MONTHYEARML0810800382008-04-0808 April 2008 Request for Extension of 3-Month Response to Generic Letter 2008-01, Managing Gas Accumulation in Emergency Core Cooling, Decay Heat Removal, and Containment Spray Systems Project stage: Request ML0813403102008-05-0909 May 2008 Three Month Response to NRC Generic Letter 08-001, Managing Gas Accumulation in Emergency Core Cooling, Decay Heat Removal, and Containment Spry Systems Project stage: Request ML0813604972008-05-0909 May 2008 Three Month Response to NRC Generic Letter 2008-01, Managing Gas Accumulation in Emergency Core Cooling, Decay Heat Removal, and Containment Spray Systems Project stage: Request ML0813100152008-05-22022 May 2008 Response to Extension Request for Generic Letter 2008-01, Managing Gas Accumulation in Emergency Core Cooling, Decay Heat Removal, and Containment Spray Systems Project stage: Other ML0821406132008-07-25025 July 2008 Committed Actions Related to NRC Generic Letter 2008-01, Managing Gas Accumulation in Emergency Core Cooling, Decay Heat Removal, and Containment Spray Systems Project stage: Request ML0821104232008-08-0808 August 2008 Generic Letter 2008-01, Managing Gas Accumulation in Emergency Core Cooling, Decay Heat Removal, and Containment Spray Systems, Proposed Alternative Course of Action Project stage: Other ML0821100032008-08-12012 August 2008 Generic Letter 2008-01, Managing Gas Accumulation in Emergency Core Cooling, Decay Heat Removal, and Containment Spray Systems, Proposed Alternative Course of Action Project stage: Other ML0816907182008-09-25025 September 2008 Generic Letter 2008-01, Managing Gas Accumulation in Emergency Core Cooling, Decay Heat Removal, and Containment Spray Systems, Proposed Alternative Course of Action Project stage: Other ML0816505982008-09-25025 September 2008 Generic Letter 2008-01, Managing Gas Accumulation in Emergency Core Cooling, Decay Heat Removal, and Containment Spray Systems, Proposed Alternative Course of Action Project stage: Other 3F1008-05, Nine Month Response to NRC Generic Letter 2008-01, Managing Gas Accumulation in Emergency Core Cooling Decay Heat Removal, and Containment Spray Systems2008-10-13013 October 2008 Nine Month Response to NRC Generic Letter 2008-01, Managing Gas Accumulation in Emergency Core Cooling Decay Heat Removal, and Containment Spray Systems Project stage: Other BSEP 09-0079, Post-Outage Supplemental Response to Generic Letter 2008-01, Managing Gas Accumulation in Emergency Core Cooling, Decay Heat Removal, and Containment Spray Systems2009-07-27027 July 2009 Post-Outage Supplemental Response to Generic Letter 2008-01, Managing Gas Accumulation in Emergency Core Cooling, Decay Heat Removal, and Containment Spray Systems Project stage: Request ML0922502262009-08-10010 August 2009 Nine-Month Supplemental (Post-Outage) Response to NRC Generic Letter 2008-01, Managing Gas Accumulation in Emergency Core Cooling, Decay Heat Removal, and Containment Spray Systems Project stage: Request ML0930804442009-11-10010 November 2009 RAI, Response to Generic Letter 2008-01, Managing Gas Accumulation in Emergency Core Cooling, Decay Heat Removal and Containment Spray Systems Project stage: RAI ML0933604572009-12-10010 December 2009 Request for Additional Information Regarding the Response to Generic Letter 2008-01, Managing Gas Accumulation in Emergency Core Cooling, Decay Heat Removal, and Containment Spray Systems Project stage: RAI ML0935100912009-12-18018 December 2009 Request for Additional Information Related to Generic Letter 2008-01, Managing Gas Accumulation in Emergency Core Cooling, Decay Heat Removal, and Containment Spray Systems Project stage: RAI BSEP 09-0130, Response to Request for Additional Information Regarding Generic Letter 2008-01 (NRC TAC Nos. MD7802 and MD7803)2009-12-21021 December 2009 Response to Request for Additional Information Regarding Generic Letter 2008-01 (NRC TAC Nos. MD7802 and MD7803) Project stage: Response to RAI ML1001400842010-01-19019 January 2010 Request for Additional Information Regarding Supplemental Response to Generic Letter 2008-01, Managing Gas Accumulation in Emergency Core Cooling, Decay Heat Removal, and Containment Spray Systems Project stage: RAI 3F0110-11, Crystal Rive, Unit 3 - Submittal of Response to Generic Letter 2008-01, Managing Gas Accumulation in Emergency Core Cooling, Decay Heat Removal and Containment Spray Systems, Response to a Request for Additional Information2010-01-25025 January 2010 Crystal Rive, Unit 3 - Submittal of Response to Generic Letter 2008-01, Managing Gas Accumulation in Emergency Core Cooling, Decay Heat Removal and Containment Spray Systems, Response to a Request for Additional Information Project stage: Response to RAI ML1004304442010-01-28028 