ML051050562

From kanterella
Jump to navigation Jump to search
IR 05000285-05-010, on 08/20/2004 Through 02/24/2005 & NOV, Fort Calhoun Station. Operability Evaluation
ML051050562
Person / Time
Site: Fort Calhoun Omaha Public Power District icon.png
Issue date: 04/15/2005
From: Mallett B
NRC Region 4
To: Ridenoure R
Omaha Public Power District
References
EA-05-038 IR-05-010
Download: ML051050562 (35)


See also: IR 05000285/2005010

Text

UNITED STATES

NUCLEAR REGULATORY C O M M I S S I O N

REGION I V

611 RYAN PLAZA DRIVE, SUITE 400

ARLINGTON. TEXAS 76011-4005

April 15, 2005

EA-05-038

R. T. Ridenoure

Vice President

Omaha Public Power District

Fort Calhoun Station FC-2-4 Adm.

P.O. Box 550

Fort Calhoun, NE 68023-0550

SUBJECT: FINAL SIGNIFICANCE DETERMINATION FOR A WHITE FINDING AND

NOTICE OF VIOLATION - FORT CALHOUN STATION - NRC INSPECTION

REPORT 05000285/2005010

Dear Mr. Ridenoure:

On February 24, 2005, the U.S. Nuclear Regulatory Commission (NRC) completed an

inspection at your Fort Calhoun Station. The purpose of the inspection was to follow up on the

failure of Emergency Diesel Generator 2 during surveillance testing. The enclosed inspection

report documents an inspection finding which was discussed on March 2, 2005, with

Mr. R. Phelps, Division Manager of Nuclear Engineering, and other members of your staff.

As described in Section 1R15 of this report, a finding was identified involving the failure to

promptly identify and correct a condition adverse to quality resulting in Emergency Diesel

Generator 2 being inoperable for a period of approximately 29 days, a violation of plant

Technical Specifications. The inspection finding was assessed using the Significance

Determination Process and was characterized as White, a finding with low to moderate

increased importance to safety, which may require additional NRC inspection.

This finding does not present a current safety concern because Emergency Diesel Generator 2

was returned to an operable condition following repairs involving replacement of a failed

component.

During the exit meeting conducted on March 2, 2005, your staff acknowledged the finding and

indicated that Omaha Public Power District agreed with the safety significance of the finding

being characterized as White. In addition, on March 23, 2005, in a telephone conversation with

Dr. Bruce Mallett, Region IV Regional Administrator, you stated Omaha Public Power District's

intention to decline an opportunity to discuss this issue in a Regulatory Conference or provide a

written response.

You have 30 calendar days from the date of this letter to appeal the staff's determination of

significance for the identified White finding. Such appeals will be considered to have merit only

if they meet the criteria given in NRC Inspection Manual Chapter 0609. Attachment 2.

Omaha Public Power District -2-

The NRC also has determined that the finding involves a violation of 10 CFR Part 50,

Appendix B, Criterion XVI, Corrective Actions, which resulted in a violation of plant Technical

Specifications. The violation is cited in the enclosed Notice of Violation, and the circumstances

surrounding the violation are described in the subject inspection report. In accordance with the

NRC Enforcement Policy, the Notice of Violation is considered escalated enforcement action

because it is associated with a White finding.

You are required to respond to the violation and should follow the instructions specified in the

enclosed Notice of Violation when preparing your response.

Because plant performance for this issue has been determined to be in the regulatory response

band, we will use the NRC Action Matrix to determine the most appropriate NRC response for

this condition. We will notify you, by separate correspondence, of that determination.

In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter, its

enclosure, and your response will be made available electronically for public inspection in the

NRC Public Document Room or from the Publicly Available Records (PARS) component of

NRC's document system (ADAMS). ADAMS is accessible from the NRC Web site at

http://www.nrc.qov/readina-rm/adams.html (the Public Electronic Reading Room).

Should you have any questions concerning this inspection, w e will be pleased to discuss them

with you.

Regional Administrator I

Docket: 50-285

License: DPR-40

Enclosures:

1. Notice of Violation

2. NRC Inspection Report 05000285/2005010

cc w/enclosures:

John B.Herman, Manager

Nuclear Licensing

Omaha Public Power District

Fort Calhoun Station

FC-2-4 Adm.

P.O. Box 550

Fort Calhoun, NE 68023-0550

Omaha Public Power District -3-

Richard P. Clemens, Division Manager

Nuclear Assessments

Fort Calhoun Station

P.O. Box 550

Fort Calhoun, NE 68023-0550

David J. Bannister

Manager - Fort Calhoun Station

Omaha Public Power District

Fort Calhoun Station FC-I -1 Plant

P.O. Box 550

Fort Calhoun, NE 68023-0550

James R. Curtiss

Winston & Strawn

1400 L. Street, N.W.

Washington, DC 20005-3502

Chairman

Washington County Board of Supervisors

P.O. Box 466

Blair, NE 68008

Sue Semerena, Section Administrator

Nebraska Health and Human Services System

Division of Public Health Assurance

Consumer Services Section

301 Centennial Mall, South

P.O. Box 95007

Lincoln, NE 68509-5007

Daniel K. McGhee

Bureau of Radiological Health

Iowa Department of Public Health

401 SW 7th Street, Suite D

Des Moines, IA 50309

Chief Technological Services Branch

National Preparedness Division

Department of Homeland Security

Emergency Preparedness and Response Directorate

FEMA Region VI1

2323 Grand Boulevard, Suite 900

Kansas City, MO 64108-2670

Omaha Public Power District -4-

Electronic distribution by RIV:

Regional Administrator (BSMI)

DRP Director (ATH)

DRS Director (DDC)

DRS Deputy Director (SKW)

Senior Resident Inspector (JDHI)

Branch Chief, DRP/C (MCHZ)

Senior Project Engineer, DRP/C (WCW)

Team Leader, DRP/TSS (RLNI)

RlTS Coordinator (KEG)

RidsNrrDiprnLipb

DRS STA (DPL)

J. Dixon-Herrity, OED0 RIV Coordinator (JDH)

FCS Site Secretary (BMM)

Dale Thatcher (DFT)

W. A. Maier, RSLO (WAM)

G. F. Sanborn, D:ACES (GFS)

K. S. Fuller, RC (KSF)

F. J. Congel, OE (FJC)

T. Gwynn (TPG) M. Vasquez (GMV)

D. Powers (DAP) A. Vegel (AXV)

D. Starkey (DRS) M. Tschiltz (MDT)

R. Franovich (RLFZ) S. Richards (SAR)

0E:EA File (RidsOeMailCenter) R4ALLEGE

RIDSSECYMAILCENTER RIDSOCAMAILCENTER

RIDSEDOMAILCENTER RIDSOGCMAILCENTER

RIDSNRROD RIDSNRRADIP

RIDSOPAMAIL RIDSOIMAILCENTER

RIDSOIGMAILCENTER RIDSOCFOMAILCENTER

RlDSRGNlMAILCENTER RIDSRGN2MAILCENTER

RIDSRGN3MAILCENTER RlDSNRRDlPMllPB

OEWEB OEMAIL

SlSP Review Completed: -yes- ADAMS: % Yes 0 No Initials: -mch

% Publicly Available 0 Non-Publicly Available 0 Sensitive X Non-Sensitive

S:\RAS\ACES\ENFORCEMENnEA CASES - OPEN\Fort Calhoun EDG\Final Action\EA-05-038

NOTICE OF VIOLATION

Omaha Public Power District Docket 50-285

Fort Calhoun Station License DPR-40

EA -05-038

During an NRC inspection conducted from August 20, 2004, through February 24, 2005, a

violation of NAC requirements was identified. In accordance with the General Statement of

Policy and Procedure for NRC Enforcement Actions, NUREG-I600, the violation is listed

below:

10 CFR Part 50, Appendix B, Criterion XVI, requires, in part, that measures shall be

established to ensure that conditions adverse to quality, such as failures, malfunctions,

etc., are promptly identified and corrected.

