ML020090300

From kanterella
Jump to navigation Jump to search
Radiological Emergency Response Plan Implementing Procedures
ML020090300
Person / Time
Site: Kewaunee Dominion icon.png
Issue date: 10/22/2001
From: Webb T
Nuclear Management Co
To:
Document Control Desk, Office of Nuclear Security and Incident Response
References
-RFPFR, NRC-01-109
Download: ML020090300 (31)


Text

NRC-01-109 Kewaunee Nuclear Power Plant Point Beach Nuclear Plant N490, Highway 42 6610 Nuclear Road NMC Kewaunee, WI 54216-9511 920-388-2560 Two Rivers, Wl 54241 920-755-2321 Committed to Nuclear Excellence Kewaunee / Point Beach NucZear Operated by NucZear Management Company, LLC October 22, 2001 10 CFR 50, App. E U. S. Nuclear Regulatory Commission Attention: Document Control Desk Washington, D.C. 20555 Ladies/Gentlemen:

DOCKET 50-305 OPERATING LICENSE DPR-43 KEWAUNEE NUCLEAR POWER PLANT RADIOLOGICAL EMERGENCY RESPONSE PLAN IMPLEMENTING PROCEDURES Pursuant to 10 CFR 50 Appendix E, attached is the latest revisions to the Kewaunee Nuclear Power Plant Radiological Emergency Response Plan Implementing Procedures (EPIPs). These revised procedures supersede the previously submitted procedures.

Pursuant to 10 CFR 50.4, two additional copies of this letter and attachment are hereby submitted to the Regional Administrator, U. S. Nuclear Regulatory Commission, Region III, Lisle, Illinois. As required, one copy of this letter and attachment is also submitted to the Kewaunee Nuclear Power Plant NRC Senior Resident Inspector.

Sincerely, Thomas J. Webb Site Licensing Director SLC Attachment cc - US NRC Senior Resident Inspector, w/attach.

US NRC, Region III (2 copies), w/attach.

Electric Division, PSCW, w/o attach.

QA Vault, w/attach.

0

KEWAUNEE NUCLEAR POWER PLANT October 19, 2001 EMERGENCY PLAN IMPLEMENTING PROCEDURES TRANSMITTAL FORM RETURN TO DIANE FENCL - KNPP OUTSIDE AGENCY COPIES (1-20)

T. Webb - NRC Document Control Desk (1)* Bill Yarosz - Wisconsin Electric Power Co. (10)*

T. Webb - NRC Region III (2 & 3)* Craig Weiss - Wisconsin Power & Light (11)*

T. Webb - NRC Resident Inspector (4) (receives Appx. A phone numbers)*

T. Webb - State of Wisconsin (5)* Jim Holthaus - Nuclear Management Company (12)*

T. Webb - KNPP QA Vault w/NRC Letter (15)*

PERSONAL COPIES (21-40) These copies are for the personal use of the listed individuals for reference or emergency response.

J. Bennett (33) D. Mielke (35) H. Kocourek (13) K. Hoops (28)

D. Masarik (32) D. Seebart (24) B. Bartelme (34)

REFERENCE COPIES - CUSTODIAN (41-100) These copies are for general reference by anyone. They are distributed throughout the plant and corporate offices. The named individual is the responsible custodian for the procedures and shall insure they are properly maintained.

STF (86, 87, 88) LOREB - STF (62, 66, 67, 68, 70, 72, 73, 74)

L. Welch - Fuel Services (65) STF Library (43)

NO Library - KNPP (59) Resource Center (82, 89, 94, 131)

C. Sternitzky - ATF-2 (44) D. Schrank - Maintenance Off. (41)

D. Braun - ATF-3 (45) D. Krall - CR/SS Office (51, 56)

P. Ehlen - I&C Office (42) P&FS Adm - GB-D2 (Nuclear Library) (84)

M. Daron - Security Building (46) H. Kocourek - TSC (50)

P&FS Adm - GB D2-3 (EOF) (81) W. Galarneau - RAF (53)

H. Kocourek - OSF (52) W. Galarneau - SBF/EMT (54)

C. Hutter - ATF-1 (64) W. Galarneau - RPO (55)

WORKING COPIES (101-199) These copies of procedures are kept in the areas designated for use in response to an emergency. These are not complete sets, but contain only those procedures that are used to implement activities in the location where they are kept. Please dispose of any sections distributed that are not tabbed in the indicated copy.

6 W. Galarneau - RAF/RPO (106, 107) D. Krall - CR/Communicator (11 )(Partial Distribution)

W. Galarneau - SBF/ENV (108, 109) Simulator/Communicator (117)

W. Galarneau - SBFIEM Team (110, 111, lllA) J. Fletcher - Security (121)

W. Galarneau - Aurora Medical Center (118, 119) N. Deda - Security Building (120)

W. Flint - Cold Chem/HR Sample Room (113) S. VanderBloomen (125)

N. Deda - SBF/SEC (114) J. Stoeger (126)

Originals to KNPP QA Vault Please follow the directions when updating your EPIP Manual. WATCH FOR DELETIONS!!! These are controlled procedures and random checks may be made to ensure the manuals are kept up-to-date.

  • THIS IS NOT A CONTROLLED COPY. ITISA COPYFOR INFORMATION ONLY.

1

KEWAUNEE NUCLEAR POWER PLANT REVISION OF EMERGENCY PLAN IMPLEMENTING PROCEDURES October 19, 2001 Please follow the directions listed below. If you have any questions regarding changes made to the EPIPs, please contact Dave Seebart at ext. 8719. If you are a controlled copy holder (see cover page), return this page to Diane Fencl by November 19, 2001, SIGNED AND DATED to serve as a record of revision.

EPIP Index, dated 10-19-2001.

REMOVE INSERT PROCEDURE REV. PROCEDURE REV.

EPIP-SEC-03 AA EPIP-SEC-03 AB EPIP-TSC-07 H EPIP-TSC-07 I EPIP-APPX-A-02 BK EPIP-APPX-A-02 BL I CERTIFY Copy No.___ (WPSC No.) of the Kewaunee Nuclear Power Plant's EPIPs has been updated.

SIGNATURE DATE Please return this sheet to DIANE FENCL.

