L-PI-22-047, Resubmittal of Prairie Island Nuclear Generating Plant (PINGP) 2018 Unit 1 180-Day Steam Generator Tube Inspection Report

From kanterella
Jump to navigation Jump to search
Resubmittal of Prairie Island Nuclear Generating Plant (PINGP) 2018 Unit 1 180-Day Steam Generator Tube Inspection Report
ML22356A053
Person / Time
Site: Prairie Island Xcel Energy icon.png
Issue date: 12/21/2022
From: Borgen T
Northern States Power Company, Minnesota, Xcel Energy
To:
Office of Nuclear Reactor Regulation, Document Control Desk
References
L-PI-22-047
Download: ML22356A053 (1)


Text

(},, Xcel Energy 1717 Wakonade Drive Welch, MN 55089 December 21, 2022 L-PI-22-047 TS 5.6.7 ATTN: Document Control Desk U.S. Nuclear Regulatory Commission Washington, DC 20555-0001 Prairie Island Nuclear Generating Plant, Unit 1 Docket No. 50-282 Renewed Facility Operating License No. DPR-42 Resubmittal of Prairie Island Nuclear Generating Plant (PINGP) 2018 Unit 1 180-Day Steam Generator Tube Inspection Report

References:

1) NSPM Letter L-PI-19-015, 2018 Unit 1 180-Day Steam Generator Tube Inspection Report, dated April 18, 2019. (NRC ADAMS Accession Number ML19108A291)
2) NSPM Letter L-PI-22-003, Application to Revise Technical Specifications to Adopt TSTF-577, Revised Frequencies for Steam Generator Tube Inspections, dated June 7, 2022. (NRC ADAMS Accession Number ML22158A090)
3) NSPM Letter L-PI-22-040, Supplement to Application to Revise Technical Specifications to Adopt TSTF-577, Revised Frequencies for Steam Generator Tube Inspections, dated October 6, 2022.

(NRC ADAMS Accession Number ML22279B046)

4) NRC Letter subject: Prairie Island Nuclear Generating Plant, Units 1 and 2 - Issuance of Amendments 241 and 229 re: TSTF-577 Revised Frequencies for Steam Generator Tube Inspections, dated November 1, 2022 (EPID L-2022-LLA-0084). (NRC ADAMS Accession Number ML22300A223)

Northern States Power Company, a Minnesota corporation, doing business as Xcel Energy (hereafter NSPM), hereby resubmits a revised report of steam generator tube inspections performed during the 2018 refueling and maintenance outage on Unit 1 per Technical Specification (TS) 5.6.7, Steam Generator Tube Inspection Report. The report originally submitted with Reference 1, is revised to meet new reporting requirements in TS 5.6.7 which were proposed by NSPMs license amendment request submitted with References 2 and 3 and approved by Reference 4.

As noted in Reference 2, NSPM is resubmitting this report using the revised TS 5.6.7 reporting requirements in order to start the new steam generator tube inspection period

Document Control Desk l-Pt--22~047 Page2 based on the Inspection or 100 percent of Untt 1 steam generator tubes that NSPM oonduct~ In 2018.

Please contact Mr. Jeff Kivi at (612) 330-6788 << Jeffrey.L.Ktvl@xcetenergy.com ff ther$

are any questions or if edditlonat lnfotmadon Is needed.

This letter makes no new commltmenls and no revisions to existing commitments.

Tim **** n *.

Plant Manager. Prairie tstand Nudeer Generating Plant Northern States Power Company- Minnesota Enclosure

<le! Admlnlstmtor, Region tu, USNRC Project Manager, Prairie Island, USNRC Resident fne,,eet<<, Ptalrfe Island, USNRC State of Minnesota

ENCLOSURE 1 PRAIRIE ISLAND NUCLEAR GENERATING PLANT - UNIT 1 2018 STEAM GENERATOR TUBE INSPECTION REPORT In accordance with Prairie Island Nuclear Generating Plant (PINGP), Unit 1 Technical Specification (TS) 5.6.7, Northern States Power Company, a Minnesota corporation, doing business as Xcel Energy (hereafter NSPM), hereby submits this report of steam generator tube inspections performed during the 2018 refueling and maintenance outage for Unit 1 (1R31). This report is a revision of the report previously submitted under in NSPM letter L-PI-19-015, dated April 18, 2019, (NRC ADAMS Accession Number ML19108A291) and incorporates revised reporting guidance of PINGP TS 5.6.7, which the NRC approved with PINGP Unit 1 and Unit 2 license amendments 241 and 229, respectively, by letter dated November 1, 2022. (NRC ADAMS Accession Number ML22300A223)

PINGP Unit 1 has two Framatome Model 56/19 Replacement Steam Generators (RSGs)

(see Figure 1 - Steam Generator Schematic) with approximately 5,600 square meters of heat transfer area utilizing tubes with 19 millimeter outside diameter. Each RSG has 4,868 thermally-treated Alloy 690 u-tubes manufactured by Sandvik which have an outside diameter of 0.750 inch and a nominal wall thickness of 0.043 inch. The tubes are configured in a square pitch of 1.0425 inches with 55 rows and 114 columns (see Figure 2).

The tube u-bends vary in radius from 2.7000 inches for a row 1 tube to 58.9950 inches for a row 55 tube. The tubes vary in length from 738.16 inches for row 1 tubes to 923.04 inches for row 55 tubes. Row 1 through row 9 tubes were subject to stress relieving following the bending process using the thermal treatment process for an additional 2 hour2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br /> minimum soak time. The tubes were hydraulically expanded at each end for the full depth of the tubesheet with the expansion transition being between 0.079 inches and 0.236 inches below the secondary tubesheet face.

The tubesheet is low alloy steel 21.46 inches thick with alloys 82 and 182 cladding 0.375 inches thick for an overall thickness of 21.835 inches. The tubes are supported by eight tube support plates (TSPs) and five anti-vibration bars (AVBs) intersecting tubes between 1, 3, 5, 7 and 9 times (see Figure 3). There is one straight bar that intersects all rows at the center of each bend, two 57 degree bars that intersect rows 13 through 55 and two 14 degree bars that intersect rows 25 through 55. In addition, there are 24 peripheral tubes with nine staples (one at each AVB location) that carry the entire load of the complete AVB assembly. All TSPs are constructed from Type 410 stainless steel. The TSPs have a minimum thickness of 1.18 inch and have quatrefoil-shaped holes through which the tubes pass. The AVBs are constructed from Type 405 stainless steel and are rectangular in cross section (nominally 0.5 inch by 0.3 inch).

Each RSG is equipped with a Loose Parts Trapping Systems (LPTS), which is composed of screens at the top of the downcomer and at the top of the primary separators (cyclones).

These screens (0.14 inch square mesh formed from 0.031 inch diameter wire), prevent foreign material from entering the steam generator tube area from the main feedwater and auxiliary feedwater systems (see Figure 3).

Page 1 of 39

Figure 1 E RUM BOILI G SECTIO AND TUBE BUN L C AN EL HEAD Page 2 of 39

Figure 2 110 105 100 95 90 85 80 75 70 65 60 55 50 45 40 35 30 25 20 15 10 5 55 55 50 50 45 45 40 40 35 35 30 30 25 25 20 20 15 15 10 10 5 5 110 105 100 95 90 85 80 75 70 65 60 55 50 45 40 35 30 25 20 15 10 5 Page 3 of 39

Figure 3 LPP£RMOST TSP The original PINGP Unit 1 Westinghouse Model 51 Steam Generators (SGs) were replaced during the 2004 refueling outage after 25.73 effective full power years (EFPY) of operation.

During the 2006 refueling outage the first inservice inspection (100% full length bobbin) was conducted on the RSGs after accumulating the initial 1.36 EFPY of RSG operation.

Based on the lack of a definitive root cause for TSP wear and only a single cycle growth rate trend for both AVB and TSP wear identified during 1R24, NSPM conservatively elected to inspect the RSGs during 1R25 (2008 refueling outage) after an additional 1.62 EFPY of RSG operation (2.98 RSG cumulative EFPY). Based on the inspection results of both 1R24 and 1R25, NSPM elected to skip two inspections (1R26 and 1R27; 2009 and 2011 refueling outages, respectively) and perform an inspection of the RSGs during 1R28 (2012 refueling outage) after an additional 4.17 EFPY of RSG operation (7.15 RSG cumulative EFPY). Based on the inspection results of 1R28, NSPM elected to skip two additional inspections (1R29 and 1R30; 2014 and 2016 refueling outages, respectively) and perform an inspection of the RSGs during 1R31 (2018 refueling outage) after an additional 5.17 EFPY of RSG operation (12.32 RSG cumulative EFPY).

There was no operational leakage reported during this operating interval. The nominal THOT during the inspection interval was 590.5 degrees F. There were no Degradation Assessment defined sub-populations of tubes with increased degradation susceptibility.

There were no deviations taken from Mandatory and/or Needed (Shall) requirements important to tube integrity from the Electric Power Research Institute (EPRI) Guidelines referenced by Nuclear Energy Institute (NEI) 97-06 since the last inspection.

Italicized text represents technical specification excerpts. Each excerpt is followed by the appropriate information intended to address each specific requirement and includes additional details based on benchmarking previous NOTE: submittals, Staff requests for additional information of peer Licensees, and EPRI Tube Integrity Assessment Guidelines reporting requirements. A legend of codes and field names is included at the end of the report.

5.6.7 Steam Generator Tube Inspection Report A report shall be submitted within 180 days after the initial entry into MODE 4 following completion of an inspection performed in accordance with the Specification 5.5.8, Steam Generator (SG) Program.

Page 4 of 39

Timing of the submittal of this revised report is based on receipt of PINGP Unit 1 and Unit 2 license amendments 241 and 229, the license amendment request for which noted submittal of the revised report will be completed within 30 days of implementation.

The report shall include:

a. The scope of inspections performed on each SG, Table 1 and the notes that follow, provides the scope of inspections performed during 1R31. There was no NDE inspection scope expansion required during Prairie Island 1R31.

TABLE 1 SCOPE LEG EXTENT TECHNIQUE SG 11 SG 12 Row 7 through H/C F/L X-Probe' 100%(4178) 100%(4177) 55 Row 3 through 6 H AV5TEH X-Probe' 100%(456) 100%(456)

Row 1 and 2 H 08HTEH X-Probe' 100%(228) 100%(228)

Row 1 and 2 H/C Various Bobbin 100%(228) 100%(228)

Row 1 and 2 C 08CTEC X-Probe' 100%(228) 100%(228)

Row 3 through 6 C AV5TEC X-Probe' 100%(456) 100%(456)

Post Plugging H/C N/A Visual 100%(4) 100%(10)

Upper Internals N/A N/A Visual 100% 100%

Top of H/C N/A Visual 100% 100%

Tubesheet In-bundle H/C N/A Visual ~17% ~17%

PLP FOSAR H/C N/A Visual 100%(2) N/A Notes:

The X-Probe' deployed contained both a standard bobbin coil and a 16 coil array of transmit/receive coils.

The scope of inspections is provided as a percentage of the open tubes (or plugs) followed by the total number of tests parenthetically (where practical).

No tubes were plugged during the RSG manufacturing or prior to service.

Six tubes were plugged in SG 11 and seven tubes were plugged in SG 12 during previous inspections (1R24, 1R25 and 1R28).

The Row 7 through 55 inspections were completed from both legs (either hot or cold) over the full length (F/L) of each tube (TEHTEC or TECTEH).

Row 1 and 2 bobbin inspections were performed using various extents (08CTEH, 08HTEC, 07HTEC or AV5TEH and AV5TEC).

Post tube plugging visual inspections were conducted by Engineering to validate the tube plug location and proper insertion.

Inspections of the upper internals included the visual inspections of all bolted closures (manways and camera ports), Feedwater Ring (including J-tubes and antistratification (helix) device), Primary Separators (cyclones) Loose Parts Trapping System (LPTS) screens, Downcomer LPTS screens and wrapper position per NRC Generic Letter 97-06 Page 5 of 39

and Prairie Island Unit 1 56/19 Replacement Steam Generator Operation and Maintenance Manual.

Tube lane and periphery of the tube bundle inspected using a camera transport system.

Random fiber-optic inspection of one out of every six columns.

Foreign Object Search and Retrieval of possible loose part (PLP) indications for evaluation and possible removal based on eddy current results (SG 11 only - no PLPs detected in SG 12).

b. The nondestructive examination techniques utilized for tubes with increased degradation susceptibility, PINGP does not have any specifically identified tubing areas with an increased degradation susceptibility. This fact notwithstanding, as described in Table 1 above, the X-Probe' was utilized on 100% of the tubing full length (from tube end to tube end) except for portions of rows 1 through 5 u-bends.
c. For each degradation mechanism found:
1. The nondestructive examination techniques utilized; Primary Side Inspections:

AVB wear and TSP wear were the only degradation mechanisms found in both SGs during 1R31. The findings of the 1R31 steam generator examination are bounded by the through wall depth behavior projected in the 1R28 operational assessment. Specifically, the deepest %TW sizing of any AVB wear indication by either bobbin or array probe observed during U1R31 was measured at 27% TW. This indication in SG12 tube R42C54 is considerably less than the worst case projected AVB support wear indication of 33%TW from the U1R28 Operational Assessment (OA). Additionally, the deepest %TW sizing of any TSP wear indication by either bobbin or array probe observed during U1R31 was measured at 22% TW. This indication in SG11 tube R47C87 is considerably less than the worst case projected TSP wear indication of 34%TW from the U1R28 OA. In addition to none of AVB or TSP wear indications approaching the condition monitoring (CM) limit, the Upper 95th growth rates from 1R31 have decreased slightly for AVB wear and increased slightly for TSP wear as compared to 1R28 and the actual number of indications reported in 1R31 is less than the projected number of indications in the 1R28 operational assessment.

