ML050540508

From kanterella
Jump to navigation Jump to search
Draft Version of Edwin I. Hatch Nuclear Power Plant - NRC Triennial Fire Protection IR 05000321-03-006 and 05000366-03-006
ML050540508
Person / Time
Site: Hatch  Southern Nuclear icon.png
Issue date: 08/31/2003
From: Ogle C
Division of Reactor Safety II
To: Sumner H
Southern Nuclear Operating Co
References
FOIA/PA-2004-0277 IR-03-006
Download: ML050540508 (41)


See also: IR 05000321/2003006

Text

UNITED STATES

ock

NUCLEAR REGULATORY COMMISSION

REGION 11

sSAM

NUNN ATLANTA FEDERAL CENTER

61 FORSYTH STREET SW SUITE 23T85

g

<ATLANTA,

GEORGIA 30303-8931

Southern Nuclear Operating Company, Inc.

,

ATTN: Mr. H. L. Sumner, Jr.

-:

Vice President

P. O. Box 1295

Birmingham, AL 35201-1295

SUBJECT:

EDWIN I. HATCH NUCLEAR POWER PLANT - NRC TRIENNIAL FIRE

PROTECTION INSPECTION REPORT 05000321/2003006 AND

05000366/2003006

b

Dear Mr. Sumner:

On July 25, 2003; the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at

your Hatch Nuclear Plant Units 1 and 2. T146 enclosed inspection report documents the

inspection findings, which were discussed on that date with Mr. R. Dedrickson and other

members of your staff. Following completion of additional review in the Region II office, a final

exit was held by telephone with Mr. S. Tipps and other members of your staff on

The inspection examined activities conducted under your license as they relate to safety and

compliance with the Commission's rules and regulations and with the conditions of your license.

The inspectors reviewed selected procedures and riecords, observed activities, and interviewed

personnel.

i

This report documents two findings that have potential safety significance greater than very

low significance, however, a safety significance determination has not been completed. One

issue involving a procedural inadequacy did present an immediate safety concern, however,

your staff revised the procedure pri6r to the end of the inspection. The other issue did not

present an immediate safety concbern. In addition, the repor documents three NRC-identified

findings of very low safety significance (Green), all of which were determined to involve

violations of NRC requirements/However, because of the very low safety significance and

because they are entered into your corrective action program, the NRC is treating these three

findings as non-cited violations (NCVs) consistent with Section VLA of the NRC Enforcement

Policy. If you contest any NCV in this report, you should provide a response within 30 days of

the date of this inspection report, with the basis for your denial, to the Nuclear Regulatory

Commission, ATTN.: Docuument Control Desk, Washington DC 20555-0001; with copies to the

Regional Administrator Re" ion II; the Director, Office of Enforcement, United States Nuclear

Regulatory Commission, Washington, DC 20555-0001; and the NRC Resident Inspector at the

Hatch Nuclear Power Plant.

g

V

10

2.

Local Manual Operator Action was Too Difficult and Physically Unsafe

Introduction: A finding of very low safety significance was identified in that a local

manual operator action to operate SSD equipment was too difficult and was also

physically unsafe. The team judged that some operators would not be able to perform

the action. This finding involved a violation of NRC requirements.

Description: The team observed that Steps 4.15.8.1.1 and 9.3.5.1 of the Fire Procedure

relied upon local manual operator actions instead of providing physical protection for

cables or providing a procedure for cold shutdown repairs. Both steps required the

same local manual operator action: 'Manually OPEN 2E1 1 -F01 5A, Inboard LPCI

Injection Valve, as required." This action was to be taken in the Unit 2 drywell access,

which was a locked high radiation, contaminated, and hot area with temperatures over

100 degrees F.

Valve 2E1 1-F015A was a large (24-inch diameter) motor-operated gate valve with a

three-foot diameter handwheel. The main difficulty with manually opening this valve was

lack of an adequate place to stand. An operator showed the team that to perform the

action he would have to climb up to, and stand on a small section of pipe lagging (a

curved area about four inches wide by 12 inches long), and then reach back and to his

right side, to hold the handwheel with his right hand, while reaching forward and to his

right to hold the clutch lever for the motor operator with his left hand. The operator

would not have good balance while performing the action. The foothold, which was

large enough to support only one foot, was well flattened and appeared to have been

used in the past to manually operate this valve. The foothold was about six to seven

feet above a steel grating, and the team observed that the space available for potential

use of a ladder to better access the 2E1 1 -F01 5A valve handwheel was not good.

Other difficulties with manually opening the valve included the heat; the need to wear

full anti-contamination clothing, a hardhat, and safety glasses; and inadequate

emergency lighting (see Section 1 R05.07). Also, there was no note or step in the

procedure to ensure that the RHR pumps were not running before attempting to

manually open the 2E11-FO15A valve. If an RHR pump were running, it could create a

differential pressure across the valve which could make manually opening it much more

difficult. If the operator did not have sufficient agility, strength or stamina, he would be

unable to complete the action. Also, the team judged that inability to remove sweat from

his eyes, due to wearing gloves that could be contaminated, would be a limiting factor

for the operator. In addition, if the operator slipped or lost his balance, he could fall and

become injured. Considering all of the difficulties, the team judged that this action was

physically unsafe and that some operators would not be able to perform it.

The licensee had no operator training JPM for performing this action an

demonstrv

1hat-alfoperators-oouldlperform-the-ectien. One experienced operator,

who appeared to be in much better physical condition that an average nuclear plant

operator, stated that he had manually operated the valve in the past, but that it had bee

very difficult for him.

NAcXe~c

-tC

v

!p

.

I .

I

18

b.

Findings

-No

findings of significance were identified.

1 R21 Safety System Design And Performance Capability

-.01

Design Change Reauest 91-134. SRV Backup Actuation Via Pressure Transmitter

Signals

a.

Inspection Scope

The team performed an independent design review of plant modification DCR 91-134 in

order to evaluate the technical adequacy of the design change package. The scope of

the review and circuit analysis performed by the team was limited to the Group A SRVs

for which the licensee takes credit in mitigating a fire in the fire areas selected for the

inspection.

b.

Findings

Introduction:

An inadequate plant modification, DCR 91-134, failed to implement the design input

requirements of "one-out-of-two taken twice" logic for the SRV's backup actuation using

PT signals.

Description:

DCR 91-134 was implemented in response in to concerns raised in General Electric

Report NEDC-3200P, Evaluation of SRV Performance during January-February 1991

Turbine Trip Events for Plant Hatch Units 1 and 2. In order to ensure that individual

SRVs will actuate at or near the appropriate set point and within allowable limits, a

backup mode of operation for the SRVs was implemented by this DCR. The design was

intended to mitigate the effects of corrosion-induced set point drift of the Target Rock

SRVs.

Automatically controlled, two stage SRVs are installed on the main steam lines inside

containment for the purpose of relieving nuclear boiler pressure either by normal

mechanical action or by automatic action of an electro-pneumatic control system. Each

SRV can be manually controlled by use of a two position switch located in the main

control room. When placed in the "Open" position, the switch energizes the pilot valve

of the~ iidual SRV and causes it to go open. When the switch is placed in the uAuto"

positi nstle SRV is opened upon receipt of either an Automatic Depressurization

SysteDS), or Low-Low Set (LLS) control logic signal. Either signal will initiate

opening of the valve. DCR 91-134 provided a backup mode for initiation of electrical trip

of the pilot valve solenoid which was independent of ADS or LLS logic. The backup

mode required no operator action to initiate opening of the SRVs and was considered a

"blind control loop" to the operators, (i.e., there are no instruments that provide the

operators information concerning the open/close status of the SRVs.)

I

21

specified design input requirements; The independent design verification performed for

DCR 91-134 failed to identify this error in the logic scheme. Additionally, the

Appendix R Impact Review performed for DCR 91-134 failed to identify the potential

failure mode of all eleven SRVs because of fire-induced damage in Fire Area 2104.

Based on the logic input from trip unit master unit relays K31 OD, and K335D and their

associated trip unit slave relays, the plant modification installed for DCR 91-134 failed to

correctly implement the one-out-of-two taken twice" logic that was specified in the SRV

backup actuation via PT signals design change package. This failure has created a

condition where fire-induced failures of two reactor pressure instrument circuit cables,

(within close proximity to each other), could result in spurious actuation of all eleven

SRVs with the eleven SRVs os

i

a stuck open mode of operation. Pending

completion of a significance det rmination by the NRC, this item is identified as URI 50-

366/03-06-06, Inspector Conce s Associated with Implementation o0 DCR 91-134.'

OTHER ACTIVITIES

0

Irtnt~f~ot-^

rn-t

-o~ttn

-

dDoloc

4.

AP'A

- Ads:_

lUetIMMUCIllUIl C111U r-1:ZiU1UL1U11 U1 r-1U~l)VilbZ

a.

Inspection Scope

The team reviewed a sample of licensee audits, self-assessments, and CRs to verify

that items related to fire protection and to SSD were appropriately entered into the

licensee's CAP in accordance with the Hatch quality assurance program and procedural

requirements. The items selected were reviewed for classification and appropriateness

of the corrective actions taken or initiated to resolve the issues. In addition, the team

reviewed the licensee's applicability evaluations and corrective actions for selected

industry experience issues related to fire protection. The operating experience reports

were reviewed to verify that the licensee's review and actions were appropriate.-

The team reviewed licensee audits and self-assessments of fire protection and safe

shutdown to assess the types of findings that were generated and to verify that the

findings were appropriately entered into the licensee's corrective action program.

b.

Findings

No findings of significance were identified.

-

40A6 Meetings. Including Exit

The lead inspector presented the inspection results to licensee management and other

members of the licensee's staff at the conclusion of the onsite inspection on July 25,

2003. Subsequent to the onsite inspectiori, the lead inspector and the Team Leader,

Fire Protection, held a follow-up exit by telephone with Mr. S. Tipps and other members

of licensee management on seugue9003, to update the licensee on changes to the

preliminary inspection findings. The licensee acknowledged the findings.

ADS,:

AOP

APCSB

ATTS

BTP.

CAP

Co 2 .

CRs'

CST.

DCR

ERFBS

FHA

FPP

HCTL

HPCI

1MG

'P

JPM

LLS

LOCA

ma

MOVs

NCV

NFPA~

NRC

OSHA

PT

RCIC'

RHR

SCBAs

SDP

SERs

SRVs;

SSAR

SSD

TS

UFSAR

URI

XLPE

LIST OF ACRONYMS

Automatic Depressurization System

Abnormal Operating Procedure

Auxiliary and Power Conversion System Branch

Analog Transmitter Trip System

Branch Technical Position

Corrective Action Program

Carbon Dioxide

Condition Reports

Condensate Storage

s

Design Change Request

Electrical Raceway Fire Barrier System

Fire Hazards Analysis

Fire Protection Program

Heat Capacity Temperature Limit

High Pressure Coolant Injection

Inspection Manual Chapter

Inspection Procedure

Job Rerformance Measure

WTop Set

of oolant Accident

lb-a

\\Motoyperated Valves

-Cited Violations

National Fire Protection Association'

Nuclear Regulatory Commission

Occupational Safety and Health Administration

Pressure Transmitter

Reactor Core Isolation Cooling

Residual Heat Removal

Self-Contained Breathing Apparatuses

Significance Determination Process

Safety Evaluation Reports

Safety Relief Valves

Safe Shutdown Analysis Report,

Safe Shutdown

Technical Specification

Updated Final Safety Evaluation Reports

Unresolved Item

Cross-Linked Polyethylene

Attachment

cUNITED

-I

^< - at:NUCLEAR

REGULA'

REG

Cfr

SAM NUNN ATLANT

61 FORSYTH STRE

ATLANTA, GEOI

Southern Nuclear Operating Company, Inc.

ATTN: Mr. H. L.'Sumner, Jr.

Vice

President

' P. 0. Box 1295

  • .

Al

Q20fln1 4 0nC

STATES

TORY COMMISSION

ION 11

A FEDERAL CENTER

ET SW SUITE 23T85 .

RGIA 30303-8931

. .

  • ol -

.I

..

Y

csr

Ing am

/AL. Q;JrL I - I rU;

.-,.

'.SUBJECT:

EDWIN I. HATCH NUCLEAR POWER PLANT - NRC TRIENNIAL FIRE'

PROTECTION INSPECTION REPORT 05000321/2003006 AND.'

.05000366/2003006

Dear Mr. Sumner.

'

On July 25, 2003, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at

your Hatch Nuclear Plant Units 1 and 2. The enclosed inspection rep fi documents the

rispection findings, which were discussed on that date with Mr. R. D drickson and other

me

ers of your staff.

