ML050540462

From kanterella
Jump to navigation Jump to search
Draft Version of Edwin I. Hatch Nuclear Power Plant - NRC Triennial Fire Protection IR 05000321-03-006 and 05000366-03-006
ML050540462
Person / Time
Site: Hatch  Southern Nuclear icon.png
Issue date: 08/31/2003
From: Ogle C
Division of Reactor Safety II
To: Sumner H
Southern Nuclear Operating Co
References
FOIA/PA-2004-0277 IR-03-006
Download: ML050540462 (40)


See also: IR 05000321/2003006

Text

UNITED STATES

.

NUCLEAR REGULATORY COMMISSION

REGION II

/) 7X

SAM NUNN ATLANTA FEDERAL CENTER

61 FORSYTH STREET SW SUITE 23T85

ATLANTA, GEORGIA 30303.8931

/f

X,

Southern Nuclear Operating Company, Inc.

ATTN: Mr. H. L. Sumner, Jr.

Vice President

P. 0. Box 1295

Birmingham, AL 35201-1295

/ro

7

r^

A

SUBJECT:

EDWIN I. HATCH NUCLEAR POWER PLANT - NRC TRIENNIAL FIRE

PROTECTION INSPECTION REPORT '0 382 1 &S3-66ND J0 3860/S-0

ier:

.

50003.2//12.0ob&;A/D

5eB>oo3v/zooa,0

Depar Mr. Sumr

On July 25, 2003, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at

your Hatch Nuclear Plant Units 1 and 2. The enclosed inspection report documents the

inspection findings, which were discussed on that date with Mr. R. Dedrickson and other

members of your staff.

The inspection examined activities conducted under your licenrse as they relate to safety and

compliance with the Commission's rules and regulations and with the conditions of your license.

The inspectors reviewed selected procedures and records, observed activities, and interviewed

personnel

.7'

This report doc ments thee findings that have potential safety significance greater than very

low significa e, however a safety significance determination has not been completed. One

issue invol ng a procedural inadequacy did present an immediate safety concern, how ver,

your staff evised the procedure prioj to the

Iefd of the inspection. The othertA issue did not

present $ immediate safety concern{. In addition, the report documents three NRC-identified

findings of very low safety significance (Green), all of which were determined to involve

violations of NRC requirements. Howev&r, because of the very low safety significance and

because they are entered into your corrective action program, the NRC is treating these three.

findings as non-cited violations (NCVs) consistent with Section VL.A of the NRC Enforcement

Policy. If you contest any NCV intfiis report, you should provide a response within 30 days of

the date of this inspection reportrwith the basis for your denial, to the Nuclear Regulatory

Commission, ATTN.: Documeent Control Desk, Washington DC 20555-0001; with copies to the

Regional Administrator Regioh I1; the Director, Office of Enforcement, United States Nuclear

Regulatory Commission, Washington, DC 20555-0001; and the NRC Resident Inspector at -4

Hatch Nuclear Power Plart.

-

/

A

pva

+7.X-7-

42-

1" .

19

9.-se /(

AJZE, 97

Ia6

a,_e(l a-

e_1111

si//1

5

I

-- 7'

SNC, Inc.

2

In accordance with 10 CFR 2.790 of the NRC's NRules of Practice,' a copy of this letter and its.

enclosure will be available electronically for public inspection in the NRC Public Document

Room or from the Publically Available Records (PARS) component of NRC's document system

(ADAMS). ADAMS is accessible from the NRC Website at

http://www.nrc.gov/readina-rmnfadams.html (the Public Electronic Reading Room).

Sincerely,

Charles R. Ogle, Chief

Engineering Branch 1

Division of Reactor Safety

Docket Nos.: 50-321, 50-366

License Nos.: DPR-57, NPF-5

Enclosure:

NRC Triennial Fire Protection Inspection Report 50-321/03-06, 50-366103-06

w/Attachment: Supplemental Information

cc w/encl:

J. D. Woodard

Executive Vice President

Southern Nuclear Operating Company, Inc.

Electronic Mail Distribution

George R. Frederick

General Manager, Plant Hatch

Southern Nuclear Operating Company, Inc.

Electronic Mail Distribution

Raymond D. Baker

Manager Licensing - Hatch

Southern Nuclear Operating Company, Inc.

Electronic Mail Distribution

Arthur H. Domby, Esq.

Troutman Sanders

Electronic Mail Distribution

Laurence Bergen

Oglethorpe Power Corporation

Electronic Mail Distribution

(cc w/encl cont'd - See page 3)

.

-1

I ".

'-

-

'SNC, Inc.

(cc w/encl cont'd)

Director

Department of Natural Resources

205 Butler Street, SE, Suite 1252

Atlanta, GA 30334

Manager, Radioactive Materials Program

Electronic Mail Distribution

Chairman

A

....

-

.

.

.

~

..

3

'

  • -AppiUng kauunty WaU11ommbilsiabr

. County Courthouse

.

Baxley, GA 31513

Resident Manager

Oglethorpe Power Corporation

Edwin I. Hatch Nuclear Plant

Electronic Mail Distribution

Senior Engineer - Power Supply

Municipal Electric Authority

of Georgia

Electronic Mail Distribution

Reece McAlister

Executive Secretary

Georgia Public Service Commission

244 Washington Street, SW

Atlanta, GA 30334

Distribution w/encl:

S. Bloom, NRR

L. Slack, RII EICS

RIDSNRRDIPMLIPB

PUBLIC

OFFICE

RII:DRS

DRS

RII:DRS

CONTRCTOR

RII:DRP

SIGNATURE

NAME

CSMITH

RSCHIN

GWISEMAN

KSULVA

BONSER

DATE

8/

/2003

8/

/200

8/

/12003

8/

/2003

/

/2

003

E-MAIL COPY?

YES

NO

S

NO IYES

NO I YES

NO

YES

NO

YES

NO-

YE

N

PUBLIC DOCUMENT I

YES

NO I______I__

I

I

I

I

a~al

H-A.UHU

lam-'Y

UUUUMLN

Nn

r l

AM

.....

=

tisng rncn i\\n-tcn .uuult...

E)FFIL;IAL HLUUHU UUVY

UUUUMtN I NAMt: b:whbxtng bmnen 1 Viatch 2003-061trmpa

Docket Nos.:

License Nos.:

Report No.:

Licensee:

Facility:

Location:

Dates:

U. S. NUCLEAR REGULATORY COMMISSION

REGION II

50-321, 50-366

DPR-57, NPF-5

05000321/2003006 and 05000366/2003006

Southern Nuclear Operating Company

E. l. Hatch Nuclear Plant

P. O. Box 2010

Baxley, GA. 31513

July 7-11, 2003 (Week 1)

July 21-25, 2003 (Week 2)

C. Smith, P E., Senior Reactor lnspec prkgead Inspec

R. Schin, Senior Reactor Inspector

G. Wiseman, Fire Protection Inspector

K. Sullivan, Consultant, Brookhaven National Laboratory

Inspectors:

S. Belcher, Nuclear Safety Intern, Week I

A/L

J. e

0 Approved by:

Charles R. Ogle, Chief

Engineering Branch 1

Division of Reactor Safety

Enclosure

CONTENTS

,SUMMARY OF FINDINGS.

......

REPORT DETAILS ...............................................................................................................

.

.

.IPE T9~

.

.~~e

Systems Required to Achieve and Maintain Safe Shutdown .

Fire Protection of Safe Shutdown Capability.

Post-FireSafe Shutdown Capability .

-Operational Implementation of Alternative Shutdown Capability.

C

L

54Cm

'u ii S ons...................;.l

-ergency

Lighting....................................................................................................

Cold Shutdown Repairs......................

................................................................

Fire Barriers and Fire Area/Zone/Room Penetration Seals.........................................

Fire Protection Systems, Features, and Equipment.................................................

SAFETY SYSTEM DESIGN AND PERFORMANCE CAPAIlITY

Dteik4g

34, giV Backup Actuation va Pressure Transmitter Signals .......................

FTHER ACTIVITIES

Identification and Resolution of Problems.

Meetings Including Et..

.

upplem e t

aton .. .. .........

....

...; g.......

......>..\\.+

L eoff

I

pened, C

nd

isc+-----\\\\----7

Lis

Docurne t

...

....

.....

........

...

,//

SUMMA

OF FINDINGS

IR 05000321/20

-006 p05000366/2003-00 , E. l. Hatch Nuclear Plant, Units 1 and 2;

003 and 712125/2003;

riennial Fire Protection

The report covered' two-wek period of inspection by three regional inspectors and a,

oontr

tf

from Brookhaven National Laboratory. Three Green non-cited violations (NCVs) and -

AO

three unresolved items with potential safety significance greater than Green were identified..-'.,'.,.

usgnificance of most findings is indicated by their color (Green, White, Yellow, Red) using %tfr

--

_M¢,)J609, "Significance Determination Process" (SDP). Findings for which the SDP does not

apply may be Green or be assigned a severity level after NRC management review. The:

NRC's program for overseeing the safe operation of commercial nuclear power reactors Is

described in NUREG-1 649, "Reactor Oversight Process," Revision 3, dated July 2000.

<1

A.

NRC-Identified and Self-Revealinq Findings

/Srnersto

itiating Events, Mitigating Systems, and Barrier Integrity

he team identified an unresolved item in that a local manual operator action, to

event spurious opening of all eleven safety relief valves (SRVs) during a fire event,

would not be performed in sufficient time to be effective. Also, licensee reliance on this

.

. manual action for hot shutdown during a fire, instead of physically protecting cables from

fire dam

age

n approved by the NRC.

This finding is u

solved pending completion of a significance determination. Th

finding is greate

an minor because it affects the objective of the mitigating systj

cornerstone.

Iso, the findin has potential safety significance greater than very I

safety sign icance bec

ailure

revent spurious operation of the SRVs cod:

result in t

openingi certain fire sce

rios, thereby compI'ating the post-fire re c c

I'

atns. (Section 1 R05.04/.05.b.1)

1- -

TBD: he team identified an unresolved item in con

oeln with t

implementati'

design phange request (DCR) 91-1

p Actuation

assure Trans

' S

The installed plant mod ication failed to implement t e o

-out-of-two ts

ce loic that was specified as esign in

quirements in t

esign chan

pac

e. Additionally, implementation of a

-out-of-two coincident taken tw e r

-

has introduced a potential common cause

ure of all eleven SRVs

induced damage to two instrumentation circuit cables in close proximity to

h er

This finding is unresolved pending completion of a significance determination. This

finding is greater than minor because it impacts the mitigating system cornerstone. This

finding has the potential for defeating manual control of Group A SRVs that are required

for ensuring that the suppression pool temperature will not exceed the heat capacity

temperature limit (HCTL) forthe suppressiorq pool.,(Section 1 R21.01.b)

Green. The team identified

manual operator action to operate safe shutdown equipment was too difficult and was

also unsafe. The licensee had relied on this action instead of providing physical

..

.

i

i

I

4

6

S1

IIIl

I

I

I

protection of cables from fire damage or preplanning cold shutdown repairs. However,

the team

some operators would not be able to perform the action.'-

Thisevlo

andsP_

CFR 50, Appendix R. Se~ction l1I.!G~.2lhafn~ding

i F

Specifcation 5~.4~.VIe finding Is greater Planerbeaa it uledfthe':- '

avaiiability

and

reliability objectivu

ent performance attribute of the

mitigating systems cornerstone.5

n

Sincethe.

-

implement cold shutdown repairs to facilishe

operatorshment of the action, this finding

did not have potential safety significance greater than very low safety significanc'e.'

(Section 1 R05.04/.05.b.2)

Green. The team identified a tinding with v

my(w

c

ao

in that the

licensee relied on some manual operator actions to operate safe shutdown equipment

instead of providing the required physical protection of cables from fire damage without

<

~~NRC approval.

--

-

-

J } _r

-_.

Thri finding involved a "iolation of10 CFR 50, A

endix R, Section lI.GJ.