Table 2 and the notes that follow, provide the Electric Power Research Institute (EPRI)

Examination Technique Specification Sheet (ETSS) (techniques) utilized during 1R31 for existing and potential degradation.

Page 6 of 39

TABLE 2 CLASSIFICATION MECHANISM LOCATION PROBE TECHNIQUE Bobbin 96004.1 Rev. 13 Existing Wear TSP X-Probe' 11956.1 Rev. 3 AVB and Bobbin M96041.1 Rev. 5 Existing Wear Staple X-Probe' M17909.2 Rev. 1 Bobbin 27091.2 Rev. 2 Potential Wear PLP X-Probe' 1790X.Y Rev. 0

+Point' 2790Z.1 Rev. #

Bobbin 13091.1 Rev. 0 Potential Wear Tube-to-Tube X-Probe' 13902.1 Rev. 0

+Point' 13901.1 Rev. 1 Notes:

Existing or Potential degradation as defined in the EPRI SGMP: Steam Generator Integrity Assessment Guidelines, Revision 4.

Each listed technique was site validated for both detection and sizing except for PLP wear with the Bobbin probe which utilized the above listed technique for detection while sizing would have been based on the X-Probe' and/or +Point' had PLP wear been detected. In addition, bobbin ETSSs 96010.1 Rev. 7, 24013.1 Rev. 2 and 96007.1 Rev.

12 were site validated for use on non-degradation (MBMs, DNGs, PDSs and cold laps).

M indicates the cited ETSS is an Appendix I qualified technique with system performance quantified using Model Assisted Probability of Detection (MAPOD).

X represents 1 through 6 where the user selects the best EPRI ETSS based on the as found wear scar shape, Y represents .1 or .3 based on the applicable coil detection set and the user applies the published performance indices for that ETSS.

Z represents 1 through 7 where the user selects the best EPRI ETSS based on the as found wear scar shape, # represents the current revision and the user applies the published performance indices for that ETSS.

2. The location, orientation (if linear), measured size (if available), and voltage response for each indication. For tube wear at support structures less than 20 percent through-wall, only the total number of indications needs to be reported; Tables 3 and 4 provide the location, orientation and measured size of each reported AVB wear indication in each steam generator respectively for the degradation found during 1R31. All the tubes in these two tables were returned to service.

Tables 5 and 6 provide the location, orientation and measured size of each reported TSP wear indication in each steam generator respectively for the degradation found during 1R31. All the tubes in these two tables were returned to service.

Tables 7 and 8 provide the location, orientation and measured sizes of AVB and TSP wear indications in each steam generator respectively for tubes preventively plugged during 1R31. The preventive tube plugging criteria implemented during 1R31 was any wear Page 7 of 39

indication greater than or equal to 21% through wall as measured by either the bobbin or array coil.

Within Tables 4 through 6, sixteen tubes with a UTIL2 NCA code were detected by the bobbin coil and not confirmed by the array coil. Within Tables 3 through 8, twelve tubes (with 21 indication locations) were reported with multiple VOL calls at the same ROW/COL/LOC/PROBE which would confirm indications of double sided AVB wear or multiple wear location sites on multiple land contact points of a single Quatrefoil TSP.

Conversely, all VOL calls at the same ROW/COL/LOC/PROBE confirm only single sided wear sites at all the remaining AVB and TSP locations.

A legend of fields and codes with brief explanations is provided at the end of this enclosure for clarification purposes.

TABLE 3 Steam Generator 11 AVB Wear Tube # Ind # Row Col Volts Ind Pct Locn Inch1 Inch2 Length PType Util1 Util2 Util3 1 1 51 41 0.65 VOL 12 AV3 -0.14 0.26 0.40 Array WAR TPR 1 1 51 41 0.17 AVB 6 AV3 0.12 Bobbin CBA 1 2 51 41 0.29 VOL 9 AV4 -0.20 0.20 0.40 Array WAR FLT NBC 1 3 51 41 0.44 VOL 10 AV5 -0.23 0.20 0.43 Array WAR TPR 1 3 51 41 0.16 AVB 6 AV5 0.12 Bobbin CBA 2 4 52 41 0.4 VOL 10 AV5 -0.09 0.46 0.55 Array WAR TPR 2 4 52 41 0.13 AVB 5 AV5 0.29 Bobbin CBA 3 5 50 42 0.24 VOL 8 AV3 -0.26 0.09 0.35 Array WAR TPR NBC 4 6 42 45 1.18 VOL 16 AV2 -0.37 0.25 0.62 Array WAR FLT 4 6 42 45 0.48 AVB 13 AV2 -0.06 Bobbin CBA 4 7 42 45 0.41 VOL 10 AV7 -0.31 -0.06 0.25 Array WAR FLT 4 7 42 45 0.15 AVB 5 AV7 -0.11 Bobbin CBA 5 8 49 49 0.2 VOL 8 AV6 -0.14 0.23 0.37 Array WAR TPR NBC 5 9 49 49 0.51 VOL 11 AV7 -0.52 0.26 0.78 Array WAR TPR 5 9 49 49 0.13 AVB 5 AV7 -0.09 Bobbin CBA 6 10 45 50 0.25 VOL 8 AV5 -0.42 0.28 0.70 Array WAR FLT NBC 7 11 49 53 0.39 VOL 9 AV3 -0.34 0.25 0.59 Array WAR FLT NBC 7 12 49 53 0.51 VOL 11 AV5 -0.23 0.31 0.54 Array WAR FLT 7 12 49 53 0.19 AVB 6 AV5 0.00 Bobbin CBA 7 13 49 53 1.46 VOL 18 AV6 -0.34 0.48 0.82 Array WAR FLT 7 13 49 53 0.47 AVB 13 AV6 -0.03 Bobbin CBA 7 14 49 53 0.66 VOL 12 AV7 -0.25 0.25 0.50 Array WAR FLT 7 14 49 53 0.14 AVB 4 AV7 -0.03 Bobbin CBA 8 15 41 54 0.34 VOL 9 AV8 -0.23 0.31 0.54 Array WAR TPR NBC 9 16 40 56 0.44 VOL 10 AV4 -0.23 0.20 0.43 Array WAR TPR 9 16 40 56 0.1 AVB 3 AV4 0.11 Bobbin CBA 10 17 33 57 0.77 VOL 13 AV3 -0.28 0.34 0.62 Array WAR TPR 10 17 33 57 0.17 AVB 5 AV3 0.14 Bobbin CBA Page 8 of 39

TABLE 3 Steam Generator 11 AVB Wear Tube # Ind # Row Col Volts Ind Pct Locn Inch1 Inch2 Length PType Util1 Util2 Util3 10 18 33 57 0.22 AVB 7 AV4 0.11 Bobbin CBA 10 18 33 57 0.79 VOL 13 AV4 0.25 0.87 0.62 Array WAR TPR 10 19 33 57 0.42 VOL 10 AV5 -0.31 0.23 0.54 Array WAR TPR 10 19 33 57 0.53 VOL 11 AV5 -0.25 0.34 0.59 Array WAR TPR 10 19 33 57 0.28 AVB 9 AV5 0.08 Bobbin CBA 10 20 33 57 0.66 VOL 12 AV6 -0.37 0.37 0.74 Array WAR TPR 10 20 33 57 0.25 AVB 8 AV6 0.03 Bobbin CBA 10 21 33 57 0.28 VOL 8 AV7 -0.39 0.31 0.70 Array WAR TPR NBC 10 22 33 57 0.62 VOL 12 AV8 -0.34 0.31 0.65 Array WAR TPR 10 22 33 57 0.21 AVB 7 AV8 0.06 Bobbin CBA 10 23 33 57 1.06 VOL 15 AV9 -0.23 0.31 0.54 Array WAR TPR 10 23 33 57 0.4 AVB 12 AV9 0.08 Bobbin CBA 11 24 42 59 0.42 VOL 9 AV6 -0.14 0.28 0.42 Array WAR FLT 11 24 42 59 0.11 AVB 4 AV6 0.23 Bobbin CBA 12 25 46 61 0.13 VOL 7 AV3 -0.11 0.08 0.19 Array WAR TPR 12 25 46 61 0.08 AVB 3 AV3 -0.06 Bobbin CBA 12 26 46 61 0.4 VOL 10 AV4 -0.17 0.25 0.42 Array WAR FLT 12 26 46 61 0.15 AVB 5 AV4 -0.06 Bobbin CBA 12 27 46 61 0.28 VOL 9 AV6 -0.23 0.25 0.48 Array WAR TPR 12 27 46 61 0.09 AVB 3 AV6 0.03 Bobbin CBA 13 28 40 62 0.28 VOL 8 AV7 -0.08 0.23 0.31 Array WAR FLT 13 28 40 62 0.13 AVB 4 AV7 0.14 Bobbin CBA 14 29 48 62 1.1 VOL 16 AV3 -0.14 0.31 0.45 Array WAR TPR 14 29 48 62 0.31 AVB 10 AV3 0.14 Bobbin CBA 14 30 48 62 0.49 VOL 10 AV5 -0.25 0.28 0.53 Array WAR FLT 14 30 48 62 0.32 VOL 9 AV5 -0.23 0.25 0.48 Array WAR TPR 14 30 48 62 0.24 AVB 8 AV5 -0.03 Bobbin CBA 14 31 48 62 0.36 VOL 9 AV6 -0.20 0.23 0.43 Array WAR FLT 14 31 48 62 0.08 AVB 3 AV6 0.03 Bobbin CBA 14 32 48 62 0.37 VOL 9 AV9 -0.14 0.17 0.31 Array WAR TPR NBC 15 33 50 65 0.27 VOL 8 AV6 -0.11 0.08 0.19 Array WAR TPR 15 33 50 65 0.24 AVB 7 AV6 -0.08 Bobbin CBA 15 33 50 65 0.42 VOL 10 AV6 -0.06 0.42 0.48 Array WAR TPR 15 34 50 65 0.59 VOL 11 AV7 -0.14 0.40 0.54 Array WAR FLT 15 34 50 65 0.24 AVB 7 AV7 0.00 Bobbin CBA 16 35 46 67 0.38 VOL 9 AV2 -0.17 0.20 0.37 Array WAR TPR NBC 16 36 46 67 0.31 VOL 9 AV5 -0.20 0.17 0.37 Array WAR NBC TPR 17 37 48 67 0.62 VOL 12 AV5 -0.17 0.26 0.43 Array WAR TPR 17 37 48 67 0.18 AVB 6 AV5 -0.06 Bobbin CBA 18 38 53 68 0.57 VOL 11 AV5 -0.12 0.20 0.32 Array WAR TPR Page 9 of 39

TABLE 3 Steam Generator 11 AVB Wear Tube # Ind # Row Col Volts Ind Pct Locn Inch1 Inch2 Length PType Util1 Util2 Util3 18 38 53 68 0.1 AVB 3 AV5 0.06 Bobbin CBA 19 39 53 69 0.47 VOL 10 AV6 -0.20 0.29 0.49 Array WAR FLT 19 39 53 69 0.14 AVB 5 AV6 0.20 Bobbin CBA 20 40 47 72 0.25 VOL 8 AV3 -0.09 0.12 0.21 Array WAR TPR 20 40 47 72 0.09 AVB 3 AV3 -0.06 Bobbin CBA TABLE 4 Steam Generator 12 AVB Wear Tube # Ind # Row Col Volts Ind Pct Locn Inch1 Inch2 Length PType Util1 Util2 Util3 1 1 12 35 0.39 VOL 10 AV5 -0.20 0.23 0.43 Array WAR TPR 1 1 12 35 0.17 AVB 6 AV5 0.00 Bobbin CBA 2 2 50 40 0.46 VOL 10 AV8 -0.23 0.25 0.48 Array WAR FLT 2 2 50 40 0.16 AVB 5 AV8 0.06 Bobbin CBA 3 3 51 42 0.74 VOL 13 AV4 -0.31 0.17 0.48 Array WAR FLT 3 3 51 42 0.15 AVB 5 AV4 -0.03 Bobbin CBA 4 4 45 43 0.39 VOL 10 AV4 -0.23 0.11 0.34 Array WAR TPR 4 4 45 43 0.17 AVB 6 AV4 -0.03 Bobbin CBA 5 5 50 45 0.6 VOL 11 AV6 -0.42 0.23 0.65 Array WAR TPR 5 5 50 45 0.13 AVB 5 AV6 -0.03 Bobbin CBA 5 6 50 45 0.84 VOL 13 AV7 -0.17 0.37 0.54 Array WAR TPR 5 6 50 45 0.24 AVB 9 AV7 0.14 Bobbin CBA 6 7 49 46 0.36 VOL 9 AV3 -0.23 0.31 0.54 Array WAR TPR NBC 7 8 50 49 0.98 VOL 15 AV3 -0.25 0.25 0.50 Array WAR FLT 7 8 50 49 0.3 AVB 10 AV3 0.14 Bobbin CBA 7 9 50 49 0.31 VOL 9 AV4 -0.23 0.20 0.43 Array WAR FLT 7 9 50 49 0.16 AVB 5 AV4 -0.03 Bobbin CBA 7 10 50 49 0.77 VOL 13 AV5 -0.25 0.31 0.56 Array WAR FLT 7 10 50 49 0.21 AVB 7 AV5 0.06 Bobbin CBA 8 11 42 50 0.38 VOL 9 AV4 -0.17 0.25 0.42 Array WAR TPR NBC 8 12 42 50 0.51 VOL 11 AV5 -0.23 0.25 0.48 Array WAR FLT 8 12 42 50 0.24 AVB 8 AV5 0.03 Bobbin CBA 9 13 48 50 0.97 VOL 14 AV3 -0.25 0.25 0.50 Array WAR TPR 9 13 48 50 0.29 AVB 9 AV3 0.14 Bobbin CBA 9 14 48 50 0.47 VOL 10 AV4 -0.28 0.14 0.42 Array WAR FLT 9 14 48 50 0.26 AVB 9 AV4 0.11 Bobbin CBA 9 15 48 50 1.19 VOL 16 AV5 -0.25 0.28 0.53 Array WAR FLT 9 15 48 50 0.36 AVB 11 AV5 0.00 Bobbin CBA 9 16 48 50 1.11 VOL 16 AV6 -0.25 0.28 0.53 Array WAR FLT 9 16 48 50 0.4 AVB 12 AV6 -0.03 Bobbin CBA 10 17 48 52 0.49 VOL 9 AV3 -0.27 0.27 0.54 Array WAR TPR Page 10 of 39