Fort Calhoun Technical Specification 2.7(1), Minimum Requirements, states, in part, that

the reactor shall not be heated up or maintained at temperatures above 300°F unless

the following electrical systems are operable: two emergency diesel generators (DG-I

and DG-2). Technical Specification 2.7(2), Modification of Minimum Requirements,

states, in part, that the minimum requirements may be modified under certain

conditions. Item 2.7(2)(i) states that either one of the emergency diesel generators may

be inoperable for up to 7 days (total for both) during any month, provided certain

conditions are met.

Contrary to the above, on July 21, 2004, during surveillance testing of an emergency

diesel generator, DG-2, the licensee failed to promptly identify and correct a condition

adverse to quality. Specifically, the licensee failed to identify the failure of Fuse 2FU in

the emergency diesel generator excitation circuit. The failure to promptly identify this

failure and correct it resulted in DG-2 being inoperable from July 21 to August 19, 2004,

a period of 10 days in July and 19 days in August. This exceeded the total allowed time

in Technical Specification 2.7 for either emergency diesel generator to be inoperable

during any month.

This violation is associated with a White significance determination process finding.

Pursuant to the provisions of 10 CFR 2.201, Omaha Public Power District is hereby reauired to

submit a written statement or explanation to the U.S. Nuclear Regulatory Commission,

ATTN: Document Control Desk, Washington, DC 20555, with a copy to the Regional

Administrator, U.S. Nuclear Regulatory Commission, Region IV, 61 1 Ryan Plaza Drive,

Suite 400, Arlington, Texas 76011, and a copy to the NRC Resident Inspector at the facility that

is the subject of this Notice, within 30 days of the date of the letter transmitting this Notice of

Violation (Notice). This reply should be clearly marked as a Reply to a Notice of Violation;

EA-05-038 and should include: (1) the reason for the violation or, if contested, the basis for

disputing the violation or severity level, (2) the corrective steps that have been taken and the

results achieved, (3) the corrective steps that will be taken to avoid further violations, and

(4) the date when full compliance will be achieved. Your response may reference or include

previous docketed correspondence, if the correspondence adequately addresses the required

Enclosure 1

-2-

response. If an adequate reply is not received within the time specified in this Notice, an Order

or a Demand for Information may be issued as to why the license should not be modified,

suspended, or revoked, or why such other action as may be proper should not be taken.

Where good cause is shown, consideration will be given to extending the response time.

If you contest this enforcement action, you should also provide a copy of your response, with

the basis for your denial, to the Director, Office of Enforcement, U.S. Nuclear Regulatory

Commission, Washington, DC 20555-0001.

Because your response will be made available electronically for public inspection in the NRC

Public Document Room or from the NRCs document system (ADAMS), accessible from the

NRC Web site at http://w.nrc.aov/readina-rm/adams.html, to the extent possible, it should

not include any personal privacy, proprietary, or safeguards information so that it can be made

available to the public without redaction. If personal privacy or proprietary information is

necessary to provide an acceptable response, then please provide a bracketed copy of your

response that identifies the information that should be protected and a redacted copy of your

response that deletes such information. If you request withholding of such material, you must

specifically identify the portions of your response that you seek to have withheld and provide in

detail the bases for your claim of withholding (e.g., explain why the disclosure of information will

create an unwarranted invasion of personal privacy or provide the information required by

10 CFR 2.390(b) to support a request for withholding confidential commercial or financial

information). If safeguards information is necessary to provide an acceptable response, please

provide the level of protection described in 10 CFR 73.21.

Dated this 15Ihday of April 2005

Enclosure 1

US. NUCLEAR REGULATORY COMMISSION

REGION IV

Docket.: 50-285

License: DPR-40

Report: 05000285/2005010

Licensee: Omaha Public Power District

Facility: Fort Calhoun Station

Location: Fort Calhoun Station FC-2-4 Adm.

P.O. Box 399, Highway 75 - North of Fort Calhoun

Fort Calhoun, Nebraska

Dates: August 20, 2004, through February 24, 2005

Inspectors: J. Hanna, Senior Resident Inspector

L. Willoughby, Resident Inspector

D. Loveless, Senior Reactor Analyst

Approved By: A. Howell 111, Director, Division of Reactor Projects

Enclosure 2

SUMMARY OF FINDINGS

lR05000285/2005010; 08/20/04 - 02/24/05; Fort Calhoun Station; Operability Evaluation.

The report documents the NRCs inspection for Emergency Diesel Generator 2 being

inoperable for 29 days. The inspection identified one finding whose safety significance has

been determined to be White. The significance of most findings is indicated by their color

(Green, White, Yellow, Red) using Inspection Manual Chapter 0609, Significance

Determination Process. The NRCs program for overseeing the safe operation of commercial

nuclear power reactors is described in NUREG-I649, Reactor Oversight Process, Revision 3,

dated July 2000.

A. NRC-identified and Self-Revealincj Findinas

Cornerstone: Mitigating Systems

. White. A violation of 10 CFR Part 50, Appendix 6,Criterion XVI, was identified

for the failure to ensure that conditions adverse to quality, such as failures,

malfunctions, etc., are promptly identified and corrected. Specifically, on July 21,

2004, during surveillance testing of Emergency Diesel Generator 2, the licensee

failed to promptly identify and correct a failure of Fuse 2FU in the emergency

diesel generator excitation circuit. The failure to identify and correct this

condition resulted in Emergency Diesel Generator 2 being inoperable from

July 21 to August 19, 2004, a period of 29 days, exceeding Technical

Specification 2.7 allowed outage time of 7 days during any month when the

reactor coolant system temperature was greater than 300°F.

This finding was considered more than minor because it was associated with the

equipment performance attribute of the mitigating systems cornerstone in that

the licensee failed to promptly identify and correct a failed fuse in the Emergency

Diesel Generator 2 excitation circuit that left the emergency diesel generator

inoperable for a period of 29 days. The finding was characterized under the

significance determination process as having low to moderate safety significance

because Emergency Diesel Generator 2 was unavailable to respond upon

demand for a loss of off-site power and would have been unable to perform its

mitigating system function (Section 1R15).

Enclosure 2

REPORT DETAILS

1. REACTOR SAFETY

Cornerstones: Mitigating Systems

1R15 Operabilitv Evaluations

a. Inspection Scope

The inspectors reviewed the events and the root cause analysis regarding Emergency

Diesel Generator 2 being inoperable for 29 days.

b. Findinas

Introduction. A violation of 10 CFR Part 50, Appendix B, Criterion XVI, was identified for

the failure to ensure that conditions adverse to quality, such as failures, malfunctions,

etc., are promptly identified and corrected. On July 21, 2004, during surveillance testing

of Emergency Diesel Generator 2, the licensee failed to promptly identify and correct a

failure of Fuse 2FU in the emergency diesel generator excitation circuit. The failure to

identify and correct this condition resulted in Emergency Diesel Generator 2 being

inoperable from July 21 to August 19, 2004, a period of 29 days, exceeding Technical

Specification 2.7 allowed outage time of 7 days when the reactor coolant system

temperature was greater than 300°F.

Description. On July 21, 2004, at 8:30 a.m., Emergency Diesel Generator 2 was

declared inoperable and Technical Specification 2.7(2)j was entered to support

conducting the monthly diesel generator surveillance in accordance with Operating

Procedure OP-ST-DG-0002. Emergency Diesel Generator 2 was started to idle speed

and allowed to warm up. Following warmup, the Emergency Diesel Generator 2 speed

was increased to normal operating speed.