Diane Fencl Enclosure 2

EMERGENCY PLAN IMPLEMENTING PROCEDURES INDEX DATE: 10-19-2001 PROC. NO. TITLE REV. DATE EP-AD EPIP-AD-01 Personnel Response to the Plant Emergency H 09-10-2001 Siren EPIP-AD-02 Emergency Class Determination AB 09-18-2001 EPIP-AD-03 KNPP Response to an Unusual Event AB 03-20-2001 EPIP-AD-04 KNPP Response to Alert or Higher AD 10-09-2001 EP-AD-5 Site Emergency Deleted 04-27-87 EPIP-AD-05 Emergency Response Organization Shift Relief C 06-05-2001 Guideline EP-AD-6 General Emergency Deleted 04-24-87 EPIP-AD-07 Initial Emergency Notifications AM 01-30-2001 EP-AD-8 Notification of Alert or Higher Deleted 02-26-96 EP-AD-9 Notification of Site Emergency Deleted 04-27-87 EP-AD-10 Notification of General Emergency Deleted 04-27-87 EPIP-AD- 11 Emergency Radiation Controls Q 09-27-2001 EP-AD-12 Personnel Assembly and Accountability Deleted 03-26-94 EP-AD- 13 Personnel Evacuation Deleted 04-25-94 EP-AD-13A Limited Area Evacuation Deleted 03-01-83 EP-AD- 13B Emergency Assembly/Evacuation Deleted 03-01-83 EP-AD-13C Site Evacuation Deleted 03-01-83 EP-AD-14 Search and Rescue Deleted 05-25-94 EPIP-AD-15 Recovery Planning and Termination N 08-29-2000 EP-AD-16 Occupational Injuries or Vehicle Accidents Deleted 03-14-97 During Emergencies EP-AD-17 Communications Deleted 03-05-84 EPIP-AD-18 Potassium Iodide Distribution 0 06-05-2001 EPIP-AD-19 Protective Action Guidelines P 10-31-2000 PAGE 1 OF 11

EMERGENCY PLAN IMPLEMENTING PROCEDURES INDEX DATE: 10-19-2001 PROC. NO. TITLE REV. DATE EP-ENV EPIP-ENV-01 Environmental Monitoring Group Organization V 10-02-2001 and Responsibilities EPIP-ENV-02 Environmental Monitoring Team Activation X 10-02-2001 EP-ENV-3A Environmental Protection Director Actions and Deleted 09-26-84 Directives EP-ENV-3B EM Team Actions Deleted 09-26-84 Dose Projection Using RASCAL Version 2.2 V 10-09-2001 EPIP-ENV-03C Software Revision and Control of ISODOSE II Deleted 02-14-95 EP-ENV-3D Manual Determination of X/Q Deleted 04-24-87 EP-ENV-3E EP-ENV-3F Manual Determination of X/Q (Green Bay Deleted 05-30-86 Meteorological Data)

EP-ENV-3G Manual Dose Projection Calculation Deleted 06-02-89 EP-ENV-3H Protective Action Recommendations Deleted 04-13-90 Portable Survey Instrument Use S 06-15-2000 EPIP-ENV-04A Air Sampling and Analysis W 10-09-2001 EPIP-ENV-04B Environmental Monitoring Teams Deleted 04-13-90 EP-ENV-4C Ground Deposition Sampling and Analysis W 10-09-2001 EPIP-ENV-04C EPIP-ENV-04D Plume Tracking for Environmental Monitoring N 10-02-2001 Teams LCS-1 Operation Deleted 04-14-86 EP-ENV-5A EP-ENV-5B MS-3 Operation Deleted 04-14-86 EP-ENV-5C SAM II Operation Deleted 04-14-86 EP-ENV-5D PAC-4G (Alpha Counter) Operation Deleted 04-14-86 EP-ENV-5E Reuter-Stokes Operation Deleted 08-27-85 Data Analysis, Dose Projections and Protective Deleted 12-21-81 EP-ENV-6 Action Recommendations PAGE 2 OF 11

"EMERGENCYPLAN IMPLEMENTING PROCEDURES INDEX DATE: 10-19-2001 PROC. NO. TITLE REV. DATE EP-ENV-6 Alternate Sample Analysis and Relocation of Deleted 04-14-86 EM Team EP-ENV-6A Relocation of Site Access Facility (Habitability) Deleted 03-23-84 EP-ENV-6B SAF Environmental Sample Analysis Relocation Deleted 03-23-84 EP-ENV-7 Site Access Facility Communications Deleted 09-26-84 EP-ENV-8 Total Population Dose Estimate Calculations Deleted 04-14-86 EP-EOF EP-EOF-1 Corporate Emergency Response Organization Deleted 03-11-94 EPIP-EOF-2 Emergency Operations Facility (EOF) Activation X 10-24-2000 EPIP-EOF-03 EOF Staff Action for Unusual Event AA 09-27-2001 EPIP-EOF-04 EOF Staff Action for Alert or Higher AG 09-27-2001 EP-EOF-5 Corporate Staff Action for Site Emergency Deleted 04-24-87 EP-EOF-6 Corporate Staff Action for General Emergency Deleted 04-24-87 EP-EOF-7 Notification of Unusual Event Deleted 04-06-94 EP-EOF-8 Relocation of EOF Deleted 03-01-83 EPIP-EOF-08 Continuing Emergency Notifications S 09-26-2000 EP-EOF-9 Interface with Support Organizations Deleted 03-05-84 EP-EOF-9 Notification of Site Emergency Deleted 04-24-87 EP-EOF-10 Notification of General Emergency Deleted 04-24-87 EPIP-EOF- 11 Internal Communication and Documentation T 06-01-2000 Flow EPIP-EOF- 12 Media Center/Emergency Operation P 07-19-2001 Facility/Joint Public Information Center Security PAGE 3 OF 11

EMERGENCY PLAN IMPLEMENTING PROCEDURES INDEX DA,TE: 10-19-2001 PROC. NO. TITLE REV. DATE EP-OP EP-OP-1 Control Room Emergency Organization Deleted 04-24-87 EP-OP-2 Emergency Control Room Activation for Deleted 04-24-87 Emergency Response EP-OP-3 Control Room Communications Deleted 04-24-87 EP-OSF EP-OSF-1 Operation Support Facility Emergency Deleted 04-24-87 Organization EPIP-OSF-02 Operational Support Facility Operations S 08-29-2000 EPIP-OSF-03 Work Requests During an Emergency 0 09-27-2001 EP-OSF-4 Operational Support Facility Communications Deleted 04-24-87 EPIP-OSF-04 Search and Rescue D 09-12-2000 EP-RET EP-RET- 1 Radiation Emergency Team Organization Deleted 04-16-96 EPIP-RET-02 In-Plant Radiation Emergency Team T 10-02-2001 EPIP-RET-02A Radiation Protection Office/Radiological S 10-02-2001 Analysis Facility (RPO/RAF) Activation EP-RET-2B Gaseous Effluent Sample and Analysis Q 03-03-98 EP-RET-2C Containment Air Sampling and Analysis Deleted 03-01-83 EPIP-RET-02D Emergency Radiation Entry Controls and M 06-12-2001 Implementation EP-RET-2E Handling of Injured Personnel Deleted 04-16-96 EP-RET-2F Personnel Decontamination Deleted 04-13-90 EPIP-RET-03 Chemistry Emergency Team 0 02-01-2000 EP-RET-3A Liquid Effluent Release Paths K 01-12-99 EP-RET-3B Post-Accident Reactor Coolant Alternate Deleted 01-25-88 Sampling Procedure PAGE 4 OF 11