TABLE 4 Steam Generator 12 AVB Wear Tube # Ind # Row Col Volts Ind Pct Locn Inch1 Inch2 Length PType Util1 Util2 Util3 10 17 48 52 0.09 AVB 3 AV3 -0.09 Bobbin CBA 10 18 48 52 0.28 VOL 8 AV5 -0.15 0.30 0.45 Array TPR NBC 11 19 35 53 0.63 VOL 12 AV1 -0.18 0.28 0.46 Array WAR FLT 11 19 35 53 0.25 AVB 8 AV1 -0.03 Bobbin CBA 11 20 35 53 0.68 VOL 12 AV2 -0.17 0.31 0.48 Array WAR FLT 11 20 35 53 0.25 AVB 8 AV2 0.14 Bobbin CBA 11 21 35 53 1.25 VOL 17 AV3 -0.14 0.37 0.51 Array WAR TPR 11 21 35 53 0.41 AVB 13 AV3 0.17 Bobbin CBA 11 22 35 53 0.56 VOL 11 AV4 -0.20 0.31 0.51 Array WAR FLT 11 22 35 53 0.21 AVB 7 AV4 0.00 Bobbin CBA 11 23 35 53 1.55 VOL 19 AV5 -0.23 0.37 0.60 Array WAR FLT 11 23 35 53 0.45 AVB 14 AV5 -0.03 Bobbin CBA 11 24 35 53 0.46 VOL 10 AV6 -0.17 0.31 0.48 Array WAR FLT 11 24 35 53 0.23 AVB 8 AV6 0.14 Bobbin CBA 11 25 35 53 0.72 VOL 12 AV7 -0.20 0.31 0.51 Array WAR FLT 11 25 35 53 0.25 AVB 8 AV7 0.11 Bobbin CBA 11 26 35 53 0.87 VOL 14 AV8 -0.20 0.34 0.54 Array WAR FLT 11 26 35 53 0.32 AVB 10 AV8 -0.03 Bobbin CBA 11 27 35 53 1.11 VOL 16 AV9 -0.17 0.37 0.54 Array WAR FLT 11 27 35 53 0.44 AVB 14 AV9 -0.06 Bobbin CBA 12 28 47 53 0.61 VOL 11 AV5 -0.14 0.42 0.56 Array WAR FLT 12 28 47 53 0.28 AVB 10 AV5 0.17 Bobbin CBA 12 29 47 53 1.65 VOL 20 AV6 -0.23 0.37 0.60 Array WAR FLT 12 29 47 53 0.57 AVB 18 AV6 -0.03 Bobbin CBA 12 30 47 53 1.13 VOL 16 AV7 -0.20 0.37 0.57 Array WAR FLT 12 30 47 53 0.34 AVB 12 AV7 -0.06 Bobbin CBA 13 31 54 54 0.41 VOL 10 AV4 -0.34 0.25 0.59 Array WAR TPR 13 31 54 54 0.15 AVB 6 AV4 -0.08 Bobbin CBA 13 32 54 54 0.38 VOL 9 AV5 -0.17 0.20 0.37 Array WAR TPR 13 32 54 54 0.14 AVB 6 AV5 -0.11 Bobbin CBA 13 33 54 54 1.45 VOL 18 AV6 -0.20 0.37 0.57 Array WAR TPR 13 33 54 54 0.49 VOL 10 AV6 -0.20 0.17 0.37 Array WAR TPR 13 33 54 54 0.52 AVB 17 AV6 -0.08 Bobbin CBA 13 34 54 54 1.09 VOL 15 AV7 -0.17 0.40 0.57 Array WAR TPR 13 34 54 54 0.32 AVB 11 AV7 -0.03 Bobbin CBA 13 35 54 54 1.17 VOL 16 AV8 -0.17 0.40 0.57 Array WAR TPR 13 35 54 54 0.73 VOL 13 AV8 -0.14 0.45 0.59 Array WAR TPR 13 35 54 54 0.57 AVB 18 AV8 0.00 Bobbin CBA 14 36 51 55 0.32 VOL 9 AV3 -0.14 0.20 0.34 Array WAR FLT 14 36 51 55 0.09 AVB 3 AV3 0.06 Bobbin CBA Page 11 of 39

TABLE 4 Steam Generator 12 AVB Wear Tube # Ind # Row Col Volts Ind Pct Locn Inch1 Inch2 Length PType Util1 Util2 Util3 15 37 52 55 0.23 VOL 8 AV7 -0.17 0.20 0.37 Array WAR FLT NBC 16 38 42 58 0.27 VOL 8 AV6 0.00 0.26 0.26 Array WAR TPR NBC 16 39 42 58 0.93 VOL 14 AV7 -0.12 0.43 0.55 Array WAR FLT 16 39 42 58 0.31 AVB 10 AV7 0.12 Bobbin CBA 16 40 42 58 0.35 VOL 9 AV8 -0.06 0.26 0.32 Array WAR TPR NBC 17 41 47 58 0.45 VOL 10 AV3 -0.37 -0.03 0.34 Array WAR FLT 17 41 47 58 0.17 AVB 6 AV3 -0.14 Bobbin CBA 17 42 47 58 0.86 VOL 14 AV4 -0.42 0.03 0.45 Array WAR FLT 17 42 47 58 0.26 AVB 9 AV4 -0.17 Bobbin CBA 17 43 47 58 0.45 VOL 10 AV5 -0.31 0.11 0.42 Array WAR FLT NBC 17 44 47 58 0.31 VOL 9 AV6 -0.25 0.11 0.36 Array WAR FLT NBC 18 45 33 60 0.17 VOL 7 AV4 -0.26 0.00 0.26 Array WAR TPR NBC 18 46 33 60 0.67 VOL 12 AV7 -0.23 0.17 0.40 Array WAR TPR 18 46 33 60 0.18 AVB 7 AV7 0.06 Bobbin CBA 19 47 39 61 0.24 VOL 8 AV2 -0.20 0.12 0.32 Array WAR TPR NBC 19 48 39 61 0.65 VOL 12 AV3 -0.35 0.17 0.52 Array WAR TPR 19 48 39 61 0.22 AVB 8 AV3 -0.06 Bobbin CBA 19 49 39 61 0.37 VOL 9 AV4 -0.29 0.14 0.43 Array WAR TPR 19 49 39 61 0.11 AVB 4 AV4 -0.06 Bobbin CBA 20 50 54 61 0.39 VOL 9 AV3 -0.28 0.28 0.56 Array WAR FLT 20 50 54 61 0.16 AVB 6 AV3 -0.03 Bobbin CBA 20 51 54 61 0.32 VOL 8 AV4 -0.34 0.25 0.59 Array WAR FLT NBC 21 52 55 61 0.66 VOL 12 AV9 -0.14 0.46 0.60 Array WAR FLT 21 52 55 61 0.17 AVB 6 AV9 0.11 Bobbin CBA 22 53 41 64 0.27 VOL 8 AV2 -0.23 0.14 0.37 Array WAR FLT 22 53 41 64 0.16 AVB 6 AV2 -0.06 Bobbin CBA 22 54 41 64 1.02 VOL 15 AV3 -0.26 0.29 0.55 Array WAR FLT 22 54 41 64 0.42 AVB 14 AV3 0.06 Bobbin CBA 22 55 41 64 0.4 VOL 10 AV4 -0.32 0.20 0.52 Array WAR FLT 22 55 41 64 0.18 AVB 7 AV4 0.03 Bobbin CBA 22 56 41 64 0.28 VOL 8 AV5 -0.23 0.17 0.40 Array WAR FLT 22 56 41 64 0.25 AVB 9 AV5 -0.03 Bobbin CBA 22 57 41 64 0.86 VOL 14 AV6 -0.29 0.23 0.52 Array WAR FLT 22 57 41 64 0.29 AVB 10 AV6 -0.09 Bobbin CBA 23 58 35 65 0.36 VOL 9 AV4 -0.32 0.09 0.41 Array WAR TPR 23 58 35 65 0.09 AVB 3 AV4 0.00 Bobbin CBA 24 59 47 65 0.13 AVB 5 AV2 0.00 Bobbin NCA 24 60 47 65 0.79 VOL 13 AV3 -0.23 0.26 0.49 Array WAR TPR 24 60 47 65 0.2 AVB 7 AV3 0.11 Bobbin CBA 24 61 47 65 0.33 VOL 9 AV4 -0.55 0.06 0.61 Array WAR TPR Page 12 of 39

TABLE 4 Steam Generator 12 AVB Wear Tube # Ind # Row Col Volts Ind Pct Locn Inch1 Inch2 Length PType Util1 Util2 Util3 24 61 47 65 0.13 AVB 5 AV4 -0.17 Bobbin CBA 24 62 47 65 0.6 VOL 11 AV5 -0.37 0.23 0.60 Array WAR FLT 24 62 47 65 0.45 VOL 10 AV5 -0.26 0.17 0.43 Array WAR FLT 24 62 47 65 0.35 AVB 12 AV5 -0.03 Bobbin CBA 25 63 31 66 0.28 VOL 9 AV7 -0.29 -0.03 0.26 Array WAR TPR 25 63 31 66 0.09 AVB 3 AV7 -0.23 Bobbin CBA 26 64 39 66 0.46 VOL 10 AV3 -0.32 0.14 0.46 Array WAR TPR 26 64 39 66 0.1 AVB 4 AV3 -0.12 Bobbin CBA 26 65 39 66 1.08 VOL 15 AV4 -0.38 0.17 0.55 Array WAR FLT 26 65 39 66 0.45 AVB 14 AV4 0.03 Bobbin CBA 26 66 39 66 0.42 VOL 10 AV5 -0.29 0.26 0.55 Array WAR TPR 26 66 39 66 0.17 AVB 6 AV5 0.09 Bobbin CBA 26 67 39 66 0.97 VOL 14 AV6 -0.35 0.23 0.58 Array WAR TPR 26 67 39 66 0.32 AVB 11 AV6 -0.12 Bobbin CBA 26 68 39 66 1.65 VOL 20 AV7 -0.38 0.20 0.58 Array WAR TPR 26 68 39 66 0.48 AVB 15 AV7 -0.12 Bobbin CBA 26 69 39 66 0.71 VOL 12 AV8 -0.32 0.17 0.49 Array WAR TPR 26 69 39 66 0.23 AVB 8 AV8 -0.09 Bobbin CBA 27 70 51 66 0.31 VOL 9 AV4 -0.32 0.12 0.44 Array WAR TPR NBC 27 71 51 66 0.49 VOL 10 AV6 -0.38 0.09 0.47 Array WAR TPR NBC 27 72 51 66 0.42 VOL 10 AV7 -0.35 0.06 0.41 Array WAR TPR NBC 28 73 41 67 0.26 VOL 8 AV7 0.06 0.32 0.26 Array WAR TPR NBC 29 74 37 69 0.24 VOL 8 AV3 -0.26 0.06 0.32 Array WAR TPR NBC 29 75 37 69 0.17 VOL 7 AV4 -0.17 0.09 0.26 Array WAR TPR NBC 29 76 37 69 0.08 AVB 3 AV6 -0.29 Bobbin CBA 29 76 37 69 0.23 VOL 8 AV6 -0.26 0.00 0.26 Array WAR TPR 30 77 42 71 0.23 VOL 8 AV3 -0.12 0.14 0.26 Array WAR TPR NBC 30 78 42 71 0.41 VOL 10 AV6 -0.03 0.32 0.35 Array WAR TPR 30 78 42 71 0.09 AVB 3 AV6 0.00 Bobbin CBA 31 79 47 73 0.58 VOL 11 AV4 -0.34 0.34 0.68 Array WAR TPR 31 79 47 73 0.15 AVB 5 AV4 -0.03 Bobbin CBA 31 80 47 73 0.59 VOL 11 AV5 -0.34 0.28 0.62 Array WAR TPR 31 80 47 73 0.1 AVB 4 AV5 -0.03 Bobbin CBA 32 81 51 74 0.48 VOL 10 AV4 -0.25 0.22 0.47 Array WAR TPR 32 81 51 74 0.12 AVB 4 AV4 -0.08 Bobbin CBA 33 82 39 79 0.2 VOL 8 AV4 -0.20 0.06 0.26 Array WAR TPR 33 82 39 79 0.11 AVB 4 AV4 0.00 Bobbin CBA 33 83 39 79 0.77 VOL 13 AV5 -0.32 0.23 0.55 Array WAR TPR 33 83 39 79 0.18 AVB 6 AV5 0.00 Bobbin CBA 33 84 39 79 0.81 VOL 13 AV6 -0.26 0.29 0.55 Array WAR TPR Page 13 of 39