A

The inspection examined activities conducted under your licens as they relate to safety and

compliance with the Commission's rules and regulations and with the conditions of your license.

. 'The inspectors reviewed selected procedures and records, bserved activities, and interviewed

personnel.

This report docume ts two findings that have potential s fety significance greater than very

low significance, ho

ver a safety significance determi ation has not been completed. One

'

issue involving a proc dural inadequacy did present aa immediate safety concern, however,

your staff revised the

ocedure prior to the end of th inspection. The other issue did not

present an immediate safety concern. In addition, t

report documents three NRC-identified.'.

findings of very low safe

significance (Green), all f which were determined to involve

violations of NRC require ents. However, becaus of the very low satety significance and

because they are entered to your corrective acti n program, the NRC is treating these three

findings as non-cited violati ns (NVs) consiste

with Section VL.A of the NRC Enforcement

Policy. If you contest any N V in this report, y

should provide a response within 30' days of

the date of this inspection repa, with the bas

for your denial, to the Nuclear Regulatory

Commission, ATTN.: Documen

ontrol

k, Washington DC 20555-0001; with copies to the

\\

Regional Administrator Region II; t

ctor, Office of Enforcement, United States Nuclear

Regulatory Commission, Washington, DC .20555-0001; and the NRC Resident Inspector at the

Hatch Nuclear Power Plant.

(C

following completion of additional review in the Region II office, a final exit was held with'

/ .

And other members of your staff onr

i

SNC, Inc.

'

2

In accordance with 1 0 CFR 2.790 of the NRC's 'Rules of Practice," a copy of this letter and its

enclosure will be available electronically for public inspection in the NRC Public Document

Room or from the Publically Available Records (PARS) component of NRC's document system

(ADAMS). ADAMS is accessible from the NRC Website at

http: /www.nrc.aov/readin -rm/adams.html (the Public Electronic Reading Room).

Sincerely,

Charles R. Ogle, Chief

. I -

Engineering Branch 1

Division of Reactor Safety

Docket Nos.: 50-321, 50-366

License Nos.: DPR-57- NPF-5

Enclosure:

NRC Triennial Fire Protection Iinspection Report 50-321/03-06,.50-366/03-06

w/Attachment: Supplemental Information

i

. .

. .

i

i

.

I

I

.. ...

!

.

i

cc w/en'cl:

J. D. Woodard

Executive Vice President

Southern Nuclear Operating Company, Inc.'

Electronic Mail Distribution

George R. Frederick

General Manager,'Plant Hatch

-

Southern Nuclear Operating Company, Inc.

Electronic Mail Distribution

.

..

.

.

.

.

..

.

.

.I

Raymond D. Baker

Manager Licensing - Hatch

Southern Nuclear Operating Company, Inc.

Electronic Mail Distribution

Arthur H. Domby, Esq.

Troutman Sanders

Electronic Mail Distribution

Laurence Bergen

Oglethorpe Power Corporation

Electronic 'Mail Distribution

(cc w/encl cont'd - See page 3)

I

SNC, Inc.,

3

(cc w/erncl cont'd)

-'Director

Department of Natural Resources

205 Butler Street, SE, Suite 1252

.tlantaGA

30334

Manager, Radioactive Materials Program

Department of Natural Resources

Electronic Mail Distribution

Chairman.

Appling County Commissioners

County Courthouse

Baxley, GA 31513

Resident Manager:

Oglethorpe Power Corporation

Edwin I. Hatch Nuclear Plant

..Electronic Mail Distribution

Senior Engineer - Power Supply

Municipal.Electric Authority

of Georgia'.'

Electronic Mail Distribution

Reece McAlister

Executive Secretary

Georgia Public Service Commission

244 Washington Street, SW

Atlanta, GA 30334

Distribution w/encl:

'

S. Bloom, NRR

L. Slack, RII EICS

RIDSNRRDIPMLIPB

PUBLIC.

OFFICE

RII:DRS

RII:DRS

RII:DRS

.

CONTRCTOR

RiI:DRP

SIGNATURE

NAME

OSMITHR

IN

WI

KSULLIVAN

BONSER

DATE

8/

12003

8/

12003

8/

1200 3

0

8/

12003

8/

/2003

8/

/2003

E-MAILCOPY?

NO

YES

NO

YES

NO

YES

NO

YES

NO

YES

. NO

Y

N

PUBLIC DOCUMENTI

YES

NO

.

FIrlIAL

-nLLUH UUI-T

IAJl.U~

ICIT I'AC.sM\\~cc

.~J~l

Clrancn 1\\hotrcn ' uuSSutitrw

OFFICIAL RECORD COPY

L)UUUMtN I NAMt:

SMRSEng Branch I Viatch 2003-061irmpa

.. 1. .

-

.1

.

.

Docket Nos.:

License Nos.:

Report No.:

Licensee:

Facility:

Location:

Dates:

Inspectors:

Accompanying

Personnel:

U. S. NUCLEAR REGULATORY COMMISSION

REGION II

50-321, 50-366

DPR-57, NPF-5

05000321/2003006 and 05000366/2003006

Southern Nuclear Operating Company

E. I. Hatch Nuclear Plant

P. O. Box 2010-

Baxley, GA. 31513

July 7-11,2003 (Week 1)

July 21-25, 2003 (Week 2)

C. Smith, P E., Senior Reactor Inspector, (Lead Inspector)

R. Schin, Senior Reactor Inspector

G. Wiseman, Fire Protection Inspector

K. Sullivan, Consultant, Brookhaven National Laboratory

S. Belcher, Nuclear Safety Intern, Week 1

Approved by:

Charles R. Ogle, Chief

Engineering Branch 1

Division of Reactor Safety

Enclosure

CONTENTS

SUMMARYOFFINDINGS

.. ........

FIRE .PROTECTION

.

.............

.

.................... .........

..

Systems Required to Achieve and Maintain Post- ire Safe Shutdown ....

Fire Protection of Safe Shutdown Capability ......................................

Post-Fire Safe Shutdown Capability .........................-..

.

Alternate Shutdown Capability/Operational Implementation of Alternative Shutdown

Capability ..................

,

.,.;.'

Communications ....................

'.-

...

Emergency Lighting .................................................

'.':

'Cold Shutdown Repairs .....................................................

iFre Barriers and Fire Area/Zone/Room Penetration Seals ........................

Fire Protection Systems, Features, and Equipment ............................

Compensatory Measures

.

.;.'.'.;

SAFETY SYSTEM DESIGN AND PERFORMANCE CAPABILITY

Design Change Request 91-134, SRV* Backup Actuation Using Pressure Transmitter

'

"'

'

Signals ...

...

~~Sgn l

....

.. .,...,.

...............................................................

OTHER ACTIVITIES

-

Identification and Resolution of Problems.

Meetings Including Exit ...............

.

a

.

.

T

SUMMARY OF FINDINGS

IR 05000321/2003-006, 05000366/2003-006; 7/7-11/2003 and 7/21-25/2003 E. l. Hatch'

Nuclear Plant, Units 1 and 2; Triennial Fire Protection

The report covered an announced two-week period of inspection by three regional inspectors

and a consultant from Brookhaven National Laboratory. Three Green non-cited violations

(NCVs) and two unresolved items with potential safety significance greater than Green were :

'I

identified. The significance of most findings is indicated by their color (Green, White, Yellow,'

Red) using Inspection Manual Chapter (IMC) 0609, 'Significance Determination Process.

(SDP). Findings for which the SDP does not apply may be Green or be assigned a'severity

level after NRC management review. The NRC's program for overseeing the safe operation of

commercial nuclear power reactors is described in NUREG-1 649, "Reactor Oversight Process,"

Revision 3, dated July 2000.

A.

NRC-Identified and Self-Revealing Findings

Cornerstone: Initiating Events, Mitigating Systems, and Barrier Integrity

TBD. The team identified an unresolved item in that a local n)anual operator action, to

prevent spurious opening of all eleven safety relief valves (SFiVs) during a fire event,

would not be performed in sufficient time to be effective. Also, licensee reliance on this

manual action for hot shutdown during a fire, instead of physically protecting cables from

fire damage, had not been approved by the NRC.

-This finding is unresolved pending completion of a significance determination. The

finding is greater than minor because it affects the objective of the mitigating system

cornerstone. Also, the finding has potential safety significance greater than very low'..

safety significance because failure to prevent spurious operation of the SRVs could

result in them opening durinn/certain fire scenariop, thereby complicating the post-fire

recovery actions. (Section

05.04/.05.b.1)

/

Green. The team identified non-cited violatioI/qf 10 CFR 50, Appendix R,

Section III.G.1 and Technical Specificatio Y$)i,.4.1 because a local manual operator

'

action to operate safe shutdown equipme rs

too difficult and was also unsafe. The

licensee had relied on this action Instead of providing physical protection of cables from

fire damage or preplanning cold shutdown repairs. However, the team determined that'

some operators would not be able to perform the action.

The finding is greater than minor because it affected the availability and reliability

objectives and the equipment performance attribute of the mitigating systems

cornerstone. This finding is of very low safety significance because the licensee would

have time to develop and implement cold shutdown repairs to facilitate accomplishment

of the action, this finding did not have potential safety significance greater than very low

safety significance. (Section 1 R05.04/.05.b.2)

I:~

2.:z

Green. The team identified a non-cited violation of 10 CFR 50, Appendix R,.:

Section III.G.2 in that the licensee relied on some manual operator actions to operate

safe shutdown equipment, instead of providing the required physical protection of cables

from fire damage without NRC approval..

The finding is greater than minor because it affected the availability and reliability.

objectives and the equipment performance attribute of the mitigating systems -:.

cornerstone. Since the actions could reasonably be accomplished by operators in a

timely manner, this finding did not have potential safety significance greater than very

low safety significance. (Section 1 R05.04/.05.b.3) -

Green. The team identified non-cited violation 10 CFR 50, Appendix R, Section III.J

were needed to support post-fire operation of safe shutdown equipment.:

The finding is greater than minor because it affected the reliability objective and the

equipment performance attribute of the mitigating systems cornerstone. Since

operators would be able to accomplish the actions with the use of flashlights, this finding

did not have potential safety significance greater than very low safety significance.,:

(Section 1 R05.07.b)

/

TBD: The team identifi~ed rnresolved item in connection with the implementation of

-

Ad

design change reques((Dl))b 1-134, SRV Backup Actuation via Pressure Transmitter

'

-

Signals. The installed plant modification failed to implement the "one-out-of-two taken

twice logic that was specified as a design input requirements in the design change

package. Additionally, implementation of a "two-out-of-two coincidence taken twice

logic has introduced a potential common cause failure of all eleven SRVs as a result of

-

the potential for fire induced damage to two instrumentation circuit cables in close

proximity to each other.

""- '

.i..1

!

This finding is unresolv4 d pending completion of a significance determination. This

finding is greater thpn

ninor because it impacts the mitigating systpr~i cornerstone. 'This

finding has the pot nti I for defeating manual control of Group

-

RVs that are required

for ensuring that t e-s

pession pool temperature will not e

ed the heat capacity

temperature limit

the suppression pool. (Sectio

R21.01.b) -

Licensee-Identified Violations

B.

/Jt~T.i

None

i

REPORT DETAILS

1.

REACTOR SAFETY

Cornerstones: Initiating Events, Mitigating Systems and Barrier Integrity

1R05 Fire Protection

The purposq'of this inspection was to review the Hatch Nuclear Plant fire protection

program (FPP) for selected risk-significant fire Ureas. Emphasis was placed on

verification that the post-fire safe shutdown (SSD) capability and the fire protection

features provided for ensuring that at least one redundant train of safe shutdown

systems is maintained free of fire damage. The inspection was performed in

accordance with the Nuclear Regulatory Commission (NRC) Reactor Oversight Program

using a risk-informed approach for selecting the fire areas and attributes to be

inspected. The team used the licensee's Individual Plant Examination for External

Events and in-plant tours to choose four risk-significant fire areas for detailed inspection

and review. The fire areas chosen for review during this inspection were:,.

Fire Area 2016, West 600 V Switchgear Room, Control Building, Elevation 130

feet.

Fire Area 2104, East Cableway, Turbine Building, Elevation 130 feet.

.

Fire Area 2404, Switchgear Room 2E, Diesel Generator Building, Elevation 130 -

.feet.

  • -

-

Fire Area 2408, Switchgear Room 2F, Diesel Generator Building, Elevation 130

feet.

.