Emergency Diesel Generator 2 ran fully loaded for over an hour as required by the

surveillance test. Following the loaded run, Emergency Diesel Generator 2 was

unloaded and the output breaker opened. Within a minute of opening the diesel

generator output breaker, the diesel generator output voltage decreased to

approximately 2200 volts and the Emergency Response Facility Computer (Plant

Computer) annunciated an urgent low alarm for low voltage on Emergency Diesel

Generator 2. The inspectors noted this alarm was acknowledged by a licensed operator

who failed to recognize that this was an indication for an abnormal low voltage condition.

Additionally, at this time, WH/D2 Power Distribution Indicator D-2, a watt-hour meter,

stopped indicating.

Emergency Diesel Generator 2 was operated at normal speed, unloaded, for

approximately 12 minutes to cool down the turbo charger. During this time operators

discussed the loss of indication on the watt-hour meter and decided to write a condition

report on the discrepancy. The inspectors noted that the unexpected low voltage

Enclosure 2

-2-

condition was not identified and entered into the corrective action process. Following

cooldown, Emergency Diesel Generator 2 was then shut down. Operators determined

the surveillance test was successfully completed and declared Emergency Diesel

Generator 2 operable at 11:l8 a.m., exiting Technical Specification 2.7(2)].

No other Emergency Diesel Generator 2 operations occurred until August 18, 2004. On

August 18, 2004, at 10:30 a.m., Emergency Diesel Generator 2 was declared inoperable

and Technical Specification 2.7(2)j was entered to support conducting the monthly

diesel generator surveillance test per Procedure OP-ST-DG-0002. Emergency Diesel

Generator 2 was started to idle speed at 10:51 a.m. and allowed to warm up. Following

warmup, the Emergency Diesel Generator 2 speed was increased to normal operating

speed.

At 11:06 a.m. Emergency Diesel Generator 2 was secured because Emergency Diesel

Generator 2 output voltage had only increased to approximately 2200 volts following

field flash vice its normal value of approximately 4200 volts. Trouble shooting of the

problem commenced at 12:35 p.m. and was completed at 4:55 p.m. A failed fuse, 2FU,

was found in the generator excitation circuit and was replaced. Following successful

testing, Emergency Diesel Generator 2 was declared operable at 5:25 p.m. and

Technical Specification 2.7(2)j was exited. Diesel Generator 1 was also tested to

ensure no common cause failure existed.

On August 19, 2004, Emergency Diesel Generator 2 successfully passed its monthly

surveillance test. The licensee believed Fuse 2FU failed when Emergency Diesel

Generator 2 was started on August 18 when the generator field was flashed.

On October 19, 2004, the licensee notified the NRC that Fuse 2FU failed on

July 21,2004, when the Emergency Diesel Generator 2 output breaker was opened.

This signified that Emergency Diesel Generator 2 was inoperable from July 21 to

August 19,2004.

After a review of this event, the inspectors noted that the licensee had several

opportunities to promptly identify the degraded voltage condition that affected the safety

function of Emergency Diesel Generator 2. These opportunities included:

. The failure to recognize the alarm for low emergency diesel generator output

voltage was indicative of a degraded voltage condition.

. The failure to recognize that the watt-hour meter turns off when emergency

diesel generator output voltage goes below the watt-hour trigger setpoint,

indicative of a degraded voltage condition.

. The failure to recognize that the emergency diesel generator output voltage

meter indications were reading approximately half their normal value, indicative

of a degraded voltage condition.

Enclosure 2

. The failure to recognize that data obtained during surveillance Operating

Procedure OP-ST-DG-0002, performed on July 21,2004, showed the

emergency diesel generator output voltage decreasing to approximately

2200 volts, indicative of a degraded voltage condition. This surveillance

procedure was reviewed and determined satisfactory by three operations

personnel and the system engineer.

Analvsis. The licensee failed to promptly identify and correct a condition adverse to

quality. Specifically, on July 21, 2004, during surveillance testing of Emergency Diesel

Generator 2, the licensee failed to promptly identify and correct a failure of Fuse 2FU in

the emergency diesel generator excitation circuit. The failure to promptly identify and

correct this condition resulted in Emergency Diesel Generator 2 being inoperable from

July 21 to August 19, 2004, a period of 29 days.

The issue was more than minor because it is similar to Example 4.f in NRC Inspection

Manual Chapter 0612, Appendix E, "Examples of Minor Issues," and met the "not minor

if" statement because the failed fuse affected the operability of the diesel generator.

The finding was determined to be of low to moderate safety significance based on a

Phase 1 screening analysis, Phase 2 evaluation, and Phase 2 confirmation analysis.

Siclnificance determination Drocess Phase 1:

In accordance with NRC Inspection Manual Chapter 0609, Appendix A,

"Significance Determination of Reactor Inspection Findings for At-Power

Situations," the inspectors conducted a significance determination process

Phase 1 screening and determined that the finding resulted in loss of the safety

function of Emergency Diesel Generator 2 for greater than the Technical

Specification allowed outage time. Therefore, a significance determination

process Phase 2 evaluation was required.

Siqnificance determination Drocess Phase 2:

In accordance with Manual Chapter 0609, Appendix A, Attachment 1, "User

Guidance for Significance Determination of Reactor Inspection Findings for At-

Power Situations," the inspectors evaluated the subject finding using the Risk-

Informed Inspection Notebook for Fort Calhoun Station, Revision 1. The

following assumptions were made:

. Emergency Diesel Generator 2 was not functional upon the Fuse 2FU

failure and would not have responded upon demand.

. Emergency Diesel Generator 2 was out of service for 28 days 10 hours1.157407e-4 days <br />0.00278 hours <br />1.653439e-5 weeks <br />3.805e-6 months <br />.

Therefore, the exposure window used was 3 to 30 days.

Enclosure 2

-4-

. The failure of Emergency Diesel Generator 2 only affected the risk

associated with a loss of offsite power (LOOP) initiating event, as

provided in Table 2 of the risk-informed notebook.

. While Fuse 2FU was failed, Emergency Diesel Generator 2 could not

have been recovered prior to postulated core damage because of the

following:

- No direct indication existed that Fuse 2FU had failed

- Required use of multimeter to identify that the fuse had failed

- Fuse 2FU was of unique design and replacements were not

immediately available to the operators

Table 2 of the risk-informed notebook requires that only the LOOP worksheet be

evaluated when a performance deficiency affects the diesel generators. All core-

damage sequences requiring emergency power were evaluated. The sequences

from the notebook are as follows:

lnitiatina Event Seauence Mitiaatina Functions Results

Loss of Offsite Power 5 EAC-REC8 6

Loss of Offsite Power I6 I EAC-RECI-TDAFW 1 7 I

Using the counting rule worksheet, this finding was estimated to be WHITE for

internal initiators. In accordance with Inspection Manual Chapter 0609,

Attachment 1, Significance and Enforcement Review Process, the NRC

conducted an independent confirmation of this Phase 2 result.

Phase 2 confirmation analysis:

The NRC compared the results from the modified notebook estimation with an

evaluation developed using a Standardized Plant Analysis Risk (SPAR) model

simulation of the failed Emergency Diesel Generator 2, as well as an

assessment of the licensees evaluation provided by the licensees probabilistic

risk assessment staff. The SPAR runs were based on the following NRC

assumptions:

. The Fort Calhoun SPAR, Revision 3.1 1, model represents an appropriate

tool for evaluation of the subject finding.

. Draft NUREG/CR-XXXX (INEEUEXT-04-02326), Evaluation of Loss of

Offsite Power Events at Nuclear Power Plants: 1986 - 2003, contains the

Enclosure 2

-5-

NRC's current best estimate of both the likelihood of each of the LOOP

classes (i.e., plant-centered,switchyard-centered, grid-related, severe

weather-related, and extreme weather-related) and their recovery

probabilities.

. Emergency Diesel Generator 2 was unavailable to respond upon demand

for the entire time that Fuse 2FU was failed.

