Letter Sequence Other |
---|
TAC:MC8095, Elimination of Hydrogen Recombiners and Change to Hydrogen and Oxygen Monitors (Approved, Closed) |
|
MONTHYEARLIC-04-0076, License Amendment Request, Application for Technical Specification Improvement to Eliminate Requirements for Hydrogen Monitors Using the Consolidated Line Item Improvement Process.2004-09-0808 September 2004 License Amendment Request, Application for Technical Specification Improvement to Eliminate Requirements for Hydrogen Monitors Using the Consolidated Line Item Improvement Process. Project stage: Request ML0508402652005-03-22022 March 2005 3/22/05 Fort Calhoun Station Unit 1 - Issuance of Amd. 234 Elimination of Requirements for Hydrogen Monitors Using the Consolidated Line Item Improvement Process. (Tac. MC4305) Project stage: Approval ML0508404912005-03-22022 March 2005 2 Pages Fort Calhoun - for Amd. 234. Elimination of Requirements for Hydrogen Monitors Using the Consolidated Line Item Improvement Process (Tac. MC4305) Project stage: Other LIC-05-0075, Response to Request for Additional Information on the License Amendment Request, Revisions of Technical Specifications Table 1-1 and Section 4.0.2005-07-0808 July 2005 Response to Request for Additional Information on the License Amendment Request, Revisions of Technical Specifications Table 1-1 and Section 4.0. Project stage: Response to RAI LIC-05-0098, License Amendment Request (Lar), Deletion of Shutdown Margin Surveillance Requirement and Miscellaneous Administrative Changes.2005-08-11011 August 2005 License Amendment Request (Lar), Deletion of Shutdown Margin Surveillance Requirement and Miscellaneous Administrative Changes. Project stage: Request LIC-05-0070, License Amendment Request, Application for Technical Specification Improvement to Add LC0 2.0.1(3) on the Inoperability of Snubbers Using the Consolidated Line Item Improvement Process.2005-08-11011 August 2005 License Amendment Request, Application for Technical Specification Improvement to Add LC0 2.0.1(3) on the Inoperability of Snubbers Using the Consolidated Line Item Improvement Process. Project stage: Request ML0525105042005-08-31031 August 2005 Framatome Anp, Inc 77-5069740-NP-00, Shearon Harris Criticality Evaluation. Project stage: Request ML0525105022005-09-0101 September 2005 Request for License Amendment to Credit Soluble Boron for Fuel Storage Pools Project stage: Request ML0516802672005-10-0303 October 2005 Issuance of License Amendment 236 Conversion of TS Section 4.0 to STS Format Project stage: Approval ML0528003522005-10-0303 October 2005 Tech Spec Pages for Amendment 236 Conversion of TS Section 4.0 to STS Format Project stage: Other ML0606902832006-02-0101 February 2006 Technical Specifications, Deletion of Shutdown Margin During Low Power Testing from TS and Various Other Editorial and Administrative Changes Project stage: Acceptance Review ML0527005232006-02-0101 February 2006 License Amendment, Deletion of Shutdown Margin During Low Power Testing from TS and Various Other Editorial and Administrative Changes Project stage: Other ML0606703202006-03-0101 March 2006 License Amendment 238 Regarding Inoperability of Snubbers Project stage: Approval ML0606902822006-03-0101 March 2006 Tech Spec Pages for Amendment 238 Regarding Inoperability of Snubbers Project stage: Other LIC-06-0029, Commitment to Fuel Storage Area Radiation Monitoring for 10 CFR 50.68(b)2006-03-17017 March 2006 Commitment to Fuel Storage Area Radiation Monitoring for 10 CFR 50.68(b) Project stage: Request LIC-06-0023, Response to Requests for Additional Information and Revision of Fort Calhoun Station Unit No. 1 License Amendment Request, Criticality Control During Spent Fuel Cask Loading in the Spent Fuel Pool.2006-03-27027 March 2006 Response to Requests for Additional Information and Revision of Fort Calhoun Station Unit No. 1 License Amendment Request, Criticality Control During Spent Fuel Cask Loading in the Spent Fuel Pool. Project stage: Response to RAI ML0610100482006-04-10010 April 2006 Tech Spec Pages for Amendment 239 Regarding Adding Limits and Controls for the Spent Fuel Cask Loading and Unloading Operations in the Spent Fuel Pool Project stage: Acceptance Review ML0610006062006-04-10010 April 2006 Issuance of License Amendment 239 Regarding Adding Limits and Controls for the Spent Fuel Cask Loading and Unloading Operations in the Spent Fuel Pool Project stage: Approval LIC-06-0065, Closure of NRC TAC Issues for Fort Calhoun Station Unit No. 12006-07-0606 July 2006 Closure of NRC TAC Issues for Fort Calhoun Station Unit No. 1 Project stage: Other 2005-09-01
[Table View] |
|
---|
Category:Letter
MONTHYEARML24019A1672024-01-31031 January 2024 Issuance of Amendment to Renewed Facility License to Add License Condition to Include License Termination Plan Requirements IR 05000285/20230062023-12-21021 December 2023 NRC Inspection Report 05000285/2023006 LIC-23-0007, Response to Fort Calhoun, Unit 1 & Independent Spent Fuel Storage Installation Review of License Amendment Request to Add License Condition to Include License Termination Plan Requirements Request for Additional Information2023-12-0606 December 2023 Response to Fort Calhoun, Unit 1 & Independent Spent Fuel Storage Installation Review of License Amendment Request to Add License Condition to Include License Termination Plan Requirements Request for Additional Information IR 05000285/20230052023-11-0202 November 2023 NRC Inspection Room 05000285/2023005 ML23276A0042023-09-28028 September 2023 U.S. EPA Response Letter to NRC Letter on Consultation and Finality on Decommissioning and Decontamination of Contaminated Sites MOU - Fort Calhoun Station, Unit 1 (License No. DPR-40, Docket No. 50-285) IR 05000285/20230042023-09-13013 September 2023 NRC Inspection Report 05000285/2023-004 LIC-23-0005, Response to Fort Calhoun Station, Unit No. 1 - Review of License Amendment Request to Add License Condition to Include License Termination Plan Requirements - 2nd Request for Additional Information (EPID L-2021-LIT-0000) June 2, 20232023-08-24024 August 2023 Response to Fort Calhoun Station, Unit No. 1 - Review of License Amendment Request to Add License Condition to Include License Termination Plan Requirements - 2nd Request for Additional Information (EPID L-2021-LIT-0000) June 2, 2023 ML23234A2412023-08-18018 August 2023 Email - Letter to M Porath Re Ft Calhoun Unit 1 LTP EA Section 7 Informal Consultation Request ML23234A2392023-08-18018 August 2023 Letter to B Harisis Re Ft Calhoun Unit 1 LTP EA State of Nebraska Comment Request.Pdf IR 05000285/20230032023-07-10010 July 2023 NRC Inspection Report 05000285/2023003 ML23082A2202023-06-26026 June 2023 Consultation on the Decommissioning of the Fort Calhoun Station Unit 1 Pressurized Water