TABLE 4 Steam Generator 12 AVB Wear Tube # Ind # Row Col Volts Ind Pct Locn Inch1 Inch2 Length PType Util1 Util2 Util3 33 84 39 79 0.21 AVB 7 AV6 0.03 Bobbin CBA 33 85 39 79 0.21 VOL 8 AV8 -0.20 0.00 0.20 Array WAR TPR 33 85 39 79 0.09 AVB 3 AV8 -0.12 Bobbin CBA 33 86 39 79 0.18 VOL 8 AV9 -0.20 0.12 0.32 Array WAR TPR NBC TABLE 5 Steam Generator 11 TSP Wear Tube # Ind # Row Col Volts Ind Pct Locn Inch1 Inch2 Length PType Util1 Util2 Util3 1 1 3 1 0.39 VOL 15 05H -1.04 -0.55 0.49 Array WAR TPR 1 1 3 1 0.08 WAR 7 05H -0.81 Bobbin CBA 1 2 3 1 0.78 VOL 20 04C 0.23 0.70 0.47 Array WAR TPR 1 2 3 1 0.15 WAR 13 04C 0.37 Bobbin CBA 2 3 5 1 0.43 VOL 16 05C -0.90 -0.53 0.37 Array WAR TPR 2 3 5 1 0.1 WAR 9 05C -0.76 Bobbin CBA 3 4 6 6 0.41 VOL 15 04C -0.90 -0.42 0.48 Array WAR TPR 3 4 6 6 0.13 WAR 11 04C -0.73 Bobbin CBA 4 5 25 8 0.37 VOL 15 05C -0.93 -0.61 0.32 Array WAR TPR 4 5 25 8 0.15 WAR 13 05C -0.70 Bobbin CBA 5 6 27 9 0.36 VOL 14 06C -0.96 -0.64 0.32 Array WAR TPR NBC 6 7 30 10 0.26 VOL 13 05C -0.84 -0.64 0.20 Array WAR TPR NBC 7 8 32 12 0.75 VOL 19 06C -0.96 -0.58 0.38 Array WAR TPR 7 8 32 12 0.17 WAR 14 06C -0.72 Bobbin CBA 8 9 33 14 0.5 VOL 16 06C -0.93 -0.55 0.38 Array WAR TPR 8 9 33 14 0.14 WAR 12 06C -0.76 Bobbin CBA 9 10 34 14 0.82 VOL 20 06C -0.95 -0.46 0.49 Array WAR TPR 9 10 34 14 0.16 WAR 13 06C -0.72 Bobbin CBA 10 11 36 16 0.42 VOL 15 05C -0.87 -0.55 0.32 Array WAR TPR NBC 11 12 23 17 0.29 VOL 13 04H -0.95 -0.66 0.29 Array WAR TPR 11 12 23 17 0.12 WAR 10 04H -0.75 Bobbin CBA 12 13 37 18 0.47 VOL 16 04H -0.98 -0.66 0.32 Array WAR TPR 12 13 37 18 0.12 WAR 10 04H -0.78 Bobbin CBA 13 14 39 18 0.39 VOL 15 05C -0.84 -0.52 0.32 Array WAR TPR NBC 14 15 38 19 0.39 VOL 15 06C -0.96 -0.58 0.38 Array WAR TPR 14 15 38 19 0.12 WAR 10 06C -0.73 Bobbin CBA 15 16 37 20 0.4 VOL 15 06C -0.90 -0.55 0.35 Array WAR TPR 15 16 37 20 0.11 WAR 10 06C -0.70 Bobbin CBA 16 17 41 20 0.34 VOL 14 06C -0.87 -0.58 0.29 Array WAR TPR NBC 16 18 41 20 0.41 VOL 15 05C -0.90 -0.58 0.32 Array WAR TPR 16 18 41 20 0.13 WAR 11 05C -0.70 Bobbin CBA 17 19 7 23 0.35 VOL 14 04C -0.92 -0.58 0.34 Array WAR TPR Page 14 of 39

TABLE 5 Steam Generator 11 TSP Wear Tube # Ind # Row Col Volts Ind Pct Locn Inch1 Inch2 Length PType Util1 Util2 Util3 17 19 7 23 0.12 WAR 10 04C -0.63 Bobbin CBA 18 20 42 23 0.49 VOL 16 06C -0.84 -0.55 0.29 Array WAR TPR 18 20 42 23 0.09 WAR 8 06C -0.73 Bobbin CBA 19 21 38 27 0.6 VOL 18 06C -0.99 -0.55 0.44 Array WAR TPR 19 21 38 27 0.16 WAR 13 06C -0.73 Bobbin CBA 20 22 48 29 0.53 VOL 17 06H -1.01 -0.63 0.38 Array WAR TPR NBC 20 23 48 29 0.28 VOL 13 08H -1.12 -0.46 0.66 Array WAR TPR 20 23 48 29 0.09 WAR 8 08H -0.84 Bobbin CBA 21 24 41 30 0.4 VOL 15 05H -0.90 -0.61 0.29 Array WAR TPR NBC 22 25 50 37 0.08 WAR 7 02H 0.40 Bobbin NCA 22 26 50 37 0.44 VOL 16 04H -0.86 -0.37 0.49 Array WAR TPR 22 26 50 37 0.1 WAR 9 04H -0.66 Bobbin CBA 23 27 50 38 0.39 VOL 15 04H -1.07 -0.61 0.46 Array WAR TPR 23 27 50 38 0.09 WAR 8 04H -0.72 Bobbin CBA 24 28 49 39 0.32 VOL 14 08C -1.08 -0.61 0.47 Array WAR TPR NBC 25 29 51 39 0.38 VOL 15 04H -0.86 -0.32 0.54 Array WAR TPR 25 29 51 39 0.11 WAR 10 04H -0.72 Bobbin CBA 25 30 51 39 0.45 VOL 16 06H -0.92 -0.49 0.43 Array WAR TPR 25 30 51 39 0.12 WAR 10 06H -0.78 Bobbin CBA 26 31 43 40 0.28 VOL 13 05C -0.90 -0.55 0.35 Array WAR TPR NBC 27 32 51 40 0.52 VOL 17 02H 0.32 0.69 0.37 Array WAR TPR 27 32 51 40 0.18 WAR 15 02H 0.40 Bobbin CBA 27 33 51 40 0.58 VOL 17 08C -1.11 -0.50 0.61 Array WAR TPR 27 33 51 40 0.14 WAR 12 08C -0.82 Bobbin CBA 28 34 52 40 0.3 VOL 13 04H 0.26 0.52 0.26 Array WAR TPR 28 34 52 40 0.19 WAR 15 04H 0.43 Bobbin CBA 29 35 51 41 0.32 VOL 14 07H -0.93 -0.58 0.35 Array WAR TPR NBC 30 36 3 42 0.35 VOL 14 03C -0.90 -0.53 0.37 Array WAR TPR 30 36 3 42 0.1 WAR 9 03C -0.45 Bobbin CBA 31 37 22 42 0.6 VOL 18 04H -1.01 -0.64 0.37 Array WAR TPR 31 37 22 42 0.07 WAR 6 04H -0.81 Bobbin CBA 32 38 46 42 0.55 VOL 17 05C -0.87 -0.51 0.36 Array WAR TPR 32 38 46 42 0.06 WAR 6 05C -0.76 Bobbin CBA 33 39 49 42 0.27 VOL 13 05H -0.95 -0.66 0.29 Array WAR TPR NBC 34 40 51 42 0.53 VOL 17 08C -1.04 -0.61 0.43 Array WAR TPR NBC 35 41 52 42 0.34 VOL 14 06C -0.95 -0.69 0.26 Array WAR TPR NBC 36 42 53 42 0.24 VOL 12 05C -0.99 -0.73 0.26 Array WAR TPR NBC 37 43 17 43 0.35 VOL 14 05H -1.04 -0.72 0.32 Array WAR TPR 37 43 17 43 0.07 WAR 6 05H -0.87 Bobbin CBA 37 44 17 43 0.64 VOL 18 06H -1.07 -0.72 0.35 Array WAR TPR Page 15 of 39

TABLE 5 Steam Generator 11 TSP Wear Tube # Ind # Row Col Volts Ind Pct Locn Inch1 Inch2 Length PType Util1 Util2 Util3 37 44 17 43 0.14 WAR 12 06H -0.87 Bobbin CBA 38 45 18 43 0.35 VOL 14 04H -0.98 -0.72 0.26 Array WAR TPR NBC 39 46 19 43 0.36 VOL 14 05H -1.04 -0.75 0.29 Array WAR TPR NBC 40 47 20 43 0.41 VOL 15 04H -1.01 -0.67 0.34 Array WAR TPR NBC 41 48 21 43 0.52 VOL 17 05H -1.04 -0.72 0.32 Array WAR TPR 41 48 21 43 0.06 WAR 6 05H -0.84 Bobbin CBA 42 49 42 43 0.34 VOL 14 05H -0.93 -0.62 0.31 Array WAR TPR 42 49 42 43 0.09 WAR 8 05H -0.65 Bobbin CBA 43 50 51 43 0.25 VOL 12 04H -0.84 -0.61 0.23 Array WAR TPR 43 50 51 43 0.12 WAR 10 04H -0.78 Bobbin CBA 44 51 53 43 0.47 VOL 16 05H -0.83 -0.52 0.31 Array WAR TPR NBC 44 52 53 43 0.46 VOL 16 08H -0.93 -0.58 0.35 Array WAR TPR NBC 44 53 53 43 0.36 VOL 14 05H -0.80 -0.55 0.25 Array WAR TPR NBC 44 54 53 43 0.46 VOL 16 08H -1.01 -0.66 0.35 Array WAR TPR NBC 45 55 16 44 0.27 VOL 13 05H -0.91 -0.60 0.31 Array WAR TPR 45 55 16 44 0.12 WAR 10 05H -0.86 Bobbin CBA 46 56 19 44 0.25 VOL 12 05H -0.91 -0.63 0.28 Array WAR TPR 46 56 19 44 0.13 WAR 11 05H -0.83 Bobbin CBA 47 57 20 44 0.44 VOL 16 05H -0.91 -0.63 0.28 Array WAR TPR 47 57 20 44 0.16 WAR 13 05H -0.89 Bobbin CBA 48 58 22 44 0.36 VOL 14 03H -0.87 -0.61 0.26 Array WAR TPR 48 58 22 44 0.13 WAR 11 03H -0.78 Bobbin CBA 49 59 23 44 0.29 VOL 13 02H -0.81 -0.58 0.23 Array WAR TPR 49 59 23 44 0.12 WAR 10 02H -0.69 Bobbin CBA 50 60 37 44 0.61 VOL 18 08C -1.01 -0.56 0.45 Array WAR TPR 50 60 37 44 0.1 WAR 9 08C -0.84 Bobbin CBA 51 61 51 44 0.29 VOL 13 05H -1.10 -0.69 0.41 Array WAR TPR 51 61 51 44 0.1 WAR 9 05H -0.75 Bobbin CBA 52 62 53 44 0.59 VOL 18 07H -1.01 -0.63 0.38 Array WAR TPR 52 62 53 44 0.18 WAR 15 07H -0.78 Bobbin CBA 53 63 15 45 0.48 VOL 16 05H -1.04 -0.72 0.32 Array WAR TPR 53 63 15 45 0.11 WAR 10 05H -0.87 Bobbin CBA 54 64 18 45 0.42 VOL 15 04H -0.98 -0.67 0.31 Array WAR TPR 54 64 18 45 0.08 WAR 7 04H -0.69 Bobbin CBA 55 65 20 45 0.57 VOL 17 04H -1.01 -0.70 0.31 Array WAR TPR 55 65 20 45 0.12 WAR 10 04H -0.78 Bobbin CBA 56 66 21 45 0.51 VOL 17 04H -1.07 -0.72 0.35 Array WAR TPR NBC 57 67 22 45 0.32 VOL 14 02H -0.90 -0.70 0.20 Array WAR TPR 57 67 22 45 0.07 WAR 6 02H -0.72 Bobbin CBA 58 68 23 45 0.53 VOL 17 03H -1.04 -0.72 0.32 Array WAR TPR Page 16 of 39