The findings

is greater than minor because it affecte the

reliabilitybjcectives and the

e

n

equipment performance attribute of the mitigating systems cornerstone. Since theor

w

b

actions could reasonably be accomplished by operators in a timely manner, this finding

d

did not have potential safety significance greater than very low safety signiiicance.

(

(Section 1 R05.04/.05.b.3)

Nonee

Green. The team identified

PrF low 4nfnc

gmerg

ncy.'

A

l~ighting was not adequate for some manual operator actions that were needed to

0

tef it-

support post-fire operation of safe shutdown equipment.Ll'-

1bno

10 CR50, Appendix R. S

o l..

efnding is.I

greater than minor because it affected te reliability objectiv-eand the e-quipment-.l

performance attribute of the mitigating systems cornerstone. Since operators would be[

'

able to accomplish the actions with the use of flashlights, this finding did not have -

'

potential safety significance greater than very low safety significance. (Section

'/

1 R05.07.b)

.

Licensee-Identified Violationsl

-None

'

11 At X,?w

/O

SUMMARY OF FINDINGS

IR 05000321/2003-006, 05000366/2003-006; E. l. Hatch Nuclear Plant, Units 1 and 2;

7/7-11/2003 and 7/21-25/2003; Triennial Fire Protection

The report covered a two-week period of inspection by three regional inspectors and a.

contractor from Brookhaven National Laboratory.- Three Green non-cited violations (NCVs) and

three unresolved items with potential safety significance greater than Green were identified.

The significance of most findings is indicated by their color (Green, White, Yellow, Red) using

IMC 0609, "Significance Determination Process" (SDP). Findings for which the SDP does not

apply may be Green or be assigned a severity level after NRC management review. The

NRC's program for overseeing the safe operation of commercial nuclear power reactors is

described in NUREG-1 649, "Reactor Oversight Process," Revision 3, dated July 2000.

A.

NRC-identified and Self-Revealin Findings

Cornerstor: Mitigating Systems ohs

Af*tk,?t/

-- *) "b~i~rThe team identified an unresolved item in that a local manual operator action, to

prevent spurious opening of all eleven safety relief valves (SRVs) during a fire event,

would not be performed in sufficient time to be effective. Also, licensee reliance on this

, manual action for hot shutdown during a fire, instead of physically protecting cables from

fire damage, had not been approved by the NRC.

o,

This finding is unresolved pending completion of a sig

determination. Tle

finding is greater than minor because it affects the tigating system cornerstone. Also,

the finding has potential safety significance greater than very low safety significance

because failure to prevent spurious operation of the SRVs could result in the opening is

certain fire scenarios, thereby complicating the post-fire recovery actions. (Section

1 R05.04/.05.b.1)

he team identified an unresolved item in that a fire in Fire Area 2104 could

all e

SRVs to open. The inspection team was concerned that the licen action

A/

to preclu

is scenario were not consistent withtthe current licensin

s of the

p nt. In additi

o objective evidence existed 4o demonstrat

he post-fire safe

shutdown equipmenas adequate to mitigateAeleven S opening. Finally the team

noted that if the Group A

Vs were to spuriously

te as a result of fire damage,

they could not be manually co

led by th ator as part of the licensee's fire

mitigation strategy

This finding is identified

resolved

N RC review of the concerns associated

with the potential fig

of SRVs. This finding

determined to have potential

safety sign

greater than very low significance bese of the concerns

asso

with potential opening of the SRVs and the limite

t of equipment that

,d be available for safe shutdowp n

hese conditions. (Se

1 R.05.03.b)

ran The team identified an unr

d item in connection with the implementation of

design change request (DCR)

1-134, SRV Backup Actuation via Pressure Transmitter

Signals. The installed plant modification failed to implement the one-out-of-two taken

twice logic that was specified as design input requirements in the design change

2

package. Additionally, implementation of a two-out-of-two coincident taken twice logic,

has introduced a potential common cause failure of all eleven SRVs because of fire

induced damage to two instrumentation circuit cables in close proximity to each other.

C

This finding is unresolved pending completion of a significance determination. This

finding is greater than minor because it impacts the mitigating system cornerstone. This

finding has the potential for defeating manual control of GroupOA!SRVs that are

required for ensuring that the suppression pool temperature will not exceed the heat

capacity temperature limit (HCTL) for the suppression pool. (Section 1 R211.01 .b)

Green. The team identified a finding with very low safety significance in that a local

J

manual operator action to operate safe shutdown equipment was too difficult and was

also unsafe. The licensee had relied on this action instead of providing physical

protection of cables from fire damage or preplanning cold shutdown repairs. However,

the team judged that some operators would not be able to perform the action.

-

This finding involved a violation of 10 CFR 50, Appendix R, Section lIl.G.1 and

Technical Specification 5.4.1. The finding is greater than minor because it affected the

availability and reliability objectives and the equipment performance attribute of the

mitigating systems comerstone. Since the licensee could have time to develop and

implement cold shutdown repairs to facilitate accomplishment of the action, this finding

J -did

not have potential safety significance greater than very low safety significance.

-

(Section 1 R05.04/.05.b.2)

Green. The team identified a finding with very low safety significance in that the

licensee relied on some manual operator actions to operate safe shutdown equipment,

instead of providing the required physical protection of cables from fire damage

d

without NRC approval.

This finding involved a violation of 10 CFR 50, Appendix R, Section Ill.G.2. The finding

is greater than minor because it affected the availability and reliability objectives and the

equipment performance attribute of the mitigating systems comerstone. Since the

actions could reasonably be accomplished by operators in a timely manner, this finding

did not have potential safety significance greater than very low safety significance.

(Section 1 R05.04/.05.b.3)

  • a

Green. The team identified a finding with very low safety significance in that emergency

lighting was not adequate for some manual operator actions that were needed to

support post-fire operation of safe shutdown equipment.

This finding involved a violation of 10 CFR 50, Appendix R, Section IIU.J. The finding is

greater than minor because it affected the reliability objective and the equipment

performance attribute of the mitigating systems cornerstone. Since operators would be

able to accomplish the actions with the use of flashlights, this finding did not have

potential safety significance greater than very low safety significance. (Section

1 R05.07.b)

S

-

Ii

I

.

. 1

..

ii

3

B.

Licensee-identified Violations

. None

l l *

J

"' ",,

-

.:

@/

v

b

,.jr.'..,

At 7 stsslo

-

4

-

z -:

.

+

^S

.

/

.

.

R

'-' .,

' ' . . "

' 1 ' '

ate

F:

fi

w

-

.:

l:

S

A:

P

-

f 0

0

-

1 R05

..

......

..

.

.

.

.

.

.

.:-

. .



.

.

-

.

.

....

.

..

...

. >

..

.

..

....

.

,!

- ;-

,

....

...

,.

-

, '

.

'

..

..

-.

..

.

.

.

!

.

'

, .

.,

.

.

.

,.

-

.

  • .

.

}

REPORT DETAILS

REACTOR SAFETY

Cornerstones: Initiating Events, Mitigating Systems and Barrier Integrity

FIRE PROTECTION

The purpose of this inspection was to review the Hatch Nuclear Plant fire protection

program (FPP) for selected risk-significant fire areas. Emphasis was placed on

verification that the post-fire safe shutdown (SSD) capability and the fire protection

features provided for ensuring that at least one fed nda# train of safe shutdown

systems is maintained free of fire damage. The inspection was performed in

accordance with the Nuclear Regulatory Commission (NRC) Reactor Oversight Program

using a risk-informed approach for selecting the fire areas and attributes to be

inspected. The team used the licensee's Individual Plant Examination for External

Events and in-plant tours to choose four risk-significant fire areas for detailed inspection

and review. The fire areas chosen for review during this inspection were:

Fire Area 2016, West 600 V Switchgear Room, Control Building, Elevation 130

feet.

Fire Area 2104, East Cableway, Turbine Building, Elevation 130 feet.

,*

Fire Area 2404, Switchgear Room 2E, Diesel Generator Building, Elevation 130

feet.

!

Fire Area 2408, Switchgear Room 2F, Diesel Generator Building, Elevation 130

feet.

I

\\.-The team evaluated the licensee's FPP against applicable requirements, including

Operating License Condition 2.C.(3)(a), Fire Protection; Title 10 of the Code of Federal

Regulations, Part 50 (10 CFR 50), Appendix R; 10 CFR 50.48; Appendix A of Branch

Technical Position (BTP) Auxiliary and Power Conversion Systems Branch (APCSB)

9.5-1; related NRC Safety Evaluation Reports (SERs); the Hatch Nuclear Plant Updated

Final Safety Analysis Report (HNP-FSAR); and plant Technical Specifications (TS). The

team evaluated all areas of this inspection, as documented below, against these

requirements.

Documents reviewed by the team are listed in the attachment.

.1J

Systems Required to Achieve and Maintain Post-Fire Safe Shutdown

Inspection Scope

The licensee's Safe Shutdown Analysis Report (SSAR) was reviewed to determine the

components and systems necessary to achieve and maintain safe shutdown conditions

in the event of fire in each of the selected fire areas. The objectives of this evaluation

were as follows:

I

2

1.

Verify that the licensee's shutdown methodology has correctly identified

the components and systems necessary to achieve and maintain a safe

-

shutdown condition.

2.

Confirm the adequacy of the systems selected for reactivity control,

-"

reactor coolant makeup, reactor heat removal, process monitoring and

support system functions.

3.

Verify that a safe shutdown can be achieved and maintained without off-

site power, when it can be confirmed that a postulated fire in any of the

selected fire areas could cause the loss of off-site power.

4.

Verify that local manual operator actions are consistent with the plant's

fire protection licensing basis.

b.

Findinas

The team identified a potential concern in that the licensee used manual actions to':

disconnect terminal board sliding links in order to isolate two 4-20 milli-amp (ma

'

instrumentation loop control circuits in order to prevent the spurious actuation f eleven

SRVs, This issue is discussed in section 1 R05.03.b of the report.

4o,

a 7

.02

Fire Protection of Safe Shutdown Caabilit-y

a.

InsDection Scope

For the selected fire areas, the team evaluated the frequency of fires or the potential for

fires, the combustible fire load characteristics and potential fire severity, the separation

of systems necessary to achieve safe shutdown (SSD), and the separation of electrical

components and circuits located within the same fire area to ensure that at least one

SSD path was free of fire damage. The team also inspected the fire protection features

to confirm they were installed in accordance with the codes of record to satisfy the

applicable separation and design requirements of 10 CFR 50, Appendix R, Section III.G,

and Appendix A of BTP APCSB 9.5-1. The team reviewed the following documents,

which established the controls and practices to prevent fires and to control combustible

fire loads and ignition sources, to verify that the objectives established by the

NRC-approved fire protection program (FPP) were satisfied:

Updated Final Safety Analysis Report (UFSAR) Section 9.1 -A, Fire Protection

Plan

Administrative Procedure 40AC-ENG-008-OS, Fire Protection Program

Administrative Procedure 42FP-FPX-01 8-OS, Use, Control, and Storage of

Flammable/Combustible Materials

Preventive Maintenance Procedure 52PM-MEL-012-0, Low Voltage Switchgear

Preventive Maintenance

The team toured the selected plant fire areas to observe whether the licensee had

properly evaluated in-situ fire loads and limited transient fire hazards in a manner

consistent with the fire prevention and combustible hazards control procedures. In

addition, the team reviewed the licensee's fire safety inspection reports and corrective

action program (CAP) condition reports (CRs) resulting from fire, smoke, sparks, arcing,

and overheating incidents for the years 2000-2002 to assess the effectiveness of the fire

3

prevention program and to identify any maintenance or material condition problems

related to fire incidents.

The team reviewed fire brigade response, fire brigade qualification training, and drill

program procedures; fire brigade drill critiques; and drill records for the operating shifts

from January 1999 - December 2002. The reviews were performed to determine

whether fire brigade drills had been conducted in high fire risk plant areas and whether

fire brigade personnel qualifications, drill response, and performance met the

requirements of the licensee's approved FPP.