The team evaluated the licensee's FPP against applicable requirements, including

Operating License Condition 2.C.(3)(a), Fire Protection; Title 10 of the Code of Federal

Regulations, Part 50 (10 CFR 50), Appendix R; 10 CFR 50.48; Appendix A of ranch.

Technical Position (BTiP) Auxiliary and Power Co rversion Systems Branch (A7CSB)

9.5-1; related NRC Safety Evaluatj6n Reports (S Rs); the Hatch Nuclear. Plant Updated

Final Safety Analysis Report (UFVAR); and plant'rS. The team evaluated all areas of

this inspection, as documented below, against these requirements.

Documents reviewed by the team are listed in the attachment.

.01

Systems Required to Achieve and Maintain Post-Fire SSD

a.

Inspection Scope

The licensee's Safe Shutdown Analysis Report (SAR) was reviewed to determine the

components and systems necessary to achieve and maintain safe shutdown conditions

in the event of fire in each of the selected fire areas. The objectives of this evaluation

were as follows:

A^

2.

c

X Verify that the licensee's shutdown methodology has correctly identified

the components and systems necessary to achieve and maintain a SSD

condition.

Confirm the adequacy of the systems selected for reactivity control,

'reactor

coolant makeup, reactor heat removal, process monitoring and

support system functions.-'

c

Verify that a SSD can be achieved and maintained without off-site power,'

when it can be confirmed that a postulated fire in any of the selected fire

areas could cause the loss of off-site power.

-

Verify that local manual operator actions are consistent with the plant's'-

fire protection licensing basis.

  • b.

.Findings

The team identified a potential concern in that the licensee used manual actions tV

di connect terminal board sliding links In order to isolate two 4 to 20 milli-amp (r)

'

intrumentation loop control circuits in order to prevent the spurious actuation of eleven'

V

This issue is discussed in section 1 R05.03.b of the report. No other findings of

significance were identified.'

.02

Fire Protection of SSD Capabilitv

a.

Inspection Scope

For the selected fire areas, the team evaluated the frequency of fires or the potential for

fires, the combustible fire load characteristics and potential fire severity, the separation

of systems necessary to achieve SSD, and the separation of electrical components and: -

'

circuits located within the same fire area to ensure that at least one SSD path was free

of fire damage. The team also inspected the fire protection features to confirm they..

were installed in accordance with the codes of record to satisfy the applicable separation

and design requirements of 10 CFR 50, Appendix R, Section III.G, and Appendix A of

BTP APCSB 9.5-1. The team reviewed the following documents, which established the

controls and practices to prevent fires and to control combustible fire loads and ignition

sources, to verify that the objectives established by the NRC-approved FPP were

'

satisfied:

,

UpdatedFinarSaferyAnalysi

4Section 9.1-A, Fire'Protection

Plan

Administrative Procedure 40AC-ENG-008-OS, Fire Protection Program

Administrative Procedure 42FP-FPX-01 8-OS, Use, Control, and Storage of

Flammable/Combustible Materials

.

Preventive Maintenance Procedure 52PM-MEL-012-0, Low Voltage Switchgear

Preventive Maintenance

The team toured the selected plant fire areas to observe whether the licensee had

properly evaluated in-situ fire loads and limited transient fire hazards in a manner

consistent with the f-ie prevention and combustible hazards control procedures. In

addition, the team reviewed the licensee's ffOe safety inspection reports and corrective

action program (CA ) condition reports (C s) resulting from fire, smoke, sparks, arcing,

'and oehangiciet frte years 2000-2002 to assess the effectiveness of the fire'

prevention Orogrami

and to identify any maintenance or material condition problems

related to fire incidents.

The team reviewed fire brigade response, fire brigade qualification training, and drill

iprogram procedures; fire brigade drill critiques; and drill records for the operating shifts

from January 1999 - December 2002.; The reviews were performed to determine

whether fire brigade drills had been conducted in high fire risk plant areas and whether

fire brigade personnel qualifications; drill response, and performance met the

  • requirements of the licensee's approved FPP.

The team walked down the fire brigade equipment storage areas and dress-out locker

areas in the fire equipment building and the turbine building to assess the condition of

  • .~~fire

fighting and smoke control equipment. Fire brigade personal protective equipment..

located at both of the fire brigade dress-out areas and fire fighting equipment storage

area in the turbine building were revijewed to evaluate equipment accessibility and

functionality. Additionally, the team observed whether emergency exit lighting was

' .

providedtfor personn

eacuaoition pathways to the oUtside exits as identified in' t

National Fire Protection Association (N-jPA) 101 L

afety Code' and the

Occupational Safety and Health Administrto (S(IA)Pr

190, Occupational Safety

and Health Standards. This review also included examination of whether backup

emergencylighting was provided for access pathways to and within the fire brigade

equipment storage areas an- dress-out locker areas in support of fire brigade'

operations should power faill uring a fire emergency. The fire brigade self-contained

breathing 'apparatuses (SCq As) were reviewed for adequacy as well as the availability

of supplemental breathing air tanks and their refill capability.

The team reviewed fire fighting pre-f ire plans for the selected areas to determine If

appropriateainformation was provided to fire brigade members and plant operators to

facilitate suppression of a fire that could impact SSD. Team members also walked

down the selected fire areas to compare the tsscinated pre-f ire plans and drawings with

as-built plant conditions. This was done to v. rifyethat fire fighting pre-fcire plans and

drawings were consistent with the fire protetion features and potential fire conditions

described in'the Fire Hazards Analysis (FfA).

  • The team reviewed the adequacy of the design, installation, and operation of the Manual

suppression standpipe and fire hose system for the control building. This was

s

accomplished by reviewing the FHA, pre-fire plans and drawings, engineering'

  • mechanical equipment drawings, design flow and pressure calculations, and NFPA 14

for hose station location, water flow requirements and effective reach capability. -Team

members also walked down the selected fire areas in the control building to ensure that

hose stations were not blocked and to verify that the required fire hose lengths to reach

the safe shutdown equipment in each of the selected areas were available. Additionally,

the team observed placement of the fire hoses and extinguishers to assess consistency

'

.'with

the fire fighting pre-fire plans and drawings..

    • b.

Findings

No findings of significance were Identified.

.03.

a.-

4

Post-Fire SSD Capability

Inspection Scope

On a sample basis, the inspectors evaluated whether the systems and equipment

identified in the licensee's SSAR as being required to achieve and maintain hot,.

.::

shutdown conditions would remain free of fire damage in the event of fire in the selected

fire areas. The evaluation included a review of cable routing data depicting the location

of power and control cables asso ated with SSD Path I and Path 2 components of the

reactor core isolation cooling (RqlC) and high pressure coolant injection (HVCI).

systems. Additionally, on a sample basis, the team reviewed the licensee's analysis of..

electrical protective devicg (e.g., circuit breaker, fuse, relay) coordination. The following

motor operated valves (10Vs)

and other components were reviewed:.-

Component ID '

Description

2E51-F029

RCIC Pump Suction from Suppression Pool Valve "

2E51 -F01 0

RCIC Pump Suction Valve from Condensate Storage Task (CIT

.

2P41-C001A

Plant Service Water Pump

2211-F011A

Residual Heat Removal (RI 1R) Heat Exchanger A Drain to

Suppression Pool Valve

2P41 -C001 B

Plant Service Water Pump 2B

2E41-F001

HPCI Turbine Steam Supply Valve

2E41-F002

HPCI Turbine Steam Supply Inboard Containment Isolation Valve:

I

II

2E41 -F006

HPCI Pump Inboard Discharge Valve

2E41 -FOO8

HPCI Pump Discharge Bypass Test Valve to CST

. b..

Findings

The team identified a potential concern In that the licensee used manual actions to

isolate two 4 to 20 ma instrumentation loop control circuits associated with eleven SRVs

in lieu of providing physical protection. This did not appear to be consistent with the

plant's licensing basis nor 1 0 CFR 50 Appendix R. Spurious action of these SRVs could

impact the licensee's fire mitigation strategy. In addition, the licensee provided no

objective evidence that post-fire safe shutdown equipment could mitigate this event.

The SSAR stated that a fire in Fire Area 2104 could cause all eleven SRVs to spuriously

actuate as a result of fire damage to two cables located in close proximity in this area.

The specific circuits that could cause this event were identified by the licensee as

circuits: ABE019C08 and ABE019C09. Each circuit separately provides a 4 to 20 ma

instrumentation signal from an SRV high-pressure actuation transmitter 2B21-N127B or

2B21-N127D to its respective master trip unit (2B21-N697B or 2B21-N697D). The

purpose of this circuitry was to provide an electrical backup to the mechanical trip:

capability of the individual SRVs. In the event of high reactor pressure, the circuits

would provide a signal to the master trip units which would cause all eleven SRVs to

actuate (open). The pressure signal from each transmitter would be conveyed to its

respective master trip unit through a two-conductor, instrument cable that was routed

through this fire area (two separate cables). Each cable consisted of a single twisted

pair of insulated conductors, an uninsulated drain wire that was wound around the

twisted pair of conductors, and a foil shield. In Fire Area 2104, the two cables were

located in close proximity in the same cable tray. Actuation of the SRV electrical backup..

is completely "blind" to the operators. That is, unlike ADS, it does not provide any pre-

actuation indication (e.g., actuation of the ADS timer) or an inhibit capability (e.g., ADS

inhibit switch). Because the operators typically would not initiate a manual scram until

fire damage significantly interfered with control of the plant, it is possible that all eleven

SRVs could open at 100% power, prior to scramming the reactor. This event could

-place the plant in an unanalyzed condition..

Unlike a typical control circuit, a direct short or "hot short" between conductors of a

4 to 20 ma instrument circuit may not be necessary to initiate an undesired (false high)

signal. For cables that transmit low-level Instrument signals, degradation of the..

insulation of the individual twisted conductors due to fire damage may be sufficient to

cause leakage current to be generated between the two conductors. Such leakage'

'current would appear as a false high pressure signal to the master trip units. If both

-

cables were damaged as a result of fire, false signals generated as a result of leakage

current in each cable, could actuate the'SRV electrical backup scheme which would

i cause all eleven SRVs to open. The con ductor insulation and jacket material of each

cable was cross-linked polyethylene (XLOPE). Because both cables were in the same

tray and exposed to the same heating rate, there would be a reasonable likelihood that

' both instrumentation cables could suffer insulation damage at the samne time and both

circuits could fail high simultaneously..'

The licensee's SSAR recognized the potential safety significance of this event and'

described methods that have been developed to'prevent its occurrence and/or to

mitigate its impact on the plant's post-fire SSD capability (should it occur). To prevent

this event, the licensee developed procedural guidance which directs operators to open

link BB-10 in panel 2H11-P927 and link BB-10 in panel 2H11-P928. These panels are

located in the main control room. 'Opening of these links would prevent actuation of the

SRV trip units by removing the 4 to 20 ma signal fed by the pressure transmitters to the

master trip units. In the event the SRVs were to open prior, to the operators completing

this action, the SStRslang-Core spray loop Alto mitigate the event.

The inspection team had several concerns regarding the licensee's approach to this

'

potential spurious actuation of the SRVs. Specific concerns identified by the team

'.

include:.

1.'

The links may not be opened in time to preclude inadvertent actuation of the

SRVs.

2.

The use of links to avoid Inadvertent actuation of the SRVs did not appear to be

consistent with the current licensing basis.

3. Noobjecive eidence existed to demonstrate that the post-fire SSD equipment

could adequately mitigate a fire in Fire Area 2104, if the SRVs; were to open.

4.

The operations staff would be unable to manually control the Group A SRVs,

which are credited for mitigating a fire in Fire Area 2104, should they spuriously,...

actuate'as a result of fire-induced damage.

With regard to the timing of operator actions to prevent fire damage from causing all

SRVs to open, the licensee performed an evaluation during the inspection which

estimated that approximately thirty minutes would pass from the time of fire detection to

the time an operator would implement procedural actions to open the links. -The

inspectors independently arrived at a similar time estimate based on their review of the

procedure. In response to inspector's concerns that this interval may be too lengthy to

preclude fire damage to the cables of interest and subsequent actuation of the SRVs,.

the licensee agreed to enhance its existing procedures so that the action would be

taken immediately following confirmation of fire in areas where the'spurious actuation:

could occur. This issue is discussed in Section 1 R05.'04/.05.b.1 of this report..

