branch II-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos. 50-321 and 50-366
Enclosure:
Federal Register Notice cc w/encl: See next page DISTRIBUTION:
PUBLIC RidsNrrLAGLappertResource RidsRgn2MailCenterResource LPL2-1 R/F RidsNrrDorlLpl2-1Resource RidsAcrsAcnw_MailCenterResource RidsNrrPMRMartinResource RidsOgcRpResource ADAMS Accession Package No. ML081900321 Letter No. ML081900331 Notice No. ML081900338 OFFICE NRR/LPL2-1/PM NRR/LPL2-1/LA NRR/LPL2-1/BC NAME RMartin:
GLappert MWong DATE 07/ 14 /08 07/ 14 /08 07/ 14 /08 OFFICIAL RECORD COPY
Edwin I. Hatch Nuclear Plant, Units 1 & 2 cc:
Laurence Bergen Oglethorpe Power Corporation 2100 E. Exchange Place P.O. Box 1349 Tucker, GA 30085-1349 Mr. R. D. Baker Manager - Licensing Southern Nuclear Operating Company, Inc.
P.O. Box 1295 Birmingham, AL 35201-1295 Resident Inspector Plant Hatch 11030 Hatch Parkway N.
Baxley, GA 31531 Harold Reheis, Director Department of Natural Resources 205 Butler Street, SE., Suite 1252 Atlanta, GA 30334 Steven M. Jackson Senior Engineer - Power Supply Municipal Electric Authority of Georgia 1470 Riveredge Parkway, NW Atlanta, GA 30328-4684 Mr. Reece McAlister Executive Secretary Georgia Public Service Commission 244 Washington St., SW Atlanta, GA 30334 Arthur H. Domby, Esq.
Troutman Sanders Nations Bank Plaza 600 Peachtree St, NE, Suite 5200 Atlanta, GA 30308-2216 Chairman Appling County Commissioners County Courthouse Baxley, GA 31513 Mr. Jeffrey T. Gasser Executive Vice President Southern Nuclear Operating Company, Inc.
P.O. Box 1295 Birmingham, AL 35201-1295 General Manager Edwin I. Hatch Nuclear Plant Southern Nuclear Operating Company, Inc.
U.S. Highway 1 North P.O. Box 2010 Baxley, GA 31515 Mr. K. Rosanski Resident Manager Oglethorpe Power Corporation Edwin I. Hatch Nuclear Plant P.O. Box 2010 Baxley, GA 31515