EMERGENCY PLAN IMPLEMENTING PROCEDURES INDEX DATE: 10-19-2001 PROC. NO. TITLE REV. DATE EP-RET-3C Post Accident Operation of the High Radiation 0 01-18-2000 Sample Room EP-RET-3D Containment Air Sampling Analysis Using M 01-18-2000 CASP EP-RET-3E Post Accident Operation of High Rad Sample Deleted 08-27-85 Room Inline Multiported Count Cave EPIP-RET-04 SBF Activation R 10-02-2001 EP-RET-4A EOF Radiological Monitoring Deleted 03-10-83 EPIP-RET-04A SBF Operation/Relocation Deleted 10-02-2001 EP-RET-4B Radiological Controls at Site Access Facility Deleted 07-12-94 EP-RET-4C Site Radiological Monitoring Deleted 07-12-94 EP-RET-4D SAM-II Operation Deleted 07-12-94 EP-RET-5 Plume Projection Deleted 09-26-84 EPIP-RET-05 Site Boundary Dose Rates During Controlled H 10-09-2001 Plant Cooldown EP-RET-5A Plume Projection Deleted 04-27-87 EP-RET-6 Dose Projection Deleted 04-24-87 EP-RET-7 Radiological Analysis Facility/Radiation Deleted 04-24-87 Protection Office Communications EPIP-RET-08 Contamination Control of the Aurora Medical 0 06-15-2000 Center EPIP-RET-09 Post-Accident Population Dose K 08-29-2000 EP-SEC EP-SEC-1 Security Organization Deleted 04-24-87 EPIP-SEC-02 Security Force Response to Emergencies W 08-28-2001 EP-SEC-2A Manual Activation of Emergency Sirens Deleted 04-16-82 EPIP-SEC-03 Personnel Assembly and Accountability AB 10-19-2001 EPIP-SEC-04 Security Force Actions for Dosimetry Issue P 10-02-2001 PAGE 5 OF 11

EMERGENCY PLAN IMPLEMENTING PROCEDURES INDEX DATE: 10-19-2001 PROC. NO. TITLE REV. DATE EP-SEC-5 Security Force Response to the EOF Deleted 07-28-88 EPIP-SEC-05 Personnel Evacuation F 07-05-2001 EP-TSC EPIP-TSC-01 Technical Support Center Organization and P 10-02-2001 Responsibilities EPIP-TSC-02 Technical Support Center Activation R 07-18-2000 EPIP-TSC-03 Plant Status Procedure V 10-09-2001 EPIP-TSC-04 Emergency Physical Changes, Major Equipment M 10-02-2001 Repair EP-TSC-5 Technical Support Center Communications Deleted 04-24-87 Equipment EP-TSC-6 Assessment of Reactor Core Damage Deleted 09-30-86 EPIP-TSC-07 RV Head Venting Time Calculation I 10-19-2001 EPIP-TSC-08A Calculations for Steam Release from Steam M 03-07-2000 Generators EPIP-TSC-08B* STMRLS Computer Program F 10-02-2001 EP-TSC-8C* See EP-TSC-8B Deleted 04-16-92

  • EP-TSC-8B was totally deleted; therefore, EP-TSC-8C was changed to EP-TSC-8B EP-TSC-9 Core Damage Assessment Using Released Deleted 09-30-86 Radionuclides EP-TSC-9A* Core Damage Assessment I 02-23-99 EPIP-TSC-09B* CORE Computer Program J 10-02-2001 EP-TSC-9C* See EP-TSC-9B Deleted 04-16-92

EPIP-TSC-10 Technical Support for IPEOPs I 03-20-2001 PAGE 6 OF 11

EMERGENCY PLAN IMPLEMENTING PROCEDURES INDEX DATE: 10-19-2001 FIGURES EPIP FIG# Figure EPIPFG DESCRIPTION REV. DATE EP-SEC-5 Technical Support EPIP-APPX-A-06 EP-FIG-03 APPX-A-06-03 Center - KNP Floor Plan B 06-12-2001 Site Boundary Facility EPIP-APPX-A-06 EP-FIG-005 APPX-A-06-02 KNP Floor Plan A 10-31-2000 Radiological Analysis Facility - KNP Floor EPIP-APPX-A-06 EP-FIG-oo8 APPX-A-06-01 Plan A 10-31-2000 EPIP-EOF- 12 Division Office Building Form EPIPF-EOF-02-01 EP-FIG-009 EOF-12-01 (2nd Floor) Floor Plan B 10-24-2000 State/County Work Area - WPSC D2-1 EPIP-APPX-A-06 EP-FIG-012 APPX-A-06-08 Floor Plan C 10-31-2000 NRC Work Area EPIP-APPX-A-06 EP-FIG-013 APPX-A-06-09 WPSC D2-4 Floor Plan A 10-31-2000 Population Distribution by Geographical Sub EPIP-AD-19 EP-FIG-014 AD- 19-01 Areas (with sectors) A 10-31-2000 EOF - WPSC D2-3 EPIP-APPX-A-06 EP-FIG-022 APPX-A-06-04 Floor Plan B 10-31-2000 Map - Location of JPIC, EPIP-EOF-12 EP-FIG-024 EOF-12-02 MBC, GOB, DOB, etc. B 09-27-2001 EP-SEC-5 EP-FIG-026 SEC-05-01 Site Map B 09-27-2001 Floor Plan - Media APPX-A-6 EP-FIG-034 - - - Briefing Center DEL 08-04-98 General Office EPIP-EOF- 12 Building - WPSC (1st EPIP-APPX-A-06 EP-FIG-035 APPX-A-06-06 Floor) Floor Plan C 10-24-2000 Floor Plan - Corporate APPX-A-6 EP-FIG-037 - -- Response Center DEL 08-04-98 APPX-A-6 EP-FIG-039 - - - Floor Plan - JPIC DEL 08-04-98 EPIP-OSF-02 EP-FIG-039 OSF-02-01 High Priority Work A 10-02-2001 EPIP-OSF-02 EP-FIG-039A OSF-02-02 Lower Priority Work A 10-02-2001 JPIC - Federal Work EPIP-APPX-A-06 EP-FIG-043 APPX-A-06-10 Area - WPSC D2-9 A 10-31-2000 JPIC - State and County Work Area EPIP-APPX-A-06 E,-FIG-044 APPX-A-06-07 WPSC D2-8 A 10-31-2000 JPIC - Utility Work EPIP-APPX-A-06 EP-FIG-045 APPX-A-06-05 Area - WPSC D2-7 A 10-31-2000 Aurora Medical Center RET-08 EP-FIG-046 RET-08-01 Location A 06-15-2000 EPIP-APPX-A-02 --- APPX-A-02-01 ERO Call Tree A 01-30-2001 PAGE 7 OF 11