The team walked down the fire brigade equipment st age areas and dress-out locker

areas in the fire equipment building and the turbin

iulding to assess the condition of

fire fighting and smoke control equipment. Fire

igade personal protective equipment

located at both of the fire brigade dress-out are s and fire fighting equipment storage

area in the turbine building were reviewed to e aluate equipment accessibility and

functionality. Additionally, the team observe whether emergency exit lighting was

provided for personnel evacuation pathways a the outside exits as identified in the

National Fire Protection Association (NFPA) 101, Life Safety Code, and the

Occupational Safety and Health Administration (OSHA) Part 1910, Occupational Safety

and Health Standards. This review also included examination of whether backup

emergency lighting was provided for access pathways to and within the fire brigade

equipment storage areas and dress-out locker areas in support of fire brigade

operations should power fail during a fire emergency. The fire brigade self-contained

breathing apparatuses (SCBAs) were reviewed for adequacy as well as the availability

of supplemental breathing air tanks and their refill capability.

The team reviewed fire fighting pre-fire plans for the selected areas to determine if

appropriate information was provided to fire brigade members and plant operators to

facilitate suppression of a fire that could impact SSD. Team members also walked down

the selected fire areas to compare the associated pre-fire plans and drawings with as-

built plant conditions. This was done to verify that fire fighting pre-fire plans and

drawings were consistent with the fire protection features and potential fire conditions

described in the Fire Hazards Analysis (FHA).

The team reviewed the adequacy of the design, installation, and operation of the manual

suppression standpipe and fire hose system for the control building. This was

accomplished by reviewing the FHA, pre-fire plans and drawings, en

ring

mechanical equipment drawings, design flow and pressure calculatio

a d NFPA 14

for hose station location, water flow requirements and effective reach

ability. Team

members also walked down the selected fire areas in the control building to ensure that

hose stations were not blocked and to verify that the required fire hose lengths to reach

the safe shutdown equipment in each of the selected areas were available. Additionally,

the team observed placement of the fire hoses and extinguishers to assess consistency

with the fire fighting pre-fire plans and drawings.

b.

Findings

No findings of significance were identified.

-

l

- f

l f ;

of r 7 ; a;?

¢

lv

v*erS

Rae

s Of 'S

. s

,

L,

.

,.,,

.

,

2

.

.

.

'

'

.

.

':'

" ' ' ;'."

' .'

'

'

", .' '

'.

. .

_.

.

.

.

.

.

-,

_

.

S I,- '

f ' .. "'

'

' - ' '

..

:,'..,.

"'

.

'

.

, '.

.03

- .

...

. - -

..

-

..

>;- ->;

'

a

.

. .

...

.

.

.

.

.

k

-

k :

,. -

e , :

-,

.,

,

-

s

.

.,

, .-

...

....

....

.

. -

-

4

. .

T

.

.

...

..

...

.

.

'" ' 'I '

'

.

'

'

,

.

....

',':,,

.'

.

'

.

.

.

..

..

.

.

.

.

.

'.:

,

',

..

^

..

.

.

...

.

,

.

]

,

..

.

.

.

.

' . ' 'I'd '

' .

.

..

.

.

.

.

"",:

' ' '

_

'

i

,

.

.

.

..

.

.

.

.

.

.

..

.,

_

'. '

' .

.

.

..

..

.

.

"',

'

_ "

,

.

.

.

.

....

.

a' ".'

"'"',

_

'.'

.

....

.

.

.

v

s

l

.

.

,

'

.

. .

'

.

.

.

.

.

.

..

.

.

.,

,.

I

'

'

.,

'

.

.

..

.

.

Inspection Scope

On a sample basis, the inspectors paluated whether the systems an equipment

identified in the licensee's SSAR s being required to achieve and mentain hot

shutdown conditions would re

in free of fire damage in the event of ire in the

fire areas. The evaluation in uded a review of cable routing data de icting the L,

of power and control cable associated with SSD Path 1 and Path 2 component.

RCIC and HPCI systems. Additionally, on a sample basis, the team reviewed the

licensee's analysis of electrical protective device (e.g., circuit breaker, fuse, relay),

coordination. The following motor operated valves (MOVs) and other components

reviewed:

IM.

.

iI

7

11

1

LiOm1ponenit IL)

2E51-F029

2E51 -F010

2P41 -CO01 A

2E11-F011A

-2P41 -C001 B

2E41-F001

eUsbUrILtluI

RCIC Pump Suction from Suppressionspal

RCIC Pump Suction Valve from

DC

e

Plant SerVice Water Pump 2A

^RH-!Veat Exchanger A Drain to Suppression Pool Valve

Plant Service Water Pump 2B

HPCI Turbine Steam Supply Valve

I-

2E41 -F002

2E41 -F006

2E41-F008

HPCI Turbine Steam Supply Inboard Containment Isolation Valve

HPCI Pump Inboard Discharge Valve

HPCI Pump Discharge Bypass Test Valve to CST

b.

Findings

The team identified a potential concern in that the licensee used manual actions to

isolate two 4 to 20 ma instrumentation loop control circuits associated with eleven SRVs

in lieu of providing physical protection. This did not appear to be cgrjtstent with theIJo

.plant's licensing basis nor 10 CFR 50 Appendix R. Spurious acti'he tlese SRVs e

ese could impact the licensee's fire mitigation strategy. In addi ion th licensee had

no objective evidence that post-fire safe shutdown equipment co

figate this event.

The SSAR stated that a fire in Fire Area 2104 could cause all eleven SRVs to spuriously

actuate as a result of fire damage to two cables located in close proximity in this area.,N

The specific circuits that could cause this event have been identified by the licensee A&Y

4c6rcuitlern: ABE01 9C08 and ABE01 9C09P Each of these two circuits provides a 4 to

20 ma instrumentation signal from SRV high-pressure actuation transmitters4B21 -

.I

N127B and 2B21-N127Dgto master trip us 2

-N697B and 2B21-N697D,

respectively. The purpose of this circui

is to provide an electrical backup to the

mechanical trip capability of the indivj ual SRVs. In the event of high reactor pressure,

the circuits would provide a signal

the master trip units which would cause all eleven

SRVs to actuate (open). The pr sure signal from each transmitter is conveyed to its

respective master trip unit thro gh a two-conductor, instrument cable that is routed

through this fire area (two se arate cables). Each cable consists of a single twisted pair

of insulated conductors, an ninsulated drain wire that is wound around the twisted pair

of conductors, and a foil

leld. In Fire Area 2104 the two cables are located in close

proximity, in the same c

le tray. Actuation of the SRV electrical backup is completely.

"blind" to the operators. hat is, unlike ADS, it does not provide any pre-actuation

indication (e.g., actuation of the ADS timer) or an inhibit capability (e.g., ADS inhibit

switch). Since the operators typically would not initiate a manual scram until fire

damage significantly interfered with control of the plant, its possible that all eleven SRVs

could open at 100% power, prior to scramming the reactor. This scenario could place

the plant in an unanalyzed condition.

Unlike a typical control circuit, a direct short or "hot short" between conductors of a 4 to

20 ma instrument circuit may not be necessary to initiate an undesired (false high)

signal. For cables that transmit low-level instrument signals, degradation of the

insulation of the individual twisted conductors due to fire damage may be sufficient to

cause leakage currents to be generated between the two conductors. Such leakage,

current would appear as a false high pressure signal to the trip units. If both cables

were damaged as a result of fire, false signals generated as a result of leakage current

in each cable, could actuate the SRV electrical backup scheme which would cause all

eleven of the SRVs to open. The conductor insulation and jacket material of each cable

is cross-linked polyethylene (XLPE). Since both cables are in the same tray and

exposed to the same heating rate, there is a reasonable likelihood that both

instrumentation cables could suffer insulation damage at the same time and both circuits

could fail high simultaneously.

The licensee's SSAR recognizes the potential safe significance of this eve

nd

describes methods that have been developed to revent its occurrence an or mitigate

its impact on the plant's post-fire safe shutdow capability should it occur. o prevent

this scenario, the licensee has developed pro edural guidance which directs operators

to open link BB-10 in panel 2H1 1-P927 and nk BB-10 in panel 2H11-P928. These

panels are located in the main control room. Opening of these links would prevent

actuation of the SRV trip units by removing the 4 to 20 ma signal fed by the pressure

transmitters to the master trip units. In the event the SRVs were to open prior to

operators completing this action, the SSAR credits core spray loop A to mitigate the

event.

The inspection team had several concerns regarding the licensee's approach to this

potential spurious actuation of the SRVs. Specific concerns identified by the team

included:

1.

The links may not be opened in time to preclude inadvertent actuation of

the SRVs.

6

2.

The use of links to avoid inadvertent actuation of the SRVs did not

appear to be consistent with the current licensing basis.

3.

No objective evidence existed to demonstrate that the post-fire safe

shutdown equipment could adequately mitigate a fire in Fire Area 2104, if

the SRVs were to open.

4.

The operations staff is unable to manually control the group A SRVs that

are credited for mitigating a fire in Fire Area 2104 if they spuriously

actuatska a result of fire induced damage.

.

I-

-F,

I-.

With regard to t

iming of operator actions to prevent fire damage from causing all

SRVs to open, u ng the inspection, the licensee performed an evaluation which

estimated that approximately thirty minutes would pass from the time of fire detection to

the time an operator would implement procedural actions to open the links. The

inspectors independently arrived at a similar time estimate based on their review of the

procedure. In response to inspectors concerns that this interval may be too lengthy to

preclude fire damage to the cables of interest and subsequent actuation of the SRVs,

-

the licensee agreed to enhance its existing procedures so that the action would be

taken immediately following confirmation of fire in areas where the spurious actuation

could occur. This issuep0cliscussed is Section IR.04/.05.b.1,of this report.

The team also considered opening terminal board inko be not in compliance with the

plant's licensing basis. Current licensing basis d -uments, specifically Georgia Power

request for exemption dated May 16, 1986,

a subsequent NRC Safety Evaluation

Report (SER) dated January 2, 1987, ch

cterized the opening of links as a repair

activity that is not permitted as a mean of complying with Section IIL.G of Appendix R.

The inspectors concluded that, the o

ning of links was considered a repair by both the

licensee and the NRC staff in 1987. he licensee could not provide any evidence to

justify why these actions are not characterized as a repair activity in its current SSAR.

Additionally, because there is a potential for all SRVs to spuriously actuate as a result of

fire in Fire Area 2104 at a time when RHR is not available, the SSAR credits the use of

core spray loop A to accomplish the reactor coolant makeup function. During the

inspection, the licensee performed a simulator exercise of an event which caused all 11

SRVs to open. During this exercise, simulator RPV level instruments indicated that core

spray would be capable of maintaining level above the top of active fuel. However, the

licensee did not provide any objective evidence (e.g., specific calculation or analysis)

which demonstrated that, assuming worst-case fire damage in Fire Area 2104, the

limited set of equipment available would be capable of mitigating the event in a manner

that satisfies the shutdown performance goals specified in Appendix R, Section L.. .e to

10 CFR 50.

-C/un

Finally, the kli~,bee s tailure o lImiipunie

1nt Je input

-

two taken twice logic for DCfl 31-134 resulted i the followl--inga1

ir

or

the logic

that was installed by DCR 91-134 for the SRVs was a two-out-of-two coincident taken

twice logic in addition to a one-out-of-two coincident taken twice logic. The team

determined that the two-out-of-two coincident logic input from trip unit master relays

K31 OD and K335D represented a common cause failure for group "A" SRVs for a fire in

I

%

r-OY

J,

F

,

.7

/-AA ie.%te .(5

!

