June 15, 2005 Mr. Dennis L. Koehl Site Vice President Point Beach Nuclear Plant Nuclear Management Company, LLC 6590 Nuclear Road Two Rivers, WI 54241-9516

SUBJECT:

REQUALIFICATION PROGRAM INSPECTION

Dear Mr. Koehl:

In a telephone conversation on June 9, 2005, Mr. T. VanDerwarf, Acting Training Manager, and Mr. B. Palagi, Region III Inspector, made arrangements for the NRC to inspect the licensed operator requalification program at the Point Beach Nuclear Plant. The inspection is planned for the week of August 29, 2005, which coincides with your regularly scheduled requalification examination cycle. The staff at your facility should prepare and conduct the requalification examinations in accordance with your NRC-approved requalification program.

In accordance with 10 CFR 55.59(c), the NRC may request facility licensees to submit their biennial comprehensive requalification written examinations or annual operating tests as necessary to support the NRC's inspection program needs. In order for the NRC to adequately prepare for this inspection, please furnish the written examinations and operating tests scheduled for the week of the inspection to the NRC by August 22, 2005. Mr. VanDerwarf has been advised of this request and provided with the name and address of the NRC lead inspector assigned to this inspection.

This letter contains information collections that are subject to the Paperwork Reduction Act of 1995 (44 U.S.C. 3501 et seq.). These information collections were approved by the Office of Management and Budget, approval number 3150-0018, which expires on June 30, 2006.

The public reporting burden for this collection of information is estimated to average 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br /> per response, including the time for reviewing instructions, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments on any aspect of this collection of information, including suggestions for reducing the burden, to the Information and Records Management Branch (T-6 F33), U.S. Nuclear Regulatory Commission, Washington, D.C. 20555-0001, or by Internet electronic mail at BJS1@NRC.GOV; and to the Desk Officer, Office of Information and Regulatory Affairs, NEOB-10202, (3150-0018), Office of Management and Budget, Washington, D.C. 20503-0001.

The NRC may not conduct or sponsor, and a person is not required to respond to, a collection of information unless it displays a currently valid OMB control number.

D. Koehl In accordance with 10 CFR 2.390 of the NRC's Rules of Practice, a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).

Thank you for your cooperation in this matter. If you have any questions regarding this inspection, please contact Bruce Palagi at (630) 829-9611, or me at (630) 829-9707.

Sincerely,

/RA/

Hironori Peterson, Chief Operations Branch Division of Reactor Safety Docket Nos. 50-266; 50-301 License Nos. DPR-24; DPR-27 cc: F. Kuester, President and Chief Executive Officer, We Generation J. Cowan, Executive Vice President Chief Nuclear Officer D. Cooper, Senior Vice President, Group Operations J. McCarthy, Site Director of Operations D. Weaver, Nuclear Asset Manager Plant Manager Regulatory Affairs Manager Training Manager Site Assessment Manager Site Engineering Director Emergency Planning Manager J. Rogoff, Vice President, Counsel & Secretary K. Duveneck, Town Chairman Town of Two Creeks Chairperson Public Service Commission of Wisconsin J. Kitsembel, Electric Division Public Service Commission of Wisconsin State Liaison Officer

D. Koehl In accordance with 10 CFR 2.390 of the NRC's Rules of Practice, a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).

Thank you for your cooperation in this matter. If you have any questions regarding this inspection, please contact Bruce Palagi at (630) 829-9611, or me at (630) 829-9707.

Sincerely,

/RA/

Hironori Peterson, Chief Operations Branch Division of Reactor Safety Docket Nos. 50-266; 50-301 License Nos. DPR-24; DPR-27 cc: F. Kuester, President and Chief Executive Officer, We Generation J. Cowan, Executive Vice President Chief Nuclear Officer D. Cooper, Senior Vice President, Group Operations J. McCarthy, Site Director of Operations D. Weaver, Nuclear Asset Manager Plant Manager Regulatory Affairs Manager Training Manager Site Assessment Manager Site Engineering Director Emergency Planning Manager J. Rogoff, Vice President, Counsel & Secretary K. Duveneck, Town Chairman Town of Two Creeks Chairperson Public Service Commission of Wisconsin J. Kitsembel, Electric Division Public Service Commission of Wisconsin State Liaison Officer DOCUMENT NAME: G:DRS\

To receive a copy of this document, indicate in the box: "C" = Copy without attachment/enclosure "E" = Copy with attachment/enclosure "N" = No copy OFFICE RIII RIII NAME BPalagi:tr HPeterson DATE 06/14/05 06/15/05 OFFICIAL RECORD COPY

D. Koehl ADAMS Distribution:

WDR HKC RidsNrrDipmIipb GEG KGO RGK DRPIII DRSIII PLB1 JRK1 DCT MAB1