. The condition existed for 29 days. The diesel generator was removed

from service at 8:30 a.m. on July 21, 2004, and Fuse 2FU failed prior to

the machine being restored to an operable condition. Repairs were

completed on August 18, 2004, at 5 2 5 p.m. Additionally, the diesel

generator had to be removed from service again on August 19, 2004, to

repeat the required surveillance. The actual outage time was 28 days,

10 hours1.157407e-4 days <br />0.00278 hours <br />1.653439e-5 weeks <br />3.805e-6 months <br />.

. Operators would have been unable to recover Emergency Diesel

Generator 2 prior to postulated core damage.

. The nominal likelihoodfor a LOOP was unaffected by the subject finding.

Initial SPAR Evaluation:

The Fort Calhoun Station SPAR Revision 3.11 model, with the associated LOOP

curves from the draft NUREG, was used for the evaluation of this finding. The

resulting baseline core damage frequency, CDF,. was 1.44 x 10-5/yr.

The NRC developed a change set, to adjust Basic Event EPS-DGN-FS-IB,

"Emergency Diesel Generator 2 Fails to Start, to the House Event "TRUE,"

indicating failure of the component. The SPAR model was requantified with the

resulting current case conditional core damage frequency, CDF ,, of 2.28 x 10

4/yr.

The change in core damage frequency (ACDF) from the model was:

ACDF = CDF,, - CDF,

= 2.28 x I O 4 - 1.44 x I O 5 = 2.14 x 104/yr.

Therefore, the total change in core damage frequency over the exposure time

that was related to this finding was calculated as:

ACDF = 2.14 x 104/yr + 365 dayslyr * 29 days = 1.70 x over the period.

Enclosure 2

-6-

This result indicated that the significance of the finding was inconsistent with the

Phase 2 result. Therefore, the finding was further evaluated.

Adiustments to SPAR:

The NRC noted that the results of the initial SPAR evaluation were more

significant than both the licensee's evaluation and the risk-informed notebook. In

reviewing these differences, it was noted that the licensee's model provided for

recovery of auxiliary feedwater during a station blackout, following battery

depletion. The licensee stated that Fort Calhoun Station had a unique

arrangement for auxiliary feedwater. Auxiliary Feedwater Pump FW-54 is diesel

driven and does not rely on vital ac or dc power. The pump is supplied with fuel

from Diesel Fuel Oil Storage System Tank FO-10. Tank FO-10 has a minimum

volume of 10,000 gallons of diesel fuel as required by Technical Specification 2.7. Eight thousand gallons of the tank's inventory are readily available for use

by Pump FW-54. Therefore, the pump could run for 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> without fuel

addition. The NRC noted that the condensate storage tank would provide about

30 hours3.472222e-4 days <br />0.00833 hours <br />4.960317e-5 weeks <br />1.1415e-5 months <br /> of water based on licensee calculated steam generator steaming rates.

Therefore, makeup water sources were not assessed.

Traditionally, SPAR methodology assumes that auxiliary feedwater fails upon

loss of vital batteries. This failure assumes that instrumentation is lost and

operators overfill the steam generators. Once the steam generators fill to the

main steam lines, water flowing into the steam lines suppresses the steam

supply to the turbine-driven pump. Given the postulated failure of the turbine-

driven pump, the steam generators boil dry and the scenario leads to core

damage. Providing a reliable diesel-driven pump resolves this problem, and the

pump could theoretically continue to feed the steam generators for the 24-hour

mission time.

To give credit for Pump FW-54, the failure mechanisms of the system, including

the operator actions required to continue to feed the steam generators for

24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> were evaluated. These included the following:

. Pump FW-54 must continue to run for 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br />, including fuel supply,

suction source, and the operator attention necessary.

. Operators must transfer the discharge of the system to the auxiliary

feedwater nozzles and manually throttle discharge Valves HCV-I 1078

and HCV-11088 prior to battery depletion.

. Operators must ensure that there is sufficient auxiliary feedwater flow to

prevent core damage.

Enclosure 2

-7-

. The reactor coolant pump seals must remain intact for 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> without

vital ac or dc power. The NRC determined that the reactor coolant pump

seals at Fort Calhoun Station were of the upgraded seal design.

Therefore, the NRC utilized the value for the probability of seal failure

during an extended loss of power, documented in the SPAR model. This

value was 8.9 x lo3.

. Operators must isolate the condensate storage tank prior to loss of

pressure in the associated nitrogen bottle. This action requires manual

isolation of the hotwell supply line before the air-operated valve fails open

and the condensate storage tank inventory is vacuum dragged to the

condenser.

. Operators have a varying amount of time to perform these actions,

depending on the success or failure of two operator actions: (1) operators

minimize dc loads on the battery quickly following a station blackout and;

(2) operators flood the steam generators to 94 percent wide-range level

prior to battery depletion using either Pump W - 5 4 or the turbine-driven

auxiliary feedwater pump.

The NRC used generic steam generator data and certain plant-specific

information from the Final Safety Analysis Report to calculate the

approximate time that operators would have to successfully operate

Pump FW-54 following battery depletion conditional upon the success or

failure of these two actions. The following table documents those times:

Table 3.a

The NRC quantified the probability that the operators fail to minimize dc loads in

a short period of time using the SPAR-H method described in draft NUREG/CR-

XXXX (INEEUEXT-02-01307), The SPAR-H Human Reliability Analysis

Method. The procedural requirements in Emergency Operating Procedure

EOP-00, Standard Post Trip Actions, and Emergency Operating Procedure

Enciosure 2

-8-

Attachment 6, Minimizing DC Loads, were evaluated. The NRC assumed that

this particular action did not require a significant amount of diagnosis because

the EOP-00 has a step and multiple notes reminding the operators to take the

action when necessary. The NRC adjusted the nominal human error

probabilities using the following performance shaping factors:

. Available time was 15 minutes. The NRC assumed that this was just

enough time to coordinate with two plant operators and to open breakers

in the turbine building and the auxiliary building. Therefore, a factor of 10

was used.

. The stress was assumed to be high because of an ongoing station

blackout. Therefore, a factor of 2 was used.

. The complexity was assumed to be moderate because of the

coordination needed with plant operators at two different locations and

the low lighting during the station blackout conditions. Therefore, a factor

of 2 was used.

In addition to these three shaping factors, the NRC adjusted the final result using

the Odds ratio as documented in the draft NUREG, Section 2.5. The probability

that operators would fail to minimize dc loads within 15 minutes of a station

blackout was calculated to be 3.8 x

Using a similar approach, the NRC calculated probabilities of human error for

each of the required operator actions listed above. The times available

documented in Table 3.a. were used to modify the performance shaping factors

based on the time operators had to respond to the particular action. The HRA

values calculated are documented in Table 3.b.

Odds ratio is a method of accounting for the number of successes as well as failures

when calculating a conditional human error probability. This method of accounting for

uncertainties associated with individual performance shaping factors is described in draft

NUCREG-CR-XXXXX (INEEUEXT-02-10309), SPAR-H METHOD, and tends to provide a

less conservative result.

Enciosure 2

-9-

Table 3.b

Operator Failure Probabilities

I Performance Shaping Factors

Operator Action

Isolate CST' 1 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br /> I l.O/O.l' I 2.0 I 0.5/1.0b I 1.0 I1.2~103

Notes:

' Nominal time was available for diagnosis, but there was barely adequate time to take the action.

Nominal stress was used for diagnosis because of control room environment and verbatim emergency

operating procedure compliance. High stress in the field because actions would affect plant safety.

The following items also had the Complexity PSF changed to 0.1 for an obvious diagnosis, and 2.0 for a

moderately complex action: minimize dc loads and swap to AFW nozzles.

Complexity values adjusted to indicate an obvious diagnosis based on emergency operating procedure

review.

The procedures for diagnosing the need for this step were symptom based, but the procedures foi

implementationwere considered by the NRC to be poor.

The procedures for diagnosing the need for this step were symptom based, but the procedures for

implementationwere considered by the NRC to be nominal.