January 2010 Response to Request for Additional Information Related to Generic Ltr. 2008-01, Managing Gas Accumulation in Emergency Core Cooling, Decay Heat Removal, and Containment Spray Systems Project stage: Response to RAI HNP-10-016, Response to Request for Additional Information Related to Generic Ltr. 2008-01, Managing Gas Accumulation in Emergency Core Cooling, Decay Heat Removal, and Containment Spray Systems.2010-01-28028 January 2010 Response to Request for Additional Information Related to Generic Ltr. 2008-01, Managing Gas Accumulation in Emergency Core Cooling, Decay Heat Removal, and Containment Spray Systems. Project stage: Response to RAI BSEP 10-0089, Post-Outage Supplemental Response to Generic Letter 2008-01, Managing Gas Accumulation in Emergency Core Cooling Decay Heat Removal, and Containment Spray Systems2010-07-22022 July 2010 Post-Outage Supplemental Response to Generic Letter 2008-01, Managing Gas Accumulation in Emergency Core Cooling Decay Heat Removal, and Containment Spray Systems Project stage: Supplement 3F1010-04, Nine-Month Supplemental (Post-Outage) Response to NRC Generic Letter 2008-012010-10-0808 October 2010 Nine-Month Supplemental (Post-Outage) Response to NRC Generic Letter 2008-01 Project stage: Supplement ML11174A1422011-06-24024 June 2011 Closure Letter for the Licensees Response to Generic Letter 200-01 Managing Gas Accumulation in Emergency Core Cooling, Decay Heat Removal and Containment Spray Systems Project stage: Other ML11143A1392011-06-24024 June 2011 Closure Letter for the Licensees Response to Generic Letter 2008-01, Managing Accumulation in Emergency Core Cooling, Decay Heat Removal and Containment Spray Systems Project stage: Other ML11174A1432011-06-24024 June 2011 Closure Letter for the Licensees Response to Generic Letter 2008-01, Managing Accumulation in Emergency Core Cooling, Decay Heat Removal and Containment Spray Systems Project stage: Other ML1008900252011-06-24024 June 2011 Closure Letter for the Licensees Response to Generic Letter 2008-01, Managing Accumulation in Emergency Core Cooling, Decay Heat Removal and Containment Spray Systems Project stage: Other 2009-12-10
[Table View] |
Text
10 CFR 50.4 PO Box 1551 411 Fayetteville Street Mall Raleigh NC 27602 Serial: PE&RAS-08-025 April 8, 2008 United States Nuclear Regulatory Commission ATTENTION: Document Control Desk Washington, DC 20555-0001 BRUNSWICK STEAM ELECTRIC PLANT, UNIT NOS. 1 AND 2 DOCKET NOS. 50-325 AND 50-324 / LICENSE NOS. DPR-71 AND DPR-62 SHEARON HARRIS NUCLEAR POWER PLANT, UNIT NO. 1 DOCKET NO. 50-400 / LICENSE NO. NPF-63 H. B. ROBINSON STEAM ELECTRIC PLANT, UNIT NO. 2 DOCKET NO. 50-261 / LICENSE NO. DPR-23 CRYSTAL RIVER UNIT 3 NUCLEAR GENERATING PLANT DOCKET NO. 50-302 / LICENSE NO. DPR-72
Subject:
Request for Extension of 3-Month Response to Generic Letter 2008-01, "Managing Gas Accumulation in Emergency Core Cooling, Decay Heat Removal, and Containment Spray Systems"
Reference:
NRC Generic Letter 2008-01, "Managing Gas Accumulation in Emergency Core Cooling, Decay Heat Removal, and Containment Spray Systems," dated January 11, 2008 Ladies and Gentlemen:
This letter is provided to document the April 3, 2008, telephone conversation between Jared Wermiel (Deputy Director, Division of Safety Systems, NRR) of the NRC staff and Brian McCabe (Manager, Nuclear Regulatory Affairs, Progress Energy) representing Carolina Power & Light Company, now doing business as Progress Energy Carolinas, Inc., and Florida Power Corporation, now doing business as Progress Energy Florida, Inc. During the telephone conversation, Progress Energy requested a 30-day extension to the referenced Generic Letter 3-month response and the staff agreed to that extension for Brunswick Steam Electric Plant, Unit Nos. 1 and 2; Shearon Harris Nuclear Power Plant, Unit No. 1; H. B.
Robinson Steam Electric Plant, Unit No. 2; and Crystal River Unit 3 Nuclear Generating Plant. It is expected that Progress Energy will submit the required response letters no later than May 9, 2008.
ALM(
United States Nuclear Regulatory Commission PE&RAS-08-025 Page 2 No new commitments have been made in this submittal. If you have additional questions, please call me at (919) 546-6901.
Sincerely, J.aul Fulford anager - Performarn e
Evaluation & Regulatory Affairs DMF c:
Jared Wermiel, Deputy Director, Division of Safety Systems - NRR Victor McCree, USNRC Regional Administrator - Region II F. Saba, NRR Project Manager - BSEP, Unit Nos. 1 and 2; CR3 M. Vaaler, NRR Project Manager - SHNPP, Unit No. 1; HBRSEP, Unit No. 2 USNRC Resident Inspector - BSEP, Unit Nos. 1 and 2 USNRC Resident Inspector - CR3 USNRC Resident Inspector - SHNPP, Unit No. 1 USNRC Resident Inspector - HBRSEP, Unit No. 2