Letter Sequence Request |
---|
|
|
MONTHYEARML0810800382008-04-0808 April 2008 Brunswick, Shearon Harris, H.B. Robinson, Crystal River, Request for Extension of 3-Month Response to Generic Letter 2008-01, Managing Gas Accumulation in Emergency Core Cooling, Decay Heat Removal, and Containment Spray Systems. Project stage: Request RNP-RA/08-0014, Three Month Response to NRC Generic Letter 08-001, Managing Gas Accumulation in Emergency Core Cooling, Decay Heat Removal, and Containment Spry Systems2008-05-0909 May 2008 Three Month Response to NRC Generic Letter 08-001, Managing Gas Accumulation in Emergency Core Cooling, Decay Heat Removal, and Containment Spry Systems Project stage: Request HNP-08-047, Three Month Response to NRC Generic Letter 2008-01, Managing Gas Accumulation in Emergency Core Cooling, Decay Heat Removal, and Containment Spray Systems.2008-05-0909 May 2008 Three Month Response to NRC Generic Letter 2008-01, Managing Gas Accumulation in Emergency Core Cooling, Decay Heat Removal, and Containment Spray Systems. Project stage: Request ML0813100152008-05-22022 May 2008 Response to Extension Request for Generic Letter 2008-01, Managing Gas Accumulation in Emergency Core Cooling, Decay Heat Removal, and Containment Spray Systems Project stage: Other RNP-RA/08-0071, Committed Actions Related to NRC Generic Letter 2008-01, Managing Gas Accumulation in Emergency Core Cooling, Decay Heat Removal, and Containment Spray Systems.2008-07-25025 July 2008 Committed Actions Related to NRC Generic Letter 2008-01, Managing Gas Accumulation in Emergency Core Cooling, Decay Heat Removal, and Containment Spray Systems. Project stage: Request ML0821104232008-08-0808 August 2008 Generic Letter 2008-01, Managing Gas Accumulation in Emergency Core Cooling, Decay Heat Removal, and Containment Spray Systems, Proposed Alternative Course of Action Project stage: Other ML0821100032008-08-12012 August 2008 Generic Letter 2008-01, Managing Gas Accumulation in Emergency Core Cooling, Decay Heat Removal, and Containment Spray Systems, Proposed Alternative Course of Action Project stage: Other ML0816505982008-09-25025 September 2008 Generic Letter 2008-01, Managing Gas Accumulation in Emergency Core Cooling, Decay Heat Removal, and Containment Spray Systems, Proposed Alternative Course of Action Project stage: Other 3F1008-05, Nine Month Response to NRC Generic Letter 2008-01, Managing Gas Accumulation in Emergency Core Cooling Decay Heat Removal, and Containment Spray Systems.2008-10-13013 October 2008 Nine Month Response to NRC Generic Letter 2008-01, Managing Gas Accumulation in Emergency Core Cooling Decay Heat Removal, and Containment Spray Systems. Project stage: Other BSEP 09-0079, Post-Outage Supplemental Response to Generic Letter 2008-01, Managing Gas Accumulation in Emergency Core Cooling, Decay Heat Removal, and Containment Spray Systems2009-07-27027 July 2009 Post-Outage Supplemental Response to Generic Letter 2008-01, Managing Gas Accumulation in Emergency Core Cooling, Decay Heat Removal, and Containment Spray Systems Project stage: Request HNP-09-079, Nine-Month Supplemental (Post-Outage) Response to NRC Generic Letter 2008-01, Managing Gas Accumulation in Emergency Core Cooling, Decay Heat Removal, and Containment Spray Systems2009-08-10010 August 2009 Nine-Month Supplemental (Post-Outage) Response to NRC Generic Letter 2008-01, Managing Gas Accumulation in Emergency Core Cooling, Decay Heat Removal, and Containment Spray Systems Project stage: Request ML0935100912009-12-18018 December 2009 Request for Additional Information Related to Generic Letter 2008-01, Managing Gas Accumulation in Emergency Core Cooling, Decay Heat Removal, and Containment Spray Systems Project stage: RAI BSEP 09-0130, Response to Request for Additional Information Regarding Generic Letter 2008-01 (NRC TAC Nos. MD7802 and MD7803)2009-12-21021 December 2009 Response to Request for Additional Information Regarding Generic Letter 2008-01 (NRC TAC Nos. MD7802 and MD7803) Project stage: Response to RAI ML1001400842010-01-19019 January 2010 Request for Additional Information Regarding Supplemental Response