  • 2~AR

~~2-.O~'

Fire Area 2104. Specifically, cable ABE01 9C08 associated with pressure transmitter

2B21 -Ni27B current loop, and cable ABE019CO9 associated with pressure transmitter

2B21-N127D current loop, are routed in close proximity to each other in 'the same cable'

tray in Fire Area 2104. Both shielded twisted pair instrument cables are unprotected,

from the effects of a fire in this fire area. Fire induced insulation damage to both cables

could result in leakage currents which causes the instrument loops to fail high.' This - I

failure mode simulates a high nuclear boiler pressure condition and would initiate SRV

backup actuation of all the group UA! SRVs. Whenever a SRV lifts, it will remain open

until pressure reduces to about 85% of its overpressure lift setpoint The instrument

loops having ifailed high, however, will 'ensure that the trip unit master relays and the trip

unit slave re ays continue to energize the pilot valve of the individual SRV and keep'the

SRV open.

his failure mode prevents the operators from manually controlling the'-..

s as is required per the SSAR.

In response, the licensee initiated a Condition Report (CR 2003800152, dated 7/24/03)

to evaluate actions to open links, in order to determine if they are necessary to achieve

hot shutdown, and if an exemption from Appendix R is required. Pending additional

review by the NRC, this issue is identified aSAVRI 50-366/20G030G690,

Concerns'

Associated with Potential Opening of SR Ccn.

.04/.05 Alternate Shutdown Capabilitv/O erational Implementation of Alternative Shutdown

Capability

a.

Inspection Scope

The selected fire areas that were the focus of this inspection all involved reactor

shutdown from the control room. None involved abandoning the control room and1 #J

alternative safe shutdown from outside of the control room. Thus, alternate shutlown

capability was not reviewed during this inspection. However, the licensee's plans for

SSD following a fire in the selected areas Involved many local manual operator actions

that would be performed outside of the control area of the control room. This section of

the inspection focused on those local manual operator actions.

.1'

The team reviewed the operational Implementation of the SSD capability for a 4in thy

>

selected fire areas to determine if: (1) the procedures were consistent with th

pendix

R safe shutdown analysis (SSA); (2) the procedures were written so that the operator

actions could be correctly performed within the times that were necessary for the actions

to be effective; (3) the training program for operators included SSD capability; (4)

6

personnel required to achieve and maintain the plant in hot standby could be provided

from the normal onsite staff, exclusive of the fire brigade; and (5) the licensee

periodically performed operability testing of the SSD equipment.

The team walked down SSD manual operator actions that were to be performed outside

of the control area of the main control room for a fire in the selected fire areas and

discussed them with operators. These actions were documented in Abnormal Operating

Procedure (AOP) 34AB-X43-001 -2, Version 10.8, dated May 28, 2003. The team

evaluated whether the local manual operator actions could reasonably be performed,

using the criteria outlined in NRC Inspection Procedure (IP) 71111.05, Enclosure 2. The

team also reviewed applicable operator training lesson plans and job performance

-

-

-

r:

4

i J

':

^ i:

-

-

F

\\

.

-

-

A:

-

8

measures (JPMs) and discussed them with operators. In addition, the team reviewed

I records of actual operator staffing on selected days.

Findings

- 1.-

Untimely and Unapproved Manual Operator Action for Fire Safe Shutdown

Introduction: The team found that a local manual operator action to prevent spurious

-

opening of all eleven SRVs would not be performed in sufficient time to be effective.

Licensee reliance on this manual action for hot shutdown during a fire, instead of

physically protecting cables from fire damage, had not been approved by the NRC.

4,1

.

.

.

I -

Description: The team noted that Step 9.3.2.1 of AOP 34AB-X43-001-2, Fire

/

Procedure, Version 10.8, dated May 28, 2003, stated: 'To prevent all eleven Srgs fro

opening simultaneously, open links BB-10 in Panel 2H1 1-P927 and BB-10 in lanel

2H1-1-P928." The team noted that spurious opening of all eleven SRVs would be

considered a large loss of coolant accident (LOCA), and that a LOCA raf be

Z prevenTe -fiom

iicurR5 g a ire venIAAdditionally, the team observed that this

step was sufficiently far back in the proceddrb that it may not be completed in time to

prevent potential fire damage to cables from causing all eleven SRVs to spuriously

open.

The licensee had no preplanned estimate of how long it would take operators to

complete this step during a fire event. There was no event time line or operator training

job performance measure (JPM) on this step. The team noted that, during a fire-eyent,

operators could be using many other procedures concurrent with the Fire Procedure.

For example, they could be using other procedures to communicate with the fire brigade

about the fire, respond to a reactor trip, deal with a loss of offsite power, and provide

emergency classifications and offsite notifications of the fire event. During the

inspection, licensee operators estimated that, during a fire event, it could take aboutt,

minutes before operators would accomplish Step 9.3.2.1. The team concurred with i

time estimate. However, NRGfire models indicated that fires could potentially cause

damage to cables inaslt66

to ten minutes. Consequently, the teams

I

concluded that during a fire eveihe

licensee's procedures would not ensure thatp7

9.3.2.1 would be accomplished Ine

to prevent potential spurious opening of all

l1even SRVs.

-A

g1

The team also identified other

s with Step 9.3.2.1. There was no emergency

2

lighting inside the panels, hen ef he fire caused a loss of normal lighting (e.g., by

causing a loss of offsite pow

e erators would need to use flashlights to plerform the

actions inside the panels. Consequently, the team considered the emergency lighting

for Step 9.3.2.1 to be inadequate (see Section 1 R05.07.b). In addition labeling of the

links inside the panels was so poor that operators stated that the

y

n fully rely on

E

the labeling. Also, the tool that operators would use to loosen a

sli

he links inside

-a

the energized panels was made of steel and was not professio allele rically

insulated. Further, licensee reliance on this operator action, insad

physically

£

protecting the cables as required by

tN0

CFR 50, Appendix R. S

n I.G.2, had notNC

bleen approved by the NRC.-

tzr -1I

0 Cr-~P.

ff

-L'- YŽ)j -C-~-

~NZ

L- -

  • ,a^

M L. re Zc~ e. 1etL ttU-J"t

A- f 0i4-K#e.

9

The licensee stated that cable damage to two instrument cables, for reactor pressure.:

signals, would be needed to spuriously open all eleuenNSRVs. Since the licensee stated

that the two cables were in the same cable tray in We Krea 2104,A4heI- 4 -

--

ableay, the team considered that a fire in that area could potentially cause all eleven-

SRVs to spuriously open (see section 1 R21.01 .b).

In response to this issue, the licensee initiated CR 2003008203 and promptly revised

the Fire Procedure before the end of the inspection, moving the actions of Step 9.3.2.1-

to the beginning of the procedure. The procedure change enabled the actions to be

accomplished much sooner during a fire in the Unit 2 east cableway or in other fire

areas that were vulnerable to the potential for spuriously opening all eleven SRVs. The

team determined that this issue is related to associated circuits. As described in NRC

Inspection Procedure (IP) 71111.05, Fire Protection, inspection of associated circuits Is

temporarily limited. Consequently, the team did not pursue the cable routing or circuit

analysis that would be necessary to evaluate the possibility, risk, or potential safety

significance of Group B and C SRVs .spuriously

opening due to fjre damage to the -

1 ..

instrument cables. The team did, however, perform a circuit ana ysis of Group A SRVs

for which the licensee takes credit for a fire in fire a

2104. &'e section 1 R21.01). c#

Analysis: The team determined that this finding wssociated with the protection

against external factors attribute. It affected the 4bjective of the mitigating systemo

ensure the availability of systems that respond t nitiating events and*

ater7'-

than minor. The team determined that the finding had pot

safety significance

greater than very low safety significance because, failu to prevent spurious operation

of the SRVs could result in them opening in certair -fiscenarios, thereby complicating

the post-fire recovery a

ns. Howev r the finding remains unresolved pending

completion of the

Enforcement: 1

R 50 A

endix R, Section Ill.G.2 requires that where cables or

equipment, including ass

ated non-safety circuits that could prevent operation or

cause mal-operation d to hot shorts, open circuits, or shorts to ground, of redundant

trains of systems ne

ssary to achieve and maintain hot shutdown conditions are.

located within the me fire area outside of the primary containment, one of the'

following means f ensuring that one or the redundant trains is free of fire damage shall

be provided: 1) a fire barrier with a 3-hour rating; 2) separation of cables by a horizontal

distance of more than 20 feet with no intervening combustibles and with fire detectors

and automatic fire suppression; or 3) a fire barrier with a 1-hour rating with fire detectors

and automatic suppression.

The licensee had not provided physical protection against fire damage for the two

instrument cables by one of the prescribed methods. Instead, the licensee had relied on

manual operator actions to prevent the spurious opening of all eleven SRVs. Licensee

personnel contended that fire damage to two cables was outside of the Hatch licensing

basis and consequently that there was no requirement to protect the instrument cables.

However, the licensee could provide no evidence to support that position.

This potential issue will remain unresolved pending the completion of a significance

determination by the NRC. This issue is identified as URI 50-366/03-06-02, Untimely

and Unapproved Manual Operator Action foroFire Safe Shutdown.

.10

2.

Local Manual Operator Action was Too Difficult and Unsafe

Introduction: A finding of very low safety significance was identified in at a local

manual operator action to operate SSD equipment was too difficult

d was also unsafe.'

The team judged that some operators would not be able to perfo

the action. This

finding involved a violation of NRC requirements.

Description: The team observed that Steps 4.15.8.1.1 a

9.3.5.1 of the Fire Procedure

were relied on instead of providing'physical protection

r cables or providing a

procedure for cold shutdown repairs. Both steps re

wed the same local manual

operator action: "Manually OPEN 2E1 1 -F0l 5A, In ard LPCI Injection Valve, as

required." This action was to be taken in the Uni

drywell access, which was a locked

high radiation, contaminated, and hot area with emperatures over 100 degrees F.

Valve 2E1 I -F01 5A was a large (24-inch dia eter) motor-operated gate valve with a

three-foot diameter handwheel. The main ifficulty with manually opening this valve was

lack of an adequate place to stand. An oprator showed the team that to perform the

action he would have to climb up to and

and on a small section of pipe lagging (a

curved area about four inches wide by l inches long), and then reach back and to his

right side, to hold the handwheel with

s right hand, while reaching forward and to his

right to hold the clutch lever for the m or operator with his left hand. He would not have

good balance while performing the a ion. The foothold, which was large enough to'

support only one foot, was well flatte ed and appeared to have been used in the past to

manually operate this valve. The fo thold was about six to seven feet above a steel

grating, and the team observed tha space available for potential use of a ladder to

better access the 2E1 1-F015A valve handwheel was not good.

Other difficulties with manually opening the valve included the heat; the need to wear'

full anti-contamination clothing, a hardhat, and safety glasses; and inadequate

'

emergency lighting (see Section 1 R05.07). Also, there was no note or step in the

procedure to ensure that the RHR pumps were not running before attempting to

manually open the 2E1 1-FO15A valve. If an RHR pump were running, it could create a

differential pressure across the valve which could make manually opening it much more

difficult. If the operator did not have sufficient agility, strength or stamina, he would be

unable to complete the action. Also, the team judged that inability to remove sweat from

his eyes, due to wearing gloves that could be contaminated, would be a limiting factor

for the operator. In addition, if the operator slipped or lost his balance, he could fall and

become injured. Considering all of the difficulties, the team judged that this action was

unsafe and that some operators would not be able to perform it.

The licensee had no operator trainingJPM for performing this action and could not

demonstrate that all operators could perform the action. One experienced operator,

who appeared to be in much better physical condition that an average nuclear plant

operator, stated that he had manually operated the valve in the past, but that it had been

very difficult for him.

The team judged that, since this action was not required to maintain hot shutdown and

was required for cold shutdown following a fire in one of the four selected fire areas,

licensee personnel could have time to improve the working conditions after a fire. They

I

11

ave time to in

SC

oding or temporary ventilation; improve the lighting; and

assignImultiple oper to to

anually open the valve. They could have time to perform

afcol shutdown re

H ever, the licensee had not preplanned any cold shutdown

prs for opening t Y

e.