EMERGENCY PLAN IMPLEMENTING PROCEDURES INDEX DATE: 10-19-2001 NUMBER TITLE REVISION DATE APPENDIX A APPX-A-1 Communication System Description AF 08-04-98 EPIP-APPX-A-02 Response Personnel Call List BL 10-19-2001 EPIP-APPX-A-03 Off-Site Telephone Numbers BN 09-27-2001 EPIP-APPX-A-06 WPSC Emergency Response Telephone Numbers Y 07-30-2001 PAGE 8 OF 11

EMERGENCY PLAN IMPLEMENTING PROCEDURES INDEX DATE: 10-19-2001 FORM EPIPF TITLE REV. DATE APPENDIX B EP-AD AD 7.1 Event Notice (Wisconsin Nuclear Accident Reporting P 02-01-2000 Form)

AD 7.2 State Call-Back - Question Guideline B 04-16-96 AD 11.1 Emergency Radiation Work Permit F 04-16-96 EP-ENV ENV-01-01 Environmental Dispatch Area Activation Checklist D 10-31-2000 ENV-01-02 EMT Status B 10-31-2000 ENV-01-03 Meteorological and Plant Status Data B 10-31-2000 ENV-01-04 EMT Orders/Field Data B 10-31-2000 ENV-02-01 EMT Activation Checklist M 06-15-2000 1............ EP-EOF EOF-02-01 EOF Activation Checklist R 10-24-2000 EOF-02-02 EOF Deactivation Checklist K 10-24-2000 EOF 4.1 SRCL Initial Action Checklist B 09-16-97 EOF 4.2 Telephone Communications Log Sheet ORIG 04-16-96 EOF 8.3 Fax for Emergency Declaration or Status Updates F 09-21-99 EOF 8.5 Plant Emergency Status Report ORIG 02-21-95 EOF 8.6 Radiological Status Report C 03-14-97 EOF 11.2 Operating Status E 02-14-95 EOF 11.3 Environmental Status Board E 07-31-95 EOF-12-01 I.D. Badge Registration Form G 10-24-2000 EP-OSF OSF 2.2 Maintenance Work in Progress Deleted 07-08-98 OSF-03-01 Operational Support Facility Team Briefing B 09-12-2000 PAGE 9 OF 11

EMERGENCY PLAN IMPLEMENTING PROCEDURES INDEX DATE: 10-19-2001 FORM EPIPF TITLE REV. DATE EP-RET RET-02A-02 Emergency Sample Worksheet E 06-05-2001 RET 2B. 1 Containment Stack Release (Grab Sample) C 04-16-96 RET 2B.2 Auxiliary Building Stack (Grab Sample) C 04-16-96 RET 2B.3 Auxiliary Building Stack (Sping Reading) C 04-16-96 RET 2B.4 Containment Stack (Sping Reading) B 04-16-96 RET 2B.5 Steam Release C 04-16-96 RET 2B.6 Field Reading (Grab Sample) A 04-16-96 RET-04-01 SAM-2 Counting Equipment Worksheet E 06-12-2001 Hospital Survey 1 Deleted 06-05-2001 RET 8.3 RET 8.4 Hospital Survey 2 Deleted 07-25-97 RET 8.5 Hospital Survey 3 Deleted 07-25-97 RET-08-06 Hospital Survey 4 F 06-15-2000 RET 9 Environmental TLD Record Sheet C 02-14-95 EP-SEC Emergency Accountability Log A 03-28-2000 Emergency Dosimeter Log F 02-16-2000 EP-TSC TSC 1.1 Plant Status Summary for SAM Implementation TSC 1.2 Severe Accident Management Summary and Strategy Recommendation TSC 1.3 Severe Accident Management - Status TSC-02-01 TSC and OSF Activation Checklist TSC 2.2 TSC Ventilation Checklist TSC-02-03 Emergency Response Data System (ERDS) Link Initiation Checklist PAGE 10 OF 11

EMERGENCY PLAN IMPLEMENTING PROCEDURES INDEX D LTE: 10-19-2001 FORM EPIPF TITLE REV. DATE TSC-02-04 TSC Chart Recorder Operation Checklist D 01-30-2001 TSC-02-05 TSC and OSF De-activation Checklist A 10-09-2001 TSC-03-01 Plant System Status L 06-12-2001 TSC-03-02 Plant Equipment Status L 06-12-2001 TSC-03-03 Environmental Status Board J 06-12-2001 TSC-03-04 Radiation Monitors H 06-12-2001 TSC-04-01 Emergency Physical Change Request F 08-29-2000 TSC-04-02 Emergency Physical Change Safety Review F 08-29-2000 TSC-04-03 Emergency Physical Change Index F 08-29-2000 TSC-07-01 Head Venting Calculation F 10-31-2000 TSC 8A.1 Steam Release Data Sheet (Energy Balance) G 02-14-95 TSC 8A.2 Steam Release Calculation Sheet (Energy Balance) F 02-14-95 TSC 8A.3 Steam Release Data/Calculation Sheet (Open Valve) D 02-14-95 TSC 8A.4 Steam Release Data/Calculation Sheet (STMRLS C 04-16-96 Program)

TSC 9A.1 Core Damage Based on Reactor Vessel Level & Fuel Rod C 02-14-95 Temp.

TSC 9A.2 Core Damage Based on Radiation Monitors C 02-14-95 TSC 9A.3 Cs-134 and Cs-137 PCF Determination D 04-16-96 TSC 9A.4 Core Damage Based on Activity Ratios C 02-14-95 TSC 9A.5 Core Damage Assessment (Monitoring Data) D 04-16-96 TSC 9A.6 Core Damage Summary C 02-14-95 PAGE 11 OF 11

WISCONSIN PUBLIC SERVICE CORP. No. EPIP-SEC-03 Rev. AB Title Personnel Assembly and Accountability Kewaunee Nuclear Power Plant Emergency Plan Implementing Procedure Date Page I of 11 Reviewed By W . Apprd By X Nuclear 4-1 PORC 0 Yes Tempovary Safety [ Yes Review Temporary El No Chan es Required El No Related El No Required 1.0 Purpose 1.1 This procedure provides instruction for establishing and maintaining personnel accountability within the Protected Area (PA) of the plant.