Reactor in Fort Calhoun, Nebraska ML23151A0032023-06-0505 June 2023 Review of License Amendment Request to Add License Condition to Include License Termination Plan Requirements 2nd Request for Additional Information (EPID L-2021-LIT-0000) June 2, 2023 IR 05000285/20230022023-06-0505 June 2023 NRC Inspection Report 05000285/2023002 LIC-23-0004, (FCS) Radiological Effluent Release Report and Radiological Environmental Operating Report2023-04-20020 April 2023 (FCS) Radiological Effluent Release Report and Radiological Environmental Operating Report LIC-23-0003, Annual Decommissioning Funding / Irradiated Fuel Management Status Report2023-03-15015 March 2023 Annual Decommissioning Funding / Irradiated Fuel Management Status Report LIC-23-0001, Response to Fort Calhoun Station, Unit No. 1 - Review of License Amendment Request to Add License Condition to Include License Termination Plan Requirements - Request for Additional Information2023-02-27027 February 2023 Response to Fort Calhoun Station, Unit No. 1 - Review of License Amendment Request to Add License Condition to Include License Termination Plan Requirements - Request for Additional Information IR 05000285/20230012023-02-24024 February 2023 NRC Inspection Report 05000285/2023001 ML22361A1022023-02-24024 February 2023 Reactor Decommissioning Branch Project Management Changes for Some Decommissioning Facilities and Establishment of Backup Project Manager for All Decommissioning Facilities LIC-23-0002, Independent Spent Fuel Storage Installation, Annual Radioactive Effluent Release Report2023-02-20020 February 2023 Independent Spent Fuel Storage Installation, Annual Radioactive Effluent Release Report ML23020A0462023-01-19019 January 2023 Threatened and Endangered Species List: Nebraska Ecological Services Field Office IR 05000285/20220062023-01-0505 January 2023 NRC Inspection Report 05000285/2022-006 ML22357A0662022-12-30030 December 2022 Technical RAI Submittal Letter on License Amendment Request for Approval of License Termination Plan IR 05000285/20220052022-10-26026 October 2022 NRC Inspection Report 05000285/2022-005 ML22276A1052022-09-30030 September 2022 Conclusion of Consultation Under Section 106 NHPA for Ft. Calhoun Station LTP ML22258A2732022-09-29029 September 2022 Letter to John Swigart, Shpo; Re., Conclusion of Consultation Under Section 106 Hnpa Fort Calhoun Station Unit 1 ML22265A0262022-09-26026 September 2022 U.S. Nuclear Regulatory Commission'S Analysis of Omaha Public Power District'S Decommissioning Status Report (License No. DPR-40, Docket No. 50-285) IR 05000285/20220042022-09-14014 September 2022 NRC Inspection Report 05000285/2022004 ML22138A1252022-08-0303 August 2022 Letter to Mr. Timothy Rhodd, Chairperson, Iowa Tribe of Kansas and Nebraska, Re., Ft Calhoun LTP Section 106 ML22138A1262022-08-0303 August 2022 Letter to Roger Trudell, Chairman, Santee Sioux Nation, Nebraska, Re., Ft Calhoun LTP Section 106 ML22101A1092022-08-0303 August 2022 Letter to Mr. Durell Cooper, Chairman, Apache Tribe of Oklahoma; Re., Ft Calhoun LTP Section 106 ML22138A1242022-08-0303 August 2022 Letter to Mr. Reggie Wassana, Governor, Cheyenne and Arapaho Tribes, Oklahoma, Re., Ft Calhoun LTP Section 106 ML22138A1292022-08-0303 August 2022 Letter to Tiauna Carnes, Chairperson, Sac and Fox Nation of Missouri in Kansas, Re., Ft Calhoun LTP Section 106 ML22138A1212022-08-0303 August 2022 Letter to Mr. Edgar Kent, Chairman, Iowa Tribe of Oklahoma, Re., Ft Calhoun LTP Section 106 ML22138A1282022-08-0303 August 2022 Letter to Victoria Kitcheyan, Chairwoman, Winnebago Tribe of Nebraska, Re., Ft Calhoun LTP Section 106 ML22138A1232022-08-0303 August 2022 Letter to Mr. Leander Merrick, Chairperson, Omaha Tribe of Nebraska, Re., Ft Calhoun LTP Section 106 ML22138A1222022-08-0303 August 2022 Letter to Mr. John Shotton, Chairman, Otoe-Missouria Tribe of Indians, Oklahoma, Re., Ft Calhoun LTP Section 106 ML22138A1272022-08-0303 August 2022 Letter to Vern Jefferson, Chairman, Sac and Fox Tribe of the Mississippi in Iowa, Re., Ft Calhoun LTP Section 106 ML22214A0922022-08-0303 August 2022 Letter to Stacy Laravie, Thpo, Ponca Tribe of Nebraska, Re., Ft Calhoun LTP Section 106 ML22138A1302022-08-0303 August 2022 Letter to Justin Wood, Principal Chief, Sac and Fox Nation, Oklahoma, Re., Ft Calhoun LTP Section 106 ML22159A2152022-06-28028 June 2022 Letter Forwarding FRN on Public Meeting and Request for Comment on License Termination Plan LIC-22-0010, Response to Fort Calhoun Station, Unit No. 1 - Review of License Termination Plan Requirements - Request for Additional Information2022-06-15015 June 2022 Response to Fort Calhoun Station, Unit No. 1 - Review of License Termination Plan Requirements - Request for Additional Information IR 05000285/20220032022-06-15015 June 2022 NRC Inspection Report 05000285/2022003 ML22119A2472022-05-0303 May 2022 Review of Amendment Request to Add a LC to Include LTP Requirements, RAI for Environmental Review IR 05000285/20220022022-04-28028 April 2022 NRC Inspection Report 050-00285/2022-002 LIC-22-0005, (FCS) Radiological Effluent Release Report and Radiological Environmental Operating Report2022-04-20020 April 2022 (FCS) Radiological Effluent Release Report and Radiological Environmental Operating Report LIC-22-0009, Annual Decommissioning Funding / Irradiated Fuel Management Status Report2022-03-30030 March 2022 Annual Decommissioning Funding / Irradiated Fuel Management Status Report 2024-01-31
[Table view] Category:License-Operating (New/Renewal/Amendments) DKT 50
MONTHYEARML24019A1672024-01-31031 January 2024 Issuance of Amendment to Renewed Facility License to Add License Condition to Include License Termination Plan Requirements ML20071E1042020-03-25025 March 2020 Issuance of Amendment to Change the Security Plan, Training and Qualification Plan, and Safeguards Contingency Plan to Reflect an ISFSI-Only Configuration ML19297D6772019-12-11011 December 2019 Issuance of Amendment to Revise the Permanently Defueled Technical Specifications to Align to the Requirements for Permanent Removal of Spent Fuel from the Spent Fuel Pool ML18047A6612018-03-28028 March 2018 Issuance of Amendment No. 298, Request to Modify License Condition 3.C to Delete Requirement for Commission-Approved Cyber Security Plan (CAC No. MF9850; EPID L-2017-LLA-0236) ML18068A1652018-03-0909 March 2018 Correction to Page 1 of Attachment to Enclosure 1 for Amendment No. 297, Request for Technical Specification Changes to Align to Those Requirements for Decommissioning (CAC No. MF9567; EPID L-2017-LLA-0192) ML18010A0872018-03-0606 March 2018 Issuance of Amendment No. 297, Request for Technical Specification Changes to Align to Those Requirements for Decommissioning (CAC No. MF9567; EPID L-2017-LLA-0192) ML17338A1722018-01-19019 