Letter Sequence Other |
|---|
TAC:MC4305, Elimination of Hydrogen Recombiners and Change to Hydrogen and Oxygen Monitors (Approved, Closed) |
|
MONTHYEARLIC-04-0076, License Amendment Request, Application for Technical Specification Improvement to Eliminate Requirements for Hydrogen Monitors Using the Consolidated Line Item Improvement Process2004-09-0808 September 2004 License Amendment Request, Application for Technical Specification Improvement to Eliminate Requirements for Hydrogen Monitors Using the Consolidated Line Item Improvement Process Project stage: Request ML0508402652005-03-22022 March 2005 3/22/05 Fort Calhoun Station Unit 1 - Issuance of Amd. 234 Elimination of Requirements for Hydrogen Monitors Using the Consolidated Line Item Improvement Process. (Tac. MC4305) Project stage: Approval ML0508404912005-03-22022 March 2005 2 Pages Fort Calhoun - for Amd. 234. Elimination of Requirements for Hydrogen Monitors Using the Consolidated Line Item Improvement Process (Tac. MC4305) Project stage: Other LIC-05-0075, Response to Request for Additional Information on the License Amendment Request, Revisions of Technical Specifications Table 1-1 and Section 4.02005-07-0808 July 2005 Response to Request for Additional Information on the License Amendment Request, Revisions of Technical Specifications Table 1-1 and Section 4.0 Project stage: Response to RAI LIC-05-0098, License Amendment Request (Lar), Deletion of Shutdown Margin Surveillance Requirement and Miscellaneous Administrative Changes2005-08-11011 August 2005 License Amendment Request (Lar), Deletion of Shutdown Margin Surveillance Requirement and Miscellaneous Administrative Changes Project stage: Request ML0525105042005-08-31031 August 2005 Framatome Anp, Inc 77-5069740-NP-00, Shearon Harris Criticality Evaluation Project stage: Request HNP-05-103, Request for License Amendment to Credit Soluble Boron for Fuel Storage Pools2005-09-0101 September 2005 Request for License Amendment to Credit Soluble Boron for Fuel Storage Pools Project stage: Request ML0516802672005-10-0303 October 2005 Issuance of License Amendment 236 Conversion of TS Section 4.0 to STS Format Project stage: Approval ML0528003522005-10-0303 October 2005 Tech Spec Pages for Amendment 236 Conversion of TS Section 4.0 to STS Format Project stage: Other ML0609300532005-11-0808 November 2005 FCS LAR for Criticality Control During Spent Fuel Cask Project stage: Other ML0527005232006-02-0101 February 2006 License Amendment, Deletion of Shutdown Margin During Low Power Testing from TS and Various Other Editorial and Administrative Changes Project stage: Other ML0606902832006-02-0101 February 2006 Technical Specifications, Deletion of Shutdown Margin During Low Power Testing from TS and Various Other Editorial and Administrative Changes Project stage: Other ML0606703202006-03-0101 March 2006 License Amendment 238 Regarding Inoperability of Snubbers Project stage: Approval ML0606902822006-03-0101 March 2006 Tech Spec Pages for Amendment 238 Regarding Inoperability of Snubbers Project stage: Other LIC-06-0023, Response to Requests for Additional Information and Revision of Fort Calhoun Station Unit No. 1 License Amendment Request, Criticality Control During Spent Fuel Cask Loading in the Spent Fuel Pool2006-03-27027 March 2006 Response to Requests for Additional Information and Revision of Fort Calhoun Station Unit No. 1 License Amendment Request, Criticality Control During Spent Fuel Cask Loading in the Spent Fuel Pool Project stage: Response to RAI ML0610100482006-04-10010 April 2006 Tech Spec Pages for Amendment 239 Regarding Adding Limits and Controls for the Spent Fuel Cask Loading and Unloading Operations in the Spent Fuel Pool Project stage: Other ML0610006062006-04-10010 April 2006 Issuance of License Amendment 239 Regarding Adding Limits and Controls for the Spent Fuel Cask Loading and Unloading Operations in the Spent Fuel Pool Project stage: Approval LIC-06-0065, Closure of NRC TAC Issues for Fort Calhoun Station Unit No. 12006-07-0606 July 2006 Closure of NRC TAC Issues for Fort Calhoun Station Unit No. 1 Project stage: Other 2005-08-31
[Table View] |
Text
TECHNICAL SPECIFICATIONS TABLE 2-10 Post-Accident Monitorinq Instrumentation Operating Limits Minimum Operable Instrument Channels Action
- 1. Containment Wide Range Radiation 2
(a)
Monitors (RM-091A & B)
- 2. Wide Range Noble Gas Stack Monitor RM-063 (Noble Gas Portion Only) 1 (a)
- 3. Main Steam Line Radiation Monitor 1
(a)
(RM-064)
- 4. Not Used
- 5. Containment Water Level Narrow Range (LT-599 & LT-600) 1 (d)
Wide Range (LT-387 & LT-388) 2 (b)(c)
- 6. Containment Wide Range Pressure 2
(b)(c)
- 7. Reactor Coolant System Subcooled Margin Monitor 2
(e)(f)
- 8. Core Exit Thermocouples (i) 2/Core Quadrant (g)(h)
- 9. Reactor Vessel Level (HJTC) ()
2 (k)(l)
(a) With the number of OPERABLE channels less than required by the minimum channels operable requirements, initiate the pre-planned alternate method of monitoring the appropriate parameter(s) within 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br />, and
- 1. either restore the inoperable channel(s) to OPERABLE status within 7 days of the event, or
- 2. prepare and submit a special report to the Commission pursuant to specification 5.9.3 within 14 days following the event outlining the action taken, the cause of the inoperability, and the plans and schedules for restoring the system to OPERABLE status.
(b) With one channel inoperable, restore the inoperable monitor to OPERABLE status within 30 days or be in at least HOT SHUTDOWN within the next 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br />.
2.21 - Page 3 Amendment No. 81,82,83,87,11O,1,1, 234
TECHNICAL SPECIFICATIONS TABLE 3-3 (Continued)
MINIMUM FREQUENCIES FOR CHECKS, CALIBRATIONS AND TESTING OF MISCELLANEOUS INSTRUMENTATION AND CONTROLS Channel Description
- 25.
Containment Purge Isolation Valves (PCV-742A, B, C, & D)
- 26.
Not Used
- 27.
Containment Water Level Narrow Range (LT-599
& LT-600)
Wide Range (LT-387 &
LT-388)
- 28.
Containment Wide Range Pressure Indication Surveillance Function
- a. Check FrequencV M
- a. Check
- b. Calibrate
- a. Check
- b. Calibrate
- a. Check
- b. Calibrate M
R M
R M
R Surveillance Method
- a. Verify valve position using control room indication.
- a. CHANNEL CHECK
- b. CHANNEL CALIBRATION
- a. CHANNEL CHECK
- b. CHANNEL CALIBRATION
- a. CHANNEL CHECK
- b. CHANNEL CALIBRATION
- 29.
Toxic Gas Detectors:
YIS-6287A&B (NH3)
- a. Check S
- a. Comparison of readings from redundant channels.
- b. Gas calibration.
- b. Calibrate Q
3.1 - Page 19 Amendment No. 54,68,82,87,107,182, 183, 234