2.0 General Notes 2.1 When initial assembly and accountability are in progress, certain individuals (as designated in EPIP-AD-01, "Personnel Response to the Plant Emergency Siren") will be allowed to move in, out, and about the PA before initial accountability is complete.

2.2 Emergency Response Organization (ERO) staff shall report to their duty locations.

2.3 Visitors, Contractors, and non-ERO personnel on-site should assemble in the nearest designated Assembly Area.

2.4 Severe Weather 2.4.1 Several of the Assembly Areas are NOT appropriate for severe weather safety.

a. Warehouse Annex Lunchroom - relocate to the locker room.
b. Administrative Training Facility (ATF) Lunchroom - relocate to the ATF Basement.
c. Simulator Training Facility (STF) Lobby - relocate to the Simulator Control Room away from the glass partition along the west wall close to the floor.
d. Classroom C Security Building - relocate to the Security Building locker room.

Note IF unable to relocateas stated above, personnel should relocateon lower levels of buildings in interiorrooms away from all windows.

2.4.2 The following locations are adequate during severe weather:

a. Control Room (CR)
b. Radiation Protection Office (RPO)
c. Technical Support Center (TSC) n:ýnucdoc\procedures\draft\epip\esec03.doc-Diane FencilDiane Fend-Jeanne Fernis

WISCONSIN PUBLIC SERVICE CORP. No. EPIP-SEC-03 IRev. AB Title Personnel Assembly and Accountability Kewaunee Nuclear Power Plant Emergency Plan Implementing Procedure Date OCT 1 9 2001 T Page 2 of 11 3.0 Precautions and Limitations 3.1 Initial accountability starts from the site announcement (siren sounding/public address message) and needs to be completed within 30 minutes.

a. The SMS Emergency Accountability Program will begin 2 minutes after site announcement. This allows for personnel to exit areas that are not their normal emergency work area (i.e., Control Room).
b. The first report should be generated after 5 minutes.
c. After 10 minutes, print a report or review the computer screen every minute until the number of unaccounted for personnel plateaus.
d. When the number of unaccounted for personnel plateaus, accountability is complete.

3.2 Allow pro=pt movement of ERO personnel into and out of the Protected Area when the Site Protection Director has determined there is no personnel hazard restricting such movement.

3.3 Adhere to the radiation control policies and requirements outlined in EPIP-AD-11, "Emergency Radiation Controls" and EPIP-RET-02D, "Emergency Radiation Entry Controls and Implementation."

3.4 Personnel who are in the Control Room when the Emergency Accountability Program is started are accounted for by the SMS.

3.5 Security Force Members, Fire Brigade Members, NAOs, and dispatched Emergency Teams are exempt from the SMS Emergency Accountability Program. They will be accounted for as defined in EPIP-AD-01, Step 5.1.1.c.

4.0 Initial Conditions 4.1 Personnel assembly is required whenever the plant emergency siren is sounded.

Accountability will be required upon assembly unless otherwise directed by the Shift Manager/Emergency Director.

5.0 Procedure 5.1 Site Protection Director (SPD) or Designee shall:

5.1.1 IF a designated Master Accountability Coordinator (MAC) is not available, THEN direct the Security Shift Captain to perform accountability functions.

5.1.2 Contact the Emergency Director (ED) or Radiological Protection Director (RPD) to determine the location of any personnel hazards on-site or off-site and continue to monitor conditions.

WISCONSIN PUBLIC SERVICE CORP. No. EPIP-SEC-03 Rev. AB Title Personnel Assembly and Accountability Kewaunee Nuclear Power Plant Emergency Plan Implementing Procedure Date OCT 19 2001 T Page 3 of 11 5.1.3 IF conditions warrant, THEN direct the Security Force to hold exiting personnel in the Security Building until the RPD determines a safe evacuation route.

5.1.4 Advise the MAC of all hazardous areas and/or severe weather.

5.1.5 Advise on-site directors of hazardous areas or severe weather conditions.

5.1.6 Direct Security Force personnel to make a tour through the Owner Controlled Area (OCA), sewage plant, exterior warehouses, exterior substation, and Met Tower to inform personnel to assemble in the STF or Security Building, or to leave the site, as appropriate.

5.1.7 Ensure attempts are made by any available means to contact all personnel who are unaccounted for.

5.1.8 IF attempts fail to locate personnel who are unaccounted for, THEN direct the Central Alarm Station (CAS) or Secondary Alarm Station (SAS) operator to run a computer report for that person(s).

5.1.9 Provide the Support Activities Director (SAD) and the RPD with information regarding all personnel who are unaccounted for based upon last known locations obtained from the computer report.

5.1.10 Keep the ED informed of the status of personnel accountability.

5.1.11 When initial accountability is complete, ensure the following message is announced over the Gai-tronics:

"I"Attention all personnel. Initial accountability is complete. Personnel may relocate to other areas but shall maintain accountability." I 5.1.12 Maintain cognizance of all personnel outside the PA who remain on-site.

5.1.13 Continue to provide the MAC with updates on any location determined to be a personnel hazard including areas outside the PA.

WISCONSIN PUBLIC SERVICE CORP. No. EPIP-SEC-03 Rev. AB Title Personnel Assembly and Accountability Kewaunee Nuclear Power Plant Emergency Plan Implementing Procedure Date OCT 1 9 2001 Pa e4of 11 5.2 Master Accountability Coordinator (MAC) shall:

5.2.1 WHEN accountability is required:

a. Report to the Security Building.
b. IF a MAC has been designated and UNTIL they are released,
1. If appropriate, plan a shift relief per EPIP-AD-05, "Emergency Response Organization Shift Relief Guideline."
2. Help the designated MAC.
c. IF a MAC has NOT been designated, notify the SPD of your intent to assume the responsibilities of the MAC and continue implementation of this procedure.
d. Assign an Accountability Coordinator to the South Security Building Visitor's Desk.
1. Inform this Accountability Coordinator to complete Form EPIPF-SEC-03.01, "Emergency Accountability Log," for ERO members entering the Protected Area.
2. Perform Step 5.3.9.
e. IF there is no Accountability Coordinator available for the Security Visitor's Desk, THEN assign a plant staff or security staff member to perform Step 5.2.1.d.

5.2.2 Two minutes after the sound of the plant emergency siren, ensure that the SAS/CAS has started the "Emergency Accountability Program" on the SMS.

5.2.3 Contact Security to verify there is NOT a hard copy visitor list. If this list is available, pick up the KNPP Protected Area Visitor and Non-Designated Vehicle log (SIP 20.02-1) at the Registration Desk.