' The experience of operators is nominal for diagnosing this need, but they do not routinely operate the valve

gags in this situation.

The ergonomics were considered poor for swapping the AFW nozzle because an unfamiliar task would have

to be done without normal lighting.

'These actions did not include a significant amount of diagnosis. Therefore, only the action failure probability

was calctilateri

The NRC created an event tree to model the actions required to successfully use Pump

FW-54 following battery depletion. This event tree, provided as Attachment 2 to this

analysis, covered each of the functions required to achieve success, as well as the

Enclosure 2

-1 0-

probability that actions affecting the time available (Le., minimizing dc loads) would be

completed. The NRC used the SPAR to quantify Fault Tree AFW-FW54, "Fort Calhoun

PWR G AFW FW-54," and provide a probability that the Pump FW-54 train would fail

from nominal reasons at any time during the accident sequence. The probability of

failure was determined to be 3.14 x 10'. The NRC then quantified the event tree using

the human reliability values listed in Table 3.b and the solution from the SPAR fault tree

for Pump FW-54 as split fractions. This quantification provided the total failure

probability of the Pump FW-54 train during an unrecovered station blackout, upon

depletion of the station vital batteries. The probability was quantified as 1.08 x 10-1.

The failure probability was a factor of 2, lower than that calculated by the licensee, using

the EPRl Human Reliability Calculator, Revision 2.01. However, given that all human

reliability analysis values used in the SPAR were developed using similar methods, it

was determined that this was a valid best estimate. The sensitivity evaluation

documented below, indicates that the final risk value is very sensitive to this assumption.

Results of Adiusted Analvsis:

The NRC evaluated cutsets from the initial SPAR model evaluation ascertained that

90.4 percent (P(Dep,e,sJ of the risk involved cutsets with auxiliary feedwater failing upon

battery depletion. The NRC determined that these cutsets should be adjusted by the

new failure probability of Pump FW-54, P(54).Therefore, the best estimate change in

core damage frequency was calculated as follows:

ACDF = (Initial ACDF) * ((P(54) * P<Dep,te))+ (1 - Ppep$teJ)

= (1.70 X IO5) * ((1.08 X lo" * 90.4%) + (1 - 90.4%))

= 3.3 x

This best estimate value was in line with the licensee's internal evaluation and

appropriately accounted for the unique design of the Fort Calhoun Station auxiliary

feedwater system. Therefore, it was concluded that the Phase 2 estimation was valid

and should stand as the agency's preliminary risk significance for internal events. This

resulted in determining that the finding was of low to moderate risk significance

(WHITE).

External lnitiatins Events:

In accordance with Manual Chapter 0609, Appendix A, Attachment 1, step 2.5,

"Screening for the Potential Risk Contribution Due to External Initiating Events," the

NRC assessed the impact of external initiators because the Phase 2 significance

determination process result provided a Risk Significance Estimation of 7 or greater.

The methodology used to assess the impact of external events evaluated each initiator

for the Dotential to:

Enclosure 2

-11-

Increase the likelihood of a LOOP.

Impact the reliability or availability of mitigating systems used during a LOOP.

Hiah Winds, Floods. and Other External Events:

The NRC reviewed the licensees Phase I report on the Individual Plant Examination for

External Events (IPEEE) for Fort Calhoun, dated December 29, 1993. The licensee

evaluated these external events in the following categories:

0 High Winds

During the IPEEE development, the licensee had quantified the risk related to

high winds at 5.3 x 1OE/yr. The NRC assumed that high wind events happen

frequently enough that the impact of these severe weather events are already

incorporated into the LOOP frequency. Therefore, only events with winds high

enough to damage safety-related structures (and thus mitigating systems) could

affect the subject finding.

Most of the calculated risk, presented in the IPEEE, was from tornados of

Categories F4 and F5. The frequency of these events hitting the Fort Calhoun

site was estimated as 4.3 x 106/yr. This results in a probability of 3.4 x 10 that

a tornado would hit during any 29-day period. Given the very low probability of

event initiation, it was determined that the change in core damage frequency

caused by the subject finding would be very low.

0 External Floods

As documented in the IPEEE, the licensee evaluated two types of external

floods: those that result from above normal precipitation andfor snow melt

(periodic flooding), and those that result from failure of upstream earthen dams.

Both events could cause a LOOP while affecting mitigating systems.

The NRC reviewed Table 5.2.1, Flood Frequency and Equipment Impact, to

assess the impact of periodic flooding on the risk related to the subject finding. It

was noted that flooding below 1007.5 feet mean sea level (MSL) had no major

impact on plant operations, and flooding above 1013.5 was assumed to fail the

diesel generators as a baseline assumption. Therefore, the NRC evaluated the

change in risk from periodic flooding that resulted in water levels between 1007.5

and 1013.5. The following table, Table 4.a, shows the calculated flooding

frequencies for these events and the equipment expected to be lost at each

level. This information was extracted from Table 5.2.1 of the licensees IPEEE.

Additionally, the conditional core damage probabilities (CCDPs) were developed

using the SPAR model and are also documented in Table 4.a.

Enclosure 2

-1 2-

Table 4.a

Risk Affects to External Flooding

Flood Elevation

II Equipment Lost 1 CCDP IACDF

I

1007.5- 1009.5 3.3x LOOP onlv I 7.8x I 3.8x IO-*

I

1009.5- 1010.8 6.0x 1 Intake I 8.0 x I O 4 I 8.3x I O 9

I

1010.8- 1012.3 9.0x IO- I Intake (10%),3,7I 1 . 5 IO-

~ I 8.4~

1012.3- 1013.5 1.Ox I O 6 Intake (90%),4,79.0x IO- 3.2x IO-

Attachment 3 of this analysis is a spreadsheet showing the calculations used to

determine the ACDF values shown in Table 4.a. The assumptions and

adjustments used are documented in the notes section of the table. Because

each of the flood elevations are statistically independent, the sum of the four

flood scenarios obtained the result of 8.8x IO over the exposure period.

0 Other External Events

Finally, the licensee used the NUREG 1407, Procedural and Submittal

Guidance for the Individual Plant Examination of External Events (IPEEE) for

Severe Accident Vulnerabilities, dated April 1991,to screen out aircraft

accidents and other external initiators from further review. Therefore, the NRC

assumed that the subject finding would have no significant change in the risk

associated with these events.

Internal Fire:

Within the Individual Plant Examination for External Events - Fort Calhoun Station. the

Enclosure 2

-13-

licensee used a screening criteria of 1 x 10 as the threshold for determining that the

fire risk in a given area was negligible. The NRC determined that this screening was

low enough to identify those areas important to the subject finding. The IPEEE

documents 14 fire areas, with 59 fire zones that yielded a nCDF greater than the

screening criteria.

In the internal events evaluation, it was determined that over 99 percent of the internal

risk was related to station blackouts with failures of the auxiliary feedwater system.

Therefore, the NRC reviewed the unscreened fire areas at Fort Calhoun Station to

identify any fires that could result in a LOOP andfor affect the auxiliary feedwater

system. The NRC documented those areas, as potentially significant, in Table 4.b, and

conducted further analyses of these areas.

Table 4.b

The NRC reviewed each of these areas as follows:

0 Transformer Yard Area

It was assumed that internal fire events happen frequently enough and that the

rate of event initiation from these fires is already incorporated into the initiating

event frequencies. To validate this assumption, the NRC took the highest fire

ignition frequency for a fire zone that could cause a LOOP, 8.29 x and

multiplied it by the nonsuppression probability for the area, 5 x This

resulted in a fire mitigation frequency of 4.1 x l o 4 , which is two orders of

magnitude below the LOOP likelihood (3.3 x 10.). Therefore, it was determined

that the fire effects on the subject finding were negligible in the Transformer Yard

Area and screened this area from further review.