to Generic Letter 2008-01, Managing Gas Accumulation in Emergency Core Cooling, Decay Heat Removal, and Containment Spray Systems Project stage: RAI 3F0110-11, Crystal Rive, Unit 3 - Submittal of Response to Generic Letter 2008-01, Managing Gas Accumulation in Emergency Core Cooling, Decay Heat Removal and Containment Spray Systems, Response to a Request for Additional Information2010-01-25025 January 2010 Crystal Rive, Unit 3 - Submittal of Response to Generic Letter 2008-01, Managing Gas Accumulation in Emergency Core Cooling, Decay Heat Removal and Containment Spray Systems, Response to a Request for Additional Information Project stage: Response to RAI HNP-10-016, Response to Request for Additional Information Related to Generic Ltr. 2008-01, Managing Gas Accumulation in Emergency Core Cooling, Decay Heat Removal, and Containment Spray Systems.2010-01-28028 January 2010 Response to Request for Additional Information Related to Generic Ltr. 2008-01, Managing Gas Accumulation in Emergency Core Cooling, Decay Heat Removal, and Containment Spray Systems. Project stage: Response to RAI BSEP 10-0089, Post-Outage Supplemental Response to Generic Letter 2008-01, Managing Gas Accumulation in Emergency Core Cooling Decay Heat Removal, and Containment Spray Systems2010-07-22022 July 2010 Post-Outage Supplemental Response to Generic Letter 2008-01, Managing Gas Accumulation in Emergency Core Cooling Decay Heat Removal, and Containment Spray Systems Project stage: Supplement 3F1010-04, Nine-Month Supplemental (Post-Outage) Response to NRC Generic Letter 2008-012010-10-0808 October 2010 Nine-Month Supplemental (Post-Outage) Response to NRC Generic Letter 2008-01 Project stage: Supplement ML11174A1422011-06-24024 June 2011 Closure Letter for the Licensee'S Response to Generic Letter 200-01 Managing Gas Accumulation in Emergency Core Cooling, Decay Heat Removal and Containment Spray Systems. Project stage: Other ML11174A1432011-06-24024 June 2011 Closure Letter for the Licensee'S Response to Generic Letter 2008-01, Managing Accumulation in Emergency Core Cooling, Decay Heat Removal and Containment Spray Systems Project stage: Other ML11143A1392011-06-24024 June 2011 Closure Letter for the Licensee'S Response to Generic Letter 2008-01, Managing Accumulation in Emergency Core Cooling, Decay Heat Removal and Containment Spray Systems. Project stage: Other 2009-12-18
[Table View] |
Brunswick, Shearon Harris, H.B. Robinson, Crystal River, Request for Extension of 3-Month Response to Generic Letter 2008-01, Managing Gas Accumulation in Emergency Core Cooling, Decay Heat Removal, and Containment Spray Systems.ML081080038 |
Person / Time |
---|
Site: |
Harris, Brunswick, Crystal River, Robinson |
---|
Issue date: |
04/08/2008 |
---|
From: |
Fulford J P Progress Energy Carolinas |
---|
To: |
Document Control Desk, Office of Nuclear Reactor Regulation |
---|
References |
---|
GL-08-001, PE&RAS-08-025 |
Download: ML081080038 (2) |
|
|
---|
Category:Letter
MONTHYEARIR 05000261/20230042024-01-31031 January 2024 Integrated Inspection Report 05000261/2023004 IR 05000400/20230042024-01-30030 January 2024 Integrated Inspection Report 05000400/2023004 ML24009A2432024-01-25025 January 2024 Unit, No. 2 - Exemption from Select Requirements of 10 CFR Part 73 (EPID L-2023-LLE-0047 (Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting)) ML24009A2712024-01-24024 January 2024 Revision to Reactor Vessel Material Surveillance Capsule Withdrawal Schedule ML23342A0942024-01-0909 January 2024 Independent Spent Fuel Storage Installation Security Inspection Plan ML23354A0052024-01-0808 January 2024 Request for Withholding Information from Public Disclosure, H. B. Robinson Steam Electric Plant, Unit No. 2 IR 05000324/20230112023-12-26026 December 2023 NRC Fire Protection Team Inspection - FPTI Report 05000324/2023011 and 05000325/2023011 ML23354A0632023-12-22022 December 2023 Cover Letter - Crystal River License Termination Plan Request for Additional Information IR 05000324/20234022023-12-14014 December 2023 Security Baseline Inspection Report 05000324-2023402 and 05000325-2023402 ML23342A0902023-12-0808 December 