5.2.4 Contact each Visitor's Escort via Gai-tronics to ensure accountability of their Visitor, place a check mark next to the Visitor's name as reported by the Escort.

5.2.5 Five minutes after the SMS Emergency Program has been started, obtain an Emergency Report from CAS/SAS.

5.2.6 Should attempts fail to locate personnel who are unaccounted for, direct the SAS/CAS to run a computer report on that person.

WISCONSIN PUBLIC SERVICE CORP. No. EPIP-SEC-03 Rev. AB Title Personnel Assembly and Accountability Kewaunee Nuclear Power Plant Emergency Plan Implementing Procedure Date OCT 1 9 2001 Page 5 of 11 5.2.7 Review the Emergency Report

a. Contact the Control Room and strike any names from the list that have been positively accounted for (individual is in the Control Room or is accounted for on their "Emergency Accountability Log").
b. Contact the Technical Support Center (TSC) and strike any names from the list that have been positively accounted for (individual is in the TSC or is accounted for on their "Emergency Accountability Log").
c. Contact all names remaining on the list by any possible means.

5.2.8 WHEN all personnel have been contacted or reasonable attempts to contact have failed, record the names of individuals not accounted for and their last known location and provide this information to the SPD.

5.2.9 Contact the Accountability Areas outside the PA (per Table 1) to determine the number and location of personnel on-site but not within the Protected Area.

5.2.10 Report to the SPD the number and location of personnel on-site but outside the PA and obtain an update regarding personnel hazards and/or severe weather.

5.2.11 IF the plant emergency siren sounds after initial accountability, THEN return to Step 5.2.2.

5.2.12 Provide Accountability Coordinators (AC) with information regarding personnel hazards and/or severe weather provided by the SPD and continue to do so on a periodic basis.

5.2.13 Brief the SPD on any change in accountability status or new problems (i.e., groups or individuals overdue in assembly areas).

5.2.14 If appropriate, plan a shift relief for the MAC per EPIP-AD-05.

5.2.15 IF Final Conditions (Section 6.0) have NOT been met, THEN return to Step 5.2.11.

5.2.16 WHEN Final Conditions (Section 6.0) are met,

a. Return your work area to normal status and return emergency procedures, forms, etc. to there proper place.
b. Record any discrepancies to emergency supplies that need correction and report them to the SPD.
c. Collect all completed forms, notes, and other documentation and give them to the SPD.

WISCONSIN PUBLIC SERVICE CORP. No. EPIP-SEC-03 Rev. AB Title Personnel Assembly and Accountability Kewaunee Nuclear Power Plant Emergency Plan Implementing Procedure Date OCT I q 7[]D1 Page 6 of 11 5.3 Accountability Coordinator (AC) shall:

5.3.1 WHEN accountability is required:

a. Report to your assigned assembly area.
b. IF an AC has been designated and UNTIL they are released,
1. Help in facility activation.
2. If appropriate, plan a shift relief per EPIP-AD-05.
3. Help the designated AC.
c. IF an AC has NOT been designated, notify the Facility Director or MAC of your intent to assume the responsibilities of the AC in the assembly area and continue implementation of this procedure.

5.3.2 Obtain Accountability packet located in the assembly areas in the following locations:

a. Control Room (CR) - On the wall behind the Control Room Supervisor's desk.

Note Make a listfor the MAC of FireBrigade Members, NAOs, and dispatched Emergency Teams that are accountabilityexempt.

b. Technical Support Center (TSC) - On the desk near the entrance door (No. 410).
c. Radiation Protection Office (RPO) - Next to the entrance door (No. 55).
d. Administrative Training Facility (ATF) - Lunchroom southwest comer, above the phone and Gai-tronics.
e. Warehouse Annex - Lunchroom west wall, above the phone and Gai-tronics.
f. Security Building - Room "C" on the wall by the phone and Gai-tronics.
g. Site Training Facility (STF) - Lobby on the wall by the Gai-tronics.
h. Containment Access Facility Break Room - On the south wall, next to accountability card reader in Craft Break Area.
i. SGR Fab Shop - On the north wall of the south room in the SGR Fab Shop.

5.3.3 Locate yourself near the SMS accountability card reader.

WISCONSIN PUBLIC SERVICE CORP. No. EPIP-SEC-03 Rev. AB Title Personnel Assembly and Accountability Kewaunee Nuclear Power Plant Emergency Plan Implementing Procedure Date OCT 19 2001 Page7of 11 Note Visitors with magnetic badges must swipe their key card in an accountability cardreader. Visitors with non-magnetic badges should Mot swipe their key card in an accountabilitycard reader.

5.3.4 WHEN the Gai-tronics announcement is made that emergency accountability has been initiated, ensure that all badged personnel located in the area swipe their Security key card in the accountability reader and receive a green light.

5.3.5 IF a Director or Supervisor notifies you of individuals who will NOT assemble, THEN record them as if they were leaving the facility per Step 5.3.9.

5.3.6 Five minutes after the Gai-tronics announcement initiating accountability, make an announcement requesting any badged personnel who have not swiped their key card to do so immediately.

5.3.7 During accountability, demand quiet and cooperation. Maintain accountability of personnel assembled there.

5.3.8 WHEN provided by the MAC, inform personnel in your assembly area of information on hazardous areas.

5.3.9 WHEN an individual elects to move to another area, log their departure on "Emergency Accountability Log," Form EPIPF-SEC-03-01, as follows:

Note This includes visitors also.

a. In the "Name" column: Enter the name of the individual leaving the area.
b. In the "Card" column: Enter the individual's security card number.

WISCONSIN PUBLIC SERVICE CORP. No. EPIP-SEC-03 Rev. AB Title Personnel Assembly and Accountability Kewaunee Nuclear Power Plant Emergency Plan Implementing Procedure Date OCT 19 200l1 Pale 8 of 11

c. In the "Destination" column: Enter the location to which the individual is heading.

Acronym Area ForAnother Accountability Area CR Control Room RPO Radiation Protection Office TSC Technical Support Center WA Warehouse Annex Lunchroom ATF Administrative Training Facility Lunchroom CAF Containment Access Facility Break Room ForRepair Team Activity LPA Leaving the Protected Area PA Outside the Buildings but inside the Protected Area ADMN Administrative Buildings TURB Turbine Building AUX Auxiliary Building CNTM Containment Building WRHS Warehouse or Shop Area

d. In the "Departure Time" column: Enter the time the individual departed the area.
e. In the "Return/Arrive Time" column: Enter the time the individual returns to the area or the time you are informed they arrive at another Assembly Area by the Accountability Coordinator in that area.