January 2018 Issuance of Amendment No. 296, Revise Technical Specifications (TS) to Delete Dry Spent Fuel Cask Loading Limits from TS 3.8.3(6), Figure 2-11, Table 3-4, Table 3-5, and TS 4.3.1.3 (CAC No. MF9831; EPID L-2017-LLA-0235) ML17276B2862017-12-12012 December 2017 Issuance of Amendment No. 295, Revise the Emergency Plan and Emergency Action Level Scheme for the Permanently Defueled Condition (CAC No. MF8951; EPID L-2016-LLA-0036) ML17289A0602017-11-22022 November 2017 Issuance of Amendment No. 294, Revise Cyber Security Plan Implementation Schedule for Milestone 8 and Associated License Condition (CAC No. MF9559; EPID L-2017-LLA-0184) ML17278A6072017-11-17017 November 2017 Issuance of Amendment No. 293, Request to Revise Current Licensing Basis for the Auxiliary Building to Use American Concrete Institute Ultimate Strength Requirements (CAC No. MF8525; EPID L-2016-LLA-0013) ML17165A4652017-07-28028 July 2017 Fort Calhoun Station, Unit 1 - Issuance of Amendment No. 292, Revise Technical Specifications to Align Staffing Requirements to Those Required for Decommissioning (CAC No. MF8437) ML17123A3482017-07-27027 July 2017 Issuance of Amendment No. 291, Revise the Radiological Emergency Response Plan for Permanently Defueled Condition ML17179A1782017-06-29029 June 2017 Correction to Technical Specification Definitions - Page 7 for Amendment No. 286, Administrative Changes to the Technical Specifications to Update Titles, Delete Obsolete Actions in Appendix B, and ... LIC-17-0047, Final Request for Additional Information Concerning License Amendment Request 16-07: Revise the Emergency Plan to the Permanently Defueled Emergency Plan and Permanently Defueled Emergency Action Level Scheme2017-05-15015 May 2017 Final Request for Additional Information Concerning License Amendment Request 16-07: Revise the Emergency Plan to the Permanently Defueled Emergency Plan and Permanently Defueled Emergency Action Level Scheme ML17053A0992017-04-0707 April 2017 Issuance of Amendment No. 290, Request to Delete License Condition 3.D., Fire Protection Program, No Longer Needed for Permanently Shutdown and Defueled Condition ML16182A3632016-08-19019 August 2016 Issuance of Amendment No. 289, Request to Adopt Technical Specification Task Force (TSTF)-501, Revision 1, Relocate Stored Fuel Oil and Lube Oil Volume Values to Licensee Control ML16139A8042016-06-0808 June 2016 Issuance of Amendment No. 288, Request to Adopt Technical Specifications Task Force (TSTF)-426, Revision 5, Revise or Add Actions to Preclude Entry Into LCO 3.0.3 - RITSTF Initiative 6b & 6c ML16084A7552016-04-0505 April 2016 Issuance of Amendment No. 287, Revise Technical Specifications to Adopt TSTF-522, Revise Ventilation System Surveillance Requirements to Operate for 10 Hours/Month, Using CLIIP ML15307A0132016-02-23023 February 2016 Issuance of Amendment No. 286, Request to Make Administrative Changes to the Technical Specifications to Update Titles, Delete Obsolete Actions in Appendix B, and Relocate a Definition ML15288A0052015-12-15015 December 2015 Issuance of Amendment No. 285, Adopt Emergency Action Level Scheme Pursuant to Nuclear Energy Institute (NEI) 99-01, Revision 6, Development of Emergency Action Levels for Non-Passive Reactors ML15294A2792015-11-19019 November 2015 Issuance of Amendment No. 284, Request to Revise License Condition Related to Cyber Security Plan Milestone 8 Full Implementation Date ML15209A8022015-08-10010 August 2015 Issuance of Amendment No. 283, Revise Updated Safety Analysis Report to Allow Pipe Stress Analysis to Be Performed in Accordance with ASME Code Section III ML15111A3992015-06-30030 June 2015 Issuance of Amendment No. 282, Revise Updated Safety Analysis Report for Controlling Raw Water Pump Operation and Safety Classification of Components During a Flood ML15035A2032015-03-27027 March 2015 Issuance of Amendment No. 281, Revise Technical Specification 3.1, Table 3-3 to Correct Administrative Error in Surveillance Method for Containment Wide Range Radiation Monitors ML15015A4132015-02-20020 February 2015 Issuance of Amendment No. 280, Revise Technical Specification 3.2, Table 3-5 to Add New Surveillance Requirement ML14356A0122014-12-29029 December 2014 Issuance of Amendment No. 279, Revise Technical Specification Surveillance Requirements for One-Time Extension from Refueling Frequency of Once Per 18 Months to Maximum of 28 Months ML14328A8142014-12-22022 December 2014 Issuance of Amendment No. 278, Revise Technical Specification 2.5, Auxiliary Feedwater (AFW) System to Allow 7-Day Completion Time for Turbine-Driven AFW Pump Based on TSTF-340, Revision 3 ML14279A2752014-11-0606 November 2014 Issuance of Amendment No. 277, Revise Technical Specification Surveillance Requirement 3.2, Table 3-5, Item 3, for One-Time Extension of Frequency to Maximum of 28 Months ML14209A0272014-08-0707 August 2014 Issuance of Amendment No. 276, Request to Revise Updated Safety Analysis Report for Westinghouse Plant-Specific Leak-Before-Break Analysis ML14098A0922014-06-16016 June 2014 Issuance of Amendment No. 275, Adopt National Fire Protection Association Standard 805, Performance-Based Standard for Fire Protection for Light-Water Reactor Generating Plants (2001 Edition) ML14003A0032014-01-28028 January 2014 Issuance of Amendment No. 274, Revise Technical Specification 2.16, River Level, and Establish EAL Classification Criteria for External Flooding Events Under Radiological Emergency Response Plan ML13296A5842013-10-25025 October 2013 Issuance of Amendment No. 273, Revise Current Licensing Basis of Pipe Break Criteria for High Energy Line Breaks (Exigent Circumstances) ML13203A0702013-07-26026 July 2013 Issuance of Amendment No. 272 - Revise Current Licensing Basis to Adopt Revised Design Basis/Methodology for Addressing Design-Basis Tornado/Tornado Missile Impact (Exigent Circumstances) ML13070A0422013-03-29029 March 2013 Issuance of Amendment No. 271, Relocate Technical Specification LCO 2.17, Miscellaneous Radioactive Material Sources, and Surveillance Requirement 3.13 to Updated Safety Analysis Report ML13043A6612013-02-28028 February 2013 Issuance of Amendment No. 270 to Revise Technical Specification 2.15 to Establish Limiting Condition for Operation Requirements for Reactor Protective System Actuation Circuits ML1126204022011-09-30030 September 2011 Issuance of Amendment No. 268, Revise Updated Safety Analysis Report to Relocate Acoustic Position and Tail Pipe Temperature Indication Surveillance Requirements from Technical Specifications ML1118615712011-08-31031 August 2011 Issuance of Amendment No. 267, Revise Technical Specification (TS) 2.15 and TS 3.1 Related to Operability of Secondary Control Element Assembly Position Indication System Channels; Correction