NOP-LP-2001-09 Corrective Action Due Date Extension CR #:
02-00921 CA #:
6 Requested Due Date:
7/22/2003 Extension Number:
1 Category:
CF Reason for Extension:
This CA has been Included in a package of CA's to be completed by a consultant (Appendix R Solutions). The task authorization and purchase requisition are in process, so that the consultant is not authorized to start work yet.
Justification:
There Is no equipment operability issue associated with this Corrective action.
Requestor:
KAHL, H Requestor Date:
5/22/2003 Approver:
Manoleras, M for Cosgrove Approver Date:
5/22/2003 l
Accept l Reject Wednesday, June 18, 2003