Letter Sequence Other |
|---|
|
|
MONTHYEARML0205706382002-03-28028 March 2002 Issuance of Amendment Revises the Test Frequency for the Containment Spray Nozzles from Once Per 10 Years to Following Activities That Could Result in Nozzle Blockage Project stage: Approval ML0208805052002-03-28028 March 2002 Tech. Spec. Page for Amendment No. 146, Revising the Test Frequency for the Containment Spray Nozzles from Once Per 10 Years to Following Activities That Could Result in Nozzle Blockage Project stage: Other ML0212105812002-04-19019 April 2002 Submittal of Proposed Alternative and Relief to the Requirements of 10CFR50.55a Concerning the Fourth Ten-Year Interval Inservice Testing Program Project stage: Request ML0212802222002-05-0707 May 2002 Licensing Actions Project stage: Other ML0213600712002-05-16016 May 2002 Request for Withholding Infornmation from Public Disclosure, Oyster Creek Nuclear Generating Station Project stage: Other ML0214003812002-05-16016 May 2002 Request for Withholding Information from Public Disclosure Project stage: Withholding Request Acceptance ML0213702202002-05-17017 May 2002 Request Conference Call Proposed Amendment Project stage: Other ML0213600022002-06-0404 June 2002 License Amendment, Revising the Technical Specifications to Be Consistent with Changes Made to 10 CFR 50.59, Changes, Tests, and Experiments Project stage: Other ML0213600052002-06-0404 June 2002 Biweekly Notice Memo, Notice of Issuance of Amendment 151. Amendment Revises Technical Specifications to Be Consistent with Changes Made to 10 CFR 50.59, Changes, Tests, & Experiments Project stage: Approval ML0216905712002-06-0404 June 2002 Tech Specs for Amendment No. 151 Revising the Tech Specs to Be Consistent with Changes Made to 10CFR 50.59, Changes, Tests and Experiments Project stage: Other ML0216301202002-06-10010 June 2002 Draft RAI on Your 04/26/02 Amendment Request Project stage: Draft RAI ML0220405862002-07-11011 July 2002 Response to Request for Additional Information - Technical Specification Change Request No. 308 General Electric Stability Analysis Methodology Project stage: Response to RAI ML0220501942002-07-23023 July 2002 Snubber Relief Request Project stage: Approval ML0219705332002-07-24024 July 2002 Request for Withholding Information from Public Disclosure, Oyster Creek Nuclear Generating Station Project stage: Withholding Request Acceptance ML0222607982002-08-0101 August 2002 Response to Request for Additional Information - Technical Specification Change Request No. 291, Safety Limit Minimum Critical Power Ratio Project stage: Response to RAI ML0221905092002-08-0505 August 2002 Conference Call Re. 04/26/02 Proposed Amend Project stage: Other ML0222609462002-08-20020 August 2002 Second Request for Additional Information Regarding Your April 26, 2002, Application for Amendment Project stage: RAI ML0223501682002-08-23023 August 2002 Site Visit to Address Issues Related to Amendment Application of April 26, 2002 Project stage: Other ML0224203602002-08-30030 August 2002 Withholding from Public, Response to Request for Additional Information - Technical Specification Change Request No. 291, Safety Limit Minimum Critical Power Ratio, MB5505 Project stage: RAI ML0226600972002-09-12012 September 2002 Response to Request for Additional Information - Technical Specification Change Request No. 308, General Electric Stability Analysis Methodology Project stage: Response to RAI ML0225600192002-09-18018 September 2002 Issuance of Amendment Licensed and Non-Licensed Operating Personnel Training Programs Project stage: Approval ML0226302742002-09-18018 September 2002 Oyster Creek,Tech Spec Pages/Amend 232 Project stage: Other ML0226005292002-09-24024 September 2002 License Amendment Revision to TSs Change