to TS 2.10.2(7)c ML1118010942011-07-27027 July 2011 Issuance of Amendment No. 266, Revise License Condition and Approve Cyber Security Plan and Associated Implementation Schedule ML1015202962010-06-0202 June 2010 License Amendment, Issuance of Amendment No. 265, Revise Technical Specification 2.15, Table 2-5, Note C for Safety Valve Acoustic Position Indication (Emergency Circumstances) ML1009100772010-05-14014 May 2010 License Amendment, 264, Revision of Tech Spec Sections 2.0.1 and 2.7 for Inoperable System, Subsystem, or Component Due to Inoperable Power Source and Deletion of Diesel Generator Surveillance Requirement 3.7(1)e ML0925405912009-10-0909 October 2009 License Amendment, Issuance of Amendment No. 263 Modify Technical Specifications to Add Operability and Testing Requirements for Steam Generator Blowdown Isolation on a Reactor Trip ML0919005692009-07-24024 July 2009 Unit No.1 - Issuance of Amendment No. 261, Modify Transformer Allowed Outage Time in Technical Specification 2.7(2) and Delete Associated 2.7(2) Special Reporting Requirements in TS 5.9.3j ML0916205692009-07-24024 July 2009 Issuance of Amendment 262, Modify Technical Specifications to Adopt TSTF-511, Eliminate Working Hour Restrictions from TS 5.2.2 to Support Compliance with 10 CFR Part 26 ML0912801022009-07-22022 July 2009 Issuance of Amendment No. 260, Modification of Surveillance Requirements in TS 3.6(3), Containment Recirculating Air Cooling and Filtering System & Removal of License Conditions ML0832606972009-05-12012 May 2009 Issuance of Amendment No. 259, Revise Technical Specifications to Correct Typographical Errors and Make Administrative Clarifications ML0907108912009-03-27027 March 2009 License Amendment, Issuance of Amendment No. 258, Revise Limiting Condition for Operation 2.7(2)j in TS 2.7, Electrical Systems, to Clarify Allowed Outage Time for Emergency Diesel Generators ML0730903612007-12-17017 December 2007 Issuance of Amendment No. 251, Modify Technical Specification Requirements to Support Addition of Safety-Related Swing Inverters to 120 Volt AC Buses ML0720400972007-07-26026 July 2007 Conforming License Amendment to Incorporate the Mitigation Strategies of Commission Order EA-02-026 (Tac No. MD4534) ML0720402832007-07-26026 July 2007 Revised Pages of Facility Operating License DPR-40 to Incorporate the Mitigation Strategies Required by Section B.5.b. of Commission Order EA-02-026 ML0706102692007-06-0606 June 2007 Issuance of Amendment No. 250 Adoption of TSTF-447 to Delete Requirements for Hydrogen Purge System - CLIIP 2024-01-31
[Table view] Category:Safety Evaluation
MONTHYEARML24019A1682024-01-31031 January 2024 Safety Evaluation Report for Approval of License Termination Plan ML21271A5992021-08-0303 August 2021 License Amendment Request (LAR) 21-01, Chapter 8, 12, Omaha Public Power District, FCS-SAF-103, FCS Deconstruction Health and Safety Plan CAC2 ML20056E4872020-02-26026 February 2020 Staff Review of Fort Calhoun Independent Spent Fuel Storage Installation Physical Security Plan, Security Training and Qualification Plan, and Safeguard Contingency Plan, Revision 0 and the Verification of Additional Security Measures (ASM) ML19297D6742019-12-0909 December 2019 FCS ISFSI Only Tech Specs SER ML18017B0052018-03-30030 March 2018 Review of the Irradiated Fuel Management Plan (CAC No. MF9553; EPID L-2017-LLL-0009) ML18047A6612018-03-28028 March 2018 Issuance of Amendment No. 298, Request to Modify License Condition 3.C to Delete Requirement for Commission-Approved Cyber Security Plan (CAC No. MF9850; EPID L-2017-LLA-0236) ML18010A0872018-03-0606 March 2018 Issuance of Amendment No. 297, Request for Technical Specification Changes to Align to Those Requirements for Decommissioning (CAC No. MF9567; EPID L-2017-LLA-0192) ML17338A1722018-01-19019 January 2018 Issuance of Amendment No. 296, Revise Technical Specifications (TS) to Delete Dry Spent Fuel Cask Loading Limits from TS 3.8.3(6), Figure 2-11, Table 3-4, Table 3-5, and TS 4.3.1.3 (CAC No. MF9831; EPID L-2017-LLA-0235) ML17276B2862017-12-12012 December 2017 Issuance of Amendment No. 295, Revise the Emergency Plan and Emergency Action Level Scheme for the Permanently Defueled Condition (CAC No. MF8951; EPID L-2016-LLA-0036) ML17263B1982017-12-11011 December 2017 Letter and Safety Evaluation, Request for Exemption from 10 CFR 50.47 and 10 CFR 50 Appendix E to Reduce Emergency Planning Requirements for Permanently Defueled Condition (CAC MF9067; EPID L-2016-LLE-0003) ML17289A0602017-11-22022 November 2017 Issuance of Amendment No. 294, Revise Cyber Security Plan Implementation Schedule for Milestone 8 and Associated License Condition (CAC No. MF9559; EPID L-2017-LLA-0184) ML17275A2642017-11-21021 November 2017 Safety Evaluation Input on Fort Calhoun Station Request for Approval of Permanently Defueled Emergency Plan and Emergency Action Level Scheme, Docket No. 50-285 ML17278A6072017-11-17017 November 2017 Issuance of Amendment No. 293, Request to Revise Current Licensing Basis for the Auxiliary Building to Use American Concrete Institute Ultimate Strength Requirements (CAC No. MF8525; EPID L-2016-LLA-0013) ML17165A4652017-07-28028 July 2017 Fort Calhoun Station, Unit 1 - Issuance of Amendment No. 292, Revise Technical Specifications to Align Staffing Requirements to Those Required for Decommissioning (CAC No. MF8437) ML17123A3482017-07-27027 July 2017 Issuance of Amendment No. 291, Revise the Radiological Emergency Response Plan for Permanently Defueled Condition ML17144A2462017-06-21021 June 2017 Approval of Certified Fuel Handler Training and Retraining Program to Facilitate Activities Associated with Decommissioning and Irradiated Fuel Handling Management ML17053A0992017-04-0707 April 2017 Issuance of Amendment No. 290, Request to Delete License Condition 3.D., Fire Protection Program, No Longer Needed for Permanently Shutdown and Defueled Condition ML16141A7392016-05-27027 May 2016 Safety Evaluation, Review of Aging Management Program of Reactor Vessel Internals Based on MRP-227-A, Materials Reliability Program: Pressurized Water Reactor Internals Inspection and Evaluation Guidelines ML16104A0742016-04-15015 April 2016 Relief Request, Request to Use a Portion of a Later Edition of the ASME B&PV Code, Section XI, Fourth 10-Year Inservice Inspection Interval ML16084A7552016-04-0505 April 2016 Issuance of Amendment No. 287, Revise Technical Specifications to Adopt TSTF-522, Revise Ventilation System Surveillance Requirements to Operate for 10 Hours/Month, Using CLIIP ML15307A0132016-02-23023 February 2016 Issuance of Amendment No. 286, Request to Make Administrative Changes to the Technical Specifications to Update Titles, Delete Obsolete Actions in Appendix B, and Relocate a Definition ML16041A3082016-02-19019 