2023 Notification of Inspection and Request for Information for NRC Problem Identification and Resolution Inspection ML23345A1882023-12-0606 December 2023 Fws to NRC Crystal River Species List of Threatened and Endangered Species That May Occur in Your Proposed Project Location or May Be Affected by Your Proposed Project IR 05000261/20234202023-11-30030 November 2023 Security Baseline Inspection Report 05000261/2023420 (Cover Letter with Report) IR 05000261/20230102023-11-28028 November 2023 Fire Protection Team Inspection Report 05000261/2023010 ML23297A0262023-11-27027 November 2023 Proposed Alternatives to ASME Code Section XI Subsection IWE Requirements for Torus Metallic Liner Inspections ML23320A2592023-11-17017 November 2023 STC-23 077 Notification of the Crystal River Unit 3 Generating Plant License Termination Plan Public Meeting and Federal Register Notice ML23313A1322023-11-15015 November 2023 Request for Additional Information for the Environmental Assessment of the License Termination Plan for Crystal River Unit 3 Nuclear Generating Plant ML23317A3462023-11-14014 November 2023 Duke Fleet - Correction Letter to License Amendment Nos. 312 & 340 Issuance of Amendments Regarding the Adoption of Technical Specifications Task Force Traveler TSTF-554, Revision 1 IR 05000400/20230032023-11-0909 November 2023 Integrated Inspection Report 05000400/2023003 ML23310A0712023-11-0707 November 2023 Audit Plan Cover Letter - Crystal River Unit 3 Nuclear Generating Plant LTP IR 05000261/20230032023-11-0707 November 2023 Integrated Inspection Report 05000261 2023003 and 07200060 2023001 IR 05000324/20230032023-11-0101 November 2023 Integrated Inspection Report 05000324/2023003 and 05000325/2023003 IR 05000324/20230102023-10-17017 October 2023 Biennial Problem Identification and Resolution Inspection Report 05000324/2023010 and 05000325/2023010 IR 05000325/20234012023-10-16016 October 2023 Security Baseline Inspection Report 05000324 and 05000325 2023401 ML23226A0862023-10-12012 October 2023 Issuance of Amendment No. 277 Regarding Revision of TSs to Add High-High Steam Generator Level Function to Table 3.3.2-1 and Remove Obsolete Content from TSs 2.1.1.1 and 5.6.5.b ML23346A1322023-10-0606 October 2023 Communication from C-10 Research & Education Foundation Regarding NextEra Common Emergency Fleet Plan License Amendment Request and Related Documents Subsequently Published ML23234A1702023-10-0303 October 2023 Issuance of Amendment No. 199 Regarding Administrative Changes to the Renewed Facility Operating License and Technical Specifications ML23256A0882023-09-25025 September 2023 Issuance of Alternative to Steam Generator Welds ML23195A0782023-08-29029 August 2023 Issuance of Amendments Regarding the Adoption of Technical Specifications Task Force Traveler TSTF-554, Revision 1 IR 05000400/20230052023-08-23023 August 2023 Updated Inspection Plan for Shearon Harris Nuclear Power Plant, Unit 1 (Report 05000400/2023005) ML23235A0552023-08-23023 August 2023 Notification of an Fire Protection Team Inspection (FPTI) (NRC Inspection Report 05000261/2023010) and Request for Information (RFI) IR 05000324/20230052023-08-23023 August 2023 Updated Inspection Plan for Brunswick Steam Electric Plant, Units 1 and 2 (Report 05000324/2023005 and 05000325/2023005) ML23234A2542023-08-22022 August 2023 RQ Inspection Notification Letter IR 05000261/20230052023-08-21021 August 2023 Updated Inspection Plan for H.B. Robinson Steam Electric Plant (Report 05000261/2023005) IR 05000261/20230022023-08-0707 August 2023 Integrated Inspection Report 05000261/2023002 IR 05000324/20230022023-08-0404 August 2023 Integrated Inspection Report 05000324/2023002 and 05000325/2023002 ML23201A2042023-07-28028 July 2023 Summary of Regulatory Audit in Support of Alternative Request RA-22-0308 for Inservice Inspection of the Torus Metallic Liner IR 05000400/20234022023-07-26026 July 2023 Security Baseline Inspection Report 05000400/2023402 ML23187A1112023-07-25025 July 2023 Acceptance of Requested Licensing Action License Request to Add License Condition to Include License Termination Plan Requirements ML23212B2682023-07-25025 