The team also determined that the opening of terminal board links was not In

compliance with the plant's licensing basis. Current licensing basis documents,

  • specifically Georgia Power request for exemptijn dated May 16, 1986, and a~

subsequent NRC Safety Evaluation Report (SVR) dated January 2, 1 987, characterized

the opening of links as a repair activity that is not permitted as a means of complying

of links was considered a repair by both the licensee and the NRC staff in 1987. The

VI~

licensee could not provide any evidence to justify why these actions should ot be

D

-A

.Additionally, because there Is a potential for all SRVs to spuriousl ac

eulto

r

104 at a time when RHR is not available, the SA

Of

core spray loop A to accomplish the reactor coolant makeup funci.

uring the

I

.inspeilorn-,the-licensee

perfogrmed a sirnulat~ctbr-i,,of an event which caused all 1 1

SRVs to open. During this exercise, simul tor RPV Iay~ Iinstruments indicated that core

:' spray would be capable of maintaining leved-abovert

ie top of active fuel. However, the

licensee did not provide any objective evidence (ag g, specific calculation r analysis)

which demonstrated that, assuming worst-case fire damage in Fire Are 2104, the.

-'limited

set of equipment available would be

unablet

of mitigating the eG nt in a manner

'

-

that satisfied theishutdowniperformanceiga

oas

afreinFire As

pendix R,

'

Section

'l..L.l.e.

(;'.

Finally, the logic that was Installed byr a

for

e

sasa fro

t-of -twcs

a

coincidence taken twice' logic in addit

o

-

i

logic.' The team determined that the two-mut-o

c

elinfrom trip

-'unit

master relays K310D and K335D repr sented

mmon cause failure for

A

SRVs for a fire in Fire Area 2104. Specifically, cable ABE01 9008 associated with

.

pressure transmitter2 B213-N12713 current loop, and cable ABE0o

t

9t 9 associated with

l

7 -

. -

pressure transmitter 2B21-N127D current loop, were routed in close proximity to each

other in the same cable tray in Fire Area 2104. Both shielded twisted pair instrument

cables were unprotected from the effects of a fire in this fire area. Fire-induced

insulation damage to both cables could result in leakage currents and cause the

instrument loops to fail high. This failure mode would simulate a high nuclear boiler

pressure condition and would initiate SRV backup actuation of all the Group A SRVs.

Whenever a SRV lifted, it would remain open until pressure reduced to about 85% of its

overpressure lift setpoint However, the instrument loops, having failed high, would

ensure that the trip unit master relays and the trip unit slave relays continued to energize

the pilot valve of the individual SRV and keep the SRV open. This issue is discussed In

-

more detail in Sectior21.01. Ultimately, this failure mode would prevent the..

operators from manualy controlling the roup A SRVs as required per the SSAR.

In response, the licensee initiated CR 2003800152, dated July 24, 2003, to evaluate

actions to open links to determine if they are necessary to achieve hot shutdown, and if

an exemptio from Appendix R in required. Pending additional review by the NRC, this

issue is ide itified a §URI,50-36 /03-06-01, Concerns Associated with Potential Opening

of SRVs. J

-

.04/.05 Alterna

hutdown Capabilitv/Overational Implementation of Alternative Shutdown

-,'.. .,Capabilttv.

i

I

.

n

I.

I. At~f ~~l

The selected fire areas that were the focus of this Inspection all Involved reactor

_ shutdown from the control room. None involved abandoning the control room a

I

alternative safe shutdown from outside of the control room. Thus, alterna

itdown

capability was not reviewed during this Inspection. However, the licensee's plans for

SSD following a fire in the selected areas involved many local manual operator actions

that would be performed outside of the control area of the control room. This section of.

the inspection focused on those local manual operator actions.

The team reviewed the operational Implementation of the SSD capability for a fire In the

selected fire areas to determine if: (1) the procedures were consistent with the SSAR;

(2) the procedures were written so that the operator actions could be correctly

performed within the times that were necessary for the actions to be effective; (3) the

training program for operators included SSD capability; (4) personnel required to

achieve and maintain the plant in hot standby could be provided from the normal onsite

staff, exclusive of the fire brigade; and (5) the licensee periodically performed operability

testing of the SSD equipment.

1
  • 1

The team walked down SSD manual operator actions that were to be performed outside

of the control aea of the main control room for a fire in the selected fire areas and

discussedthe with operators. These actions were documented in Abnormal Operating

Procedure (UP) 34AB-X43-001 -2, Version 10.8, dated Ma 28, 2003. The team

evaluated whether the local manual operator actions coul reasonably be performed,

using the criteria outlined in NRC Inspection Procedure (iP) 71111.05, Enclosure 2. The

team also reviewed applicable operator training lesson plans and job performance

-

-

8

measures (JPMs) and discussed them with operators. In addition, the team reviewed

records of actual operator staffing on selected days.

b.

Findings

Untimely and Unapgroved Manual Operator Action for Fire SSD

Introduction: The team found that a local manual operator action to prevent spurious

opening of all eleven SRVs would not be performed in sufficient time to be effective.

Licensee reliance on this manual action for hot shutdown during a fire, instead of

physically protecting cables from fire damage, had not been approved by the NRC.

Description: The team noted that Step 9.3.2.1 of AOP 34AB-X43-001-2, Fire

Procedure, Version 10.8, dated May 28, 2003, stated: "To prevent all eleven SRVs from

opening simultaneously, open links BB-1 0 in Panql 2H1 1 -P927 and BB-1 0 in Panel

2H1 1-P928." The team noted that spurious opening of all eleven SRVs should be

considered a large loss of coolant accident (L

A) and that a LOCA be prevented from

occurring during a fire event. Specifically, to comply with 10 CFR 50, Appendix R,

Section III.L. Section lll.L requires that, during a post-fire shutdown, the reactor coolant

system process variables (e.g., reactor vessel water level) shall be maintained within

those predicted for a loss of normal a.c. power. Having all eleven SRVs opened during

a fire would challenge this. Additionally, the team observed that this step was

sufficiently far back in the procedure that it may not be completed in time to prevent

potential fire damage to cables ftom causing all eleven SRVs to spuriously open.

The licensee had no preplannq 6 estimate of how long It would take operators to

complete this step during a fir) event, there was no event time line or operator training

job performance measure (M)

on this step. The team noted that, during a fire,

operators could be using many other procedures concurrent with the Fire Procedure.

For example, they could be using other procedures to communicate with the fire brigade

about the fire, respond to a reactor trip, deal with a loss of offsite power, and provide

emergency classifications and offsite notifications of the fire event. During the

inspection, licensee operators estimated that, during a fire event, it could teho about

30 minutes before operators would accomplish Step 9.3.2.1. The team concurred with

that time estimate which the team had previously determined independently. However,

NRC fire models indicated that fires could potentially cause damage to cables in as

short a period of five to ten minutes. Consequently, the team concluded that during a

fire event, the licensee's procedures would not ensure that Step 9.3.2.1 would be

accomplished in time to prevent potential spurious opening of all eleven SRVs.

The team also identified other Issues with Step 9.3.2.1. There was no emergency

lighting inside the panels, hence, if the fire caused a loss of normal lighting (e.g., by

causing a loss of offsite power), operators would need to use flashlights to perform the

actions inside the panels. Consequently, the team considered the emergency lighting

for Step 9.3.2.1 to be inadequate (see Section 1 R05.07.b). In addition, labeling of the

links inside the panels was so poor that operators stated that they would not fully rely on

the labeling. Also, the tool that operators would use to loosen and slide the links inside

the energized panels was made of steel and was not professionally, electrically

insulated. Further, licensee reliance on this operator action, instead of physically

.9

protecting the cables as required by 10 CFR 50, Appendix R, Section III.G.2, had not

been approved by the NRC.

  • .

~

~ ~ ~~.

.

.

................

The licensee stated that cable damage to two reactor pressure instrument cables, w6uld

be needed to spuriously open all eleven SRVs. Because the licensee stated that tfe

two cables were in the same cable tray in Fire Area 2104, the team considered thjt a'

fire in that area could potentially cause all eleven SRVs to spuriously open (set

ction

1 R21 .01 .b).

.

-

In response to this issue, the licensee initiated CR 2003008203 and promptly revised

the Fire Procedure before th end of the inspection, moving the actions of Step 9.3.2.1

to the beginning of the pro dure. The procedure change enabled the actions to be:

accomplished much soo

r during a fire in the Unit 2 east cableway or. in other-fire:

areas that were vulner

le to the potential for spuriously opening all eleven SRVs. The,'

team determined tha his issue is related to associated circuits. As described in NRC'

-

Inspectiorrnrpced elIPi71111.05, Fire Protection, inspection of associated circuits Is'

temporarily lirlte

Consequently, the team did not pursue the cable rou ifig or circuit

analysis that would be necessary to evaluate the possibility, risk, or po ntial safety .-'-'-..

significance of Group B and C SRVs spuriously opening due to fire

mage to the

instrument cables. The team did, however, perform a circuit analy s of Group A SRVs'

for which the licensee takes credit during a fire in fire area 21 04 -(tee Section -

1 R21.01.).

Analysis: The team determined that this finding was associated with the protection

against external factors attribute. It affected the objective of the mitigating system

cornerstone to ensure the availability of systems that respond to initiating events and Is!

therefore greater than minor. The team determined that the finding' had potential safety

significance greater than very low safety significance because failure to prevent .:

spurious operation of the SRVs could result in them opening in certain fire scenarios,

thereby complicating the post-fire recovery actions. However, the finding remains

unresolved pending completion of the SDP.

Enforcement: 10 CFR 50, Appendix R, Section lll.G.2 requires that twhere cables or

equipment, including associated non-safety circuits that could prevent operation or

cause mal-operation due to hot shorts, open circuits, or shorts to ground, of redundant.

trains of systems necessary to achieve and maintain hot shutdown conditions are

located within the same fire area outside of the primary containment, one of the

following means of ensuring that one or the redundant trains is free of fire damage shall

be provided: 1) a fire barrier with a 3-hour rating; 2) separation of cables by a horizontal

distance of mbre than 20 feet with no intervening combustibles and with fire detectors

and automatic fire suppression; or 3) a fire barrier with a 1-hour rating with fire detectors

and automatic suppression.

The licensee had not provided physical protection against fire damage for the two

instrument cables by one of the prescribed methods. Instead, the licensee had relied on

local manual operator actions to prevent the spurious opening of all eleven SRVs.

Licensee personnel stated that fire'damage to two cables was outside of the Hatch

licensing basis and, consequently, there was no requirement to protect the instrument

cables. However, the licensee could not provide evidence to support that position.

10

This potential issue' will remain unresolved pending the qompletion of a significance

determination by the NRC. This issue is identified as U RI 50-366/03-06-02, Untimely

and Unapproved Manual Operator Action for Post-Fire SSD.

2.

Local Manual Operator Action was Too Difficult and Unsafe

.'Introduction:

A finding of very low safety significance was identified in that a local

manual operator action to operate SSD equipment was too difficult and was also unsafe.'

"The

team judged that some operators would not be able to perform the action. This

finding involved a violation of NRC requirements.

Description: The team observed that Steps 4.15.8.1.1 and 9.3.5.1 of the Fire Procedure

relied upon local manual operator actions instead of providing physical protection for

cables or providing a procedure for cold shutdown repairs. Both steps required the

same local manual operator action: "Manually OPEN 2E1 I -F01 5A, InboardcLPCiV)

Injection Valve, as required." This action was to be taken in the Unit 2 dryweIaccess,

which was a locked high radiation, contaminated, and hot area with temperatures over

100 degrees F.

Valve 2E1 I -F01 SA was a large (24-inch diameter) motor-operated gate valve with a'

three-foot diameter handwheel. The main difficulty with manually opening this valve was

.lack of an adequate place to stand., An operator showed the team that to perform the

action he would have to climb up to, and stand on a small section of pipe lagging (a'

curved area about four inches wide by 12 inches long), and then reach back and to his

right side, to hold the handwheel with his right hand, while reaching forward and to his

right to hold the clutch lever for the motor operator with his left hand. The operator

would not have good balance while performing the action. The foothold, which was

large enough to support only one foot, was well flattened and appeared to have been

used in the past to manually operate this valve. The foothold was about six to seven

feet above a steel grating, and the'team observed that the space available for potential

use of a ladder to better access the 2E1 1 -F01 5A valve handwheel was not good.

'Other difficulties with manually opening the valve Included the heat; the need tc wear'

full anti-contamination clothing, a hardhat, and safety glasses; and inadequate

' : - emergency lighting (see Section 1 R05.07). Also, there was no note or step in the

procedure to ensure that the RHR pumps were not running before attempting to

manually open the 2E1l-FO15A valve. If an RHR pump were running, it could create a

differential pressure across the valve which could make manually'opening it much more

difficult. If the operator did not have sufficient agility, strength or stamina, he would be

unable to complete the action. Also, the team judged that inability to remove sweat from

his

eyes, due to wearing gloves that could be contaminated, would be a limiting factor

for the operator. In addition, if the operator slipped or lost his balance, he could fall and

become injured. Considering all of the difficulties, the team judged that this action was

unsafe and that some operators would not be able to perform it.