February 2016 Relief Requests P-1 - LPSI and CS Pumps; P-2 - Adjusting Hydraulic Parameters Consistent W/Code Case OMN-21; G-1 - Test Frequency Consistent W/Code Case OMN-20, Fifth 10-Year Inservice Testing Interval ML15288A0052015-12-15015 December 2015 Issuance of Amendment No. 285, Adopt Emergency Action Level Scheme Pursuant to Nuclear Energy Institute (NEI) 99-01, Revision 6, Development of Emergency Action Levels for Non-Passive Reactors ML15294A2792015-11-19019 November 2015 Issuance of Amendment No. 284, Request to Revise License Condition Related to Cyber Security Plan Milestone 8 Full Implementation Date ML15232A0032015-08-21021 August 2015 Relief Request RR-14, Relief from ASME Code Case N-729-1 Requirements for Reactor Vessel Head Penetration Nozzle Welds, Fourth 10-Year Inservice Inspection Interval ML15209A8022015-08-10010 August 2015 Issuance of Amendment No. 283, Revise Updated Safety Analysis Report to Allow Pipe Stress Analysis to Be Performed in Accordance with ASME Code Section III ML15111A3992015-06-30030 June 2015 Issuance of Amendment No. 282, Revise Updated Safety Analysis Report for Controlling Raw Water Pump Operation and Safety Classification of Components During a Flood ML15035A2032015-03-27027 March 2015 Issuance of Amendment No. 281, Revise Technical Specification 3.1, Table 3-3 to Correct Administrative Error in Surveillance Method for Containment Wide Range Radiation Monitors ML15015A4132015-02-20020 February 2015 Issuance of Amendment No. 280, Revise Technical Specification 3.2, Table 3-5 to Add New Surveillance Requirement ML14356A0122014-12-29029 December 2014 Issuance of Amendment No. 279, Revise Technical Specification Surveillance Requirements for One-Time Extension from Refueling Frequency of Once Per 18 Months to Maximum of 28 Months ML14328A8142014-12-22022 December 2014 Issuance of Amendment No. 278, Revise Technical Specification 2.5, Auxiliary Feedwater (AFW) System to Allow 7-Day Completion Time for Turbine-Driven AFW Pump Based on TSTF-340, Revision 3 ML14323A5992014-12-0202 December 2014 Relief Request RR-13, Relief from Inservice Testing Requirements to Perform Testing of 4 Valves During the April 2015 Refueling Outage ML14316A1672014-11-19019 November 2014 Relief Request RR-14, Proposed Alternative for Temporary Acceptance of a Pin Hole Leak in Raw Water System 20-Inch Elbow Located in Room 19 of Auxiliary Building ML14279A2752014-11-0606 November 2014 Issuance of Amendment No. 277, Revise Technical Specification Surveillance Requirement 3.2, Table 3-5, Item 3, for One-Time Extension of Frequency to Maximum of 28 Months ML14209A0272014-08-0707 August 2014 Issuance of Amendment No. 276, Request to Revise Updated Safety Analysis Report for Westinghouse Plant-Specific Leak-Before-Break Analysis ML14098A0922014-06-16016 June 2014 Issuance of Amendment No. 275, Adopt National Fire Protection Association Standard 805, Performance-Based Standard for Fire Protection for Light-Water Reactor Generating Plants (2001 Edition) ML14003A0032014-01-28028 January 2014 Issuance of Amendment No. 274, Revise Technical Specification 2.16, River Level, and Establish EAL Classification Criteria for External Flooding Events Under Radiological Emergency Response Plan ML13296A5842013-10-25025 October 2013 Issuance of Amendment No. 273, Revise Current Licensing Basis of Pipe Break Criteria for High Energy Line Breaks (Exigent Circumstances) ML13203A0702013-07-26026 July 2013 Issuance of Amendment No. 272 - Revise Current Licensing Basis to Adopt Revised Design Basis/Methodology for Addressing Design-Basis Tornado/Tornado Missile Impact (Exigent Circumstances) ML13141A6082013-06-25025 June 2013 Safety Assessment in Response to Request for Information Pursuant to 10 CFR 50.54(f) - Recommendation 9.3 Communications Assessment ML13070A0422013-03-29029 March 2013 Issuance of Amendment No. 271, Relocate Technical Specification LCO 2.17, Miscellaneous Radioactive Material Sources, and Surveillance Requirement 3.13 to Updated Safety Analysis Report ML13043A6612013-02-28028 February 2013 Issuance of Amendment No. 270 to Revise Technical Specification 2.15 to Establish Limiting Condition for Operation Requirements for Reactor Protective System Actuation Circuits ML13017A4672013-01-31031 January 2013 Approval of Request for Change to the Reactor Vessel Surveillance Capsule Removal Schedule ML12333A1192012-12-31031 December 2012 Issuance of Amendment No. 269, Incorporate New Radial Peaking Factor Definition and Clarify Limiting Condition for Operation (LCO) 2.10.2(6) ML1126204022011-09-30030 September 2011 Issuance of Amendment No. 268, Revise Updated Safety Analysis Report to Relocate Acoustic Position and Tail Pipe Temperature Indication Surveillance Requirements from Technical Specifications ML1118615712011-08-31031 August 2011 Issuance of Amendment No. 267, Revise Technical Specification (TS) 2.15 and TS 3.1 Related to Operability of Secondary Control Element Assembly Position Indication System Channels; Correction to TS 2.10.2(7)c ML1122702902011-08-18018 August 2011 Relief Request RR-12 from Code Case N-722, Additional Examinations for PWR Pressure Retaining Welds in Class 1 Components Fabricated with Alloy 600/82/182 Materials, Fourth 10-Year Inservice Inspection Interval ML1118010942011-07-27027 July 2011 Issuance of Amendment No. 266, Revise License Condition and Approve Cyber Security Plan and Associated Implementation Schedule ML1022101332010-08-20020 August 2010 Request for Use of Alternative to Depth-Sizing Qualification for Volumetric Examinations of Reactor Pressure Vessel Welds for 4th 10-year Inservice Inspection Interval ML1009100772010-05-14014 May 2010 License Amendment, 264, Revision of Tech Spec Sections 2.0.1 and 2.7 for Inoperable System, Subsystem, or Component Due to Inoperable Power Source and Deletion of Diesel Generator Surveillance Requirement 3.7(1)e 2024-01-31
[Table view] |
Text
February 1, 2006 Mr. R. T. Ridenoure Vice President - Chief Nuclear Officer Omaha Public Power District Fort Calhoun Station FC-2-4 Adm.
Post Office Box 550 Fort Calhoun, NE 68023-0550
SUBJECT:
FORT CALHOUN STATION, UNIT NO. 1 - ISSUANCE OF AMENDMENT RE:
DELETION OF THE SHUTDOWN MARGIN SURVEILLANCE REQUIREMENT (TAC NO. MC8095)
Dear Mr. Ridenoure:
The U.S. Nuclear Regulatory Commission (Commission) has issued the enclosed Amendment No. 237 to Renewed Facility Operating License No. DPR-40 for the Fort Calhoun Station, Unit No. 1. The amendment consists of changes to the Technical Specifications (TS) in response to your application dated August 11, 2005.
The amendment deletes TS 2.10.2(9)b(iii). This surveillance requirement (SR) required the licensee to verify the shutdown margin on every 8-hour shift during low power physics testing.
