Corrective Action of CR 02-00921, Due Date Extension
ML040340614
Person / Time
Site: Beaver Valley
Issue date: 05/23/2003
From: Wood W
FirstEnergy Nuclear Operating Co
To:
Office of Nuclear Reactor Regulation
References
FOIA/PA-2003-0358, NOP-LP-2001-09 CR 02-00921
Download: ML040340614 (1)


Text

NOP-LP-2001-09 Corrective Action Due Date Extension CR #:

02-00921 lCA #:

7 Requested Due Date:

9/30/2003 Extension Number:

1 Category:

CF Reason for Extension:

Westinghouse analysis will take 3 months from TA approval. A TA has not yet been approved.

Justification:

Plant continues to operate within its design bases. Also, similar analyses for Unit 1 yielded an allowable AFW delay time of 30 minutes for a fire that requires control room evacuation. Similar results are expected for Unit 2. Since the process of Initiating AFW for Unit 2 is less work Intensive than for Unit 1 (because of the dedicated AFW pump), actual operator response time Is expected to be well within 30 minutes.

Requestor:

WOOD, WT Requestor Date:

5/22/2003 Approver:

Manoleras, M Approver Date:

5/23/2003 l

Accept El Reject Wednesday, June 18, 2003