05000265/LER-2003-005

From kanterella
(Redirected from ML032671132)
Jump to navigation Jump to search
LER-2003-005, Nuclear www.exeloncorp.com Exelon Generation Company, LLC Quad Cities Nuclear Power Station
22710 206' Avenue North
Cordova, IL 61242-9740
September 15, 2003
SVP-03-103
U. S. Nuclear Regulatory Commission
ATTN: Document Control Desk
Washington, D.C. 20555
Quad Cities Nuclear Power Station, Unit 2
Facility Operating License No. DPR-30
NRC Docket No. 50-265
Subject: U Licensee Event Report 265/03-005, "Technical Specification Allowable Value
Exceeded for Main Steam Flow Switches due to Inadequate Drift Allowance
used in Setpoint Calculation"
Enclosed is Licensee Event Report (LER) 265/03-005, "Technical Specification Allowable
Value Exceeded for Main Steam Flow Switches due to Inadequate Drift Allowance used in
Setpoint Calculation,' for Quad Cities Nuclear Power Station, Unit 2.
This report is submitted in accordance with the requirements of the Code of Federal
Regulations, Title 10, Part 50.73(a)(2)(i)(B), which requires reporting of any operation or
condition which was prohibited by the plant's Technical Specifications.
Should you have any questions concerning this report, please contact Mr. W. J. Beck at
(309) 227-2800.
Respectfully,
T' othy J. Tulon
Site Vice President
Quad Cities Nuclear Power Station
cc: U Regional Administrator — NRC Region III
NRC Senior Resident Inspector — Quad Cities Nuclear Power Station
NRC FORM 366 U.S. NUCLEAR REGULATORY
(7-2001) COMMISSION
LICENSEE EVENT REPORT (LER)
APPROVED BY OMB NO. 3150-0104 EXPIRES 7-31-2004
Estimated burden per response to conWvith this mandatory information collection request 50
hours. Repo/led lessons learned are incorporated into the licensing process and fed back to
industry. Send comments regarding burden estimate to the Records Management Branch (T-6 E6),
US. Nuclear Regulatory Commission, Washington, DC 20555-0001, or by Internet e-mail to le nrc.gov, and to the Desk Officer, Was i Infonnation and Regulatory Affairs, NEC6-10202
150-0104), Offim of Management and Budget, Washington, DC 20503. If a means used b krpose
formation collection does not display a currently valid OMB control number, the NRC may not
conduct or sponsor, and a person is not required to respond to, the Information collection.
1 FAf ll ITV NAUF
Quad Cities Nuclear Power Station Unit 2
9 OflOKFT NI 111/IRFP
05000265
!I oar=
1 of 3
4. rum Technical Specification Allowable Value Exceeded for Main Steam Flow Switches due to Inadequate Drift
Allowance used in Setpoint Calculation
Event date:
Report date:
Reporting criterion: 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications
2652003005R00 - NRC Website

FACILITY NAME (1) DOCKET NUMBER (2) LER NUMBER (6

  • Pi (If more space Is required, use additional copies of NRC Form 366A)(17)

PLANT AND SYSTEM IDENTIFICATION

General Electric - Boiling Water Reactor, 2957 Megawatts Thermal Rated Core Power Energy Industry Identification System (EIIS) codes are identified in the text as [XX].

EVENT IDENTIFICATION

Technical Specification Allowable Value Exceeded for Main Steam Flow Switches due to Inadequate Drift Allowance used in Setpoint Calculation

A. CONDITION PRIOR TO EVENT

Unit: 2 � Event Date: July 17, 2003 � Event Time: 1059 hours0.0123 days <br />0.294 hours <br />0.00175 weeks <br />4.029495e-4 months <br /> Reactor Mode: 1 � Mode Name: Power Operation � Power Level: 085% Power Operation (1) - Mode switch in the RUN position with average reactor coolant temperature at any temperature.

B. DESCRIPTION OF EVENT

On July 17, 2003, at 1059 hours0.0123 days <br />0.294 hours <br />0.00175 weeks <br />4.029495e-4 months <br />, during performance of the Unit 2 Division II Main Steam Line High Flow Switch Calibration and Functional Test, two main steam [SB] flow instruments [FS] were determined to have as-found setpoints that exceeded the Technical Specification (TS) Allowable Value. The instruments were calibrated to be within the TS allowable range. A total of 16 switches, four per steam line, are installed on the Unit 2 main steam lines. The switches feed into the Primary Containment Isolation System [JM], with 'one out of two twice' logic.

C. CAUSE OF EVENT

The root cause of this event was the use of inadequate drift allowance in engineering setpoint calculations.

The main steam flow switches were installed in February 2002. Because the main steam flow switches were newly installed at the time the setpoint calculations were performed, there was no historical drift data available. Therefore, the Technical Specification allowable value was calculated using the applicable calibration uncertainty values provided by the manufacturer along with an assumed drift term in accordance with procedural guidance. Based on the historical data that is now available, the drift that has been experienced exceeds the values assumed.

D. SAFETY ANALYSIS

The safety significance of this event was minimal. Although the instruments were found to have setpoints outside the TS allowable values, the instruments would have provided the trip signal within the analytical values assumed in the accident analysis. Therefore, the safety function would have been met. This event is being FACILITY NAME (1) DOCKET NUMBER (2) LER NUMBER (6 (If more space is required, use additional copies of NRC Form 366A)(17) reported as operation prohibited by TS due to the fact that multiple instruments were found out of calibration during the same surveillance, providing sufficient evidence that the situation existed longer than allowed by TS.

E. CORRECTIVE ACTIONS

Immediate Actions

The main steam flow switches were recalibrated.

Corrective Actions to be Completed A drift analysis will be performed for the Unit 1 and Unit 2 main steam flow switches and current calibration frequencies will be evaluated. Additional actions will be taken as appropriate based on this evaluation.

The Unit 1 and Unit 2 Barton main steam flow switches will be replaced with differential pressure transmitters.

F. PREVIOUS OCCURRENCES

No instances of multiple main steam flow switches being outside of the Technical Specification Allowable Value were identified in the last two years. However, there was one instance (not reportable) of a single main steam flow switch on Unit 1 where the as-found setpoint exceeded the Technical Specification Allowable Value.

G. COMPONENT FAILURE DATA

The main steam flow switches are Barton Model 288A Differential Pressure Indicating Switches, with a setting range of 0 to 400 paid.