This change will make TS 2.10.2(9)b more consistent with SR 3.1.7 of NUREG-1432, Standard Technical Specifications Combustion Engineering Plants, Revision 3. In addition, the Containment Structural Tests Report is deleted from TS 5.9.3c and several administrative and editorial changes were approved.
A copy of the related Safety Evaluation is also enclosed. The Notice of Issuance will be included in the Commission's next biweekly Federal Register notice.
Sincerely,
/RA/
Alan B. Wang, Project Manager Plant Licensing Branch IV Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-285
Enclosures:
- 1. Amendment No. 237 to DPR-40
- 2. Safety Evaluation cc w/encls: See next page
February 1, 2006 Mr. R. T. Ridenoure Vice President - Chief Nuclear Officer Omaha Public Power District Fort Calhoun Station FC-2-4 Adm.
Post Office Box 550 Fort Calhoun, NE 68023-0550
SUBJECT:
FORT CALHOUN STATION, UNIT NO. 1 - ISSUANCE OF AMENDMENT RE:
DELETION OF THE SHUTDOWN MARGIN SURVEILLANCE REQUIREMENT (TAC NO. MC8095)
Dear Mr. Ridenoure:
The U.S. Nuclear Regulatory Commission (Commission) has issued the enclosed Amendment No. 237 to Renewed Facility Operating License No. DPR-40 for the Fort Calhoun Station, Unit No. 1. The amendment consists of changes to the Technical Specifications (TS) in response to your application dated August 11, 2005.
The amendment deletes TS 2.10.2(9)b(iii). This surveillance requirement (SR) required the licensee to verify the shutdown margin on every 8-hour shift during low power physics testing.
This change will make TS 2.10.2(9)b more consistent with SR 3.1.7 of NUREG-1432, Standard Technical Specifications Combustion Engineering Plants, Revision 3. In addition, the Containment Structural Tests Report is deleted from TS 5.9.3c and several administrative and editorial changes were approved.
A copy of the related Safety Evaluation is also enclosed. The Notice of Issuance will be included in the Commission's next biweekly Federal Register notice.
Sincerely,
/RA/
Alan B. Wang, Project Manager Plant Licensing Branch IV Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-285
Enclosures:
- 1. Amendment No. 237 to DPR-40
- 2. Safety Evaluation cc w/encls: See next page DISTRIBUTION:
PUBLIC RidsOgcRp PDIV-2 Reading RidsAcrsAcnwMailCenter RidsNrrDlpmLpdiv (HBerkow) RidsRegion4MailCenter (DGraves)
RidsNrrPMAWang RidsNrrDlpmLpdiv2 (DCollins)
RidsNrrLALFeizollahi GHill (2)
ACCESSION NO.: ML052700523 OFFICE PDIV-2/PM PDIV-2/LA SXRB/A IROB-A OGC LPLIV/BC NAME AWang LFeizollahi Nakowski TBoyce JZorn DTerao DATE 1/9/06 1/9/06 12/21/05 1/19/06 1/6/06 1/25/06 OFFICIAL RECORD COPY
OMAHA PUBLIC POWER DISTRICT DOCKET NO. 50-285 FORT CALHOUN STATION, UNIT NO. 1 AMENDMENT TO RENEWED FACILITY OPERATING LICENSE Amendment No. 237 License No. DPR-40
- 1. The Nuclear Regulatory Commission (the Commission) has found that:
A. The application for amendment by the Omaha Public Power District (the licensee) dated August 11, 2005, complies with the standards and requirements of the Atomic Energy Act of 1954, as amended (the Act), and the Commission's rules and regulations set forth in 10 CFR Chapter I; B. The facility will operate in conformity with the application, the provisions of the Act, and the rules and regulations of the Commission; C. There is reasonable assurance (i) that the activities authorized by this amendment can be conducted without endangering the health and safety of the public, and (ii) that such activities will be conducted in compliance with the Commission's regulations; D. The issuance of this license amendment will not be inimical to the common defense and security or to the health and safety of the public; and E. The issuance of this amendment is in accordance with 10 CFR Part 51 of the Commission's regulations and all applicable requirements have been satisfied.
- 2. Accordingly, Renewed Facility Operating License No. DPR-40 is amended by changes to the Technical Specifications as indicated in the attachment to this license amendment, and paragraph 3.B. of Facility Operating License No. DPR-40 is hereby amended to read as follows:
B. Technical Specifications The Technical Specifications contained in Appendix A, as revised through Amendment No. 237, are hereby incorporated in the license. The licensee shall operate the facility in accordance with the Technical Specifications.
- 3. The license amendment is effective as of its date of issuance and shall be implemented within 60 days from the date of issuance.
FOR THE NUCLEAR REGULATORY COMMISSION
/RA/
David Terao, Branch Chief Plant Licensing Branch IV Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation
Attachment:
Changes to the Technical Specifications Date of Issuance: February 1, 2006
ATTACHMENT TO LICENSE AMENDMENT NO. 237 RENEWED FACILITY OPERATING LICENSE NO. DPR-40 DOCKET NO. 50-285 Replace the following pages of the Appendix A Technical Specifications with the attached revised pages. The revised pages are identified by amendment number and contain vertical lines indicating the areas of change.
REMOVE INSERT TOC - Page 3 TOC - Page 3 2.1 - Page 21 2.1 - Page 21 2.10 - Page 9 2.10 - Page 9 Table 3-13 Table 3-13 5.0 - Page 6 5.0 - Page 6 5.0 - Page 7 5.0 - Page 7 5.0 - Page 10 5.0 - Page 10 5.0 - Page 11 5.0 - Page 11 5.0 - Page 12 5.0 - Page 12 5.0 - Page 13 5.0 - Page 13 5.0 - Page 14 5.0 - Page 14 5.0 - Page 15 5.0 - Page 15 5.0 - Page 16 5.0 - Page 16 5.0 - Page 17 5.0 - Page 17 5.0 - Page 18 5.0 - Page 18 5.0 - Page 19 -------
SAFETY EVALUATION BY THE OFFICE OF NUCLEAR REACTOR REGULATION RELATED TO AMENDMENT NO. 237 TO RENEWED FACILITY OPERATING LICENSE NO. DPR-40 OMAHA PUBLIC POWER DISTRICT FORT CALHOUN STATION, UNIT NO. 1 DOCKET NO. 50-285
1.0 INTRODUCTION
By application dated August 11, 2005 (Agencywide Documents Access and Management System Accession No. ML052240078), Omaha Public Power District (OPPD) requested changes to the Technical Specifications (TSs)(Appendix A to Renewed Facility Operating License No. DPR-40) for the Fort Calhoun Station, Unit No. 1 (FCS).
The proposed amendment will delete TS 2.10.2(9)b(iii). This surveillance requirement (SR) required the licensee to verify the shutdown margin (SDM) on every 8-hour shift during low power physics testing. This change will make TS 2.10.2(9)b more consistent with SR 3.1.7 of NUREG-1432, "Standard Technical Specifications Combustion Engineering Plants, Revision 3."
In addition, OPPD proposes to delete the Containment Structural Tests Report from TS 5.9.3c and make several administrative and editorial changes.