TABLE 5 Steam Generator 11 TSP Wear Tube # Ind # Row Col Volts Ind Pct Locn Inch1 Inch2 Length PType Util1 Util2 Util3 58 68 23 45 0.1 WAR 9 03H -0.81 Bobbin CBA 59 69 36 45 0.44 VOL 16 08C -0.96 -0.48 0.48 Array WAR TPR 59 69 36 45 0.06 WAR 6 08C -0.87 Bobbin CBA 60 70 18 46 0.35 VOL 14 05H -0.95 -0.63 0.32 Array WAR TPR 60 70 18 46 0.14 WAR 12 05H -0.86 Bobbin CBA 61 71 22 46 0.46 VOL 16 04H -0.93 -0.64 0.29 Array WAR TPR 61 71 22 46 0.16 WAR 13 04H -0.81 Bobbin CBA 62 72 23 46 0.31 VOL 14 03H -0.84 -0.58 0.26 Array WAR TPR 62 72 23 46 0.15 WAR 13 03H -0.78 Bobbin CBA 63 73 52 46 0.39 VOL 15 05H -0.87 -0.52 0.35 Array WAR TPR NBC 64 74 18 47 0.29 VOL 13 05H -1.10 -0.78 0.32 Array WAR TPR NBC 65 75 19 47 0.39 VOL 15 04H -1.01 -0.75 0.26 Array WAR TPR 65 75 19 47 0.07 WAR 6 04H -0.81 Bobbin CBA 66 76 20 47 0.28 VOL 13 03H -0.98 -0.72 0.26 Array WAR TPR NBC 67 77 21 47 0.48 VOL 16 03H -0.98 -0.72 0.26 Array WAR TPR 67 77 21 47 0.13 WAR 11 03H -0.78 Bobbin CBA 68 78 22 47 0.43 VOL 15 05H -1.01 -0.72 0.29 Array WAR TPR NBC 69 79 23 47 0.39 VOL 15 03H -0.98 -0.72 0.26 Array WAR TPR 69 79 23 47 0.1 WAR 9 03H -0.81 Bobbin CBA 70 80 24 47 0.27 VOL 13 02H -0.93 -0.70 0.23 Array WAR TPR 70 80 24 47 0.14 WAR 12 02H -0.75 Bobbin CBA 70 81 24 47 0.39 VOL 15 03H -1.01 -0.72 0.29 Array WAR TPR NBC 71 82 53 47 0.34 VOL 14 04H -0.96 -0.72 0.24 Array WAR TPR 71 82 53 47 0.07 WAR 6 04H -0.64 Bobbin CBA 72 83 54 47 0.33 VOL 14 04H -0.93 -0.67 0.26 Array WAR TPR 72 83 54 47 0.09 WAR 8 04H -0.72 Bobbin CBA 73 84 17 48 0.13 WAR 11 05H -0.86 Bobbin NCA 74 85 54 48 0.46 VOL 16 04H -0.93 -0.67 0.26 Array WAR TPR 74 85 54 48 0.11 WAR 10 04H -0.75 Bobbin CBA 75 86 17 49 0.37 VOL 15 05H -1.01 -0.72 0.29 Array WAR TPR 75 86 17 49 0.08 WAR 7 05H -0.90 Bobbin CBA 76 87 19 49 0.56 VOL 17 05H -1.01 -0.69 0.32 Array WAR TPR 76 87 19 49 0.13 WAR 11 05H -0.81 Bobbin CBA 77 88 21 49 0.48 VOL 16 04H -1.01 -0.72 0.29 Array WAR TPR 77 88 21 49 0.14 WAR 12 04H -0.84 Bobbin CBA 78 89 23 49 0.32 VOL 14 03H -0.99 -0.70 0.29 Array WAR TPR 78 89 23 49 0.11 WAR 10 03H -0.78 Bobbin CBA 79 90 52 49 0.55 VOL 17 07H -0.98 -0.72 0.26 Array WAR TPR 79 90 52 49 0.09 WAR 8 07H -0.78 Bobbin CBA 80 91 53 49 0.35 VOL 14 02H 0.20 0.49 0.29 Array WAR TPR Page 17 of 39

TABLE 5 Steam Generator 11 TSP Wear Tube # Ind # Row Col Volts Ind Pct Locn Inch1 Inch2 Length PType Util1 Util2 Util3 80 91 53 49 0.15 WAR 13 02H 0.40 Bobbin CBA 81 92 19 50 0.27 VOL 13 04H -0.90 -0.64 0.26 Array WAR TPR 81 92 19 50 0.11 WAR 10 04H -0.84 Bobbin CBA 82 93 53 50 0.55 VOL 17 04H -0.78 -0.29 0.49 Array WAR TPR 82 93 53 50 0.17 WAR 14 04H -0.64 Bobbin CBA 83 94 54 50 0.64 VOL 18 05H -0.98 -0.32 0.66 Array WAR TPR 83 94 54 50 0.65 VOL 12 05H -0.98 -0.32 0.66 Array WAR TPR 83 94 54 50 0.14 WAR 12 05H -0.72 Bobbin CBA 84 95 22 51 0.25 VOL 12 03H -0.96 -0.72 0.24 Array WAR TPR NBC 85 96 48 51 0.41 VOL 15 04H -0.95 -0.64 0.31 Array WAR TPR 85 96 48 51 0.09 WAR 8 04H -0.78 Bobbin CBA 86 97 53 51 0.25 VOL 12 03H -0.90 -0.46 0.44 Array WAR NBC TPR 86 98 53 51 0.49 VOL 16 04H -0.84 -0.46 0.38 Array WAR TPR 86 98 53 51 0.14 WAR 12 04H -0.72 Bobbin CBA 87 99 54 51 0.17 WAR 14 02H 0.30 Bobbin CBA 87 99 54 51 0.39 VOL 15 02H 0.33 0.58 0.25 Array WAR TPR 87 100 54 51 0.61 VOL 18 04H -0.89 -0.42 0.47 Array WAR TPR 87 100 54 51 0.1 WAR 9 04H -0.61 Bobbin CBA 87 101 54 51 0.84 VOL 20 07H -0.98 -0.42 0.56 Array WAR TPR 87 101 54 51 0.13 WAR 11 07H -0.64 Bobbin CBA 88 102 18 52 0.21 VOL 12 04H -1.01 -0.75 0.26 Array WAR TPR 88 102 18 52 0.1 WAR 9 04H -0.81 Bobbin CBA 89 103 53 52 0.67 VOL 18 04H -0.84 -0.51 0.33 Array WAR TPR 89 103 53 52 0.14 WAR 12 04H -0.62 Bobbin CBA 89 104 53 52 0.42 VOL 15 06H -0.88 -0.57 0.31 Array WAR TPR 89 104 53 52 0.08 WAR 7 06H -0.62 Bobbin CBA 90 105 54 52 0.55 VOL 17 04H 0.00 0.54 0.54 Array WAR TPR 90 105 54 52 0.17 WAR 14 04H 0.51 Bobbin CBA 91 106 55 52 0.31 VOL 14 03H -0.82 -0.42 0.40 Array WAR TPR 91 106 55 52 0.09 WAR 8 03H -0.56 Bobbin CBA 91 107 55 52 0.74 VOL 19 07H -0.91 -0.43 0.48 Array WAR TPR 91 107 55 52 0.14 WAR 12 07H -0.68 Bobbin CBA 92 108 52 53 0.55 VOL 17 04H -0.89 -0.25 0.64 Array WAR TPR 92 108 52 53 0.11 WAR 10 04H -0.64 Bobbin CBA 93 109 54 53 0.5 VOL 16 04H -0.86 -0.55 0.31 Array WAR TPR 93 109 54 53 0.12 WAR 10 04H -0.61 Bobbin CBA 93 110 54 53 0.33 VOL 14 06C -0.98 -0.70 0.28 Array WAR TPR 93 110 54 53 0.08 WAR 7 06C -0.84 Bobbin CBA 94 111 55 53 0.66 VOL 18 04H -0.91 -0.55 0.36 Array WAR TPR 94 111 55 53 0.14 WAR 12 04H -0.61 Bobbin CBA Page 18 of 39

TABLE 5 Steam Generator 11 TSP Wear Tube # Ind # Row Col Volts Ind Pct Locn Inch1 Inch2 Length PType Util1 Util2 Util3 94 112 55 53 0.38 VOL 15 07H -0.95 -0.42 0.53 Array WAR TPR 94 112 55 53 0.1 WAR 9 07H -0.67 Bobbin CBA 95 113 48 54 0.63 VOL 18 03H -0.96 -0.42 0.54 Array WAR TPR 95 113 48 54 0.21 WAR 16 03H -0.62 Bobbin CBA 96 114 54 54 0.61 VOL 18 04H -0.93 -0.51 0.42 Array WAR TPR 96 114 54 54 0.14 WAR 12 04H -0.65 Bobbin CBA 96 115 54 54 0.31 VOL 14 06H -0.93 -0.62 0.31 Array WAR TPR 96 115 54 54 0.07 WAR 6 06H -0.65 Bobbin CBA 97 116 55 54 0.27 VOL 13 02H 0.31 0.56 0.25 Array WAR TPR 97 116 55 54 0.15 WAR 13 02H 0.48 Bobbin CBA 97 117 55 54 0.46 VOL 16 04H -0.85 -0.34 0.51 Array WAR TPR 97 117 55 54 0.07 WAR 6 04H -0.59 Bobbin CBA 97 118 55 54 0.39 VOL 15 08H -0.95 -0.63 0.32 Array WAR TPR NBC 98 119 52 55 0.42 VOL 15 07H -1.04 -0.45 0.59 Array WAR TPR 98 119 52 55 0.1 WAR 9 07H -0.59 Bobbin CBA 99 120 53 55 0.54 VOL 17 04H -0.88 -0.41 0.47 Array WAR TPR 99 120 53 55 0.12 WAR 10 04H -0.52 Bobbin CBA 100 121 54 55 0.65 VOL 18 04H -0.99 -0.36 0.63 Array WAR TPR 100 121 54 55 0.09 WAR 8 04H -0.64 Bobbin CBA 101 122 55 55 0.32 VOL 14 05C 0.20 0.39 0.19 Array WAR TPR 101 122 55 55 0.15 WAR 13 05C 0.34 Bobbin CBA 102 123 33 56 0.27 VOL 13 05C -0.90 -0.59 0.31 Array WAR TPR 102 123 33 56 0.06 WAR 6 05C -0.68 Bobbin CBA 103 124 42 56 0.13 WAR 11 05H 0.45 Bobbin NCA 104 125 53 56 0.51 VOL 17 04H -0.87 -0.56 0.31 Array WAR TPR 104 125 53 56 0.09 WAR 8 04H -0.62 Bobbin CBA 105 126 54 56 0.07 WAR 6 02H 0.48 Bobbin NCA 105 127 54 56 0.72 VOL 19 04H -0.85 -0.48 0.37 Array WAR TPR 105 127 54 56 0.13 WAR 11 04H -0.62 Bobbin CBA 105 128 54 56 0.79 VOL 20 07H -0.99 -0.65 0.34 Array WAR TPR 105 128 54 56 0.19 WAR 15 07H -0.71 Bobbin CBA 106 129 53 57 0.43 VOL 15 04H -0.80 -0.50 0.30 Array WAR TPR NBC 107 130 55 57 0.41 VOL 15 04H -0.91 -0.44 0.47 Array WAR TPR 107 130 55 57 0.1 WAR 9 04H -0.64 Bobbin CBA 107 131 55 57 0.5 VOL 16 05C -0.95 -0.64 0.31 Array WAR TPR 107 131 55 57 0.08 WAR 7 05C -0.75 Bobbin CBA 108 132 28 58 0.65 VOL 18 05H -0.96 -0.64 0.32 Array WAR TPR NBC 109 133 43 58 0.35 VOL 14 06C -0.87 -0.59 0.28 Array WAR TPR 109 133 43 58 0.07 WAR 6 06C -0.73 Bobbin CBA 110 134 54 58 0.51 VOL 17 04H -0.84 -0.37 0.47 Array WAR TPR Page 19 of 39

TABLE 5 Steam Generator 11 TSP Wear Tube # Ind # Row Col Volts Ind Pct Locn Inch1 Inch2 Length PType Util1 Util2 Util3 110 134 54 58 0.13 WAR 11 04H -0.59 Bobbin CBA 110 135 54 58 0.36 VOL 14 06C -0.93 -0.62 0.31 Array WAR TPR 110 135 54 58 0.07 WAR 6 06C -0.81 Bobbin CBA 110 136 54 58 0.23 VOL 12 05C -0.90 -0.62 0.28 Array WAR TPR 110 136 54 58 0.08 WAR 7 05C -0.76 Bobbin CBA 110 137 54 58 0.54 VOL 17 02C 0.31 0.62 0.31 Array WAR TPR 110 137 54 58 0.21 WAR 16 02C 0.39 Bobbin CBA 111 138 55 58 0.64 VOL 18 02H 0.20 0.56 0.36 Array WAR TPR 111 138 55 58 0.22 WAR 17 02H 0.51 Bobbin CBA 111 139 55 58 0.27 VOL 13 03H -0.82 -0.37 0.45 Array WAR TPR 111 139 55 58 0.17 WAR 14 03H -0.47 Bobbin CBA 111 140 55 58 0.48 VOL 16 04H -0.87 -0.59 0.28 Array WAR TPR 111 140 55 58 0.17 WAR 14 04H -0.62 Bobbin CBA 111 141 55 58 0.45 VOL 16 05H -0.95 -0.62 0.33 Array WAR TPR 111 141 55 58 0.12 WAR 10 05H -0.62 Bobbin CBA 112 142 44 59 0.56 VOL 17 04H -0.79 -0.31 0.48 Array WAR TPR 112 142 44 59 0.1 WAR 9 04H -0.65 Bobbin CBA 113 143 50 59 0.52 VOL 17 03H -0.73 -0.48 0.25 Array WAR TPR 113 143 50 59 0.08 WAR 7 03H -0.62 Bobbin CBA 114 144 54 59 0.51 VOL 16 01H -0.65 -0.08 0.57 Array WAR TPR 114 144 54 59 0.1 WAR 9 01H -0.49 Bobbin CBA 114 145 54 59 0.58 VOL 17 04H -0.79 -0.25 0.54 Array WAR TPR 114 145 54 59 0.17 WAR 14 04H -0.65 Bobbin CBA 115 146 55 59 0.57 VOL 17 01H -0.65 -0.30 0.35 Array WAR TPR 115 146 55 59 0.15 WAR 13 01H -0.49 Bobbin CBA 115 147 55 59 0.12 WAR 10 03H 0.51 Bobbin NCA 115 148 55 59 0.57 VOL 17 07H -0.89 -0.51 0.38 Array WAR TPR 115 148 55 59 0.09 WAR 8 07H -0.68 Bobbin CBA 115 149 55 59 0.52 VOL 17 08C -1.04 -0.71 0.33 Array WAR TPR NBC 115 150 55 59 0.37 VOL 15 05C -0.93 -0.68 0.25 Array WAR TPR NBC 116 151 44 60 0.25 VOL 12 05H -0.77 -0.54 0.23 Array WAR TPR NBC 117 152 49 60 0.3 VOL 13 06H -0.82 -0.51 0.31 Array WAR TPR NBC 118 153 52 60 0.49 VOL 16 04H -0.82 -0.56 0.26 Array WAR TPR 118 153 52 60 0.13 WAR 11 04H -0.65 Bobbin CBA 119 154 54 60 0.53 VOL 17 02H 0.20 0.65 0.45 Array WAR TPR 119 154 54 60 0.13 WAR 11 02H 0.48 Bobbin CBA 119 155 54 60 0.51 VOL 17 04H -0.79 -0.22 0.57 Array WAR TPR 119 155 54 60 0.1 WAR 9 04H -0.65 Bobbin CBA 120 156 34 61 0.36 VOL 14 06H -0.76 -0.51 0.25 Array WAR TPR 120 156 34 61 0.07 WAR 6 06H -0.65 Bobbin CBA Page 20 of 39