Analysis: This finding is greater than minor because it affected the availability and

reliability objectives and the equipment performance attribute of the mitigating systems

cornerstone. Since the licensee could have time to develop and implement cold

shutdown repairs to facilitate accomplishment of the action, this finding did not impact

the effectiveness of one or more of the defense in depth elements. Hence this finding

did not have potential safety significance greater than very low safety significance

(Green).

Enforcement: 10 CFR 50, Appendix R, Section III.G.1 requires that fire protection

features shall be provided for systems important to safe shutdown and shall be capable

of limiting fire damage so that systems necessary to achieve and maintain cold

shutdown from either the control room or emergency control stations can be repaired

within 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br />. In addition, TS 5.4.1 requires that written procedures shall be

established, implemented, and maintained covering activities including fire protection

program implementation and including the applicable procedures recommended in

Regulatory Guide 1.33, Revision 2, Appendix A, February 1978. Regulatory Guide 1.33

recommends procedures for combating emergencies including plant fires and

procedures for operation and shutdown of safety-related BWR systems. The fire

protection program includes the SSAR which requires that valve 2E1 1-FO15A be

opened for SSD following a fire in Fire Area 2104, the Unit 2 east cableway. AOP

34AB-X43-001-2, Fire Procedure, Version 10.8, dated May 28, 2003, implements these

requirements in that it provides information and actions necessary to mitigate the

consequences of fires and to maintain an operable sh

r

in

i

a

age

to specific fire areas. Also, AOP 34AB-X43-001-

ovides

PSt 4.15.8.11 and 9. 5.1

for manually opening valve 2E11 1-F015A followi

a fire in eee

Contrary to the above, the licensee had no proceue

i

ted fire

damage within 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br />. Instead, the licensee relied on local manual operator actions,

as described in Steps 4.15.8.1.1 and 9.3.5.1 of AOP 34AB-X43-001-2. However, those

procedure steps were inadequate in that some operators would not be able to perform

them because the required actions were too difficult and also were unsafe. In response

to this issue, the licensee initiated CR 203008202. Because the identified inadequate

operator actions are

significance and the issue has been entered into

the licensee's corr

ive act o progra

this violation is being treated as an NCV,

consistent with

ction VI.A 'of the

C's Enforcement Policy: NCV 50-366/03-06-03,

Inadequate Pro edure for

[Ma

al Operator Action for Post-Fire Safe Shutdown

Equipment.

3.

Unanproved Manual Operator Actions for Post-Fire Safe Shutdown

Introduction: A finding of very low safety significance was identified in that the licensee

relied on some manual operator actions to operate SSD equipment, instead of providing

the required physical protection of cables from fire damage. This finding involved a

violation of NRC requirements.

12

Description: Th team observed that AOP 34AB-X43-001-2, Fire Procedure, included

some local m ual operator actions to achieve and maintain hot shutdown that had not -

been approv d by the N C. Examples of steps from the procedure included:

4.1 5.2.2, .

a loss of offsite power occurs and emergency busses energize

lace Station Service battery chargers 2R42-S026 (2R42-S029), 2R42-S027

(2R42-S030) AND 2R42-S028 (2R42-S031) in service per 34SO-R42-001 -2."-

-

Step 4.15.4.5; ...If HPCI fails to automatically trip on high RPV level... OPEN the

following links to energize 2E41-F124, Trip Solenoid Valve, AND to fail 2E41-

9'

rJ

i

,F3025

HPCI Governor Valve, in the CLOSED position:

TT-75 in panel 2H11-P601

TT-76 in panel 2H11-P601"

Step 4.15.4.6; ... lf HPCI fails to automatically trip on high RPV level..'. "OPEN

breaker 25 in panel 2R25-S002 to fail 2E41-F3052, HPCI Governor Valve, in the

CLOSED position."

The team walked down these actions using the guidance contained in Inspection

Procedure 71111.05T and judged that they could reasonably be accomplished by

operators in a timely manner. However, the team determined that these operator

actions were being used instead of physically protecting cables from fire damage that

could cause a loss of station service battery chargers or a HPCI pump runout.

Analysis: The finding is greater than minor because it affected the availability and

reliability objectives as well as the equipment performance attribute of the mitigating

systems cornerstone. Since the actions~could reasonably be accomplished by operators

in a timely manner, this finding did n t ave potential safety significance greater than

very low safety significance.

Enforcement: 10 CFR 50

pendixR.Section III.G.2 requires that where cables or

equipment, including a ociated non-safety circuits that could prevent operation or..

cause maloperation ue to hot shorts, open circuits, or shorts to ground, of redundant

trains of systems ecessary to achieve and maintain hot shutdown conditions are

located within t

same fire area outside of the primary containment, one of the

following me

s of ensuring that one of the redundant trains is free of fire damage shall

be provided: 1) a fire barrier with a 3-hour rating; 2) separation of cables by a

horizontal distance of more than 20 feet with no intervening combustibles and with fire

detectors and automatic fire suppression; or 3) a fire barrier with a 1-hour rating with fire

detectors and automatic suppression.

Contrary to the above, the licensee had not provided the required physical protection

against fire damage for power to the station service battery chargers or for HPCI

electrical control cables. Instead, the licensee relied on local manual operator actions,

without NRC approval. In response to this issue, the licensee initiated CR2003800166.

Because the issue had very lovw safety significance and has been entered into the

licensee's corrective action prpb ram, this violation is being treated as an NCV,

consistent with Section VI.AJ$lf the NRC's Enforcement Policy: NCV 50-366/03-06-04,

Unapproved Manual Operator jctions for Post-Fire Safe Shutdown.

.06:. Communications

a

lnSection Scope

The team reviewe

support fire brigac

the safe shutdowr

be available for p:

team reviewed the

brigade to commu

b. -

Findings

No findings of sigr

.07

Emer6env Licghtir

13

d the plant communications systems that would be relied upon to

le and safe shutdown activities. The team walked down portions of

i procedures to verify that adequate communications equipment would

ersonnel performing local manual operator actions. In addition, the

e adequacy of the radio communication system used by the fire

Jnicate with the main control room.

iificance were identified.

..

.,

a..

Inspection Scone

The team inspected the licensee's emergency lighting systems to verify that 8-hour

emergency lighting coverage was provided as required by 10 CFR 50, Appendix R,

Section III.J., to support local manual operator actions that were needed for post-fire

operation of SSD equipment. During walkdowns of the post-fire SSD operator actions

for fires in the selected fire areas, the team checked if emergency lighting units were

installed and if lamp heads were aimed to adequately illuminate the SSD equipment, the

equipment identification tags, and the access and egress routes thereto, so that

operators would be able to perform the actions without needing to use flashlights.

- b.

Findings

Inadequate Emergency Lighting for Operation of Safe Shutdown Equipment

Introduction: A finding with very low safety significance was identified in that emergency

lighting was not adequate for some manual operator actions that were needed to

support post-fire operation of SSD equipment. This finding involved a violation of NRC

-

requirements.

Description: The team observed that emergency lighting was not adequate for some

manual operator actions that were needed to support post-fire operation of SSD

equipment. Examples included the following operator actions in procedure 34AB-X43-

001 -2, Fire Procedure, Version 10.8, dated May 28, 2003:

.*.

Step 4.15.2.2; ...if a loss of offsite power occurs and emergency busses energize

..."Place Station Service battery chargers 2R42-S026 (2R42-S029), 2R42-S027

I

(2R42-S030) AND 2R42-S028 (2R42-S031) in service per 34SO-R42-001 -2."

Step 4.15.4.5; ... lf HPCI fails to automatically trip on high RPV level... 'OPEN the

following links to energize 2E41-F1l24, Trip Solenoid Valve, AND to fail 2E41-

F3025 HPCI Governor Valve, in the CLOSED position:

-14

TT-75 in panel 2H1 Il-P601

TT-76 in 'panel 2H1-1-P601"

Step 4.15.5; "IF 2R25-S065, Instrument Bus 26, is DE-ENERGIZED perform the

following manual actions to maintain 2C32-R655, Reactor Water Level.':

Instrument, operable:

4.15.5.1; At panel 2H11-P612, OPEN links AAA-11 and AAA-12.

4.15.5.2; At panel 2H11-P601, CLOSE links HH-48 and HH49."

Steps 4.15.8.1.1 and 9.3.5.1; "Manually OPEN 2E11 1-F01 5A, Inboard LPCI

?

tInjection Valve, as required."

Steps 4.15.8.1.2 and 9.3.5.2; "Manually CLOSE 2E1 1 -F01 8A, RHR Pump A

Minimum Flow Isolation Valve, as required."

Step 9.3.2.1; 'To prevent all 1 1 SRVs from opening simultaneously, open links

6B-10 in Panel 2H11-P927 and BB-10 in Panel 2H11-P928."

i E

Step 9.3.3; "At Panel 2H1 1 -P627, open links AA-1 9, AA-20, AA-21, and AA-22,

to prevent spurious actuation of SRVs 2B21-F013D AND 2B21-F013G."

Step 9.3.6; UOPEN link TB9-21 in Panel 2H11-P700 to open Drywell Pneumatic

System Inboard Inlet Isolation, 2P70-F005."

0

Step 9.3.7; "OPEN link TB1-12 in Panel 2H11-P700 to open Drywell Pneumatic

System Outboard Inlet Isolation, 2P70-F005."

e

lStep 9.3.9.1; "Confirm OR manually CLOSE RHR Shutdown Cooling Valve

2E1 1 -F006D."

Step 9.3.9.2; "Manually OPEN Shutdown Cooling Suction Valve 2E11-F008, IF

required..."

The team verified that flashlights were readily available and judged that operators would

le to use the flashlights and accomplish the actions, with two exceptions. One

exce ion was the action to open terminal board links in two panels to prevent all eleven

SRVs rom spuriously opening, which was judged to be untimely (see Section

1 R05.t 5.b.1). The other exception was the action to open 2E11 -F015A, which was

judged to be too difficult (see Section 1 R05.P5.b.2). For all of these actions, the lack of

adequate emergency lighting could make yre actions more difficult to complete In a

timely manner and increase the cha

operator error.

Analysis: This finding is greater than minor because it affected the reliability objective

and the equipment performance attribute of the mitigating systems cornerstone. Since

operators would be able to accomplish the actions with the use of flashlights, this finding

did not impact the effectiveness of one or more of the defense in depth elements.

Hence, this finding did not have potential safety significance greater than very low safety

significance (Green).

The lead inspector presented the inspectio results to license management and othe

members of the licensee's staff at the co

lusion of the onsit inspection on Aprif.A,

Fee. Subsequent to the onsite inspec

n, the lead inspect r and Rag'-n.

management held follow up exits by t ephone with Mr

e and other members of

licensee management oncune 20anJune 3.

o update the licensee on

changes to the preliminary inspection findings. The icensee acknowledged the findings.

eam

~ked

lice e

her

of

m

lal

a

dd

he

21

4.

OTHER ACTIVITIES

40A2 Identification and Resolution of Problems

a.

Inspection Scope

The team reviewed a sample of licensee audits, self-assessments, and condition reports

(CRs) to verify that items related to fire protection and to SSD were appropriately

entered into the licensee's CAP in accordance with the Hatch quality assurance program

and procedural requirements. The items selected were reviewed for classification and

appropriateness of the corrective actions taken or initiated to resolve the issues. In

addition, the team reviewed the licensee's applicability evaluations and corrective

actions for selected industry experience Issues related to fire protection. The operating

experience (OE) reports were reviewed to verify that the licensee's review and actions

were appropriate.

The team reviewed licensee audits and self-assessments of fire protection and safe

shutdown to assess the types of findings that were generated and to verify that the

findings were appropriately entered into the licensee's corrective action program.

b.

Findings

No findings of significance were Identified.

40A6 Meetings. Including Exit

The team presented the inspection results to Mr. R. Dedrickson, Assistant General

Mana

d other members of your staff at the conclusion of the inspection on July

25,

03

licensee acknowledged the findings presented. Proprietary information is

not i clu

in the inspection report.