Enclosure 2

-14-

0 Compressor, West Switchgear, and Turbine Building Areas

It was assumed that areas that only affected auxiliary feedwater and did not

result in a LOOP would not have a major impact on risk. To validate this

assumption, the NRC evaluated Fire Zone FA46F containing the diesel-driven

auxiliary feedwater pump, Pump FW-54. The ignition frequency was 6.27 x I O 3

and the nonsuppression probability was 5 x IO-*. Multiplying these resulted in a

conservative fire mitigation frequency of 2.1 x IO5. The fire mitigation frequency

for 29 days was then calculated as follows:

FMF=2.1 X I O . ~- 3 6 5 ' 2 9 = 1 . 6 7 X 1 0 ~ 6

It was noted that, for these areas, a LOOP would have to occur following or

coincident with the fire, but prior to the licensee placing the plant in a safe

condition. Assuming that the licensee took 3 days to shut down and cool the

reactor to shutdown cooling pressures, the NRC calculated the probability that a

LOOP occurred during this time, E IL

,,, as follows:

EIL ,, = 3.31 x 10' f 365 * 3 = 2.72 x I O 4

Therefore, the likelihood that a large fire would occur and a LOOP occurred

while the reactor was being shut down and cooled,,,,,E ,I,,L,, was calculated as

follows:

IELF,,E.Loo, = 1.67 x * 2.72 x I O 4 = 4.54 x 10.

This value is low enough to support the assumption that areas where fires would

only affect auxiliary feedwater had a negligible risk increase related to the

subject performance deficiency. Therefore, the NRC screened the compressor,

west switchgear, and turbine building areas from further review.

e East Switchgear Area

In the paragraph regarding the transformer yard above, the NRC calculated a fire

mitigation frequency of 4.1 x 10-4/yrfor this area. This represents the probability

that a fire ignites and the Halon system is unsuccessful. This scenario is the

only one deemed credible that could result in both a LOOP and a loss of the

motor-driven auxiliary feedwater pump. The likelihood that this event is initiated

within the 29 days exposure time, IELFIRE.LOOP, can be calculated as follows:

,E

I,,L, = 4.1 x 104/yr/ 365 * 29 = 3.25 x

Enclosure 2

-1 5-

The area has cabling that feeds offsite power to Switchgear 1A4 in addition to

Switchgear 1A3 itself. Therefore, a large fire without suppression is assumed to

cause a Station Blackout instead of a LOOP, because of the failure of

Emergency Diesel Generator 2.

Given the failure of Emergency Diesel Generator 2, it was determined that this

event would go to core damage without Auxiliary Feedwater Pump FW-54.

Therefore, the NRC set the conditional core damage probability for a fire in the

east switchgear area, with the failure of Emergency Diesel Generator 2,,,,,P , to

the failure probability of the diesel-driven auxiliary feedwater pump upon battery

depletion, calculated previously to be 1.08 x IO'.

To determine the baseline risk for an unsuppressedfire in this area, the NRC

quantified an unrecoverable (extreme weather) LOOP with a failure of

Switchgear 1A3. The resulting CCDP was 1.8 x 10'. It was determined that the

actual CCDP was that quantified multiplied by the failure probability of the diesel-

driven auxiliary feedwater pump upon battery depletion, calculated previously to

be 1.08 x IO-'. Therefore the final baseline CCDP, , , ,P

, was 1.94 x IO3.

The NRC then calculated the change in risk for this area as follows:

ACDF = (3.25 x 1.08 x 10.') - (3.25 x * 1.94 x I O 3 )

= 3.45 x 1 0 - 6

0 Cable Spreading Room

In their IPEEE, the licensee concluded that there were essentially no installed

ignition sources in the cable spreading room. However, hot work and transient

combustibles were considered credible sources of fire in this area. The fire

ignition frequency for hot work was set as 6.7 x 10-4/yrand the frequency for

transient ignition sources was set at 1.I x IO-'/yr by reviewing the Fire Events

Database. This fire area is protected by an automatic Halon system. The

assumed success rate for the Halon system was 95 percent, leading to a

nonsuppression probability of 5 x Therefore, the probability that a large fire

would occur in this area,,,,,P

,, is:

pLARGE = (6.7 x 10-~/yr+ 1.1 x 10-~/yr)* 5 x io2

= 3.9 x I 0-5/yr

The licensee used the same procedures for a large fire in the cable spreading

room as for a main control room evacuation. Therefore, the NRC used the

accepted screening value of 0.1 for the probability of failure to shut down the

reactor from outside the main control room. The NRC also assumed that the

Enclosure 2

-16-

total conditional core damage probability,,,,P ,, would be the failure of remote

shutdown plus the probability of failure of Pump FW-54.

PBAS, = 3.9x105/yr (1.08x10-' 0.1)

= 4.21 x 107/yr

,,,P

, = 3.9 x 105/yr * I .OB x io-'

= 4.21 x 106/yr

The NRC calculated the following ACDF over the 29-day exposure time:

ACDF = (4.21 x 10-6/yr - 4.21 x 107/yr) ) 365 days/yr * 29 days

= 3.0 x

It was determined, based on the lPEEE data, that fires in the cable spreading

room, not requiring control room evacuation, were likely not of importance to this

risk evaluation.

0 Main Control Room

The NRC reviewed a series of main control room fire scenarios documented in

the IPEEE - Fort Calhoun Station. Two major categories of fire were of interest:

(1) fires leading to evacuation, and (2) fires leading to a LOOP and/or auxiliary

feedwater system failures.

Main Control Room Evacuation:

There are 66 electrical cabinets in the Fort Calhoun Station main control room.

Seven cabinets contain automatic Halon suppression systems, while 59 cabinets

would require manual suppression. The basic fire initiation frequency was

1.44 x 10-4/cabinetlyr.Therefore, the total fire ignition frequency for those

cabinets with automatic suppression, ,,F ,I, and for those requiring manual

suppression,,,,F

,F

,I,, can be calculated as follows:

FIFAuT0= 1 . 4 4 10-4/cabinet/yr

~ * 7 = 1.01 x I O 3

FIFMANVAL = 1.44 x 10-4/cabinet/yr * 59 = 8.50 x

The assumed success rate for the Halon system was 95 percent, leading to a

nonsuppression probability of 5 x IO-*.The IPEEE provides that control room

evacuation would be required if a fire was unsuppressedfor 20 minutes.

Assuming that a fire takes 2 minutes to be detected by automatic detection

Enclosure 2

-17-

and/or by the operators, there are 18 minutes remaining in which to suppress the

fire prior to control room evacuation being required. NRC Inspection Manual

Chapter 0609, Appendix F, Attachment 6, Table 48.1, Non-suppression

Probability Values for Manual Fire Fighting Based on Fire Duration (Time to

Damage after Detection) and Fire Type Category, provides a manual

nonsuppression probability for the control room of 1.3 x 1O-*, given 18 minutes

from time to detection until time to damage. Using these values for suppression,

the fire mitigation frequency can be calculated as follows:

FM,F ,, = I .OI x 10-3 * 5 x 10-2 = 5.04 x 10-5/yr

FM,,,,F

,, = 8 . 5 0 ~ 1 0 . ~ i . 3 ~ 1 0 = ~

I . I I x1O4/yr

The NRC reviewed the licensees control room evacuation procedure contained

in Abnormal Operating Procedure AOP-07, Evacuation of Control Room. The

licensees strategy required isolating the vital switchgear from offsite power, then

reenergizing Switchgear 1A3 using Emergency Diesel Generator 2. Given the

failure of Emergency Diesel Generator 2, the NRC determined that this event

would proceed to core damage without Auxiliary Feedwater Pump FW-54.

Therefore, the NRC set the CCDP for a control room evacuation with a loss of

Emergency Diesel Generator 2, PcAsE, to the failure probability of the diesel-

driven auxiliary feedwater pump upon battery depletion, calculated previously to

be 1.08 x 10..

In the IPEEE, the licensee had used the accepted screening value of 0.1 for the

probability of failure to shutdown the reactor from outside the main control room.