The licensee had no operator training JPM for performing this action and could not

demonstrate that all operators could perform the action. One experienced operator,

who appeared to be in much better physical condition that an average nuclear plant

  • e

S

operator, stated that he had manually operated the'valve in the past,'but that itfhad been

'

very difficult for him.

The team judged that, since this action was not required to maintain hot shutdown but

only required for coid shutdown following a fire in one of the four selected fire areas,:

licensee personnel could have time to improve the working conditions after a fire. They

could have time to install scaffolding or temporary ventilation; improve the lighting; and

assign multiple operators to manually open the valve. They could have time to perform

a cold shutdown repair. However, the licensee had not preplanned any cold shutdown'.

repairs for opening this valve.

Analysis: This finding is greater'than minor because it affected the availability and

reliability objectives and the equipment performance attribute of the mitigating systems

cornerstone. Because the licensee would have time to develop and implement cold.'

shutdown repairs to facilitate accomplishment of the action, this finding did not impact

-

the effectiveness of one or more of the defense in dept elements. Hence, this finding,'

did not have potential safety significance greater than v ry low safety significance:,

(Green).

Enforcement: 10 CFR 50, Appendix R

ection III.G.1 requires that fire protection

features shall be provided for syste

important to safe shutdown and shall be capable

of limiting fire damage so that systF s necessary to achieve and maintain cold

-

shutdown from either the cor triom or emergency control stations can be-repaired

-

within 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br />. In addition,

.4.1 requires that written procedures shall be

established, implemented, and maintained covering activities including FPP

implementation and including the applicable procedures recommended In Regulatory

Guide 1.33, Revision 2, Appendix A, February 1978. Regulatory Guide 1.33'

recommends procedures for combating emergencies including plant fires and

procedures for operation and shutdown of safety-related BWR systems. The fire'

protection program includes the SSAR which requires that valve 2E11 -F01 5A be

opened for SSD following a fire in Fire Area 2104, the Unit 2 east cableway. AOP

34AB-X43-001-2, Fire Procedure, Version 10.8, dated May 28, 2003, implements these

requirements in that it provides information and actions fecess-ar, to mitigate the

consequences of fires and to maintain an operable'shutdown train following fire damage.

'to

specific fire areas. Also, AOP 34AB-X43-001-2 provides Steps 4.15.8.1.1 and 9.3.5.1'

for manually opening valve 2E11-F01 5A following a fire in Fire Area 2104.

-'

Contrary to the above, the licensee had no procedure for repairing any related fire '

damage within 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br />. Instead, the licensee relied on local manual operator actions,

as described in Steps 4.15.8.1.1 and 9.3.5.1 of AOP 34AB-X43-001-2. However, those

procedure steps were inadequate in that some operators would not be able to perforr

them because the required actions were too difficult and also were unsafe. In respobse

to this issue, the licensee initiated CR 203008202. Because the identified inadequafe

operator actions are of very low safety significance and the issue has been ejtereint6V

the licensee's corrective action program, this violation is being treated as anN

f

consistent with Section VL.A of the NRC's Enforcement Policy: NCV 50-366/6-03,

Inadequate Procedure for Local Manual Operator Action for Post-Fire Safe Shutdown

Equipment.

.

.

F

3.'"'

--.. ..

.:

. .

.

.

.

.

.

.

.

.

.

.

.

.

.

.:

.

...

,

12'

Unapproved Manual Operator Actions for Post-Fire SSD

Introduction: A finding of very low safety significance was identified in that the licensee

relied on some local manual operator actions to operate SSD equipment, 'instead of

providing the required physical protection'of cables from fire damage. This finding"'

involved a violation of NRC requirements.

Description: The team observed that AOP 34AB-X43-001-2, Fire Procedure, included

some local manual operator actions to achieve and maintain hot shutdown that had not.'.

been approved by the NRC. Examples of steps from the procedure included:

Step 4.15.2.2; ... lf a loss of offsite power occurs and emergency busses

energize ...'Place Station Service battery chargers 2R42-S026 (2R42-SO29),

2R42-S027 (2R42-S030) AND 2R42-S028 (2R42-S031) in service per,34SO-

R42-001-2.

Step 4.15.4.5; ... lf HPCI fails to automatically trip on high RPV level.... OPEN the.;

following links to energize 2E41-F1l24, Trip'Solenoid Valve, AND to fail 2E41-. -

-

F3025 HPCI Governor Valve, in the CLOSED position:

-

':

TT-75 in panel 2H1 1 -P601

-

' '

-

'

TT-76 in panel 2H11-P601 "

'.

.

Step 4.15.4.6; ... lf HPCI fails to automatically trip on high RPV level.'.. OPEN

breaker 25 in panel 2R25-S002 to fail 2E41-F3052, HPCI Governor Valv6, in the

CLOSED position.

' -

The team walked down these actions using the guidance corntained in Inspection\\

Procedure 71111.05T and judged that they could reasonably be accomplished by

..

operators in a timely manner. However, the team determined that these operator

actions were being used instead of physically protecting cables from fire damage that.

could cause a loss of station service battery chargers or a HPCI pump runout.

Analysis: The finding is greater thanri minor because It afeclteu the availability a.nd.

reliability objectives as well as the equipment performance a ribute of the mitigating

systems cornerstone. Since the actions could reasonably

accomplished by operators

in a timely manner, this finding did not have potential safe significance greater than

very low safety significance'.

Enforcement: 10 CFR 50, Appendix R, Section III

uires that where cables or'

equipment, including associated non-safety circuit

a.ould prevent operation or

cause maloperation due to hot shorts, open circuits, or shorts to ground, of redundant

trains of systems necessary to achieve and maintain hot shutdown conditions are

located within the same fire area outside of the primary containment, one of the

following means of ensuring that one of the redundant trains is free of fire damage shall

be provided: 1) a fire barrier with a 3-hour rating; 2) separation of cables by a horizontal

distance of more than 20 feet with no intervening combustibles and with fire detectors

and automatic fire suppression; or 3) a fire barrier with a 1-hour rating with fire detectors

and automatic suppression.

.

.

l

.

@ @

.

.

6

@

.

.

.

%

..

.

.

.

S

.

4

> A;

B

.

.

.

.

-

.06

.

-

.

. .

.

.

.

.

.

.

..

-

.a.

.

.

.

.

.

.

.

13

Contrary to the above, the licensee had not provided the required physical protection

against fire damage for power to the station service battery chargers or for HPCI

electrical control cables. Instead, the licensee relied on local manual operator actions,.

without NRC approval.. In response to this issue, the licensee initiated CR2003800166.

Because the issue had very low safety significance and has been entered into the

licensee's corrective action program, this violation is being treated as an NCV,

consistent with Section VL.A of the NRC's Enforcement Policy: NCV 50-366/03-06-04,

Unapproved Manual Operator Actions for Post-Fire Safe Shutdown..

Communications

Inspection Scope

l

The team reviewed the plant communications systems that would be relied upon to.

-

support fire brigade and SSD activities. The team walked down portions of the SSD

procedures to verify that adequate communications equipment would be available for

personnel performing local manual operator actions. In addition, the team reviewed the

-

.

adequacy of the radio communication system used by the fire brigade to communicate

.

. with the main control room.

b.

Findings

No findings of significance were Identified.

.07

Emergency Lighting

a.

Inspection Scope

The team inspected the licensee's emergency lighting systems to verify that 8-hour

emergency lighting coverage was provided as required by 10 CFR 50, Appendix R,

Section lll.J, to support local manual operator actions that were needed for post-fire

operation of SSD equipment. During walkdowns of the post-fire SSD operator actions'

for fires in the selected fire areas, the team checked if emergency lighting units wore

installed and if lamp heads were aimed to adequately illuminate the SSD equipment, the

equipment identification tags, and the access and egress routes thereto, so that

operators would be able to perform the actions without needing to use flashlights.

b.

Findings

Inadequate Emergency Lighting for Operation of SSD Eguipment

Introduction: A finding with very low safety significance was identified in that emergency

lighting was not adequate for some manual operator actions that were needed to

support post-fire operation of SSD equipment. This finding involved a violation of NRC

requirements.

Description: The team observed that emergency lighting was not adequate for some

manual operator actions that were needed to support post-fire operation of SSD

-

14

equipment. Examples included the following operator actions in procedure 34AB-X43-

' 001-2, Fire Procedure, Version 10.8, dated May 28, 2003:

-*

Step 4.15.2.2; ...if a loss of offsite power occurs and emergency busses energize:

.. "Place Station Service battery chargers 2R42-S026 (2R42-S029), 2R42S027..

Step 4.15.4.5; ...lf HPCI fails to automatically trip on high RPV level.'.. OPEN the.

following links to energize 2E41-F124, Trip Solenoid Valve, AND to fail 2E41'

F3025 HPCI Governor Valve, In the CLOSED position:

  • ' .

TT-75 in panel 2Hi 1-P601

-:..

-

.

TT-76 in panel 2HlI-P601'

Step 4.15.5; 'IF 2R25-S065, Instrument Bus 28, is DE-ENERGIZED perform the.

following manual actions to maintain 2C32-R655, Reactor Water Level.

Instrument, operable:

4.15.5.1;At panel 2H11-P612, OPEN links AA-11 and AAA12

4.15.5.2; At panel 2H1 1 -P601, CLOSE links HH-48 and HH-49.:

Steps 4.15.8.1.1 and 9.3.5.1; "Manually OPEN 2E11 -F015A, Inboard LPCI

'

Injection Valve, as required..

.? ..

e.

Steps 4.15.8.1.2 and 9.3.5.2; 'Manually CLOSE 2E1 -FO18A, RHR Pump A '

Minimum Flow Isolation Valve, as required.'.

.

Step 9.3.2.1; 'To prevent all 11 SRVs from opening simultaneously, open links

BB-10 in Panel 2H11-P927 and BB-10 in Panel 2H11-P928.:

  • 'Step

9.3.3; 'At Panel 2H1 1 -P627, open links AA-1 9, AA-20, AA-21, and AA-22,'

to prevent spurious actuation of SRVs 2B21-F013D AND 2B21-F013G.'

Step 9.3.6; 'OPEN link TB9-21 in Panel 2H1 1 -P700 to open Drywell Pneumatic

System Inboard Inlet Isolation, 2P70-F005.-

Step 9.3.7; 'OPEN link TBI-12 In Panel 2H11-P700 to open Drywell Pneumatic

System Outboard Inlet Isolation, 2P70-F005.'

Step 9.3.9.1; 'Confirm OR manually CLOSE RHR Shutdown Cooling Valve:

2E11-F0O6D."

Step 9.3.9.2; 'Manually OPEN Shutdown Cooling Suction Valve 2E1 1 -F008, IF'

required...'

The team verified that flashlights were readily available and judged that operators would

be able to use the flashlights and accomplish the actions, with two exceptions. One

' '

exception was the action to open terminal board links in two panels to prevent all eleven

SRVs from spuriously opening, which was judged to be untimely (see Section

1 R05.041.05.b.1). The other exception was the action to open 2E1 1 -F01 5A, which was

judged to be too difficult (see Section 1 R05.04/.05.b.2). For both of these actions, the

1 5

lack of adequate emergency lighting could make the actions mor'e difficult to complete in'-

a timely manner and increase the chance of operator error.

Analysis: This finding is greater than minor because it affected the reliability objective

and the equipment performance aPttribute of the mitigating systems cornerstone. Since

operators would be able to accomplish the actions with the use of flashlights, this finding..

-did not impact the effectiveness of one or more of the defense in depth elements.

Hence, this finding did not have potential safety significance greater than very low safety..

significanice (Green)...

Enforcement: 1 0 CFR 50, Appendix R, Section lll.J, requires that emergency lighting

units with at least an 8-hour battery power supply shall be provided in all areas needed

for operation of safe shutdown equipment, and *in access and egress routes thereto.

Contrary to the above, emergency lighting units were not adequately provided in all

areas needed for operation of SSD equipment. In response this issue, the licensee

initiated CRs 2003008237 and 2003008179. Because the identified lack of emergency'

lighting is of very low safety signif icance and has been entered into the licensee's

corrective action program, this violation is being treated as an NCV, consistent with

Section VL.A of the NRC's Enforcement Policy: NCV 50-366/03-06-05, Inadequate

Emergency Lighting for Operation of. Post-Fire Safe Shutdown Equipment.

c

wit th

ecpion

08l

Cold: Shtdw R:.air

of the potential need for a cold shutdown repair to open valve 2E1 1 -F0l 5A (see Section

1 a05.05.b.2), the team identified no other need for cold shutdown repairs.