2.0 REGULATORY EVALUATION
The SDM Test exemption of TS 2.10.2(9)b provides that a minimum amount of control element assembly (CEA) worth is immediately available for reactivity control when physics tests are performed for CEA worth measurement. This will ensure that the operators can respond promptly to unexpected increases in core reactivity during the tests. This special test exemption is needed to permit the periodic verification of the actual versus predicted core reactivity condition occurring because of fuel burnup or fuel cycling conditions. The following criteria apply to the SDM requirements:
Section XI of Title 10 of the Code of Federal Regulations (10 CFR), Part 50, Appendix B, "Quality Assurance Criteria for Nuclear Power Plants and Fuel Reprocessing Plants," requires that a test program be established to ensure that structures, systems, and components will perform satisfactorily in service. All functions necessary to ensure that specified design conditions are not exceeded during normal operation and anticipated operational occurrences must be tested. Testing is required prior to initial criticality, after each refueling shutdown, during startup, low power operation, power ascension, and at power operation. The physics
tests requirements for reload fuel cycles ensure that the operating characteristics of the core are consistent with the design predictions, and that the core can be operated as designed.
Appendix I, "Startup Manual," of the FCS Updated Safety Analysis Report (USAR) defines the requirements for initial testing of the facility, including physics tests. Requirements for reload fuel cycle physics tests are defined in ANSI/ANS-19.6.1-1985 (Reference 7.6 of the licensee's submittal). Although these physics tests are generally accomplished within the limits of all limiting conditions for operations (LCOs), conditions may occur when one or more LCOs must be suspended to make completion of physics tests possible or practical. This is acceptable as long as the fuel design criteria are not violated. As long as Linear Heat Rate (LHR) remains within its limit, fuel design criteria are preserved.
The initial condition criteria for accidents sensitive to core power distribution are preserved by the LHR and DNB parameter limits. The criteria for the loss-of-coolant accident (LOCA) are specified in 10 CFR 50.46, "Acceptance criteria for emergency core cooling systems for light-water nuclear power reactors." The criteria for the loss of a forced reactor coolant flow accident are specified in Chapter 14.6 of the FCS USAR. Operation within the LHR limit preserves the LOCA criteria; operation within the departure from nucleate boiling (DNB) parameter limits preserve the loss of flow criteria.
The remaining changes proposed by this LAR are administrative or editorial in nature.
3.0 TECHNICAL EVALUATION
3.1 Deletion of SDM SR TS 2.10.2(9)b(iii)
Physics testing is required prior to initial criticality, after each refueling shutdown, during startup, low power operation, power ascension, and at power operation. The physics tests requirements for reload fuel cycles ensure that the operating characteristics of the core are consistent with design predictions and that the core can be operated as designed.
Physics test procedures are written and approved in accordance with established formats. The procedures include all information necessary to permit a detailed execution of testing required to ensure that the design intent is met. Physics tests are performed in accordance with these procedures, and test results are approved prior to continued power escalation and long-term power operation. Examples of physics tests include determination of critical boron concentration, CEA group worths, reactivity coefficients, flux symmetry, and core power distribution. It is acceptable to suspend certain LCOs for physics tests because fuel damage criteria are not exceeded. Even if an accident occurs during physics tests with one or more LCOs suspended, fuel damage criteria are preserved because adequate limits on power distribution and shutdown capability are maintained.
TS 2.10.2(9)b provides an exemption to the SDM required by TS 2.10.2(1). During the low power physics testing for CEA worth and SDM, the SDM requirement may be reduced provided the following conditions are met:
- 1. The SDM can be reduced to the worth of the highest estimated CEA from the operable withdrawn CEAs and clarifies that during measurement of CEA worth, an allowance for the most reactive stuck CEA (of the groups withdrawn) is assumed when calculating SDM;
- 2. During low power physics testing, the position of each CEA required to be trippable is determined at least once every two hours; and
- 3. Each CEA not fully inserted must be demonstrated capable of full insertion when tripped from at least the 50 percent withdrawn position within 7 days of reducing SDM to less than the limits of TS 2.10.2(1).
These requirements ensure that SDM is sufficient at all times to enable the reactor to be quickly shutdown, if necessary, during low power physics testing. These requirements are similar to those of TS 3.1.7, "Special Test Exceptions (STE) - SHUTDOWN MARGIN (SDM)" of NUREG-1432.
OPPD has proposed to delete TS 2.10.2(9)b(iii). During the SDM low power physics testing, TS 2.10.2(9)b(iii) states that SDM "shall be verified every 8-hour shift." The purpose of TS 2.10.2(9) is to permit relaxation of existing LCOs to allow the performance of certain physics tests to determine CEA worth and shutdown margin. The SDM exemption of TS 2.10.2(9)b is needed to permit the periodic verification of the actual versus predicted core reactivity condition occurring because of fuel burnup or fuel cycling conditions. This special test exemption assures that a minimum amount of CEA worth is immediately available for reactivity control when physics tests are performed for CEA worth measurement.
Reactivity control during low power physics testing is provided primarily by trippable CEAs whose position is determined every 2 hours2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br /> in accordance with TS 2.10.2(9)b(i)2. Should the SDM required by TS 2.10.2(9)b(i) be unavailable, TS 2.10.2(9)b(ii) requires boration to be initiated immediately and continued until the SDM required by the Core Operating Limits Report (COLR) is achieved. Requiring that shutdown reactivity equivalent to at least the highest estimated CEA worth (of those CEAs actually withdrawn) be available for trip insertion from the operable CEA provides a high degree of assurance that shutdown capability is maintained for the most challenging postulated accident, a stuck CEA. If, however, the SDM requirement of TS 2.10.2 is suspended, there is not the same degree of assurance during this test that the reactor would always be shut down if the highest worth CEA was stuck out and calculational uncertainties or the estimated highest CEA worth was not as expected (i.e., the single-failure criterion is not met). However, the NRC staff concludes that this situation is acceptable because specified acceptable fuel limits are still met. The risk of experiencing a stuck CEA and subsequent criticality is reduced during this Physics Test exception by the requirements to determine CEA positions every 2 hours2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br />; by the trip of each CEA to be withdrawn 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> prior to suspending the SDM; and by ensuring that shutdown reactivity is available, equivalent to the reactivity worth of the estimated highest worth withdrawn CEA. Thus, the TS 2.10.2(9)b(iii) requirement to verify SDM every 8-hour shift is unnecessary. The SRs that remain in TS 2.10.2(9)b following the deletion of (iii) adequately verify SDM during low power physics testing and are consistent with SR 3.1.7 of NUREG-1432, Revision 3.
In addition, an audible count rate signal and makeup controller alarm warn the control room to allow corrective actions to be taken to isolate the primary makeup water source by closing valves and/or stopping the primary makeup water pumps or the charging pumps. Because of the equipment and controls and the administrative procedures provided for the boron dilution operation, the probability of erroneous dilution is considered very small. Nevertheless, if an unintentional dilution of boron in the reactor coolant does occur, numerous alarms and indications are available to alert the operator to the condition. Therefore, for the hot standby, hot shutdown, cold shutdown, and refueling modes, the maximum reactivity addition due to the dilution is slow enough to allow the operator to determine the cause of the dilution and take corrective action before the required shutdown margin is completely lost.
