Comments on Draft Operating Test
ML032460737
Person / Time
Site: FitzPatrick Constellation icon.png
Issue date: 07/21/2003
From: Williams J
NRC/RGN-I/DRS/OSB
To: Berry P
Entergy Nuclear Northeast
Conte R
References
05-333/03-301
Download: ML032460737 (1)


Text

NRC Comments on DRAFT OPERATING TEST Scenarios must describe all rewired operator actions. Referring to procedures is not adequate. (ES 301 D.5.f) Required operator actions missing in the following scenarios:

Scenario # I SelecVwithdraw all 8 IRMs per OP-16E.9 Start second condensate pump per OP-3D.7 May adjust (CRD drive pressure) up to 400 psid per OP-25 Section E Scenario #2 Power ascent with recirc. Flow Perform actions of AOP-41/42 OP-2A Section G.3 and G.7 actions Select and fully insert all rods in the lst cram group Scenario #3 Start C SW pump and place B in standby per OP-42G.1 Perform AOP-5 actions Vent torus per OP-37 Shutdown EDG A&C Place B RHR in drywell spray observing caution for excessive pump amps Scenario #4 Shutdown per OP-65 Bypass B flow unit per ARP-09-5-2-25 and OP-I 6E.22 Reset half scram per ARP-09-5-1-4 Shutdown ByRFP per OP-2A Perform AOP-40 actions The JPMs do not give the performance criteria or sPecifv the task standard as required in ES Appendix C section B.3 JPM-Conduct Emergency Rod In Functional Test. Add step 2 W . Ensure applicant selects the correct rod sequence on selector switch that matches rod withdrawal sheets.

JPM-Reopen MSlVs with RPV Pressurized. Step 4- add SVB-1 to valve list JPM-SGT Initiation Verification (AH Path)-Step 7-add note to evaluator that applicant may complete all train Aactions before looking at train B. Step 8-evaluator may need to respond as CRS and order B train start after applicants report.

JPM Jet Pump ST-23C (Alt Path) Steps 7 and 12 use loop B data where applicable for criteria (loop A data used)