Consequently, this sectiongof IP 71111.05 was not performed.

09

Fire Barriers and Fire Area/Zone/Room Penetration Seals

a.

Inspection Scoude

The team reviewed the selected fire areas to evaluate the adequacy of the fire

resistance,

o firenarea barrier enclosure walls, ceilings,nfloors, fire barrier mechanical

and electrical penetration seals, fire doors, and fire dampers. The team selected

several fire barrier features for detailed evaluation and inspection to verify proper

installation and qualification. This was accomplished by observing the material condition

and configuration of the installed fire barrier features, as well as construction details and

supporting fire endurance tests for the installed fire barrier features, to verify the as-built

configurations were qualified by appropriate fire endurance tests. The team also

reviewed the F-A to verify the fire loading used by the licensee to determine the fire

-: .

reasis

edtance

rating of the fire barrier enclosures. The team also re iesud the icenstli

instructions for sliding fire doors, the design details for mechanicalnd elea ral

penetrations, the penetrationyseal database, Generic Letter

i6-10 evaluations, and

the fire protection penetration seal deviation analysis for the tedsn ical basis of fire

requirements and license commitments. In addition, the team r

wiewed

completed

e

16

.

surveillance and maintenance procedures for selected fire barrier features to verify the,'

fire barriers were being adequately maintained.

.

.

'

The team evaluated the /dequacy of the fire resistance of fire barrier electrical raceway

- fire barrier system (ERq13S) enclosures for cable protection to satisfy the'applicabled-' '

separation and design requirements of 10 CFR 50, Appendix R, Section III.G.2..

Specifically, the team examined the.design drawings, construction details, installation

records, and supporting fire endurance tests for the ERFBS enclosures installed in Fire

Area 2104, the Unit 2 East Cableway. Visual inspections of the enclosures were.'.

performed to confirm that the ERFBS Installations were consistent with the design -

drawings ad tested configurations.

The tea

reviewed abnormal operating fire procedures, selected fire fighting pre-plans,.

firedad

per location and detail drawings, and heating ventilation and air conditioning

-

_VA )~system drawings to verify that access to shutdown equipment and selected ' '

/

operator manual actions would not be inhibited by smoke migration from one area to,

adjacent plant areas used to accomplish SSD.

-

b.

Findings

-No findings of significance were Identified.

.10.

Fire Protection Systems. Features, and Eduipment

.

' -

a.

Insnection Scope

The team reviewed flow diagrams, cable routing information, and operational valve:

lineup procedures associated with the fire pumps and fire protection water supply

system. The review evaluated whether the common fire protection water delivery and

supply components could be damaged or inhibited by fire-induced failures of electrical

power supplies or control circuits. Using operating and test procedures, the team toured

the fire pump house and diesel-driven fire pump fuel storage tanks to observe the

system material condition, consistency of as-built'configurations with engineering

drawings, and determine correct system controls and valve lineups. Additionally, the

team reviewed periodic test procedures for the fire pumps to assess whether the'

surveillance test program was sufficient to verify proper operation of the fire protection.

water supply system in accordance with the program operating requirements specified-

in Appendix B of the FHA.

The team reviewed the adequacy of the fire detection systems in the selected plant fire

areas in accordance with the design requirements in Appendix R, III.G.1 and III.G. 2.

The team walked down accessible portions of the fire detection systems in the selected

fire areas to evaluate the engineering design and operation of the installed

configurations. The team also reviewed engineering drawings for fire detector types,

spacing, locations and the licensee's technical evaluation of the' detector locations for

the detection systems for consistency with the licensee's FHA, engineering evaluations

for NFPA code deviations, and NFPA 72E. In addition, the team reviewed surveillance

procedures and the detection system operating requirements specified in Appendix B of

17'

the FHA to determine the adequacy of fire detection component testing and to ensure

that the detection systems could function when needed.

The team performed in-plant walk-downs of the Unit 2 East Cable way automatic wet

pipe sprinkler suppression system to verify the proper type, placement and spacing of

the 'sprinkler heads as well as the lack of obstructions for effective functioning. The

team examined vendor information, engineering evaluations for NFPA code deviations,

and design calculations to verify that the required suppression system water density for

the protected area was available. Additionally, the team reviewed the physical

configuration of electrical raceways'and safe shutdown components in the fre rat

determine whether water from a pipe rupture, actuation of the automatic suppression

system, or manual fire suppression activities in this area could cauise damage that could

inhibit the plant's ability to SSD.

The team r9ewed the adequacy of the design 'and installation of the manual carbon

dioxide (Q92) hose reel suppression system for the diesel generator building switchgear

rooms 2E and 2F (Fire Areas 2404 and 2408). -The team performed in-plnt walk-

downs of the diesel generator building 002 fire suppression system to determine correct

system controls and valve lineups to assure accessibility and functionality of the system,.

as well as associated ventilation system fire dampers; The team also reviewed the'

licensee's actions to address the potential for 002 migration to ensure that fire

..suppression and post-fire SSD actions would not be impacted. This was accomplished

by the review of engineering drawings, schematics, flow diagrams, and evaluations

associated with the diesel generator building'floor drain system to determine whether

systems and operator actions required for SSD would be inhibited by 002 migration

through the floor drain system.

b.

Findings

Nofindings of significance were Identified.

11 Comp6rnsatorv Measures

a

Inspection Scone

The team reviewed Appendix B of the FHA and applicable sections of the FPP.

administrative procedure regarding administrative controls to Identify the need for and to

implement compensatory measures for out-of-service, degraded, or inoperable fire

protection or post-fire SSD equipment, features, and systems. The team reviewed

licensee reports for the fire protection status of Unit 1, Unit 2, and of shared structures,

systems, and components.. The review was performed to verify that the risk associated

with removing fire protection and/or post-fire systems or components, was properly

-assessed

and implemented in accordance with the FPP. The team also reviewed CAP

-CRs

generated over the last 18 months for fire protection features that were out of

service for long periods of time. The review was conducted to assess the licensee's

effectiveness in returning equipment to service in a reasonable period of time.

18

b.

Find*ings

-No findings of significance were identified.

1 R21 Safety System Design And Performance Capability

-..01

-Gesicnifte

-nRemest-fDCR)91-134, SRV Backup Actuation Via Pre

.

re

.

Transmitter Signals

a.

lnsnection Scope

The team performed an independent design review of plant modification DCR 91-134 In

order to evaluate the technical adequacy of the design change package. The scope of

the review and circuit analysis performed by the team was limited to the Group A SRVs

for which the licensee takes credit in mitigating a fire in the fire areas selected for the

inspection.'

.

-' ,>

!8

b.

Findings..

-

..............

, .

.;

.

Introduction:

'An Inadequate plant modification, DCR 91-134, failed to implement the design input

requirements of one-out-of-two taken twice logic for the SRV's backup actuation using

pressure transmitter signals.

.

.

Description:

DCR 91-134 was implemented In response in to concerns raised in General Electric

-Report NEDC-3200P, Evaluation of SRV Performance during January-February 1991.

Turbine Trip Events for Plant Hatch Units 1 and 2. In order to ensure that individual'

SRVs will actuate at or near the appropriate set point and within allowable limits, a

backup mode of operation for the SRVs was implemented by this DCR. The design

Was intended to mitigate the effects of corrosion-induced set point drift of the Target

~Rock SRVs.-;

Automatically controlled, two stage SRVs are installed on the main steam lines inside

containment for the purpose of relieving nuclear boiler pressure either by normal

mechanical action or by automatic action of an electro-pneumatic control system. Each

SRV can be manually controlled by use of a two position switch located in the main

control room. When placed in the "Openw position, the switch energizes the pilot valve

of the individRVl SRV and causes it to go open. When the switch is placed in the

i

Aut

position thevSRV is opened upon r.ceipt of either an Automatic Depressurization

System (ADS), or Low-Low Set (LUS) control logic signal. Either signal will initiate

opening of the valve. DCR 91-134 provided a backup mode for initiation of electrical trip

of the pilot valve solenoid which was independent of ADS or LLS logic. The backup

mode required no operator action to initiate opening of the SRVs and was considered a

"blind control loop" to the operators, (i.e., there are no instruments that provide the

operators information concerning the open/close status of the SRVs.)

19

The scope of the plant modification involved the installation of four Rosemount pressure

transmitters (Model No. 1154GP9RJ), 0-3000 psig, in the 2H21-P404 and -P405

instrument racks at Elevation 158 of the reactor building. Each pressure transmitter

formed part of a 4 to 20 ma current loop and provided the analog trip signal for SRV

actuation within the following set point groups:

SRV GrouD

IA

SRV Identification Tags

SRV Set Point

2B21-F013B, D, F, and G

1120 psig

.

.

.

B

2B21 -FO13A, C, K, and M

1130psig.. .

C4

2B21-FO13E, H, and L

1140 psig

Pressu e

ransmitters (PTs) 2B21-N127A and 2B21-N127C were wired to A

S

cabinet

11 -P927. Pressure transmitter 2B21 -N127A instrument loop components

consisted of a trip unit master relay K308C and trip unit slave relays K321 C and K332C.

The loop components for PT 2B21-N127C consisted of a trip unit master relay K335C In

addition to trip unit slave relays K336C and K363C. These two instrument loops

constituted a 'division" of pressure monitoring channels and were intended to provide

the None-out-of-two" logic signal from this division for initiating SRV backup actuation.

Additionally, PTs 2B21-N127B and 2B21-N127D were wired to ATTS cabinet'

2H11-P928. Pressure transmitter 2B21-N127B instrument loop components consisted

of a trip unit master relay K31 OD and trip unit slave relays KK312D and K332D.' The

loop components for PT 2B21-N127D consisted of a trip unit master relay K335D In

addition to trip unit slave relays K336D and K363D. These two instrument loops

constituted a separate "division' pressure monitoring channels and were'intended to

provide the "one-out-of-two' logic signal from this division for initiatingRV backup

actuation. The design objective of having two instrument channels ys to assure

compliance with HNP-2-FSAR, Section 15.1.6.1, Application otSin e Failure Criteria.

This criteria requires for anticipated operational occurrences (A'

that the protection

sequences within mitigation systems be -ing!e compmnent failure proof. A fa,!ure cf on

instrument channel in a division will therefore not eliminate the protection provided by

either of the instrument channels.

The following table identifies the division, PT loops and the associated trip unit master

and slave relays:

Division

A

PT LooDs

Tri, Unit Master Relays

Trip Unit Slave Relays

K321 C and K332C

K336C and K363C

2B21-N127A

2B21-N127C

' - K308C

' K335C

B

2B21 -N127B

2B21 -N127D

K31OD

K335D

K312D and K332D

K336D and K363D

The Group A SRVs were provided logic Input signals from the trip unit master relays.

The Group B and C SRVs were provided logic input signals from the trip unit slave

20

-

relays. The 12 relays described above, (6 in ATTS cabinet 2H1 1-P927 and 6 in ATTS

'.'

cabinet 2H1 1-P928), were intended to be wired to provide

one-out-of-two taken twice.

,ogic for actuation of the SRVs. The design objective was to assure that a single relay

failure in either division would not cause'an inadvertent SRV actuation. Coincident logic

, input is required from both division instrument loops in order to initiate a SRV backup

actuation using the pressure transmitter signals. This occurs when the circuit, used to.

energize the individual SRV pilot valve to open the SRV, is enabled by receiving

simultaneous logic inputs from either instrument loop in both divisions.

The team performed a circuit analysis of SRV 2821 -FO1 3F (Path 1) and SRV 2B21-

F01 3G (Path 2) in order to verify that the design objectives of implementing a one-out-

of-two taken twice' logic had been achieved. Based on this review the team determined

'that the design objective of implementing a 'one-out-of-two taken twice' logic had not

been installed for the SRVs. The logic installed for the SRVs was a two-out-of-two

taken twice' logic in addition to a "one-out-of-two taken twice' logic.

The coincident

logic implemented using trip unit master relays K31 OD and K335D could result In

spurious actuation of Group A SRVs for a' fire in Fire Area 2104. In addition this

spurious actuation defeats the capability to manually control these SRVs. Whenever a,

  • SRV lifts, it will remain open until nuclear boiler pressure is reduced to about 85% of its

'

overpressure lift setpoint However, because the instrument loops have failed high, the

' trip unit master relays and the trip unit slave relays will continue to'energize the pilot

valve of the individual SRV and keep the SRV open. As a result, this failure. mode

-

prevents the operators from manually controlling the Group A SRVs as is required per

the SSAR.