The NRC assumed that the total CCDP,,,,P ,, would be the failure of remote

shutdown plus the probability of failure of Auxiliary Feedwater Pump W - 5 4 .

,,,P, = ( 5 . 0 4 ~10-~/yr+ 1.11 x 10-~/yr)* ( 1 . 0 8 ~O I - * 0.1)

= 1.74 x 1WG/yr

,,,P, = (5.04~10-5+i.ii XIO-4) - (I.o~xIO-~)

= I .74 x I 0-5iyr

The NRC calculated the following ACDF over the 29-day exposure time:

ACDF = (1.74 x 105/yr - 1.74 x IO-/yr) + 365 days/yr * 29 days

=1.2x10-6

Enclosure 2

-18-

e Main Control Room Cabinets:

The NRC reviewed each of the control room cabinet fire scenarios presented in

the licensee's IPEEE. Only four scenarios involved fires leading to a LOOP

and/or auxiliary feedwater system failures. These scenarios were:

. Fire in Cabinet CB-4

The NRC determined that this fire scenario affected main feedwater and

Auxiliary Feedwater Pump MI-54. As stated above, it was assumed that

fires affecting auxiliary feedwater but not resulting in a direct LOOP would

not have a major impact on risk. Therefore, this scenario screened from

further analysis.

. Fire in Cabinets CB-IO, CB-I 1, and part of CB-20

This fire scenario could result in a total LOOP. However, it would not

directly cause the failure of auxiliary feedwater system components. As

stated previously, it was assumed that internal fire events happen

frequently enough and that the rate of event initiation from these fires is

already incorporated into the initiating event frequencies. In the case of

this fire scenario, the fire ignition frequency was 4.32 x 10-4/yr. This value

is two orders of magnitude below the LOOP likelihood. Therefore, it was

determined that the fire effects on the subject finding were negligible in

these cabinets and screened this scenario from further review.

. Fire in Cabinet CB-20

This fire scenario could result in a total LOOP. However, it would not

directly cause the failure of auxiliary feedwater system components. As

stated previously, it was assumed that internal fire events happen

frequently enough and that the rate of event initiation from these fires is

already incorporated into the initiating event frequencies. In the case of

this fire scenario, the fire ignition frequency was 1.44 x 104/yr. This value

is two orders of magnitude below the LOOP likelihood. Therefore, it was

determined that the fire effects on the subject finding were negligible in

these cabinets and screened this scenario from further review.

. Fire in Cabinet AI-30A

This fire scenario could result in a reactor trip with the loss of all ac power

to Switchgear 1A3. The NRC determined that for Emergency Diesel

Generator 2 to be required following this fire scenario, offsite power

would have to be lost to Switchgear 1A4. In the case of this fire scenario,

the fire ignition frequency was 5.76 x 10-4/yr. The frequency of a LOOP

Enclosure 2

-19-

to Switchgear 1A4 is assumed to be (3.31 x 10Z/yr 1.75) = 4.8 x

over the 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br />, assuming that it would take 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> to stabilize and

cool the reactor. Therefore, the likelihood that a fire initiates sometime

over a 29-day period followed within 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> by a LOOP to

Switchgear 1A4 is:

FF

,I, = 5.76 x 1O-4/yr/ 365 days/yr * 29 days * 4.8 x 1O 4

= 2.2 x lo-@

Therefore, it was determined that the fire effects on the subject finding

were negligible in these cabinets and screened this scenario from further

review.

Main Control Room Internal Fire ACDF:

The NRC determined that all main control room fires, not requiring evacuation,

were either screened out or it was determined quantitatively that the risk

increase from the subject finding was negligible with respect to those fire

scenarios. Therefore, the total internal fire ACDF quantified was the change in

risk from fires requiring main control room evacuation.

External Events Summary:

As documented above, the NRC determined that the external events important to the

risk associated with the subject finding were external flooding and internal fire. The

four flood scenarios evaluated resulted in a ACDF of 8.8 x I O over the exposure

period. The seven fire areas evaluated resulted in a ACDF of 5.0 x I O 6 over the

exposure period. Therefore the risk of the subject finding related to external events was

the sum of the two, 5.9 x The Phase 2 estimation resulted in a single sequence

with a result of six and another with a result of seven. Using the counting rule, this can

be estimated as a ACDF of 3.6 x Therefore total ACDF for the subject finding can

be calculated as the sum of the internal and external risk:

ACDF = 3.6 x I O 6 + 5.9 x IO-@ = 9.5 x

This result indicates that the change in risk from external initiators caused by this finding

does not cause the significance to increase above the next threshold. Therefore the

finding is of low to moderate risk significance (WHITE).

Enclosure 2

-20-

Potential Risk Contribution from Larqe Earlv Release Frequency:

In accordance with Manual Chapter 0609, Appendix A, Attachment 1, step 2.6,

"Screening for the Potential Risk Contribution Due to LERF," the NRC assessed the

impact of large early release frequency because the Phase 2 significance determination

process result provided a risk significance estimation of seven.

In pressurized water reactors, only a subset of core damage accidents can lead to large,

unmitigated releases from containment that have the potential to cause prompt fatalities

prior to population evacuation. Core damage sequences of particular concern for this

type of reactor are intersystem loss of coolant accidents, steam generator tube ruptures,

and station blackouts.

In accordance with Manual Chapter 0609, Appendix H, "Containment Integrity SDP," it

was determined that this was a Type A finding, because the finding affected the plant

core damage frequency. The NRC evaluated the risk-informed notebook results and

determined that Sequences 2 and 3 were both induced by a LOOP that did not proceed

to a station blackout. In accordance with Appendix H, Section 5.1, step 2, "Accident

Sequence Screening," LOOP sequences with successful emergency ac power operation

will not generally contribute to the large-early release frequency and therefore are

screened out. Additionally, station blackout sequences (Sequences 5 and 6) are

screened from further analysis for large dry containments as described in Appendix H,

Table 5.1, "Phase 1 Screening - Type A Findings at Full Power." Therefore, it was

determined that the subject performance deficiency was not significant to the large-early

release frequency.

Licensee's Risk Assessment:

The licensee evaluated the failure of Emergency Diesel Generator 2 using their

probabilistic risk assessment model. The result of their internal events evaluation was

approximately 3.6 x 1O-6. As stated above, the licensee's model provided for recovery of

auxiliary feedwater during a station blackout, following battery depletion. The licensee

stated that Fort Calhoun Station had a unique arrangement for auxiliary feedwater.

Auxiliary feedwater Pump FW-54 is diesel-driven and does not rely on vital ac or dc

power. The pump is supplied with fuel from Diesel Fuel Oil Storage System

Tank FO-IO. Tank FO-10 has a minimum volume of 10,000 gallons of diesel fuel as

required by Technical Specification 2.7. Eight thousand gallons of the tank's inventory

are readily available for use by Pump FW-54. Therefore, the pump could run for 24

hours without fuel addition. To address this unique design, the licensee used Basic

Event XSB08DC to address the probability that operators would fail to properly run

Pump FW-54 following battery depletion. The licensee had used the EPRl Human

Reliability Calculator, Revision 2.01, to quantify this value. The failure probability used,

2.02 x IO-', was a factor of 2 higher than that calculated by the NRC. However, given

that all human reliability analyses values used in the SPAR were developed using similar

methods, the NRC determined that this was a valid best estimate.

Enclosure 2

-21-

Sensitivitv Studies:

The NRC performed sensitivity studies on major assumptions using the internal events

model. Table 6 summarizes the assumptions and the results. It was determined that

the analysis is very sensitive to the probability of failure selected for running Auxiliary

Feedwater Pump FW-54 during a station blackout following battery depletion.

Additionally, the NRC assessed diesel generator recovery times and the total exposure.