TABLE 5 Steam Generator 11 TSP Wear Tube # Ind # Row Col Volts Ind Pct Locn Inch1 Inch2 Length PType Util1 Util2 Util3 121 157 41 61 0.37 VOL 15 04H -0.92 -0.45 0.47 Array WAR TPR 121 157 41 61 0.07 WAR 6 04H -0.64 Bobbin CBA 122 158 53 61 0.35 VOL 14 04H -0.79 -0.51 0.28 Array WAR TPR 122 158 53 61 0.09 WAR 8 04H -0.42 Bobbin CBA 123 159 54 61 0.29 VOL 13 04H -0.73 -0.59 0.14 Array WAR TPR 123 159 54 61 0.08 WAR 7 04H -0.64 Bobbin CBA 123 160 54 61 0.31 VOL 14 05H -0.73 -0.54 0.19 Array WAR TPR NBC 124 161 55 61 0.43 VOL 15 03H -0.75 -0.14 0.61 Array WAR TPR 124 161 55 61 0.13 WAR 11 03H -0.56 Bobbin CBA 125 162 9 62 0.33 VOL 14 07C -0.90 -0.64 0.26 Array WAR TPR NBC 125 163 9 62 0.35 VOL 14 04C -0.92 -0.60 0.32 Array WAR TPR 125 163 9 62 0.07 WAR 6 04C -0.67 Bobbin CBA 126 164 24 62 0.5 VOL 16 06H -1.07 -0.70 0.37 Array WAR NBC TPR 127 165 48 62 0.32 VOL 14 08C -1.01 -0.68 0.33 Array WAR TPR 127 165 48 62 0.08 WAR 7 08C -0.85 Bobbin CBA 128 166 51 62 0.51 VOL 17 04H -0.84 -0.48 0.36 Array WAR TPR 128 166 51 62 0.11 WAR 10 04H -0.64 Bobbin CBA 129 167 54 62 0.51 VOL 17 04H -0.79 -0.48 0.31 Array WAR TPR 129 167 54 62 0.12 WAR 10 04H -0.62 Bobbin CBA 130 168 55 62 0.38 VOL 15 02H 0.33 0.61 0.28 Array WAR TPR NBC 131 169 17 63 0.43 VOL 15 06C -0.98 -0.55 0.43 Array WAR TPR 131 169 17 63 0.08 WAR 7 06C -0.77 Bobbin CBA 132 170 33 63 0.41 VOL 15 04H -0.84 -0.50 0.34 Array WAR TPR 132 170 33 63 0.1 WAR 9 04H -0.67 Bobbin CBA 133 171 53 63 0.59 VOL 18 04H -0.75 -0.22 0.53 Array WAR TPR 133 171 53 63 0.16 WAR 13 04H -0.59 Bobbin CBA 134 172 54 63 0.54 VOL 17 02H 0.36 0.69 0.33 Array WAR TPR 134 172 54 63 0.1 WAR 9 02H 0.50 Bobbin CBA 134 173 54 63 0.39 VOL 15 03H -0.75 -0.42 0.33 Array WAR TPR 134 173 54 63 0.11 WAR 10 03H -0.58 Bobbin CBA 134 174 54 63 0.55 VOL 17 04H -0.78 -0.47 0.31 Array WAR TPR 134 174 54 63 0.13 WAR 11 04H -0.61 Bobbin CBA 135 175 55 63 0.31 VOL 14 02H 0.25 0.64 0.39 Array WAR TPR 135 175 55 63 0.09 WAR 8 02H 0.50 Bobbin CBA 136 176 47 64 0.15 WAR 13 03H 0.48 Bobbin NCA 137 177 49 64 0.69 VOL 19 08C -0.98 -0.62 0.36 Array WAR TPR 137 177 49 64 0.13 WAR 11 08C -0.84 Bobbin CBA 138 178 50 64 0.29 VOL 13 04H -0.83 -0.58 0.25 Array WAR TPR 138 178 50 64 0.11 WAR 10 04H -0.64 Bobbin CBA 139 179 53 64 0.63 VOL 18 04H -0.81 -0.31 0.50 Array WAR TPR Page 21 of 39

TABLE 5 Steam Generator 11 TSP Wear Tube # Ind # Row Col Volts Ind Pct Locn Inch1 Inch2 Length PType Util1 Util2 Util3 139 179 53 64 0.16 WAR 13 04H -0.61 Bobbin CBA 140 180 54 64 0.4 VOL 15 02H 0.22 0.58 0.36 Array WAR TPR 140 180 54 64 0.15 WAR 13 02H 0.50 Bobbin CBA 140 181 54 64 0.12 WAR 10 03H 0.50 Bobbin NCA 140 182 54 64 0.64 VOL 18 04H -0.81 -0.33 0.48 Array WAR TPR 140 182 54 64 0.16 WAR 13 04H -0.61 Bobbin CBA 140 183 54 64 0.53 VOL 17 08H -0.94 -0.60 0.34 Array WAR TPR 140 183 54 64 0.11 WAR 10 08H -0.74 Bobbin CBA 141 184 55 64 0.37 VOL 15 04H -0.80 -0.55 0.25 Array WAR TPR NBC 141 185 55 64 0.52 VOL 17 02C 0.23 0.58 0.35 Array WAR TPR 141 185 55 64 0.21 WAR 16 02C 0.40 Bobbin CBA 142 186 30 65 0.29 VOL 13 04H -0.99 -0.70 0.29 Array WAR TPR NBC 143 187 47 65 0.51 VOL 17 04H -0.78 -0.45 0.33 Array WAR TPR 143 187 47 65 0.14 WAR 12 04H -0.67 Bobbin CBA 144 188 54 65 0.34 VOL 14 04H -0.78 -0.45 0.33 Array WAR TPR 144 188 54 65 0.07 WAR 6 04H -0.61 Bobbin CBA 144 189 54 65 0.5 VOL 16 02C 0.17 0.51 0.34 Array WAR TPR 144 189 54 65 0.15 WAR 13 02C 0.42 Bobbin CBA 145 190 48 66 0.38 VOL 15 03H -0.89 -0.58 0.31 Array WAR TPR 145 190 48 66 0.32 VOL 14 03H -0.83 -0.61 0.22 Array WAR TPR 145 190 48 66 0.23 WAR 18 03H -0.61 Bobbin CBA 145 191 48 66 0.36 VOL 14 04H -0.87 -0.56 0.31 Array WAR TPR 145 191 48 66 0.09 WAR 8 04H -0.61 Bobbin CBA 146 192 23 67 0.11 WAR 10 03H 0.38 Bobbin NCA 147 193 24 67 0.31 VOL 14 05H -1.04 -0.72 0.32 Array WAR TPR NBC 148 194 32 67 0.41 VOL 15 04H 0.12 0.37 0.25 Array WAR TPR 148 194 32 67 0.12 WAR 10 04H 0.40 Bobbin CBA 149 195 53 67 0.72 VOL 19 08C -1.07 -0.40 0.67 Array WAR TPR 149 195 53 67 0.11 WAR 10 08C -0.89 Bobbin CBA 149 196 53 67 0.64 VOL 18 02C 0.09 0.81 0.72 Array WAR TPR 149 196 53 67 0.21 WAR 16 02C 0.40 Bobbin CBA 150 197 54 67 0.71 VOL 19 02C 0.26 0.69 0.43 Array WAR TPR 150 197 54 67 0.27 WAR 20 02C 0.40 Bobbin CBA 151 198 32 68 0.29 VOL 13 05H -1.05 -0.61 0.44 Array WAR TPR 151 198 32 68 0.11 WAR 10 05H -0.70 Bobbin CBA 152 199 51 68 0.11 WAR 10 03H 0.49 Bobbin NCA 152 200 51 68 0.38 VOL 15 04H -0.80 -0.60 0.20 Array WAR TPR 152 200 51 68 0.09 WAR 8 04H -0.69 Bobbin CBA 153 201 52 68 0.23 VOL 12 03C -0.87 -0.61 0.26 Array WAR TPR 153 201 52 68 0.11 WAR 10 03C -0.66 Bobbin CBA Page 22 of 39

TABLE 5 Steam Generator 11 TSP Wear Tube # Ind # Row Col Volts Ind Pct Locn Inch1 Inch2 Length PType Util1 Util2 Util3 153 202 52 68 0.46 VOL 16 02C 0.20 0.52 0.32 Array WAR TPR 153 202 52 68 0.15 WAR 13 02C 0.40 Bobbin CBA 154 203 53 68 0.25 VOL 12 06C -0.89 -0.69 0.20 Array WAR TPR NBC 154 204 53 68 0.76 VOL 19 02C 0.23 0.58 0.35 Array WAR TPR 154 204 53 68 0.27 WAR 20 02C 0.43 Bobbin CBA 155 205 54 68 0.26 VOL 13 06H -0.90 -0.58 0.32 Array WAR TPR 155 205 54 68 0.07 WAR 6 06H -0.64 Bobbin CBA 155 206 54 68 0.36 VOL 14 08H -0.93 -0.58 0.35 Array WAR TPR 155 206 54 68 0.11 WAR 10 08H -0.73 Bobbin CBA 155 207 54 68 0.55 VOL 17 08C -1.04 -0.66 0.38 Array WAR TPR 155 207 54 68 0.18 WAR 15 08C -0.81 Bobbin CBA 155 208 54 68 0.49 VOL 16 06C -0.92 -0.61 0.31 Array WAR TPR 155 208 54 68 0.12 WAR 10 06C -0.75 Bobbin CBA 155 209 54 68 0.45 VOL 16 02C 0.20 0.58 0.38 Array WAR TPR 155 209 54 68 0.14 WAR 12 02C 0.38 Bobbin CBA 156 210 52 69 0.26 VOL 13 03C 0.35 0.55 0.20 Array WAR TPR 156 210 52 69 0.11 WAR 10 03C 0.38 Bobbin CBA 156 211 52 69 0.54 VOL 17 02C 0.29 0.60 0.31 Array WAR TPR 156 211 52 69 0.16 WAR 13 02C 0.40 Bobbin CBA 157 212 27 70 0.38 VOL 15 04H -0.89 -0.49 0.40 Array WAR TPR 157 212 27 70 0.21 WAR 16 04H -0.69 Bobbin CBA 158 213 51 70 0.28 VOL 13 08C -1.04 -0.69 0.35 Array WAR TPR 158 213 51 70 0.13 WAR 11 08C -0.84 Bobbin CBA 159 214 52 70 0.52 VOL 17 04H -0.86 -0.57 0.29 Array WAR TPR 159 214 52 70 0.14 WAR 12 04H -0.66 Bobbin CBA 159 215 52 70 0.6 VOL 18 08C -1.01 -0.61 0.40 Array WAR TPR 159 215 52 70 0.15 WAR 13 08C -0.87 Bobbin CBA 160 216 53 70 0.23 VOL 12 03H -0.85 -0.71 0.14 Array WAR TPR NBC 160 217 53 70 0.19 VOL 11 02C 0.35 0.49 0.14 Array WAR TPR 160 217 53 70 0.11 WAR 10 02C 0.43 Bobbin CBA 161 218 40 71 0.46 VOL 16 04H 0.23 0.49 0.26 Array WAR TPR 161 218 40 71 0.19 WAR 15 04H 0.40 Bobbin CBA 162 219 47 71 0.48 VOL 16 03H -0.83 -0.57 0.26 Array WAR TPR 162 219 47 71 0.13 WAR 11 03H -0.57 Bobbin CBA 163 220 53 71 0.77 VOL 20 08C -0.95 -0.58 0.37 Array WAR TPR 163 220 53 71 0.13 WAR 11 08C -0.90 Bobbin CBA 164 221 8 72 0.29 VOL 13 06C -1.04 -0.69 0.35 Array WAR TPR NBC 165 222 49 72 0.27 VOL 13 03H -0.98 -0.57 0.41 Array WAR TPR 165 222 49 72 0.31 VOL 14 03H -0.80 -0.54 0.26 Array WAR TPR 165 222 49 72 0.19 WAR 15 03H -0.63 Bobbin CBA Page 23 of 39