-

Analysis: This finding Is greater than minor because it affected the a alabil

6

y7d

reliability objectives and the equipment performance attribute of t!j mitigating system

_

cornerstone. The team determined that the finding had potentiarsafety significanc

greater than very low safety significance because it prevent

he oper torslri

' manually controlling the Group A SRVs which the license

(a

mitigating a fire in

Fire Area 2104. Manual control of the-Grou'p A SRYS is

d to ensure that the

suppression pool temperature will not exceed the CT or the suppression pool.

F 'iure to ensure that the suppression pool temperaturc Will net cxcccd the HCTL could

result in loss of net positive suction head for the Core Spray pumps which the licensee

slang for mitigating this event. However, the finding remains unresolved pending

completion of a significance determination.

-

Enforcement: 10 CFR 50, Appendix B, Criterion Ill, requires that design control

,measures

shall provide for verifying or checking the adequacy of design.

DCR 91-134 specified design input requirements for the sensor initiated logic that

electrically activates the SRVs to be a 'one-out-of-two taken twice' logic scheme. It also

identified the potential worst case failure'mode of this logic modification as a short in the

, :

logic which would result In an inadvertent opening of a SRV. It concluded that the

modification was designed so that the actuation logic would not fail to cause inadvertent

opening of a SRV nor prevent a SRV from lifting upon ADS/LLS activation. Contrary to

the above, the logic implemented by the licensee for DCR 91-134 was different from the

specified design input requirements. The independent design verification performed for

DCR 91-134 failed to identify this error in the, logic scheme. Additionally, the Appendix

m I.,I

21

R Impact Review performed for DCR 91-134 failed to identify the potential failure mode

of all eleven SRVs because of fire-induced damage in Fire Area 2104.

Based on the logic input from tripunit master unit relays K31 OD, and K335D and their

associated trip, unit slave relays. The plant modification installed for DCR 91-134 failed'-'

to correctly implement the "one-out-of-two taken twice logic that was specified in the'."

SRV backup actuation via pressure transmitter signals design change package. This .

failure has created a condition where fire-induced failures of two reactor pressure'

instrument circuit cables, (within close proximity to each other), could result in spurious

,

actuation of all eleven SRVs with the eleven SRVs assuming a stuck open mode of.'..

operation. Pending completion of a significance determination by the NRC, this item Is

identified as URI 50-366/03-06-06, Inspector Concerns Associated with Implementation

of DCR 91-134.

4.

OTHER ACTIVITIES

40A2 Identification and Resolution of Problems

a.

Inspection Scope

-The team reviewed a sample of licensee audits, self-assessments, and CRs to verify,

that items related to fire protection apd to SSD were appropriately entered into.the:

licensee's CAP in accordance with the Hatch quality assurance program and procedural,.'

requirements. The items selected were reviewed for classification and appropriateness'

of the corrective actions taken or initiated to resolve the issues. In addition, the team:'

reviewed the licensee's applicability evaluations and corrective actions for selected

'industry experience issues related to fire protection. The operating experience reports'-'

were reviewed to verify that the licensee's review and actions were appropriate.:,:

'

The team reviewed licensee audits and self-assessments of fire protection and safe.

shutdown to assess the types of findings that were generated and to verify that the

findings were appropriately entered Into the licensee's corrective action program.,

b.

Findings

No findings of significance were identified.

.

40A6 Meetings. Including Exit.

The lead inspector presented the in

etio results t licensee management and other

members of the licensee's staff at

e

r1clusion of he onsite inspection on July 25,

2003. Subsequent to the gns te

spectdn, the le

inspector and the Team Leader,'

Fire Protection, managl

11

ex

y telephone with Mr. S. Tipps and

other members of licensee

e

n August 29, 2003, to update the licensee on

changes to the preliminary inspection findings. The licensee acknowledged the findings.

SUPPLEMENTAL INFORMATION

.! s

.'

,..'..

.

.. .. ..

.KEY

POINTS OF CONTACT

Licensee personnel:

-

M. Beard, Acting Engineering Support Supervisor

V. Coleman, Quality Assurance Supervisor

.-...:M. Dean, Nuclear Specialist, Fire Protection -.

R Dedrickson, Assistant General Manager for Plant hatch

.B. Duval, Chemistry.Superintendent

M Googe, Maintenance Manager

.

-

J. Hammonds, Operations Manager

D. Javorka, Administrative Assistant, Senior

R. King, Acting Engineering Support Manager

.I Luker, Senior Engineer, Licensing

T. Metzer, Acting Nuclear safety and Compliance Manager

'-.'::.

-. ' .'A. Owens, Senior Engineer, Fire Protection:.

'.' Parker, Senior Engineer, Electrical

J. Payne, Senior Engineer, Corrective Action Program:

J. Rathod, Bechtel'Engineering Group Supervisor

.'. .:.'M. Raiybon, Summer Intern .R'~

.. Rosanski, Oglethorpe Power Corporation Resident Manager

J. Vance, Senior Engineer, Mechanical & Civil

R. Varnadore, Outages and Modifications Manager.

-. .NRC Personnel:.

.

N. Garret, Senior Resident Inspector

C. Payne, Fire Protection Team Leader

LIST OF ITEMS OPENED, CLOSED, AND DISCUSSED

Obened

' .- 50-366/03-06-01

URI

Concerns Associated with Potential Opening of S

' .

.

1

-R05.03.b)

50-366/03-06-02

URI

Untimely and Unapproved Manual Operator.Actio

'.

SSD (Section 1 R04/05.b.1)

50-366/03-06-06

URI

Inspector Concerns Associated with Implementati

' ... '

.

DCR 91 -134 (Section 1 R21.01.b)

Opened and Closed

.

RVs (Section

n for Post-Fire

on of

50-366/03-06-03

NCV

Inadequate Procedure for Local Manual Operator Action for Post-

Fire SSD Equipment (Section 1 R04/05.b.2)

Attachment

50-366/03-06-04

50-366/03-06-05

.

Discussed

None

NCV 1Unappro d Manual

erator Actions for Post-Fire'SSD'

(Sectiot1 1 R04.0

.3

. .

.

'

.

-

NCV

Inadequate Emergency Lighting for Operation of Post-Fire:SSD'--

Equipment. (Section 1 R05.07.b)

5 /

>

.~~~-' .

..

A

---

2--

.

2..A:\\

Attachment

.3

LIST OF DOCUMENTS REVIEWED

Procedures.

Administraive rcdr OCEG08OFr Protection Programn, Rev. 9.2

Adinist'ative Procedure 42FP-FPX-01 8-OS; Use, Control, and Storage of

Flammable/Combustible Materials, Rev. 1.0

Department Instruction DI-FPX-02-0693N, Fire Fighting Equipment Inspection, Rev.5

Fire Protection Procedure 42FP-FPX-005-OS, Drill Planning, Critiques and Drill Documentation.

Rev; 1 EDI

Fire Protection Procedure 42FP-FPX-007-OS, Hot0 Work, Rev. 1.2

Preventive Maintenance Procedure 52PM-ML02O LwVlaeSwitchgear Preventive

Maintenance', Rev. 25.0'

Preventive Maintenance-Procedure 52PM-M EL-Ol14-0, Transformer Maintenance, Rev. 10.1

'Surveillance Procedure 423SV-FPX-002-OS, Low Pressure CO2 System Surveillance, Rev. 7.1

'Surveillance Procedure 425SV-FPX-004-OS, Fire Pump Test, Re'v. 8.6

Surveillane Procedure 42SV-FPX-006-OS, Fire Damper Surveillance, Rev. I ED 1

Surveillance Procedure 42SV-FPX-021 -OS, Surveillance of Swinging Fire Doors, Rev.-1.6'.'

Surveillance Procedure 42SV-FPX-024-OS, Fire Hose Stations 31 Day Surveillance, Rev. I

Surveillance Procedure 42SV-FPX-030-OS, Fire Emergency'Self Contained Breathing

Apparatus Inspection and Test, Rev. I

Surveillance Procedure 42S V-FPX-032-OS, Automatic Sliding Fire Door Visual Inspection,

..Rev.'3.3

Surveillance Procedure 423SV-FPX-036-08, Annual Fire Pump Cap acity Test, Rev. 8.6 .

.

Surveillance Procedure 42S V-FPX-037-OS, Fire Detection Instrumentation Surv'eillance,,

  • Rev. 5.1

System Operating Procedure 34S0-X43-001-1, Fire Pumps Operating.Procedure, Rev.A4.3.

Training Procedure 73TR-TRN-.003-0S,.Fire Training Program, Rev.4

.

AOP 34AB-C 1-OO1 -2, Loss of CRD System, Version 2.3

~AOP 34AB-C71 -001-2, Scram Procedure, Version 9.9

~AOP 34AB-C71-002-2, Loss of RPS, Version 4.3.

AOP 34AB-N61-002-2S, Main Condenser Vacuum Low, Version 0.4

AOP 34A8%-P41-001-2, Loss of Plant Se.-ice Water, VIcrsion 8.1

  • AOP 34AB-P42-001-2S, Loss of Reactor Building Closed Cooling Water, Version 1.4.

~AOP 34AB-P51 -001-2, Loss of Instrument and Service Air System or Water Intrusion Into the

Service Air System, Version 3.0

AOP 34AB-R22-001 -2, Loss of DC Busses, Version 2.4

~AOP 34AB-R22-002-2, Loss of 41 60V Emergency Bus, Version 1.4

AOP 34AB-R22-003-2, Station Blackout, Version 2.3

'AOP 34AB-R22-004-02, Loss of 41 60V Bus 2A, 2B, 2C, or 2D, Version 1.3

AOP 34AB-R23-001-2S, Loss of 600V Emergency Bus, Version 0.4-

AOP 34AB-R24-001 -2, Loss of Essential AC Distribution Buses, Version 1.3

AOP 34AB-R25-002-02, Loss of Instrument Buses, Version 5.4

AOP 34AB-T47-001-2, Complete Loss of Dsywell Cooling, Version 1'.8

AOP 34AB-X43-OO1-2, Fire Procedure, Version 10.8

AOP 34AB-X43-002-0, Fire Protection System Failures, Version 1.3

SOP 34S0-C71-001-2,1I20VAC RPS Supply System, Version 10.2

Attachment

.4

SOP 34SO-N40-001-2, Main Generator Operation, Version 10.8

-

SOP 34SO-R42-001-2S, 125V DC and 125/250 VDC System, Version 7.1

SOP 34SO-S22-001-2, 500 KV Substation Switching, Version 5.2

31 EO-EOP-01i0-2S, RC RPV Control (Non-ATWS), Rev. 8, Attachment 1

31 EO-EOP-01 2-2S, PC-1 Primary Containment Control, Rev. 4, Attachment 1i

31 EO-EOP-013-2S, PC-2 Primary Containment Control, Rev. 4, Attachment 1

31 EO-EOP-01 4-2S, SC - Secondary Containment Control, Rev. 6, Attachment I,-

31 EO-EOP-01 6-2S, CP-2 RPV Flooding, Rev. 8, Attachment I

Procedure 34AB-X43-001 -2S, Rev.1 OED3, 41Fire Procedure," dated 5/28/03.

Calibration Procedure 57CP-CAL-097-2, Rosemount 1153 and 1154 transmitters, Revision

No. 19.9.

Drawings

'

H-i 1814, Fire Hazards Analysis, Control Bldg. El. 1 30'-0", Rev. 5

H-1 1821, Fire Hazards Analysis, Turbine Bldg. El. 130'-0", Rev. 0

H-1 1846, Fire Hazards Analysis, Diesel Generator Bldg., Rev. 2

H-26014, R.H.R. System P&ID Sheet 1, Rev. 49

H-26015, R.H.R. System P&ID Sheet 2, Rev. 46

H-26018, Core Spray System P&ID, Rev. 29

B-1 0-1 326, Rectangular Fire Damper Schedule, Rev. 2

B-10-1329, Rectangular Fire Damper, Rev. I

H-1 1033, Fire Protection Pump House Layout, Rev. 47

H-1 1035, Fire Protection Piping and Instrumentation Diagram, Rev. 22

H-1 1226, Piping-Diesel Generator Building Drainage, Rev. 6

H-1 1824, Fire Hazards Analysis Drawing, Control Building, Rev. 1

H-1 1821, Fire Hazards Analysis Drawing, Turbine Building, Rev. 1

H- 1846, Fire Hazards Analysis Drawing,' Diesel Generator Building, Rev. 2

H-1 1894, Fire Detection Equipment Layout-Diesel Generator Building, Rev. 2

H-1 1915, Fire Detection Equipment Layout-Control Building, Rev. 2

H-13008, Conduit and Grounding, Fire Pump House, Rev. 9

H-13615, Wiring Diagram, Fire Pump House, Rev. 13

H-1 6054, Control Building HVAC System, Rev. 19

H-41509, Diesel Generator Building CO2 System-P&ID, Rev. 5

H-43757,-Penetration Seals-Type, Number, and as-Built Location, Rev. 3

Calculations. Analvses, and Evaluations

'E.'I. Hatch Nuclear Plant Units I and 2 Safe Shutdown Analysis Report, Rev. 20.

