October 2006, Twelfth Refueling Outage Steam Generator In-Service Inspection Report
ML063130425
Person / Time
Site: Braidwood Constellation icon.png
Issue date: 11/09/2006
From: Coutu T
Exelon Generation Co, Exelon Nuclear
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
BW060099
Download: ML063130425 (2)


Text

_____ __ _ _ Exel n Exelon Generation Company LLC 1

w Iw~exeIoncoTp~com Nuci ear Braidwood Stat o ~

) ~ 4 November 9, 2006 BW060099 U.S. Nuclear Regulatory Commission Attn: Document Control Desk Washington, DC 20555-0001 Braidwood Station, Unit 2 Facility Operating License No. NPF 77 NRC Docket No. STN 50-457

Subject:

October 2006, Twelfth Refueling Outage Steam Generator In-Service Inspection Report In accordance with Technical Specification 5.6.9, Steam Generator (SG) Tube Inspection Reports, Exelon Generation Company, LLC is reporting the number of tubes plugged or repaired during the SG inservice inspection activities conducted during the Braidwood Station, Unit 2 October 2006 twelfth refueling outage. Technical Specification 5.6.9.a requires that following each inservice inspection of the SG tubes, the number of tubes plugged or repaired in each SO shall be reported to the NRC within 15 days.

The Braidwood Station, Unit 2 October 2006 twelfth refueling outage SG tube eddy current inspection scope included 100% full-length bobbin coil inspection, 25% +PointTM inspection of the Row 1 and 2 U-Bends, 25% +PointTM inspection of the hot leg dents/dings greater than 3.0 volts, and 20% ÷PointTMinspection of the hot leg top of tubesheet region to a depth of 17 inches, of the 2A, 26, 2C and 2D SGs. +PointTM inspection was conducted on any bobbin coil indications classified as requiring additional diagnostic testing.

The SG tube inspections were completed on October 25, 2006. No tube sleeving was performed this outage. The Braidwood Unit 2 Steam Generator Tube Plugging Summary provides the number of tubes removed from service during the October 2006 twelfth refueling outage as well as the number of tubes removed from service to date by tube plugging.

U.S. Nuclear Regulatory Commission November 9, 2006 Page 2 of 2 BRAIDWOOD UNIT 2 STEAM GENERATOR TUBE PLUGGING

SUMMARY

SO A SG B SO C SG D Total Previously Plugged 57 48 56 25 186 Plugged During October2006 9 1 4 0 14 Refueling Outage Total 66 49 60 25 200 Please direct any questions regarding this submittal to Mr. Dale Ambler, Regulatory Assurance Manager, at (815) 417-2800.

Sincerely, //

Thomas Coutu Site Vice President Braidwood Station