5.3.10 IF an individual arrives in your area who did not log out of your area and is not immediately returning to the area he checked out of, THEN contact the area he departed and notify them of the individual's arrival time and intent to stay.

5.3.11 IF moving the entire group of assembled personnel to another area, THEN:

a. Contact the MAC to inform them of the intended move.
b. Record badge numbers of people moving.
c. Instruct personnel in your area to proceed directly to the new destination, staying in a group until head count can be verified.

WISCONSIN PUBLIC SERVICE CORP. No. EPIP-SEC-03 Rev. AB Title Personnel Assembly and Accountability Kewaunee Nuclear Power Plant Emergency Plan Implementing Procedure Date OCT 1 9 .001 Page 9 of. 1

d. Verify the badge numbers upon arrival at the new location.
e. Contact the MAC to verify arrival and to provide a phone number at the new location.

5.3.12 IF the plant siren is sounded following the initial accountability, THEN initiate contacts to all individuals listed as NOT "Returned or Arrived" on your Form EPIPF-SEC-03-01:

a. WHEN contacted, give them any information you know about the siren sounding.
b. IF instructed by a Facility Director, instruct the individual to come back to an assembly area.
c. Note the individuals that were contacted and notify the MAC of individuals logged out of your area and whether you were able to contact them.
d. Return to Step 5.3.4.

5.3.13 If appropriate, plan a shift relief for the area AC per EPIP-AD-05.

5.3.14 IF Final Conditions (Section 6.0) have not been met, THEN return to Step 5.3.8.

5.3.15 IF Final Conditions (Section 6.0) are met, THEN Note Flagany discrepanciesto emergency supplies that need correction.

a. Return your work area to normal status and return emergency procedures, forms, etc. to there proper place.
b. Collect all completed forms, notes, and other documentation and give them to the SPD.

5.4 Security Force shall:

5.4.1 WHEN accountability is required and the SMS system is offline, manually maintain a log of personnel entering/exiting the PA to enable the MAC to update the accountability roster as necessary.

5.4.2 Guide PA ingress/exit in accordance with EPIP-SEC-02, "Security Force Response to Emergencies."

5.4.3 Patrolling Security Officers shall:

a. Verify their locations by portable radio to the Shift Captain for accountability.
b. Obtain personal dosimetry to take with them on patrol in accordance with EPIP-SEC-04, "Security Force Actions for Dosimetry Issue."

WISCONSIN PUBLIC SERVICE CORP. No. EPIP-SEC-03 Rev. AB Title Personnel Assembly and Accountability Kewaunee Nuclear Power Plant Emergency Plan Implementing Procedure Date OCT 19 2001 Page 10 of 11 6.0 Final Conditions 6.1 Plant Emergency has been Terminated or Recovery actions have begun and the Emergency Director has suspended the use of EPIPs or it has been determined emergency accountability is no longer required.

7.0 References 7.1 Kewaunee Nuclear Power Plant Emergency Plan 7.2 EPIP-AD-01, Personnel Response to the Plant Emergency Siren 7.3 EPIP-AD-05, Emergency Response Organization Shift Relief Guideline 7.4 EPIP-AD-1 1, Emergency Radiation Controls 7.5 EPIP-RET-02D, Emergency Radiation Entry Controls and Implementation 7.6 EPIP-SEC-02, Security Force Response to Emergencies 7.7 EPIP-SEC-04, Security Force Actions for Dosimetry Issue 8.0 Records 8.1 The following QA records and non-QA records are identified in this directive/procedure and are listed on the KNPP Records Retention Schedule. These records shall be maintained according to the KNPP Records Management Program.

8.1.1 QA Records None 8.1.2 Non-QA Records

  • Emergency Accountability Log, Form EPIPF-SEC-03-01

ACCOUNTABILITY AREAS (Inside the Protected Area)

LOCATION PHONE NUMBER Control Room 8207 Radiation Protection Office 8451 Technical Support Center (Included OSF and RAF) 8353 Administrative Training Facility (Lunchroom) 6480 Warehouse Annex (Lunchroom) 6452 Containment Access Facility Break Room 6500 ALTERNATE LOCATION PHONE NUMBER Administrative Training Facility (Basement) 6548 Warehouse Annex (Locker Room) 8427 ACCOUNTABILITY AREAS (Outside the Protected Area)

LOCATION PHONE NUMBER Security Building Classroom C 6548 Simulator Training Facility (Lobby) 8427 SGR - Fab Shop 6501 ALTERNATE LOCATION PHONE NUMBER Security Locker Room (Security Building) 8292 Simulator Training Facility (Simulator Control Room) 8427 ACCOUNTABILITY LEADERS LEADER PHONE NUMBER Master Accountability Coordinator (Security Building) 8509 Accountability Coordinator (Sec. Bldg. Visitor's Desk) 8509 Site Protection Director (Sec. Bldg.) 8418 (TSC) PBX 8591 Kew. Ex. 388-0459 A44..

Table~~~0 EPP-EC0 Rev wa Table 1 EPIP-SEC-03 Rev. AB Date: OCT 1 9 2001

WISCONSIN PUBLIC SERVICE CORP. No. EPIP-TSC-07 IRev. I Title RV Head Venting Time Calculation Kewaunee Nuclear Power Plant Emergency Plan Implementing Procedure Date OCT 1 9 Page 1 of 3 Reviewed By Nula [YsPORC ,

a irli9N-- Approved By Approval-L ,Q

  • ---*k EZ Yes, 1 SRO Of 64 zEl Yes Safety Rve NoTemporary Related []No , Required [ oChanges Required 0] No 1.0 Purpose 1.1 This procedure provides instruction for determining the maximum allowable venting period of the reactor vessel head when noncondensable gases are present in the RCS.

2.0 General Notes 2.1 None 3.0 Precautions and Limitations 3.1 This procedure should be done concurrently with FR-I.3, "Response to Voids in Reactor Vessel," Section 4.17. Determine maximum allowable venting time.

3.2 The procedure may only be performed when containment hydrogen concentration is below 3%.

4.0 Initial Conditions 4.1 The range selector switch on each monitor must remain in the 0-10% position. The high range is NOT calibrated and will result in false Control Room and computer indication.

4.2 The containment hydrogen analyzer has been placed in service per EPIP-RET-03C, "Post Accident Operation of the High Radiation Sample Room." Allow a minimum sample purge time of 10 minutes.

4.3 All available containment air circulating equipment should be operating to prevent the formation of hydrogen gas pockets and ensure a representative sample is obtained. IF only one containment dome fan is operating, THEN the sample should be taken from the operating fan discharge.