1 and 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br />

NOTES:

1) Three evaluations were run for Pump FW-54: a) using the licensee's value; b) assuming no

credit beyond battery depletion; and c) giving the system single train credit.

2) Diesel Generator recovery is based on one machine. However, for certain conditions, it may be

appropriate to increase the failure probability for recovery if one machine is unrecoverable.

3) The exposure time assumed that the licensee's performance deficiency started when they failed

to recoanize the blown fuse. Had there been reason to know the circuit would have failed. the

I machine was not functional for its mission time for longer than 29 days.

I

All Other Inspection Findings (Not IE, MS, BI Cornerstones)

Not Applicable.

Enforcement. Title 10 of CFR Part 50, Appendix B,Criterion XVI, requires, in part, that

measures shall be established to ensure that conditions adverse to quality, such as

failures, malfunctions, etc., are promptly identified and corrected.

Fort Calhoun Station Technical Specification 2.7(1), Minimum Requirements, states, in

part, that the reactor shall not be heated up or maintained at temperatures above 300°F

unless the following electrical systems are operable: two emergency diesel generators

(DG-I and DG-2). Technical Specification2.7(2), Modification of Minimum

Requirements, states, in part, that the minimum requirements may be modified under

certain conditions. Item 2.7(2)j states that either one of the emergency diesel

generators may be inoperable for up to 7 days (total for both) during any month,

provided certain conditions are met.

Contrary to the above, on July 21, 2004, during surveillance testing of DG-2, the

Enclosure 2

-22-

licensee failed to promptly identify that Fuse 2FU in the emergency diesel generator

excitation circuit had failed. The failure to promptly identify and correct this condition

resulted in DG-2 being inoperable from July 21 to August 19, 2004, a period of 29 days,

violating Technical Specification 2.7(1). This violation of 10 CFR Part 50, Appendix B,

Criterion XVI, is being treated as a violation, consistent with the Enforcement Policy

(VI0 05000285/2005010-01). This violation is in the licensees corrective action

program as Condition Report 200403634.

40A6 Meetinas. lncludina Exit

On March 2, 2005, the inspectors presented the results of the resident inspector

activities to Mr. R. Phelps, Division Manager of Nuclear Engineering, and other

members of his staff who acknowledged the finding.

The inspectors confirmed that proprietary information was not provided by the licensee

during this inspection.

ATTACHMENT 1: SUPPLEMENTAL INFORMATION

ATTACHMENT 2: EVENT TREE

ATTACHMENT 3: SPREADSHEET

Enclosure 2

ATTACHMENT 1

SUPPLEMENTAL INFORMATION

KEY POINTS OF CONTACT

Licensee Personnel

G. Cavanaugh, Supervisor, Nuclear Licensing

M. Core, Manager, System Engineering

P. Cronin, Manager, Shift Operations

M. Frans, Assistant Plant Manager

A. Hackerott, Supervisor, Probabilistic Risk Assessment

R. Haug, Manager, Chemistry

J. Herman, Manager, Nuclear Licensing

R. Kellogg, Senior Nuclear Design Engineer

K. Naser, System Engineering Supervisor

R. Phelps, Division Manager, Nuclear Engineering

C. Sterba, Supervisor, Design Engineering

D. Trausch, Manager, Quality

NRC

M. Hay, Branch Chief

T. Vegel, Deputy Director, Division of Reactor Projects

J. Hanna, Senior Resident Inspector

L. Willoughby, Resident Inspector

LIST OF ITEMS OPENED, CLOSED, AND DISCUSSED

Opened

05000285/2005010-01 VI0 Emergency Diesel Generator 2 Inoperable in Excess of

Technical Specifications due to Failed Fuse

(Section 1R15)

A-1 Attachment 1

LIST OF DOCUMENTS REVIEWED

Part 21 Report, Interim Report Concerning Failures of Gould-Shawmut Fuses, May 8, 1995

Computer plots of Diesel Generator Frequency and Voltage for surveillance testing performed

on August 18,2004

Evaluation of Plant Risk (CDF & LERF) of Diesel Generator Unavailable for 29 days, performed

on November 24,2004

Plant Review Committee Agenda for November 17,2004, Meeting

Memorandum from Peter Graffy (Exelon) to Richard Ronning (OPPD), Ongoing Failure

Anatysis/Special Test Shawmut Amptrap Fuse A25X100 Type 4, dated November 11,2004

Control Room Operator Logs for July 21, 2004

LER 05000296/1993-002-00, An Emergency Diesel Generator Auto-Started as a Result of

Degraded Voltage Condition on 4KV Shutdown Caused by a Blown Fuse, January 3, 1994

LER 05000346/2004-002-00, Reactor Trip During Reactor Trip Breaker Testing Due to Fuse

Failure, October 4, 2004

LER 05000424/2000-002-00, Manual Reactor Trip Following Main Steam Isolation Valve

Closure, June 27,2000

LER 05000457/1991-006-00, Generator Trip Caused by Spurious Actuation of Neutral Ground

Relay, December 23, 1991

LER 05000483/1996-001-00, Licensed Operators initiated a Manual Reactor Trip,

April 25, 1996

LER 05000457/2000-002-00, Automatic Reactor Trip on Power Range Neutron Flux High

Negative Rate Due to Stationary Gripper Fuse FU15 Failure for Control Rod P I 0 Causing the

Rod to Drop into the Core, May 12, 2000

Level ARoot Cause Analysis Report, lnoperability of DG-2 Diesel Generator During Engine

Shutdown, Revision 0

Emergency Response Facility Computer (Plant Computer) alarm printout for July 21, 2004

Surveillance Test Procedures:

OP-ST-DG-0002, Diesel Generator 2 Check, Revision 41 performed on July 21, 2004

OP-ST-DG-0002, Diesel Generator 2 Check, Revision 41 performed on August 18, 2004

OP-ST-DG-0002, Diesel Generator 2 Check, Revision 41 performed on August 19,2004

OP-ST-DG-0002, Diesel Generator 2 Check, Revision 41 performed on September 15, 2004

OP-ST-DG-0001, Diesel Generator 2 Check, Revision 42 performed on July 7,2004

A-2

OP-ST-DG-0001, Diesel Generator 2 Check, Revision 42 performed on August 4, 2004

OP-ST-DG-0001, Diesel Generator 2 Check, Revision 42 performed on September 1,2004

Standing Orders:

SO-G-23, Surveillance Test Program, Revision 51

SO-G-96, Planned LCO Entry Criteria and Equipment Reliability Control, Revision 11

SO-G-7, Operating Manual, Revision 52

SO-0-30, Testing Safety Related Equipment, Revision 8

SO-0-1, Conduct of Operations, Revision 56

SO-G-26, Training and Qualification Programs, Revision 46

SO-G-56, Qualified Life Program, Revision 24

Drawings and Schematics:

File No. 57227, DG-2 Diesel Generator One Line Diagram P&ID, Revision 5

File No. 17397, Schematic Engine Control, Revision 16

File No. 9808, Elementary Diagram AI-30A, Revision 17

File No. 9809, Elementary Diagram AI-30A, Revision 15

File No. 9819, Elementary Diagram AI-306, Revision 16

File No. 9818, Elementary Diagram AI-30B, Revision 15

File No. 6623, 1 Phase Full Static Exciter, Revision 7

File No. 17396, Schematic Engine Control, Revision 6

File No. 17398, Schematic Engine Control, Revision 8

File No. 56795, Component List for Static Exciters AI-l33a-28 & AI-1336-28, Revision 3

Condition Reports:

200402518

200403634

200403662

200404060

A-3 Attachment 1

ATTACHI4EIJT 2

Y)

w

u

2 2 y1

9 2 W

Y

w

Y

Y)

9

W

e:

W

e:

u 2 2 U

U

3

d 24 3

2

U

u 2 2

2- 2 2 LJ

2 2 2

=2

y1 L 4

~ L

TI d Ih c F et 3 I:

-l

r' T

L T I

i

I