July 2023 Notification of Licensed Operator Initial Examination 05000325/2024301 and 05000324/2024301 IR 05000324/20243012023-07-25025 July 2023 Notification of Licensed Operator Initial Examination 05000325/2024301 and 05000324/2024301 IR 05000400/20230022023-07-24024 July 2023 Integrated Inspection Report 05000400/2023002 IR 05000400/20234402023-07-17017 July 2023 Special Inspection Report 05000400/2023440 and Preliminary Greater than Green Finding and Apparent Violation Cover Letter ML23107A2722023-06-13013 June 2023 Letter Transmitting NRC Survey Results for East Settling Pond ML23160A2962023-06-0909 June 2023 Response to Crystal River, Unit 3 Supplemental Information Needed for Acceptance on the Application for a License Amendment Regarding Approval of the License Termination Plan ML23107A2732023-06-0707 June 2023 Orise Independent Survey Report Dcn 5366-SR-01-0 IR 05000261/20234022023-05-30030 May 2023 Cyber Security Inspection Report 05000261/2023402 ML23145A1602023-05-25025 May 2023 Submittal of Updated Final Safety Analysis Report (Revision No. 30), Independent Spent Fuel Storage Installation Safety Analysis Report (Revision No. 28), Technical Specifications Bases Revisions, Quality IR 05000302/20220032023-05-25025 May 2023 Accelerated Decommissioning Partners (ADP) CR3, LLC, Crystal River Unit 3 - NRC Inspection Report No. 05000302/2022003 ML23212A9502023-05-24024 May 2023 Engine Systems, Inc., Part 21 Report Re Woodward EGB-35P Governor/Actuator with Foreign Material ML23146A0012023-05-24024 May 2023 EN 56538 - Engine Systems Inc and Brunswick 2024-01-09
[Table view] |
Text
10 CFR 50.4 PO Box 1551 411 Fayetteville Street Mall Raleigh NC 27602 Serial: PE&RAS-08-025 April 8, 2008 United States Nuclear Regulatory Commission ATTENTION:
Document Control Desk Washington, DC 20555-0001 BRUNSWICK STEAM ELECTRIC PLANT, UNIT NOS. 1 AND 2 DOCKET NOS. 50-325 AND 50-324 / LICENSE NOS. DPR-71 AND DPR-62 SHEARON HARRIS NUCLEAR POWER PLANT, UNIT NO. 1 DOCKET NO. 50-400 / LICENSE NO. NPF-63 H. B. ROBINSON STEAM ELECTRIC PLANT, UNIT NO. 2 DOCKET NO. 50-261 / LICENSE NO. DPR-23 CRYSTAL RIVER UNIT 3 NUCLEAR GENERATING PLANT DOCKET NO. 50-302 / LICENSE NO. DPR-72
Subject:
Request for Extension of 3-Month Response to Generic Letter 2008-01,"Managing Gas Accumulation in Emergency Core Cooling, Decay Heat Removal, and Containment Spray Systems"
Reference:
NRC Generic Letter 2008-01, "Managing Gas Accumulation in Emergency Core Cooling, Decay Heat Removal, and Containment Spray Systems," dated January 11, 2008 Ladies and Gentlemen:
This letter is provided to document the April 3, 2008, telephone conversation between Jared Wermiel (Deputy Director, Division of Safety Systems, NRR) of the NRC staff and Brian McCabe (Manager, Nuclear Regulatory Affairs, Progress Energy) representing Carolina Power & Light Company, now doing business as Progress Energy Carolinas, Inc., and Florida Power Corporation, now doing business as Progress Energy Florida, Inc. During the telephone conversation, Progress Energy requested a 30-day extension to the referenced Generic Letter 3-month response and the staff agreed to that extension for Brunswick Steam Electric Plant, Unit Nos. 1 and 2; Shearon Harris Nuclear Power Plant, Unit No. 1; H. B.Robinson Steam Electric Plant, Unit No. 2; and Crystal River Unit 3 Nuclear Generating Plant. It is expected that Progress Energy will submit the required response letters no later than May 9, 2008.ALM(
United States Nuclear Regulatory Commission PE&RAS-08-025 Page 2 No new commitments have been made in this submittal.
If you have additional questions, please call me at (919) 546-6901.Sincerely, J.aul Fulford anager -Performarn e Evaluation
& Regulatory Affairs DMF c: Jared Wermiel, Deputy Director, Division of Safety Systems -NRR Victor McCree, USNRC Regional Administrator
-Region II F. Saba, NRR Project Manager -BSEP, Unit Nos. 1 and 2; CR3 M. Vaaler, NRR Project Manager -SHNPP, Unit No. 1; HBRSEP, Unit No. 2 USNRC Resident Inspector
-BSEP, Unit Nos. 1 and 2 USNRC Resident Inspector
-CR3 USNRC Resident Inspector
-SHNPP, Unit No. 1 USNRC Resident Inspector
-HBRSEP, Unit No. 2