5.0 Procedure 5.1 Obtain the RCS Pressure from the Honeywell Computer Point ID P0420A or Control Room meters and record it on Form EPIPF-TSC-07-01.

5.2 Obtain the Containment Pressure from the Honeywell Computer Point IDs P8004A, P8005A, or Control Room meters and record it on Form EPIPF-TSC-07-01.

n:\nucdoc\procedures\draft\epip\etsc07.doc--Chdstine Simmons/Amy Kudick-Ed Coen

WISCONSIN PUBLIC SERVICE CORP. No. EPIP-TSC-07 Rev. I Title RV Head Venting Time Calculation Kewaunee Nuclear Power Plant Emergency Plan Implementing Procedure Date OCT 19 2001 Page 2 of3 5.3 Obtain the Containment Hydrogen Concentration from Honeywell Computer Point IDs X8001A, X8002A, or Control Room meters (41615 and 41616). jE only one containment dome fan is running, THEN use the appropriate hydrogen analyzer channel to get a representative sample. IF both fans are running, THEN use the channel with the higher concentration indication. Record the hydrogen concentration, the dome fans in service, and which analyzer was used on Form EPIPF-TS C-07-0 1.

5.4 Obtain the Containment Temperature from the Control Room and record it on Form EPIPF-TSC-07-01.

5.5 Complete the calculations on Form EPIPF-TSC-07-01 and report the results (maximum head venting time) to the TSCD.

6.0 Final Conditions 6.1 Emergency declaration is terminated, OR 6.2 The reactor component system has been stabilized and recovery operations have been entered per EPIP-AD-15, "Recovery Planning and Termination."

7.0 References 7.1 "Background Information for Westinghouse Emergency Response Guidelines, FR-I.3 Void in Reactor Vessel," Rev. LP-BASIC, September 15, 1981 7.2 "FR-I.3, Response to Voids in Reactor Vessel," LP-Rev. 1, September 1, 1983 7.3 EPIP-AD-15, Recovery Planning and Termination 7.4 EPIP-RET-03C, Post Accident Operation of the High Radiation Sample Room 7.5 Flow Diagram, "Reactor Building Vent System Post-LOCA Hydrogen Control," M-403 8.0 Records 8.1 The following QA records and non-QA records are identified in this directive/procedure and are listed on the KNPP Records Retention Schedule. These records shall be maintained according to the KNPP Records Management Program.

8.1.1 QA Records 9 Head Venting Calculation, Form EPIP-TSC-07-01 8.1.2 Non-QA Records None

HYDROGEN FLOW RATE VERSUS RCS PRESSURE 3600 3400 3200 3000 2800 2600 2400 2200 2000 0J 1800 z 1600 0

1400 1200 1000 800 600 400 200 0

0 400 8(30 1200 1 600 2000 2400 RCS PRESSURE (PSIG)

Figure I EPIP-TSC-07 Rev. I Date: OCT FR9 2001 Page 3 of 3

WISCONSIN PUBLIC SERVICE CORP. No. EPIP-APPX-A-02 Rev. BL Title Response Personnel Call List Kewaunee Nuclear Power Plant Emergency Plan Implementing Procedure Date OCT 19 2Gt1 I Page 1 of_3 Reviewed By Nula ***,Czx-( ye,-*/5 tRCyeSTRO 7 4_.-. Approved By (Q *-2Q- Of

. Approval 11 Yes Safety ReviewTepry Related El No Required 21 No IChanges Required El No 1.0 Purpose 1.1 This appendix provides a consolidated list of all Emergency Response Organization (ERO) members sorted three ways:

"* By facility, then ERO position

"* Accountability Coordinators by Facility

"* All members alphabetically by last name 2.0 General Notes 2.1 This appendix may be used as a reference document for any declared emergency as defined in EPIP-AD-02, "Emergency Class Determination."

3.0 Precautions and Limitations 3.1 Changes made to the ERO between quarterly updates are managed in the WPSR Corporate Database "PeopleSoft."

3.2 The appendices to this procedure are reviewed and updated quarterly. This review and update is required to fulfill the requirements of the Emergency Plan Section 8.3.1.

4.0 Initial Conditions 4.1 This appendix is used for reference during an emergency at the Kewaunee Nuclear Power Plant (KNPP).

5.0 Procedure 5.1 This appendix will be updated quarterly.

6.0 Final Conditions 6.1 Plant Emergency has been Terminated or Recovery actions have begun and the Emergency Response Manager has suspended the use of EPIPs.

n:\nucdoc\procedures\draft\epip\eappxa02.doc-Diane Fend/Diane Fend-Jeanne Ferris

WISCONSIN PUBLIC SERVICE CORP. No. EPIP-APPX-A-02 FRev. BL Title Response Personnel Call List Kewaunee Nuclear Power Plant Emergency Plan Implementing Procedure Date OCT 1 9 2001 Page 2 of 3 7.0 References 7.1 Attachments

"* EPIP Table Appx-A-2.1, Appx-A Response Personnel Call List (Facility)

"* EPIP Table Appx-A-2.2, Appx-A Response Personnel Call List (Accountability Coordinators)

"* EPIP Table Appx-A-2.3, Appx-A ERO Qualified Personnel Assignments (Response Personnel Sorted By Name) 7.2 EPMP-05.03, Telephone Number Quarterly Review 7.3 EPWP-AD-02, Emergency Class Determination 8.0 Records 8.1 The following QA records and non-QA records are identified in this directive/procedure and are listed on the KNPP Records Retention Schedule. These records shall be maintained according to the KNPP Records Management Program.

8.1.1 QA Records None 8.1.2 Non-QA Records None

Appx-A Response Personnel Call List (Facility)

EPIP Table Appx-A-2.1 Appx-A Response Personnel Call List (Accountability Coordinators)

EPIP Table Appx-A-2.2 Appx-A ERO Qualified Personnel Assignments (Response Personnel Sorted By Name)

EPIP Table Appx-A-2.3 The data contained on the attached tables have been intentionally omitted from external copies of this document.

This data is withheld to ensure the privacy of the employees of Nuclear Management Company, LLC, Wisconsin Public Service Corporation, and off-site support groups which have supplied personal information for internal use by Nuclear Management Company. It has also been done to ensure the security of the Kewaunee Nuclear Power Plant Emergency Communications Systems.

All company-held copies of this appendix do contain the telephone numbers and other communication data needed to ensure a prompt response of on-site and off-site support groups over the established communication systems.

Appendix A-2 EPIP-APPX-A-02 Rev. BL Date: OCT 19 ZOUl Page 3 of 3 Page 3 of 3 Appendix A-2 EPIP-APPX-A-02 Rev. BL Date: OCT 1 9 2001