TABLE 5 Steam Generator 11 TSP Wear Tube # Ind # Row Col Volts Ind Pct Locn Inch1 Inch2 Length PType Util1 Util2 Util3 165 223 49 72 0.26 VOL 13 04H -0.95 -0.63 0.32 Array WAR TPR 165 223 49 72 0.1 WAR 9 04H -0.69 Bobbin CBA 165 224 49 72 0.38 VOL 15 08C -1.07 -0.67 0.40 Array WAR TPR 165 224 49 72 0.14 WAR 12 08C -0.72 Bobbin CBA 166 225 50 72 0.23 VOL 12 04H -0.78 -0.52 0.26 Array WAR TPR 166 225 50 72 0.11 WAR 10 04H -0.69 Bobbin CBA 167 226 52 72 0.36 VOL 14 07H -0.95 -0.58 0.37 Array WAR TPR 167 226 52 72 0.07 WAR 6 07H -0.78 Bobbin CBA 168 227 53 72 0.51 VOL 17 08C -0.93 -0.55 0.38 Array WAR TPR 168 227 53 72 0.09 WAR 8 08C -0.90 Bobbin CBA 169 228 23 73 0.58 VOL 17 04H -0.92 -0.61 0.31 Array WAR TPR 169 228 23 73 0.06 WAR 6 04H -0.66 Bobbin CBA 170 229 42 73 0.26 VOL 13 06C -0.95 -0.66 0.29 Array WAR TPR 170 229 42 73 0.14 WAR 12 06C -0.81 Bobbin CBA 171 230 45 73 0.25 VOL 12 04H -0.83 -0.57 0.26 Array WAR TPR NBC 171 231 45 73 0.34 VOL 14 08C -0.99 -0.67 0.32 Array WAR TPR 171 231 45 73 0.11 WAR 10 08C -0.84 Bobbin CBA 172 232 47 73 0.3 VOL 13 03H -0.80 -0.57 0.23 Array WAR TPR 172 232 47 73 0.18 WAR 15 03H -0.60 Bobbin CBA 172 233 47 73 0.31 VOL 14 04H -0.88 -0.60 0.28 Array WAR TPR 172 233 47 73 0.15 WAR 13 04H -0.62 Bobbin CBA 173 234 50 73 0.26 VOL 13 06C -0.95 -0.66 0.29 Array WAR TPR NBC 174 235 52 73 0.32 VOL 14 07H -0.86 -0.52 0.34 Array WAR TPR 174 235 52 73 0.11 WAR 10 07H -0.63 Bobbin CBA 175 236 20 74 0.31 VOL 14 06C -0.98 -0.66 0.32 Array WAR TPR NBC 176 237 23 74 0.42 VOL 15 06H -0.95 -0.60 0.35 Array WAR TPR NBC 177 238 39 74 0.37 VOL 9 04H -0.91 -0.54 0.37 Array WAR TPR 177 238 39 74 0.37 VOL 15 04H -0.91 -0.54 0.37 Array WAR TPR 177 238 39 74 0.1 WAR 9 04H -0.62 Bobbin CBA 178 239 43 74 0.26 VOL 13 04H -0.94 -0.62 0.32 Array WAR TPR NBC 179 240 52 74 0.4 VOL 15 08C -1.10 -0.73 0.37 Array WAR TPR 179 240 52 74 0.11 WAR 10 08C -0.82 Bobbin CBA 180 241 40 75 0.34 VOL 14 06H -0.89 -0.63 0.26 Array WAR TPR 180 241 40 75 0.13 WAR 11 06H -0.63 Bobbin CBA 181 242 49 75 0.63 VOL 18 04H -0.85 -0.51 0.34 Array WAR TPR 181 242 49 75 0.17 WAR 14 04H -0.65 Bobbin CBA 182 243 51 75 0.27 VOL 13 02C 0.32 0.58 0.26 Array WAR TPR NBC 183 244 49 76 0.49 VOL 16 04H -0.84 -0.53 0.31 Array WAR TPR 183 244 49 76 0.15 WAR 13 04H -0.62 Bobbin CBA 184 245 52 76 0.22 VOL 12 02C 0.35 0.55 0.20 Array WAR TPR Page 24 of 39

TABLE 5 Steam Generator 11 TSP Wear Tube # Ind # Row Col Volts Ind Pct Locn Inch1 Inch2 Length PType Util1 Util2 Util3 184 245 52 76 0.13 WAR 11 02C 0.43 Bobbin CBA 185 246 49 77 0.51 VOL 17 04H -0.84 -0.42 0.42 Array WAR TPR 185 246 49 77 0.16 WAR 13 04H -0.65 Bobbin CBA 186 247 50 77 0.55 VOL 17 04H -0.86 -0.57 0.29 Array WAR TPR 186 247 50 77 0.21 WAR 16 04H -0.66 Bobbin CBA 186 248 50 77 0.43 VOL 15 02C 0.29 0.58 0.29 Array WAR TPR 186 248 50 77 0.17 WAR 14 02C 0.43 Bobbin CBA 187 249 51 77 0.33 VOL 14 03C 0.23 0.52 0.29 Array WAR TPR 187 249 51 77 0.16 WAR 13 03C 0.37 Bobbin CBA 187 250 51 77 0.65 VOL 18 02C 0.14 0.58 0.44 Array WAR TPR 187 250 51 77 0.26 WAR 19 02C 0.40 Bobbin CBA 188 251 22 78 0.22 VOL 12 04C -0.92 -0.69 0.23 Array WAR TPR 188 251 22 78 0.14 WAR 12 04C -0.78 Bobbin CBA 189 252 48 78 0.35 VOL 14 03H -0.80 -0.54 0.26 Array WAR TPR 189 252 48 78 0.15 WAR 13 03H -0.57 Bobbin CBA 190 253 50 78 0.27 VOL 13 03H 0.32 0.58 0.26 Array WAR TPR 190 253 50 78 0.16 WAR 13 03H 0.46 Bobbin CBA 190 254 50 78 0.32 VOL 14 04H -0.81 -0.52 0.29 Array WAR TPR NBC 190 255 50 78 0.32 VOL 14 08C -0.98 -0.67 0.31 Array WAR TPR 190 255 50 78 0.12 WAR 10 08C -0.87 Bobbin CBA 190 256 50 78 0.33 VOL 14 02C 0.26 0.58 0.32 Array WAR TPR NBC 191 257 51 78 0.66 VOL 18 02C 0.06 0.51 0.45 Array WAR TPR 191 257 51 78 0.2 WAR 16 02C 0.39 Bobbin CBA 192 258 50 79 0.35 VOL 14 02C 0.22 0.67 0.45 Array WAR TPR 192 258 50 79 0.06 WAR 6 02C 0.45 Bobbin CBA 193 259 51 79 0.27 VOL 13 02C 0.12 0.37 0.25 Array WAR TPR 193 259 51 79 0.12 WAR 10 02C 0.43 Bobbin CBA 194 260 22 80 0.38 VOL 15 06C -1.01 -0.63 0.38 Array WAR TPR 194 260 22 80 0.14 WAR 12 06C -0.72 Bobbin CBA 195 261 33 80 0.41 VOL 15 04H -0.88 -0.60 0.28 Array WAR TPR 195 261 33 80 0.15 WAR 13 04H -0.65 Bobbin CBA 196 262 47 80 0.36 VOL 14 03H -0.80 -0.52 0.28 Array WAR TPR 196 262 47 80 0.19 WAR 15 03H -0.66 Bobbin CBA 197 263 7 81 0.47 VOL 16 06C -1.01 -0.66 0.35 Array WAR TPR NBC 198 264 47 81 0.35 VOL 14 08C -0.99 -0.64 0.35 Array WAR TPR 198 264 47 81 0.12 WAR 10 08C -0.78 Bobbin CBA 199 265 46 82 0.36 VOL 14 08H -1.06 -0.68 0.38 Array WAR TPR NBC 200 266 48 82 0.31 VOL 14 02C 0.29 0.52 0.23 Array WAR TPR 200 266 48 82 0.11 WAR 10 02C 0.40 Bobbin CBA 201 267 49 82 0.6 VOL 18 02C 0.14 0.58 0.44 Array WAR TPR Page 25 of 39

TABLE 5 Steam Generator 11 TSP Wear Tube # Ind # Row Col Volts Ind Pct Locn Inch1 Inch2 Length PType Util1 Util2 Util3 201 267 49 82 0.19 WAR 15 02C 0.40 Bobbin CBA 202 268 50 82 0.44 VOL 16 02C 0.23 0.55 0.32 Array WAR TPR 202 268 50 82 0.14 WAR 12 02C 0.37 Bobbin CBA 203 269 47 83 0.25 VOL 12 02C 0.22 0.51 0.29 Array WAR TPR 203 269 47 83 0.1 WAR 9 02C 0.34 Bobbin CBA 204 270 49 83 0.36 VOL 14 04C -0.84 -0.56 0.28 Array WAR TPR 204 270 49 83 0.1 WAR 9 04C -0.76 Bobbin CBA 204 271 49 83 0.32 VOL 14 02C 0.34 0.59 0.25 Array WAR TPR 204 271 49 83 0.1 WAR 9 02C 0.39 Bobbin CBA 205 272 47 84 0.36 VOL 14 03H -0.81 -0.59 0.22 Array WAR TPR 205 272 47 84 0.16 WAR 13 03H -0.64 Bobbin CBA 206 273 48 84 0.56 VOL 17 03H -0.78 -0.50 0.28 Array WAR TPR 206 273 48 84 0.23 WAR 18 03H -0.61 Bobbin CBA 207 274 46 86 0.28 VOL 13 08C -1.04 -0.68 0.36 Array WAR TPR 207 274 46 86 0.08 WAR 7 08C -0.73 Bobbin CBA 208 275 44 88 0.42 VOL 15 04H -0.85 -0.56 0.29 Array WAR TPR 208 275 44 88 0.13 WAR 11 04H -0.70 Bobbin CBA 209 276 12 89 0.29 VOL 13 04C -0.95 -0.69 0.26 Array WAR TPR 209 276 12 89 0.1 WAR 9 04C -0.78 Bobbin CBA 210 277 46 89 0.11 WAR 10 03H -0.64 Bobbin NCA 211 278 8 92 0.31 VOL 14 06C -0.98 -0.69 0.29 Array WAR TPR 211 278 8 92 0.1 WAR 9 06C -0.81 Bobbin CBA 212 279 1 94 0.32 VOL 14 04C -0.89 -0.53 0.36 Array WAR TPR 212 279 1 94 0.09 WAR 8 04C -0.70 Bobbin CBA 213 280 40 96 0.57 VOL 17 04H -0.76 -0.45 0.31 Array WAR TPR 213 280 40 96 0.13 WAR 11 04H -0.62 Bobbin CBA 214 281 27 99 0.43 VOL 15 04C -0.84 -0.59 0.25 Array WAR TPR 214 281 27 99 0.09 WAR 8 04C -0.79 Bobbin CBA 215 282 35 100 0.41 VOL 15 04H -0.81 -0.53 0.28 Array WAR TPR 215 282 35 100 0.09 WAR 8 04H -0.67 Bobbin CBA 215 283 35 100 0.29 VOL 13 05H 0.28 0.56 0.28 Array WAR TPR 215 283 35 100 0.09 WAR 8 05H 0.39 Bobbin CBA 216 284 29 103 0.37 VOL 15 06C -0.93 -0.62 0.31 Array WAR TPR 216 284 29 103 0.1 WAR 9 06C -0.84 Bobbin CBA 217 285 28 105 0.44 VOL 16 06C -0.90 -0.53 0.37 Array WAR TPR NBC 218 286 27 106 0.53 VOL 17 06C -0.93 -0.62 0.31 Array WAR TPR 218 286 27 106 0.1 WAR 9 06C -0.84 Bobbin CBA 219 287 13 107 0.35 VOL 14 04C -0.86 -0.61 0.25 Array WAR TPR 219 287 13 107 0.05 WAR 5 04C -0.49 Bobbin CBA 220 288 21 107 0.36 VOL 14 04C -0.90 -0.59 0.31 Array WAR TPR NBC Page 26 of 39