Id

I+41;

,*H61?

Ala-01

'117-vc-450.

Z,

-I

.

0/444

-5,

I

t

-4

K

ro-e-

I

15

Enforcement: 10 CFR 50, Appendix R, Section III.J. requires that emergency lighting

units with at least an 8-hour battery power supply shall be provided in all areas needed

for operation of safe shutdown equipment and in access and egress routes thereto.

Contrary to the above, emergencyjighting units were not adequately provided in all

areas needed for operation of safe shutdown equipment. In response this issue, the

licensee initiated CRs 2003008237 and 2003008179. Because the identified lack of

emergency lighting is of very loW safety significance and has been entered into the

licensee's corrective action r

ram, this violation is being/reated as an NCV,

consistent with Section VI.

of the NRC's EnforcementPolicy: NCV 50-366/03-06-05,

Inadequate Emergency Lighlg for Operation of Safe Slhutdown Equipment.

.08

Cold Shutdown Repairs

f

e

The licensee had identified no needed cold shutdown repairs. Also, with the exception

of the potential need for a cold shutdown repair to open valve 2E1 1 -F01 5A (see section

1 R05.05.b.2), the team identified no other need for cold shutdown repairs.

Consequently, this section of IP 71111.05 was not performed.

.09

Fire Barriers and Fire Area/Zone/Room Penetration Seals

a.

Inspection Scope

The team reviewed the selected fire areas to evaluate the adequacy of the fire

resistance of fire area barrier enclosure walls, ceilings, floors, fire barrier mechanical

and electrical penetration seals, fire doors, and fire dampers. The team selected

several fire barrier features for detailed evaluation and inspection to verify proper

installation and qualification. This was accomplished by observing the material condition

and configuration of the installed fire barrier features, as well as construction details and

supporting fire endurance tests for the installed fire barrier features, to verify the as-built

configurations were qualified by appropriate fire endurance tests. The team also

reviewed the FHA to verify the fire loading used by the licensee to determine the fire

resistance rating of the fire barrier enclosures. The team also reviewed the installation

instructions for sliding fire doors, the design' details for mechanical and electrical

penetrations, the penetration seal database, Generic Letter (GL) 86-10 evaluations, and

the fire protection penetration seal deviation analysis for the technical basis of fire

barrier penetration seals to verify that the fire barrier installations met design

requirements and license commitments. In addition, the team reviewed completed

surveillance and maintenance procedures for selected fire barrier features to verify the

fire barriers were being adequately maintained.

The team evaluated the adequacy of the fire resistance of fire barrier electrical raceway

fire barrier system (ERFBS) enclosures for cable protection to satisfy the applicable

separation and design requirements of 10 CFR 50, Appendix R, Section III.G.2.

Specifically, the team examined the design drawings, construction details, installation

records, and supporting fire endurance tests for the ERFBS enclosures Installed in Fire

Area 2104, the Unit 2 East Cableway. Visual inspections of the enclosures were

performed to confirm that the ERFBS installations were consistent with the design

drawings and tested configurations.

16

The team reviewed abnormal operating fire procedures, selected fire fighting pre-plans,,

fire damper location and detail drawings, and heating ventilation and air conditioning .

\\

(HVAC) system drawings to verify that access to shutdown equipment and selected

operator manual actions would not be inhibited by smoke migration from one area to.

adjacent plant areas used to accomplish SSD.

b.

Findings

No findings of significance were identified.

.10

Fire Protection Systems. Features, and EquiDment

a.

Inspection ScoDe

The team reviewed flow diagrams, cable routing information, and operational valve.

lineup procedures associated with the fire pumps and fire protection water supply

system. The review evaluated whether the common fire protection water delivery and

supply components could be damaged or Inhibited by fire-induced failures of electrical

power supplies or control circuits. Using operating and test procedures, the team toured

the fire pump house and diesel driven fire pump fuel storage tanks to observe the

system material condition, consistency of as-built configurations with engineering

drawings, and determine correct system controls and valve lineups. Additionally, the

team reviewed periodic test procedures for the fire pumps to assess whether the

surveillance test program was sufficient to verify proper operation of the fire protection

water supply system in accordance with the program operating requirements specified

in Appendix B of the FHA.

The team reviewed the adequacy of the fire detection systems in the selected plant fire

areas in accordance with the design requirements in Appendix R, III.G.1 and Mll.G. 2.

The team walked down accessible portions of the fire detection systems in the selected

fire areas to evaluate the engineering design and operation of the installed

configurations. The team also reviewed engineering drawings for fire detector types,

spacing, locations and the licensee's technical evaluation of the detector locations for

the detection systems for consistency with the licensee's FHA, engineering evaluations

for NFPA code deviations, and NFPA 72E. In addition, the team reviewed surveillance

procedures and the detection system operating requirements specified in Appendix B of

the FHA to determine the adequacy of fire detection component testing and to ensure

that the detection systems could function when needed.

The team performed in-plant walk-downs of the Unit 2 East Cableway automatic wet

pipe sprinkler suppression system to verify the proper type, placement and spacing of

the sprinkler heads as well as the lack of obstructions for effective functioning. The.

team examined vendor information, engineering evaluations for NFPA code deviations,

and design calculations to verify that the required suppression system water density for

the protected area was available. Additionally, the team reviewed the physical

configuration of electrical raceways and safe shutdown components in the fire area to

determine whether water from a pipe rupture, actuation of the automatic suppression

system, or manual fire suppression activities in this area could cause damage that could

inhibit the plant's ability to safely shutdown.

,1

17

The team reviewed the adequacy of the design and installation of the manual C02 hose

reel suppression system for the diesel generator building switchgear rooms 2E and 2F

(Fire Areas 2404 and 2408). The team performed in-plant walk-downs of the diesel

generator building C02 fire suppression system to determine correct system controls

and valve lineups to assure accessibility and functionality of the system, as well as

associated ventilation system fire dampers. The team also reviewed the licensee's

actions to address the potential for C02 migration to ensure that fire suppression and

post-fire safe shutdown actions would not be impacted. This was accomplished by the

review of engineering drawings, schematics, flow diagrams, and evaluations associated

with the diesel generator building floor drain system to determine whether systems and

operator actions required for SSD would be inhibited by C02 migration through the floor

drain system.

b.

Findings

No findings of significance were Identified.

.11

Comnensatorv Measures

a.

Inspection Scope

The team reviewed Appendix B of the FHA and applicable sections of the fire protection

program administrative procedure regarding administrative controls to identify the need

for and to implement compensatory measures for out-of-service, degraded, or

inoperable fire protection or post-fire safe shutdown equipment, features, and

tS.

The team reviewed licensee reports for the fire protection status of Unit 1, U

of

shared structures, systems, and components. The review was performed to

at

the risk associated with removing fire protection and/or post-fire systems or

components, was properly assessed and implemented in accordance with the approved

fire protection program. The team also reviewed Corrective Action Program Condition

Reports generated over the last 18 months for fire protection features that were out of

service for long periods of time. The review was conducted to assess the licensee's

effectiveness in returning equipment to service in a reasonable period of time.

1j~R21

Findings

No findings of significance were identified.

Design Chanae Request (DCR)91-134. SRV Backup Actuation Usiln Pressure

Transmitter Signals

a.

Inspection Scope

,

The team performed an independent design review of plant modification D

-134

in

order to evaluate the technical adequacy of the design change packag

.he

s

e of

the review and circuit analysis performed by the team was limited to e*opA

RVs

.1

a}

I

18

for which the licensee takes credit In mitigating a fire in the fire areas selected for the

inspection.

b.

Findings

.1.

Introductij

An inadeq

plant modification, DCR 91-134, failed to implement the design input

requirements of one-out-of-two taken twice logic for the SRVs backup actuation using

pressure transmitter signals.

Descrintion^.

DCR 91-134 was implemented in response in to concerns raised in General Electric

Report NEDC-3200P, Evaluation of SRV Performance during January-February 1991

Turbine Trip Events for Plant Hatch Units 1 and 2. In order to ensure that Individual

SRV(s) will actuate at or near the appropriate set point and within allowable limits, a

backup mode of operation for the SRVs was implemented by this DCR. The design

was intended to mitigate the effects of corrosion-induced set point drift of the Target

Rock SRVs.

Automatically controlled, two stage SRVs are installed on the main steam lines Inside

containment for the purpose of relieving nuclear boiler pressure either by normal

mechanical action or by automatic action of an electro-pneumatic control system.! Each

SRV can be manually controlled by use of a two position switch located in the main

control room. When placed in the 'Open" position, the switch energizes the pilot valve

of the individual SRV and causes It to go open. When the switch is placed In the "Auto"

position the SRV is opened upon receipt of either an Auto Depressurization System

(ADS), or Low-Low Set (LLS) control logic signal. Either signal will initiate opening of

the valve. DCR 91-134 provided a backup mode for initiation of electrical trip of the pilot

valve solenoid, which was independent of ADS or LLS logic. The backup mode required

no operator action to initiate opening of the SRVs and was considered a "blind control

loop" to the operators, ie. there are no Instruments that provide the operators

information concerning the open/close status of the SRVs.

The scope of the plant modification involved the installation of four Rosemount pressure

transmitters (Model No. 11 54GP9RJ), 0-3000 psig, in the 2H21 -P404 and P405

instrument racks at Elevation 158 of the reactor building. Each pressure transmitter

formed part of a 4-20 ma current loop and provided the analog trip signal for SRV

actuation within the following set point groups:

SRV Group

SRV Identification Taas

SRV Set Point

A

2B21-F013B, D, F, and G

1120 psig

B

2B21 -F01 3A, C, K, and M

1130 psig

C

2B21-F013E, H, and D

1 140 psig

--1

19

Pressure transmitters (PTs) 2B21-N127A and 2B21-N127C were wired to ATTS

cabinets 2H11-P927. Pressure transmitter 2B21-N127A instrument loop components

consisted of a trip unit master relay K308C and trip unit slave relays K321 C and K332C.

The loop components for pressure transmitter 2B21 -N127C consisted of a trip unit

master relay K335C in addition to trip unit slave relays K336C and K363C. These two

instrument loops constituted a uDivisionn pressure monitoring channels and were

intended to provide the one-out of two logic signal from this Division for initiating SRV

backup actuation.

Additionally, pressure transmitters 2B21-N127B and 2B21-N127D were wired to ATTS

cabinet 2H11-P928. Pressure transmitter 2B21-N127B instrument loop components

consisted of a trip unit master relay K31 OD and trip unit slave relays KK312D and

K332D. The loop components for pressure transmitter 2B21-N127D consisted of a trip

unit master relay K335D in addition to trip unit slave relays K336D and K363D. These

two instrument loops constituted a separate "Division" pressure monitoring channels and

were intended to provide the one-out of two logic signal from this Division for initiating

SRV backup actuation. The design objective of having two instrument channels was to

assure compliance with HNP-2-FSAR, Section 15.1.6.1, Application of Single Failure

Criteria. This criteria requires for anticipated operational occurrences (AOOs) that the

protection sequences within mitigation systems be single component failure proof. A

failure of one instrument channel in a division will therefore not eliminate the protection

provided by either of the instrument channels.

The following table identifies the Division, pressure transmitter loops and the associated

trip unit master and slave relays:

Division

A

PT Loops

Trip Unit Master Relays

Trip Unit Slave Relays

K321 C and K332C

K336C and K363C

2B21 -N127A

2B21 -N127C

K308C

K335C

B

2B21-N127B

K31OD

K312D and K332D

/B21-N127D

K335D

K336D and K363D

The Group 7SRVsere provided logic input signals from the trip unit master relays.