Edwin I. Hatch Nuclear Plant Fire Hazards Analysis and Fire Protection Program, Rev. 20

Calculation SMFP88-001, Hydraulic Analysis' of Sprinkler Systems in Control Building East

Cableway, dated 03/11/1988

Calculation SMNH94-046, FCF-F1OB-006, Fire Resistance of Concrete Block at HNP, dated

09/30/1994

Calculation SMNH94-048, FCF-F1 OB-006, Cable Tray Combustible Loading Calculation, dated

09/30/1994

Attachment

-,

5

" '

Calculation SMNH98-023, HT-98617, Fire Protection Penetration Seal Deviation Analysis

dated 10/28/1998

1

'.-

H

N

Ps

A1

date

.9108/2000

Calculation SMNHo0-01

0606, Hose Nozzle Pressure Drop Analysis, dated 09/08/2000.:'.

Evaluation HT-91722, Fire Protection Code Deviation Resolution, dated 04/22/1i992..'

Hatch Response to NRC IN 1999-005, dated 05/04/1999

'Hatch Response to NRC IN 2002-024, dated 09/20/2002

.

Calculation SENH 98-003, Rev. 0, plot K, protective relay settings 4kV bus 2E; '..

Calculation 85082MP, Plot 29, 600V Switchgear 2C

Calculation SENH 94-004, Attachment A, Sheets 7&8, 600/208 Reactor Building MCC 2C

Calculation SENH 91-011, Attachment P, Sheet 6, Reactor Building DC MCC 2A'...

Calculation SENH 94-013, Sheets 28 and 29, 600V Reactor Building MCC 2E-B"

Calculation SENH 91-011, Attachment P,. Sheet 16, Reactor Building 250VDC MCC 2B-.

' '

Audits and Self-Assessments

Audit No. 01-FP-1, Audit of the Fire Protection Program, dated April 12,2001

Audit No. 02-FP-1, Audit of the Fire Protection Program, dated February 28, 2002'.

Audit No. 03-FP-1, Audit of Fire Protection, dated April 21, 2003

1999-001106, Lighting in Fire Equipment Building

2002-000629, Inordinate Number of Buried Piping Leaks

2002-002127,InadequateBunkerGear'-'.:

2002-002129, Health Physics Support and Participation for Fire Brigade

2003-000735, Impact on Cold Weather on Operating Units

Audit Report 01-FP-1, Audit of Fire Protection Program, dated 04/12/2001

Audit Report 02-FP-1, Audit of Fire Protection Program, dated 02/28/2002

Audit Report 03-FP-1, Audit of Fire Protection Program, dated 04/21/2003

CRs Reviewed

CR 2000007119, Fire Procedure 34AB-X43-001-1 S Needs to be Enhanced,

CR 2001002032, Fire Procedure 34AB-X43-001 -2S Needs Actions for Diesel Fuel Oil Pumps

CR 2003004377, Fire Procedure 34AB-X43-001-1 Enhancements

'. .

CR 2003004379, Fire Procodure 34AB-X43-001-2 Enhancemonts

.

CR 2003004382, SSAR Discrepancies

.

CRs Generated During this Inspection

CR 2003007129, No Fire Procedure Actions for a Fire in the 2C Switchgear Room

CR 2003007719, Use of Link Wrench

.CR 2003007978, Fire Damper Corrective Action

CR 2003008141, Breaker Maintenance Handle

CR 2003008165, SSAR Section 2.100

CR 2003008179, Drywell Access Emergency Lights

CR 2003008181, Link Labeling

CR 2003008202, Manually Opening MOV 2E1 1 -F01 5A

CR 2003008203, SRV Manual Action Steps in Fire Procedure

CR 2003008237, Emergency Lights and Component Labeling for Manual Actions

Attachment

CR 2003008238, C02 Migration Through Floor Drains

CR 2003800132, SSAR Error for Position of 2E1 1 -FO04A '.

.

CR 2003800151, Instruments for Manual Actions

CR 2003800152, Sliding Links in SSAR

CR 2003800153, Promat Test Report

CR 2003008250, Communications for Post-Fire SSD

.

CR 2003800166, Review Fire Procedure Step 34AB-X43-001-2 Steps to Verify Compliance

with Appendix R.'

Design Criteria and Standards

Design Philosophy for Fire Detectors at E. I. Hatch Nuclear Plants, Rev. 2

.Completed Surveillance Procedures and Test Records

42SV-FPX-021 -OS, Surveillance of Swinging Fire Doors, Task # 1-3367-1 (completed on .

01/09/2003)

42SV-FPX-024-OS, Fire Hose Stations, Task # 1-3359-1 (completed on 06/27/2003)

42SV7FPX-030-OS, Fire Emergency Self Contained Breathing Apparatus Inspection and Test,

Task # 1-4200-3 (completed on'07/07/2003)

42SV-FPX-032-OS, Automatic Sliding Fire Door Surveillance, Task # 1-3361-2 (completed on

08/13/2002 .

Promatec Technologies Installation Inspection Report for Fire Area 2104, MWO 2-98-00881,

-Record 09367-2289, dated 09/03/1998

.

Technical ManualsNendor Information

..

nic

..

./V

.r

,

-

'DowCorning Fire Endurance Test on Penetration Seal Systems in Precast Concrete F Using

Silicone Elastomers, dated.10/28/1975

Dow Corning 561 Silicone Transformer Fluid Technical Manual,10-453-97, dated 1997

S-80393, Mesker Instructions for Installing d&H TPyromatic" Automatic Sliding Fire Door Closer.-

S-27874B, General Electric Instruction Book GEK-26501, Liquid-Filled Secondary Unit

Substation Transformers, Rev. 2

S-52429A, Bisco, Fire Rated Penetration Seal Qualification Data, dated 08/16/1990

S-52480, Factory Mutual, Fire Rated Penetration Seal Qualification Data-Chemtrol Design

FC-225, dated 08/31/1990

S-54875B, Promatec, Fire Barriers-Unit 2 East Cableway, Rev. 2

Omega Point Laboratories, SR90-005, Three Hour Wall Test, dated 06/06/1990

'

Promatec Technologies Inc., PSI-001, Issue 1, General Construction Details, dated 07/21/1998

Promatec Technologies Inc., IP-2031, Installation Inspection for Promat's Three Hour Solid

WalVCeiling Protection System, Issue C, dated 06/16/1998

System Information Document No. Sl-LP-01401-03, Main Steam and Low Low Set System,

dated 4/3/2000

.

Attachment

7

ADDlicable Codes and Standards

ANSI N45.2.11-1974, Quality Assurance Requirements for the Design of Nuclear Power Plants

NFPA 12, Standard for Carbon Dioxide Systems, 1973 Edition.

NFPA 13, Standard for the Installation of. Sprinkler Systems, 1976 Edition.'.:'.'

NFPA 14, Standard for the Installation of Standpipe and Hose Systems, 1974 Edition'

NFPA 20, Standard for the Installation of Centrifugal Fire Pumps, 1973 Edition

NFPA 72D, Standard for the Installation, Maintenance, and Use of Proprietary Protection..

Signaling Systems, 1975 Edition.

NFPA 72E, Standard on Automatic Fire Detectors, 1974 Edition

NFPA 80, Standard on Fire Doors and Windows, 1975 Edition. -

NUREG-1 552, Supplement 1, Fire Barrier Penetration Seals in Nuclear Power Plants, dated

'January 1999

OSHA Standard 29 CFR 1910, Occupational Safety and Health Standards,..

-

Underwriters Laboratory, Fire Resistance Directory, January 1998

..

Other Documents

  • ..Design Change Package 91-009, Retrofill Dielectric Fluid on Unit 2 Transformers, Rev 1

Fire Protection Inspection Reports for the period 2001-2002

.

.

Fire Service Qualification Training, FP-LP-1 0003, Fire Fighter Safety, dated 01/14/2002.:

Fire Service Qualification Training, FP-LP-1 0004, Fire Fighter Personal Protective Equipment,

dated 01/14/2002

Fire Service Qualification Training, FP-LP-1 0014, Fire Streams, dated 01/22/2002

Fire Service Qualification Training, FP-LP-10018, Fire Fighting Principles and Practices, date-d ..'.

01/22/2002

Hatch Response to NRC Information Notice 1999-05, Inadvertent Discharge of Carbon Dioxide;.

Fire Protection System and Gas Migration, dated 05/04/1999

Hatch Response to NRC Information Notice 2002-24, Potential Problems with Heat Collectors '

.'

on Fire Protection Sprinklers, dated 09/20/2002

1 OCFR21 -001, ELECTRAK Corporation, Software Error within TRAK2000 Cable Management."

and Appendix R Analysis System, dated 03/07/2003

U. S. Consumer Product Safety Commission, invensys Building Systems Anncunce P.RC-l'of

Siebe Actuators in Building Fire/Smoke Dampers, dated 10/02/2002

Pre-fire Plan A-43965, Power-Block Areas Methodology, Rev. 0'

Pre-fire Plan A-43966, Fire Area 2404, Diesel Generator Building Switchgear Room 2E, Rev. 2

Pre-fire Plan A-43966, Fire Area 2408, Diesel Generator Building Switchgear Room 2F, Rev. 2

Pre-fire Plan A-43965, Fire Area 2016, W 600V Switchgear Room 2C, Rev.4

'.

'License Basis Documents

Hatch UFSAR Section 3.4, Water Level Flood Design, Rev. 20 .

Hatch UFSAR Section 9.1-A, Fire Protection Plan, Rev. 18C

Hatch UFSAR Section 17.2, Quality Assurance During the Operations Phase, Rev. 20B

Hatch Fire Hazards Analysis, Appendix B, Fire Protection Equipment Operating and

Surveillance Requirements, Rev. 12B

Attachment

Hatch Fire Hazards Analysis, Appendix H, Application of National Fire Protection Association

Codes, Rev. 12B

Hatch SER dated April 18, 1994

-Safe Shutdown Analysis Report for E.I. Hatch Nuclear Plant Units 1 and 2, Rev. 26

Fire Hazards Analysis for E. l. Hatch Nuclear Plant Units 1 and 2, Rev.1 8C, dated 7/00.

NRC Safety Evaluation Report dated 01/02/1987; Re: Exemption from the requirements of

'-

.

-Appendix R to 10 CFR Part 50 for Hatch Units .1 and 2 (response to letter dated

May 16, 1986)..

Letter dated 05/16/86, From L. T. Guewa (Georgia Power) to D. Muller, NRC/NRR; Re: Edwin I

Hatch Nuclear Plant Units 1 and 2 1 0 CFR 50.48 and Appendix R Exemption Requests

Design Chanae Request Documents

DCR No.91-134, SRV Backup Actuation via Pressure Transmitter Signals, Revision 0.

'Drawing No. H-26000, Nuclear Boiler System P&ID, Sheet 1, Revision 39

Drawing No. H-27403, Automatic Depressurization System 2B21 C Elementary Diagram, Sheet

6 of 6, Revision 2

Drawing No. H-27472, Automatic Depressurization System 2B21 C Elementary Diagram, Sheet.

3 of 6, Revision 2-

Drawing No. H-27473, Automatic Depressurization System 2B21 C Elementary Diagram, Sheet

4 of 6, Revision 2

Drawing No. H-24427, Elementary Diagram, ATTS System 2A70 Sheet 27 of 35, Revision 3

.. Drawing No. H-24428, Elementary Diagram, ATTS System 2A70 Sheet 28 of 35, Revision 3

Drawing No. H-24429, Elementary Diagram, ATTS System 2A70 Sheet 29 of 35, Revision 5

Drawing No. H-24430, Elementary Diagram, ATTS System 2A70 Sheet 30 of 35, Revision 3

Drawing No. H-24431, Elementary Diagram, ATTS System 2A70 Sheet 31 of 35, Revision 3

-Drawing No. H-24432, Elementary Diagram, ATS System 2A70 Sheet 32 of 35, Revision 6

Attachment