Deletion of the requirement to verify SDM each shift is acceptable, because the SRs that remain in TS 2.10.2(9)b ensure that the SDM provided by the CEAs is adequate and that the CEAs are capable of full insertion. As CEA positions will be verified at least once per 2-hour interval during low power physics testing and provide adequate SDM, the 8-hour SDM SR is a redundant requirement. In addition, it would be unlikely that the SDM surveillance of TS 2.10.2(9)b(iii), which is performed at an 8-hour interval, would result in the discovery that SDM is insufficient before the control room is alerted by an increase in the count rate or makeup controller alarm. Should the SDM provided by the CEAs be unavailable, boration is initiated immediately and continued until the SDM required by the COLR is met. Based on the above, the Nuclear Regulatory Commission (NRC) staff concludes that TS 2.10.2(9)b(iii) may be deleted from the TSs. This change is consistent with SR 3.1.7 in NUREG-1432, which does not include this SR.
3.2 Deletion of Containment Structural Tests Report From TS 5.9.3c, "Special Reports" OPPD has proposed to delete "Containment Structural Tests Report" from TS 5.9.3c, "Special Reports." Amendment 216 relocated TS 3.5(5), which contained requirements for submitting the Containment Structural Test report, to the FCS USAR. Thus, although the Containment Structural Tests Report is listed in TS 5.9.3c, there is no TS requirement to submit it. Therefore, the Containment Structural Tests Report of TS 5.9.3c can be deleted from the TSs as a special report that must be submitted to the NRC. In addition, in accordance with paragraph (b)(2)(viii) of 10 CFR 50.55a, conditions indicative of containment structural deterioration or degradation are reported in the Inservice Inspection (ISI) Report prepared in accordance with the American Society of Mechanical Engineers (ASME),Section XI, Subsection IWA-6000 requirements.
OPPD inspects the containment structure in accordance with the criteria of ASME,Section XI, Subsections IWE and IWL, 1992 Edition with the 1992 Addenda. As required by paragraph (b)(2)(viii) of 10 CFR 50.55a, OPPD reports conditions indicative of containment deterioration or degradation in the ISI Summary Report required by ASME,Section XI, Subsection IWA-6000, and TS 5.9.3a. Therefore, the information provided in this report is redundant to the requirements of 10 CFR 50.55a and TS 5.9.3a, and will continue to be provided to the NRC staff.
3.3 Table of Contents Amendment 228 revised TSs 5.5, 5.6, and 5.9.2 to show that they are "Not Used" but did not revise the TOC accordingly. OPPD proposes to revise Page 3 of the Table of Contents (TOC) to reflect the changes approved in Amendment 228 to show TSs 5.5, 5.6, and 5.9.2 as "Not Used." Amendment 231 deleted the remaining routine reports (Monthly Operating Report and
Annual Occupational Exposure Report) of TS 5.9.1. OPPD proposes to revise Page 3 of the TOC to reflect the changes approved in Amendment 231 to show TS 5.9.1 is "Not Used." The NRC staff concludes that this change is administrative in nature and, therefore, is acceptable.
3.4 TS 2.1.6 and its Basis The changes proposed for TS 2.1.6 improve grammatical structure by inserting appropriate punctuation and revising sentences with missing, incomplete, or inappropriate words. The NRC staff has reviewed these changes and agree that they are editorial in nature and, therefore, are acceptable. The NRC staff does not review Bases changes as they are controlled by TS 5.20, "Technical Specification (TS) Bases Control Program."
3.5 Table 3-13, Steam Generator Tube Inspections OPPD proposes to revise Table 3-13, "Steam Generator Tube Inspections," to delete two occurrences of the phrase "Prompt notification to the NRC pursuant to specification 5.6."
Amendment 228 deleted TS 5.6, "Reportable Event Action," because its requirements were redundant to 10 CFR 50.72 and 50.73. Therefore, since the FCS TSs no longer contains TS 5.6, the statements contained in Table 3-13 can be deleted. The NRC staff has reviewed these changes and agree that they are administrative in nature and, therefore, are acceptable.
3.6 Page 10 of TS 5.0 OPPD has proposed to delete Page 10 of TS 5.0 which is currently designated as "Not Used."
With the deletion of this page all subsequent TS 5.0 pages are being renumbered accordingly.
The NRC staff has reviewed these changes and agree that they are administrative in nature and, therefore, are acceptable.
3.7 TS 5.16.1g OPPD has proposed to revise the last sentence of TS 5.16.1g to change the period following the words "For noble gases" to a comma. The NRC staff has reviewed this change and concluded it is editorial in nature and therefore, is acceptable.
3.8 TS 5.21 OPPD has proposed to revise TS 5.21 to correct an error showing Revision 3 of Regulatory Guide 1.35, "Inservice Inspection of Ungrouted Tendons in Prestressed Concrete Containments," as issued in 1989. The correct date of Regulatory Guide 1.35, Revision 3 is 1990. The NRC staff has reviewed this change and agrees that it is editorial in nature and, therefore, is acceptable.
4.0 STATE CONSULTATION
In accordance with the Commission's regulations, the Nebraska State official was notified of the proposed issuance of the amendment. The State official had no comments.
5.0 ENVIRONMENTAL CONSIDERATION
The amendment changes a requirement with respect to the installation or use of a facility component located within the restricted area as defined in 10 CFR Part 20. The NRC staff has determined that the amendment involves no significant increase in the amounts, and no significant change in the types, of any effluents that may be released offsite, and that there is no significant increase in individual or cumulative occupational radiation exposure. The Commission has previously issued a proposed finding that the amendment involves no significant hazards consideration, and there has been no public comment on such finding (70 FR 56503; September 27, 2005). Accordingly, the amendment meets the eligibility criteria for categorical exclusion set forth in 10 CFR 51.22(c)9. Pursuant to 10 CFR 51.22(b), no environmental impact statement or environmental assessment need be prepared in connection with the issuance of the amendment.
6.0 CONCLUSION
The Commission has concluded, based on the considerations discussed above, that: (1) there is reasonable assurance that the health and safety of the public will not be endangered by operation in the proposed manner, (2) such activities will be conducted in compliance with the Commission's regulations, and (3) the issuance of the amendment will not be inimical to the common defense and security or to the health and safety of the public.
Principal Contributor: A. Wang Date: February 1, 2006
Ft. Calhoun Station, Unit 1 cc:
Winston & Strawn Mr. Daniel K. McGhee ATTN: James R. Curtiss, Esq. Bureau of Radiological Health 1400 L Street, N.W. Iowa Department of Public Health Washington, DC 20005-3502 Lucas State Office Building, 5th Floor 321 East 12th Street Chairman Des Moines, IA 50319 Washington County Board of Supervisors P.O. Box 466 Blair, NE 68008 Mr. John Hanna, Resident Inspector U.S. Nuclear Regulatory Commission P.O. Box 310 Fort Calhoun, NE 68023 Regional Administrator, Region IV U.S. Nuclear Regulatory Commission 611 Ryan Plaza Drive, Suite 400 Arlington, TX 76011-4005 Ms. Sue Semerera, Section Administrator Nebraska Health and Human Services Systems Division of Public Health Assurance Consumer Services Section 301 Centential Mall, South P.O. Box 95007 Lincoln, NE 68509-5007 Mr. David J. Bannister, Manager Fort Calhoun Station Omaha Public Power District Fort Calhoun Station FC-1-1 Plant P.O. Box 550 Fort Calhoun, NE 68023-0550 Mr. Joe L. McManis Manager - Nuclear Licensing Omaha Public Power District Fort Calhoun Station FC-2-4 Adm.