The Groupp and eSRVs were provided logic input signals from the trip unit slave

relays. The otal of 12 relays described above, (6 in ATTS cabinet 2H1 1-P927 and 6 in

ATTS cabinet 2H1 1 -P928), were intended to be wired to provide "one-out-of-two taken

twice logic" for actuation of the SRVs. The design objective was to assure that a single

relay failure in either division would not cause an inadvertent SRV actuation. Coincident

logic input is required from both division instrument loops in order to initiate a SRV

backup actuation using the pressure transmitter signals. This occurs when the circuit

that is used to energize the individual SRV pilot valve to open the SRV, is enabled by

receiving simultaneous logic inputs from either instrument loop in both division.

The team performed a circuit analysis of SRV 2B21 -FO1 3F (Path 1) and SRV 2B21 -

FOI3G (Path 2) in order to verify that the design objectives of implementing a one-out-

of-two taken twice logic had been achieved. Based on this review the team determined

that the design objective of implementing a one-out-of-two taken twice logic had not

20

been installed for the SRVs. The logic installed for the SRVs was a two-out-of-two

coincident taken twice logic in addition to a one-out-of-two coincident taken twice logic.

The coincident logic implemented using trip unit master relays K31OD and K335D could:

result in spurious actuation of group "A" SRVs for a fire in Fire Area 2104. In addition,

this spurious actuation defeats the capability to manually control these SRVs.

Whenever a SRV lifts, it will remain open until nuclear boiler pressure is reduced to

about 85% of its overpressure lift setpoint However, because the instrument loops

have failed high, the trip unit master relays and the trip unit slave relays will continue to

energize the pilot valve of the individual SRV and keep the SRV open. As a result, this

failure mode prevents the operators from manually controlling the group A SRVs as is

required per the SSAR.

Analysis: This finding is greater than minor because it affected the availability and

reliability objectives and the equipment performance attribute of the mitigating system

comerstone. The team determined that the finding had potential safety significance

greater than very low safety significance because it prevented the operators from

manually controlling group A SRVs which the licensee credits with mitigating a fire in

Fire Area 2104. Manual control of the group A SRVs is required to ensure that the

suppression pool temperature will not exceed the HCTL for the suppression pool.

Failure to ensure that the suppression pool temperature will not exceed the HCTL could,

result in loss of net positive suction head for the Core Spray pumps which the licensee

credits for mitigating this event. However, the finding remains unresolved pending

completion

nificance determination.

Enforcemrn10

FR 50, Appendix B, Criterion Ill, requires that design control

measure

all pr ide for verifying or checking the adequacy of design.

DCR 91-132 pified design input requirements for the sensor initiated logic that

electrically activates the SRVs to be a one-out-of-two logic scheme. It also identified the

potential worst case failure mode of this logic modification as a short in the logic which

would results in an inadvertent opening of a SRV. It concluded that the modification is

designed so that the actuation logic will not fail to cause inadvertent opening of a SRV

nor prevent a SRV from lifting upon ADS/LLS activation. Contrary to the above the logic

implemented by the licensee for DCR 91-134 was different from the specified design

input requirements. The independent design verification performed for DCR 91-134

failed to identify this error in the logic scheme. Additionally, the Appendix R Impact

Review performed for DCR 91-134 failed to identify the potential failure mode of all

eleven SRVs because of fire induce dam

in Fire Area 2104.

The plant modification install

CR 91-134 failed to correctly implement the one-

out-of-two taken twice Ic

hat was specified in the SRV backup actuation via pressure

transmitter signals desn change package. This failure has created a condition where

fire induced failures f two instrument circuit cables, (within close proximity to each'

other), could result in spurious actuation of all eleven SRVs with the eleven SRVs

assuming a stuck open mode of operation, based on the logic input from trip unit master

unit relays K31 OD, and K335D and their associated trip unit slave relays. Pending

completion of an significance determination by the NRC, this item is identified as URI

50-366/03-06-06 ;Implementation of DCR 91-134.Refults inAur,

Artutisn of

-5 AS

!,

I. . .

..

.!~

,

. I

.

.

.

.

+b.

4

SUPPLEMENTAL INFORMATION

KEY POINTS OF CONTACT

Licensee personnel:

M. Beard, Acting Engineering Support Supervisor

V. Coleman, Quality Assurance Supervisor

M. Dean, Nuclear Specialist, Fire Protection

R. Dedrickson, Assistant General Manager for Plant hatch

B. Duval, Chemistry Superintendent

M. Googe, Maintenance Manager

J. Hammonds, Operations Manager

D. Javorka, Administrative Assistant, Senior

R. King, Acting Engineering Support Manager

1. Luker, Senior Engineer, Licensing

T. Metzer, Acting Nuclear safety and Compliance Manager

A. Owens, Senior Engineer, Fire Protection

D. Parker, Senior Engineer, Electrical

J. Payne, Senior Engineer, Corrective Action Program

J. Rathod, Bechtel Engineering Group Supervisor

M. Raybon, Summer Intern

K. Rosanski, Oglethorpe Power Corporation Resident Manager

J. Vance, Senior Engineer, Mechanical & Civil

R. Varnadore, Outages and Modifications Manager

NRC personnel:

N. Garret, Senior Resident Inspector

C. Payne, Fire Protection Team Leader

LIST OF ITEMS OP

ODened

50-366/03-06-0

URI

Concern~s

), AND I

Potentie

)ISCUSSED

il Opening of SRVs (Section

URI

URI

Opened and Closed

50-366/03-06-03

NCV

v,

Lo

V

<4q

50-366/03-06-04

50-366/03-06-05

Discussed

NCV

Unapprove Manual Operator Actions for Post-Fire Safe

Shutdown (Section 1 R05.O5.g3b

NCV

Inadequate Emergency ighting for Operation of Post-Fire Safe

Shutdown Equipment (Section 1 R05.07.b)

None

76-3iCo3-Ob

QLo

-4-

!

Attachment

3

LIST OF DOCUMENTS REVIEWED

Procedures

Administrative Procedure 40AC-ENG-008-OS, Fire Protection Program, Rev. 9.2

Administrative Procedure 42FP-FPX-018-OS, Use, Controf, and Storage of

Flammable/Combustible Materials, Rev. 1.0

Department Instruction DI-FPX-02-0693N, Fire Fighting Equipment Inspection, Rev. 5

Fire Protection Procedure 42FP-FPX-005-OS, Drill Planning, Critiques and Drill Documentation

Rev. 1 ED-

Fire Protection Procedure 42FP-FPX-007-OS, Hot Work, Rev. 1.2

Preventive Maintenance Procedure 52PM-MEL-01 2-0, Low Voltage Switchgear Preventive

Maintenance, Rev. 25.0

Preventive Maintenance Procedure 52PM-MEL-01 4-0, Transformer Maintenance, Rev. 1 0.1

Surveillance Procedure 42SV-FPX-002-OS, Low Pressure 002 System Surveillance, Rev. 7.1

Surveillance Procedure 42S;V-FPX-004-OSFire Pump Test, Rev. 8.6

Surveillance Procedure 42sV-FPX-006-OS, Fire Damper Surveillance, Rev. 1 ED 1

Surveillance Procedure 42SV-FPX-021 -OS, Surveillance of Swinging Fire Doors, Rev. 1.6

Surveillance Procedure 42SV-FPX-024-OS, Fire Hose Stations 31 Day Surveillance, Rev.

9

Surveillance Procedure 42SV-FPX-030-OS, Fire Emergency Self Contained Breathing

Apparatus Inspection and Test, Rev. 1

Surveillance Procedure 42SV-FPX-032-OS, Automatic Sliding Fire Door Visual Inspection,

Rev. 3.3

Surveillance Procedure 42SV-FPX-036-OS, Annual Fire Pump Capacity Test, Rev. 8.6

Surveillance Procedurre425V-FPX-037-MS, Fire

on Itmtation Sreveince,

Rev. 5.1

system Operating Procedure 3450-X43-001 -1, Fire Pumps Operating Procedure, Rev. 4.3

Training Procedure 73TR-TRN-003-OS, Fire Training Program, Rev.4

AOP 34AB-Ce

1-001P-2, Loss of CRD System, Version 2.3

AOP 34AB-C71-001-2, Scram Procedure, Version 9.9

AOP 34AB-C71-002-2, Loss of RPS, Version 4.3

AOP 34AB-N61-002-2S, Main Condenser Vacuum Low, Version 0.4

ASP 34AB-P41-001-2, Loss of Plant Service Water, Version 8.1

AOP 4AB-P42-001 -2S, Loss of Reactor Building Closed Cooling Water, Version 1.4

AOP 34AB-P51-001-2, Loss of Instrument and Service Air System or Water Intrusion into the

Service Air System, Version 3.0

AOP 34AB-R22-001 -2, Loss of DC Busses, Version 2.4

AOP 34AB-R22-002-2, Loss of 41 60V Emergency Bus, Version 1.4

AOP 34AB-R22-003-2, Station Blackout, Version 2.3

AOP 34AB-R22-004-02, Loss of 41 60V Bus 2A, 2B, 20, or 2D, Version 1.3

AOP 34AB-R23-001-2S, Loss of 600V Emergency Bus, Version 0.4

AOP 34AB-R24-001-2, Loss of Essential AC Distribution Buses, Version 1.3

AOP 34AB-R25-002-02, Loss of Instrument Buses, Version 5.4

AOP 34AB-T47-001-2, Complete Loss of Drywell Cooling, Version 1.8

AOP 34AB-X43-001-2, Fire Procedure, Version 10.8

AOP 34AB-X43-002-0, Fire Protection SystemoFailures, Version 1.3

SOP 34S0-C71-001-2, 1L2oVAC RPS Supply System, Version 10.2

Attachment

-4

SOP 34SO-N40-001 -2, Main Generator Operation, Version 10.8

SOP 34SO-R42-001-2S, 125V DC and 125/250 VDC System, Version 7.1

SOP 34SO-S22-001-2, 500 KV Substation Switching, Version 5.2

31 EO-EOP-01 0-2S, RC RPV Control (Non-ATWS), Rev. 8, Attachment 1

31 EO-EOP-012-2S, PC-1 Primary Containment Control, Rev. 4, Attachment 1

31 EO-EOP-01 3-2S, PC-2 Primary Containment Control, Rev. 4, Attachment I

31 EO-EOP-01 4-2S, SC - Secondary Containment Control, Rev. 6, Attachment 1

31 EO-EOP-01 6-2S, CP-2 RPV Flooding, Rev. 8, Attachment 1

Procedure 34AB-X43-001-2S, Rev.1 OED3, "Fire Procedure," dated 5/28/03.

Calibration Procedure 57CP-CAL-097-2, Rosemount 1153 and 1154 transmitters, Revision,

No. 19.9.