Request - Clarification of Requirements for Licensed Operator Qualifications & Training Project stage: Approval ML0227005082002-09-24024 September 2002 Tech Spec Pages for Amendment No. 154, Revision to TSs Change Request - Clarification of Requirements for Licensed Operator Qualifications & Training Project stage: Approval ML0227005492002-09-26026 September 2002 Tech Spec Pages for Amendment 233 Cycle 19 Safety Limit Minimum Critical Power Ratio Project stage: Other ML0226805692002-09-26026 September 2002 Issuance of License Amendment Cycle 19 Safety Limit Minimum Critical Power Ratio Project stage: Approval ML0227505422002-10-0202 October 2002 Alternative Regarding Snubber Examination and Testing Project stage: Other ML0227505562002-10-0202 October 2002 Relief Request RP-04, Service Water Pump Suction Pressure Gages & RV-51, Containment Isolation Valve Position Indication Project stage: Approval ML0228300432002-10-0909 October 2002 Current TAC List Project stage: Other ML0229503812002-10-18018 October 2002 Technical Specification Amendment 235 - 2.3 Limiting Safety System Settings Pages 2.3-1, 2.3-2, 2.3-4, 2.3-5, 2.3-6, 3.1-1, 3.1-7, 3.10-2, 3.10-3, and 3.10-4 Project stage: Other ML0229103652002-10-18018 October 2002 Issuance of Amendment Use of Option II Solution for Reactor Instability Problem Project stage: Approval RS-03-034, Delegation of Authority of Amergen Energy Company, LLC (Amergen) Nuclear Power Plants2003-02-0606 February 2003 Delegation of Authority of Amergen Energy Company, LLC (Amergen) Nuclear Power Plants Project stage: Other 2002-07-23
[Table View] |
Text
From:
Peter Tam To:
INTernet:David.distel@exeloncorp.com; INTernet:george.rombold@exeloncorp.com; internet:paul.czaya@exelon.com Date:
5/7/02 11:49AM
Subject:
Oyster Creek Licensing Actions Paul, David:
We recently received several applications all with requested NRC completion dates bunched together, and allowing about 4-5 months of turnover:
Application Target date 4/30/02 exemption (proprietary) 9/02 4/26/02 relief re. snubbers 10/1/02 4/26/02 amendment re. coupled neutronic.. 9/30/02 4/19/02 relief re. service water pump... 10/1/02 From experience, these target dates could pose significant resource problems for NRC because (1) the durations are too short, and (2) they will form a bulge clogging work flow in the Division of Licensing Project Management. Please call me to discuss these target dates.
This e-mail does not formally request information, and does not formally convey an NRC staff position. The information is solely provided to prepare you for a conference call.
Peter S. Tam, Senior Project Manager Project Directorate I-1 Division of Licensing Project Management Office of Nuclear Reactor Regulation e-mail: pst@nrc.gov Tel.: 301-415-1451 CC:
Richard Laufer Mail Envelope Properties (3CD7F79D.501 : 10 : 20510)
Subject:
Oyster Creek Licensing Actions Creation Date:
5/7/02 11:49AM From:
Peter Tam Created By:
PST@nrc.gov Recipients Action Date & Time David Transferred 05/07/02 11:49AM distel (INTernet:David.distel@exeloncorp.
george Transferred 05/07/02 11:49AM
rombold (INTernet:george.rombold@exelonco paul Transferred 05/07/02 11:49AM czaya (internet:paul.czaya@exelon.com) nrc.gov owf4_po.OWFN_DO Delivered 05/07/02 11:49AM RJL CC (Richard Laufer)
Opened 05/07/02 07:34PM Post Office Delivered Route David INTernet:exeloncorp.
com george INTernet:exeloncorp.
com paul internet:exeloncorp.c om owf4_po.OWFN_DO 05/07/02 11:49AM nrc.gov Files Size Date & Time MESSAGE 2429 05/07/02 11:49AM Options Auto Delete:
No Expiration Date:
None Notify Recipients:
Yes Priority:
Standard Reply Requested:
No Return Notification:
None Concealed
Subject:
No Security:
Standard To Be Delivered:
Immediate Status Tracking:
Delivered & Opened