Drawings

H-1 1814, Fire Hazards Analysis, Control Bldg. El. 1 30'-0", Rev. 5

H-1 1821, Fire Hazards Analysis, Turbine Bldg. El. 130'-O", Rev. 0

H-1 1846, Fire Hazards Analysis, Diesel Generator Bldg., Rev. 2

H-26014, R.H.R. System P&ID Sheet 1, Rev. 49

H-26015, R.H.R. System P&ID Sheet 2, Rev. 46

H-26018, Core Spray System P&ID, Rev. 29

B-1 0-1326, Rectangular Fire Damper Schedule, Rev. 2

B-1 0-1329, Rectangular Fire Damper, Rev. 1

H-1 1033, Fire Protection Pump House Layout, Rev. 47

H-1 1035, Fire Protection Piping and Instrumentation Diagram, Rev. 22

H-1i1226, Piping-Diesel Generator Building Drainage, Rev. 6

H-1 1814, Fire Hazards Analysis Drawing, Control Building, Rev. 5

H-1 1821, Fire Hazards Analysis Drawing, Turbine Building, Rev. 11

H-1 1846, Fire Hazards Analysis Drawing, Diesel Generator Building, Rev. 2

H-1 1894, Fire Detection Equipment Layout-Diesel Generator Building, Rev. 2

H-1 1915, Fire Detection Equipment Layout-Control Building, Rev. 2

H-1 3008, Conduit and Grounding, Fire Pump House, Rev. 9

H-13615, Wiring Diagram, Fire Pump House, Rev. 13

H-1 6054, Control Building HVAC System, Rev. 19

H-41509, Diesel Generator Building CO2 System-P&ID, Rev. 5

H-43757, Penetration Seals-Type, Number, and as-Built Location, Rev. 3

Calculations. Analyses, and Evaluations

E. I. Hatch Nuclear Plant Units 1 and 2 Safe Shutdown Analysis Report, Rev. 20.

Edwin I. Hatch Nuclear Plant Fire Hazards Analysis and Fire Protection Program, Rev. 20

Calculation SMFP88-001, Hydraulic Analysis of Sprinkler Systems in Control Building East

Cableway, dated 03/11/1988

Calculation SMNH94-046, FCF-F1OB-006, Fire Resistance of Concrete Block at HNP, dated

09/30/1994

Calculation SMNH94-048, FCF-FlOB-006, Cable Tray Combustible Loading Calculation, dated

09/30/1994

Attachment

fr

5

i,

- '

Calculation SMNH98-023, HT-98617, Fire Protection Penetration Seal Deviation Analysis,

dated 10/28/1998

Calculation SMNHOO-01 1, HT-00606, Hose Nozzle Pressure Drop Analysis, dated 09/08/2000

Evaluation HT-91722, Fire Protection Code Deviation Resolution, dated 04/22/1992

Hatch Response to NRC IN 1999-005, dated 05/04/1999

Hatch Response to NRC IN 2002-024, dated 09/20/2002

Calculation SENH 98-003, Rev. 0, plot K, protective relay settings 4kV bus 2E

Calculation 85082MP, Plot 29, 600V Switchgear 2C

Calculation SENH 94-004, Attachment A, Sheets 7&8, 600/208 Reactor Building MCC 2C

Calculation SENH 91-011, Attachment P, Sheet 6, Reactor Building DC MCC 2A

Calculation SENH 94-013, Sheets 28 and 29, 600V Reactor Building MCC 2E-B

Calculation SENH 91 -011, Attachment P, Sheet 16, Reactor Building 25OVDC MCC 2B

Audits and Self-Assessments

Audit No. 01-FP-1, Audit of the Fire Protection Program, dated April 12, 2001

Audit No. 02-FP-1, Audit of the Fire Protection Program, dated February 28, 2002

Audit No. 03-FP-1, Audit of Fire Protection, dated April 21, 2003

1999-001106, Lighting In Fire Equipment Building

2002-000629, Inordinate Number of Buried Piping Leaks

2002-002127, Inadequate Bunker Gear

2002-002129, Health Physics Support and Participation for Fire Brigade

2003-000735, Impact on Cold Weather on Operating Units

'Audit Report 01 -FP-1, Audit of Fire Protection Program, dated 04/12/2001

Audit Report 02-FP-1, Audit of Fire Protection Program, dated 02/28/2002

Audit Report 03-FP-1, Audit of Fire Protection Program, dated 04/21/2003

CRs Reviewed

CR 2000007119, Fire Procedure 34AB-X43-001 -1 S Needs to be Enhanced

CR 2001002032, Fire Procedure 34AB-X43-001 -2S Needs Actions for Diesel Fuel Oil Pumps

CR 2003004377, Fire Procedure 34AB-X43-001 -1 Enhahcements

CR 2003004379, Fire Procedure 34AB-X43-001-2 Enhancements

CR 2003004382, SSAR Discrepancies

CRs Generated During this Inspection

CR 2003007129, No Fire Procedure Actions for a Fire in the 2C Switchgear Room

CR 2003007719, Use of Link Wrench

CR 2003007978, Fire Damper Corrective Action

CR 2003008141, Breaker Maintenance Handle

CR 2003008165, SSAR Section 2.100

CR 2003008179, Drywell Access Emergency Lights

CR 2003008181, Link Labeling

CR 2003008202, Manually Opening MOV 2E1 1 -F01 SA

CR 2003008203, SRV Manual Action Steps In Fire Procedure

CR 2003008237, Emergency Lights and Component Labeling for Manual Actions

Attachment

6

CR 2003008238, C02 Migration Through Floor Drains

CR 2003800132, SSAR Error for Position of 2E1 1 -F004A

CR 2003800151, Instruments for Manual Actions'

CR 2003800152, Sliding Links in SSAR

CR 2003800153, Promat Test Report

CR 2003008250, Communications for Post-Fire SSD

CR 2003800166, Review Fire Procedure Step 34AB-X43-001-2 Steps to Verify Compliance

with Appendix R.

Design Criteria and Standards

Design Philosophy for Fire Detectors at E. l. Hatch Nuclear Plants, Rev. 2

Completed Surveillance Procedures and Test Records

42SV-FPX-021-OS, Surveillance of Swinging Fire Doors, Task # 1-3367-1 (completed on

01/09/2003)

42SV-FPX-024-OS, Fire Hose Stations, Task #1-3359-1 (completed on 06/27/2003)

42SV-FPX-030-OS, Fire Emergency Self Contained Breathing Apparatus Inspection and Test,

Task # 1-4200-3 (completed on 07/07/2003)

42SV-FPX-032-OS, Automatic Sliding Fire Door Surveillance, Task # 1-3361-2 (completed on

08/13/2002

Promatec Technologies Installation Inspection Report for Fire Area 2104, MWO 2-98-00881,

Record 09367-2289, dated 09/03/1998

Technical ManualsNendor Information

Dow Coming Fire Endurance Test on Penetration Seal Systems in Precast Concrete F Using

Silicone Elastomers, dated 10/28/1975

Dow Corning 561 Silicone Transformer Fluid Technical Manual,1 0-453-97, dated 1997

S-80393, Mesker Instructions for Installing d&H uPyromaticP Automatic Sliding Fire Door Closer

S-27874B, General Electric Instruction Book GEK-26501, Liquid-Filled Secondary Unit

Substation Transformers, Rev. 2

S-52429A, Bisco, Fire Rated Penetration Seal Qualification Data, dated 08/16/1990

S-52480, Factory Mutual, Fire Rated Penetration Seal Qualification Data-Chemtrol Design

FC-225, dated 08/31/1990

S-54875B, Promatec, Fire Barriers-Unit 2 East Cableway, Rev. 2

Omega Point Laboratories, SR90-005, Three Hour Wall Test, dated 06/06/1990

Promatec Technologies Inc., PSI-001, Issue 1, General Construction Details, dated 07/21/1998

Promatec Technologies Inc., IP-2031, Installation Inspection for Promat's Three Hour Solid

WalVCeiling Protection System, Issue C, dated 06/16/1998

System Information Document No. Sl-LP-01401-03, Main Steam and Low Low Set System,

dated 4/3/2000

Attachment

7

Applicable Codes and Standards

ANSI N45.2.11-1974, Quality Assurance Requirements for the Design of Nuclear Power Plants

NFPA 12, Standard for Carbon Dioxide Systems, 1973 Edition.

NFPA 13, Standard for the Installation of Sprinkler Systems, 1976 Edition.

NFPA 14, Standard for the Installation of Standpipe and Hose Systems, 1974 Edition.

NFPA 20, Standard for the Installation of Centrifugal Fire Pumps, 1973 Edition.

NFPA 72D, Standard for the Installation, Maintenance, and Use of Proprietary Protection

Signaling Systems, 1975 Edition.

NFPA 72E, Standard on Automatic Fire Detectors, 1974 Edition

NFPA 80, Standard on Fire Doors and Windows, 1975 Edition.

NUREG-1552, Supplement 1, Fire Barrier Penetration Seals in Nuclear Power Plants, dated

January 1999

OSHA Standard 29 CFR 1910, Occupational Safety and Health Standards,

Underwriters Laboratory, Fire Resistance Directory, January 1998

Other Documents

Design Change Package 91-009, Retrofill Dielectric Fluid on Unit 2 Transformers, Rev. 1

Fire Protection Inspection Reports for the period 2001-2002

Fire Service Qualification Training, FP-LP-1 0003, Fire Fighter Safety, dated 01/:14/2002

Fire Service Qualification Training, FP-LP-10004, Fire Fighter Personal Protective Equipment,-

dated 01/14/2002

Fire Service Qualification Training, FP-LP-1 001 4, Fire Streams, dated 01/22/2002

Fire Service Qualification Training, FP-LP-10018, Fire Fighting Principles and Practices, dated

01/22/2002

Hatch Response to NRC Information Notice 1999-05, Inadvertent Discharge of Carbon Dioxide

Fire Protection System and Gas Migration, dated 05/04/1999

Hatch Response to NRC Information Notice 2002-24, Potential Problems with Heat Collectors

on Fire Protection Sprinklers, dated 09/20/2002

1 OCFR21 -001, ELECTRAK Corporation, Software Error within TRAK2000 Cable Management

and Appendix R Analysis System, dated 03/07/2003

U. S. Consumer Product Safety Commission, Invensys Building Systems Announce Recall of

Siebe Actuators In Building Fire/Smoke Dampers, dated 10/02/2002

Pre-f ire Plan A-43965, Power-Block Areas Methodology, Rev. 0

Pre-fire Plan A-43966, Fire Area 2404, Diesel Generator Building Switchgear Room 2E, Rev. 2

Pre-fire Plan A-43966, Fire Area 2408, Diesel Generator Building Switchgear Room 2F, Rev. 2

Pre-fire Plan A-43965, Fire Area 2016, W 600V Switchgear Room 2C, Rev. 4

License Basis Documents

Hatch UFSAR Section 3.4, Water Level Flood Design, Rev. 20

Hatch UFSAR Section 9.1-A, Fire Protection Plan, Rev. 1 8C

Hatch UFSAR Section 17.2, Quality Assurance During the Operations Phase, Rev. 20B

Hatch Fire Hazards Analysis, Appendix B, Fire Protection Equipment Operating and

Surveillance Requirements, Rev. 12B

Attachment

8

Hatch Fire Hazards Analysis, Appendix H, Application of National Fire Protection Association

Codes, Rev. 1 2B

Hatch SER dated April 18, 1994

Safe Shutdown Analysis Report for E.I. Hatch Nuclear Plant Units 1 and 2, Rev. 26

Fire Hazards Analysis for E. A.

Hatch Nuclear Plant Units 1 and 2, Rev.1 BC, dated 7/00.

NRC Safety Evaluation Report dated 01/02/1987; Re: Exemption from the requirements of

Appendix R to 10 CFR Part 50 for Hatch Units 1 and 2 (response to letter dated

May.16,1986).

Letter dated 05/16/86, From L. T. Guewa (Georgia Power) to D. Muller, NRC/NRR; Re: Edwin I

Hatch Nuclear Plant Units 1 and 2 10 CFR 50.48 and Appendix R Exemption Requests

Design Chanae Request Documents

DCR No.91-134, SRV Backup Actuation via Pressure Transmitter Signals, Revision 0.

Drawing No. H-26000, Nuclear Boiler System P&ID, Sheet 1, Revision 39

Drawing No. H-27403, Automatic Depressurization System 2B21 C Elementary Diagram, Sheet

6 of 6, Revision 2

Drawing No. H-27472, Automatic Depressurization System 2B21 C Elementary Diagram, Sheet

3 of 6, Revision 2

Drawing No. H-27473, Automatic Depressurization System 2B21 C Elementary Diagram, Sheet

4 of 6, Revision 2

Drawing No. H-24427, Elementary Diagram, ATTS System 2A70 Sheet 27 of 35, Revision 3

Drawing No. H-24428, Elementary Diagram, ATTS System 2A70 Sheet 28 of 35, Revision 3

Drawing No. H-24429, Elementary Diagram, ATTS System 2A70 Sheet 29 of 35, Revision 5

Drawing No. H-24430, Elementary Diagram, ATTS System 2A70 Sheet 30 of 35, Revision 3

Drawing No. H-24431, Elementary Diagram, ATTS System 2A70 Sheet 31 of 35, Revision 3

Drawing No. H-24432, Elementary Diagram, ATTS System 2A70 Sheet 32 of 35, Revision 6

.

/

Attachment