TABLE 5 Steam Generator 11 TSP Wear Tube # Ind # Row Col Volts Ind Pct Locn Inch1 Inch2 Length PType Util1 Util2 Util3 221 289 24 108 0.45 VOL 16 04C -0.87 -0.59 0.28 Array WAR TPR 221 289 24 108 0.17 WAR 14 04C -0.70 Bobbin CBA 222 290 11 109 0.28 VOL 13 04C -0.83 -0.40 0.43 Array WAR TPR NBC 223 291 21 109 0.32 VOL 14 04C -0.90 -0.31 0.59 Array WAR TPR NBC 224 292 11 111 0.36 VOL 14 06C -0.92 -0.63 0.29 Array WAR TPR NBC 224 293 11 111 0.25 VOL 12 05C -0.81 -0.61 0.20 Array WAR TPR 224 293 11 111 0.14 WAR 12 05C -0.78 Bobbin CBA 225 294 14 111 0.28 VOL 13 04C -0.98 -0.46 0.52 Array WAR TPR 225 294 14 111 0.07 WAR 6 04C -0.75 Bobbin CBA 226 295 4 113 0.44 VOL 16 05C -0.87 -0.37 0.50 Array WAR TPR 226 295 4 113 0.14 WAR 12 05C -0.76 Bobbin CBA TABLE 6 Steam Generator 12 TSP Wear Tube # Ind # Row Col Volts Ind Pct Locn Inch1 Inch2 Length PType Util1 Util2 Util3 1 1 11 4 0.37 VOL 15 03H -0.79 -0.57 0.22 Array WAR TPR 1 1 11 4 0.11 WAR 10 03H -0.65 Bobbin CBA 2 2 6 7 0.42 VOL 15 05C -0.99 -0.69 0.30 Array WAR TPR NBC 3 3 12 7 0.33 VOL 14 03C -0.94 -0.58 0.36 Array WAR TPR 3 3 12 7 0.08 WAR 7 03C -0.72 Bobbin CBA 4 4 17 8 0.28 VOL 13 05C 0.14 0.55 0.41 Array WAR TPR 4 4 17 8 0.2 WAR 16 05C 0.38 Bobbin CBA 5 5 26 9 0.46 VOL 16 05C -0.99 -0.69 0.30 Array WAR TPR NBC 6 6 23 10 0.41 VOL 15 05C -0.96 -0.72 0.24 Array WAR TPR NBC 7 7 33 15 0.35 VOL 14 05C -0.91 -0.63 0.28 Array WAR TPR 7 7 33 15 0.15 WAR 13 05C -0.77 Bobbin CBA 8 8 35 15 0.32 VOL 14 04C -0.94 -0.55 0.39 Array WAR TPR 8 8 35 15 0.12 WAR 10 04C -0.74 Bobbin CBA 9 9 36 15 0.13 WAR 11 04C -0.83 Bobbin NCA 9 10 36 15 0.28 VOL 13 03C -0.91 -0.63 0.28 Array WAR TPR NBC 10 11 35 16 0.38 VOL 15 05C -0.91 -0.55 0.36 Array WAR TPR 10 11 35 16 0.09 WAR 8 05C -0.74 Bobbin CBA 11 12 37 16 0.43 VOL 15 04C -0.91 -0.63 0.28 Array WAR TPR 11 12 37 16 0.15 WAR 13 04C -0.77 Bobbin CBA 12 13 34 17 0.42 VOL 15 06C -0.94 -0.63 0.31 Array WAR TPR 12 13 34 17 0.06 WAR 6 06C -0.80 Bobbin CBA 13 14 36 17 0.3 VOL 13 04C -0.93 -0.66 0.27 Array WAR TPR 13 14 36 17 0.13 WAR 11 04C -0.74 Bobbin CBA 14 15 32 19 0.37 VOL 15 05C -0.93 -0.66 0.27 Array WAR TPR NBC 15 16 35 19 0.42 VOL 15 05C -0.88 -0.58 0.30 Array WAR TPR Page 27 of 39

TABLE 6 Steam Generator 12 TSP Wear Tube # Ind # Row Col Volts Ind Pct Locn Inch1 Inch2 Length PType Util1 Util2 Util3 15 16 35 19 0.13 WAR 11 05C -0.71 Bobbin CBA 16 17 38 19 0.45 VOL 16 05C -0.93 -0.63 0.30 Array WAR TPR 16 17 38 19 0.12 WAR 10 05C -0.82 Bobbin CBA 17 18 37 20 0.28 VOL 13 05C -0.91 -0.66 0.25 Array WAR TPR 17 18 37 20 0.08 WAR 7 05C -0.77 Bobbin CBA 18 19 41 20 0.38 VOL 15 04C -0.91 -0.63 0.28 Array WAR TPR NBC 19 20 40 21 0.46 VOL 16 05C -0.91 -0.63 0.28 Array WAR TPR 19 20 40 21 0.1 WAR 9 05C -0.80 Bobbin CBA 20 21 9 22 0.34 VOL 14 05C -0.93 -0.62 0.31 Array WAR TPR 20 21 9 22 0.08 WAR 7 05C -0.82 Bobbin CBA 21 22 38 22 0.36 VOL 14 05C -0.94 -0.63 0.31 Array WAR TPR 21 22 38 22 0.1 WAR 9 05C -0.77 Bobbin CBA 22 23 42 23 0.37 VOL 15 05C -0.93 -0.63 0.30 Array WAR TPR 22 23 42 23 0.14 WAR 12 05C -0.80 Bobbin CBA 23 24 42 25 0.4 VOL 15 05C -0.93 -0.60 0.33 Array WAR TPR 23 24 42 25 0.13 WAR 11 05C -0.79 Bobbin CBA 24 25 44 25 0.36 VOL 14 04C -0.91 -0.63 0.28 Array WAR TPR 24 25 44 25 0.1 WAR 9 04C -0.74 Bobbin CBA 25 26 45 25 0.45 VOL 16 05C -0.14 0.22 0.36 Array WAR TPR 25 26 45 25 0.11 WAR 10 05C 0.36 Bobbin CBA 25 27 45 25 0.48 VOL 16 04C -0.91 -0.61 0.30 Array WAR TPR 25 27 45 25 0.11 WAR 10 04C -0.77 Bobbin CBA 26 28 44 26 0.44 VOL 16 05C -0.90 -0.63 0.27 Array WAR TPR 26 28 44 26 0.15 WAR 13 05C -0.79 Bobbin CBA 27 29 46 26 0.53 VOL 17 04C -0.93 -0.63 0.30 Array WAR TPR 27 29 46 26 0.12 WAR 10 04C -0.77 Bobbin CBA 28 30 43 28 0.48 VOL 16 05C -0.91 -0.58 0.33 Array WAR TPR 28 30 43 28 0.12 WAR 10 05C -0.80 Bobbin CBA 29 31 44 28 0.32 VOL 14 05C -0.90 -0.63 0.27 Array WAR TPR 29 31 44 28 0.12 WAR 10 05C -0.77 Bobbin CBA 30 32 45 28 0.46 VOL 16 05C -0.91 -0.63 0.28 Array WAR TPR 30 32 45 28 0.11 WAR 10 05C -0.80 Bobbin CBA 31 33 47 30 0.37 VOL 15 04H -0.86 -0.55 0.31 Array WAR TPR 31 33 47 30 0.07 WAR 6 04H -0.66 Bobbin CBA 32 34 48 30 0.36 VOL 14 06H -0.98 -0.63 0.35 Array WAR TPR 32 34 48 30 0.08 WAR 7 06H -0.71 Bobbin CBA 33 35 49 31 0.27 VOL 13 03C -0.93 -0.63 0.30 Array WAR TPR 33 35 49 31 0.08 WAR 7 03C -0.71 Bobbin CBA 34 36 47 32 0.67 VOL 18 04H -0.88 -0.55 0.33 Array WAR TPR 34 36 47 32 0.12 WAR 10 04H -0.64 Bobbin CBA Page 28 of 39

TABLE 6 Steam Generator 12 TSP Wear Tube # Ind # Row Col Volts Ind Pct Locn Inch1 Inch2 Length PType Util1 Util2 Util3 35 37 48 32 0.34 VOL 14 05H -0.99 -0.61 0.38 Array WAR TPR NBC 35 38 48 32 0.41 VOL 15 04C -0.88 -0.63 0.25 Array WAR TPR 35 38 48 32 0.11 WAR 10 04C -0.80 Bobbin CBA 36 39 49 32 0.38 VOL 15 04H -0.94 -0.61 0.33 Array WAR TPR NBC 37 40 45 33 0.32 VOL 14 04C -1.05 -0.66 0.39 Array WAR TPR 37 40 45 33 0.11 WAR 10 04C -0.77 Bobbin CBA 38 41 48 34 0.53 VOL 17 04H -0.87 -0.49 0.38 Array WAR TPR 38 41 48 34 0.12 WAR 10 04H -0.65 Bobbin CBA 39 42 12 35 0.29 VOL 13 06C -1.27 -0.62 0.65 Array WAR TPR 39 42 12 35 0.05 WAR 5 06C -0.85 Bobbin CBA 40 43 51 35 0.38 VOL 15 05H -0.87 -0.59 0.28 Array WAR TPR 40 43 51 35 0.12 WAR 10 05H -0.79 Bobbin CBA 41 44 51 36 0.43 VOL 15 03H 0.20 0.53 0.33 Array WAR TPR 41 44 51 36 0.17 WAR 14 03H 0.48 Bobbin CBA 41 45 51 36 0.54 VOL 17 04H -0.87 -0.42 0.45 Array WAR TPR NBC 41 46 51 36 0.23 VOL 12 05H 0.09 0.46 0.37 Array WAR TPR 41 46 51 36 0.09 WAR 8 05H 0.46 Bobbin CBA 42 47 50 38 0.4 VOL 15 03H -0.81 -0.59 0.22 Array WAR TPR 42 47 50 38 0.11 WAR 10 03H -0.65 Bobbin CBA 43 48 52 40 0.39 VOL 15 04H -0.99 -0.62 0.37 Array WAR TPR 43 48 52 40 0.13 WAR 11 04H -0.68 Bobbin CBA 44 49 51 41 0.38 VOL 15 04H 0.17 0.65 0.48 Array WAR TPR 44 49 51 41 0.28 WAR 20 04H 0.48 Bobbin CBA 44 50 51 41 0.37 VOL 15 06H -0.95 -0.56 0.39 Array WAR TPR 44 50 51 41 0.08 WAR 7 06H -0.70 Bobbin CBA 45 51 52 41 0.75 VOL 19 04H -0.84 -0.31 0.53 Array WAR TPR 45 51 52 41 0.23 WAR 18 04H -0.65 Bobbin CBA 46 52 29 43 0.34 VOL 14 03H 0.36 0.60 0.24 Array WAR TPR 46 52 29 43 0.2 WAR 16 03H 0.43 Bobbin CBA 47 53 22 44 0.55 VOL 17 04H -0.86 -0.56 0.30 Array WAR TPR NBC 48 54 23 44 0.39 VOL 15 04H -0.95 -0.68 0.27 Array WAR TPR 48 54 23 44 0.07 WAR 6 04H -0.70 Bobbin CBA 49 55 52 44 0.49 VOL 16 08C -1.05 -0.66 0.39 Array WAR TPR 49 55 52 44 0.11 WAR 10 08C -0.91 Bobbin CBA 50 56 37 46 0.27 VOL 13 04H -0.91 -0.57 0.34 Array WAR TPR 50 56 37 46 0.1 WAR 9 04H -0.68 Bobbin CBA 51 57 24 47 0.29 VOL 13 03H -0.84 -0.60 0.24 Array WAR TPR 51 57 24 47 0.11 WAR 10 03H -0.68 Bobbin CBA 51 58 24 47 0.46 VOL 16 04H -0.81 -0.57 0.24 Array WAR TPR NBC 52 59 54 47 0.38 VOL 15 06H -0.81 -0.56 0.25 Array WAR TPR Page 29 of 39

TABLE 6 Steam Generator 12 TSP Wear Tube # Ind # Row Col Volts Ind Pct Locn Inch1 Inch2 Length PType Util1 Util2 Util3 52 59 54 47 0.14 WAR 12 06H -0.73 Bobbin CBA 53 60 54 48 0.31 VOL 14 04C 0.20 0.51 0.31 Array WAR TPR 53 60 54 48 0.15 WAR 13 04C 0.37 Bobbin CBA 54 61 20 49 0.42 VOL 15 05H -1.00 -0.65 0.35 Array WAR TPR 54 61 20 49 0.09 WAR 8 05H -0.78 Bobbin CBA 55 62 22 49 0.22 VOL 12 03H -0.79 -0.60 0.19 Array WAR TPR 55 62 22 49 0.13 WAR 11 03H -0.71 Bobbin CBA 56 63 23 49 0.42 VOL 15 03H -0.92 -0.59 0.33 Array WAR TPR 56 63 23 49 0.13 WAR 11 03H -0.65 Bobbin CBA 56 64 23 49 0.28 VOL 13 04H -0.92 -0.62 0.30 Array WAR TPR 56 64 23 49 0.05 WAR 5 04H -0.70 Bobbin CBA 57 65 22 50 0.49 VOL 16 05H -0.92 -0.54 0.38 Array WAR TPR 57 65 22 50 0.13 WAR 11 05H -0.68 Bobbin CBA 58 66 23 50 0.23 VOL 12 05H -0.86 -0.59 0.27 Array WAR TPR 58 66 23 50 0.11 WAR 10 05H -0.76 Bobbin CBA 59 67 25 50 0.29 VOL 13 03H -0.82 -0.57 0.25 Array WAR TPR 59 67 25 50 0.11 WAR 10 03H -0.66 Bobbin CBA 60 68 55 50 0.32 VOL 14 04C -0.98 -0.71 0.27 Array TPR NBC 61 69 27 51 0.33 VOL 14 07H -0.90 -0.60 0.30 Array WAR TPR NBC 62 70 54 51 0.41 VOL 18 08C -1.13 -0.74 0.39 Array WAR TPR 62 70 54 51 0.11 WAR 10 08C -0.89 Bobbin CBA 63 71 24 52 0.45 VOL 16 03H -0.81 -0.55 0.26 Array WAR TPR 63 71 24 52 0.12 WAR 10 03H -0.61 Bobbin CBA 63 72 24 52 0.53 VOL 17 04H -0.81 -0.55 0.26 Array WAR TPR 63 72 24 52 0.12 WAR 10 04H -0.67 Bobbin CBA 64 73 18 53 0.54 VOL 17 05H -0.87 -0.55 0.32 Array WAR TPR 64 73 18 53 0.11 WAR 10 05H -0.72 Bobbin CBA 65 74 22 53 0.4 VOL 15 04H -0.87 -0.49 0.38 Array WAR TPR NBC 66 75 24 53 0.38 VOL 15 03H -0.75 -0.55 0.20 Array WAR TPR 66 75 24 53 0.12 WAR 10 03H -0.64 Bobbin CBA 67 76 55 53 0.42 VOL 15 07C -0.99 -0.68 0.31 Array WAR TPR NBC 68 77 24 54 0.43 VOL 15 03H -0.75 -0.49 0.26 Array WAR TPR NBC 69 78 54 54 0.36 VOL 14 04C -0.93 -0.70 0.23 Array WAR TPR NBC 70 79 55 55 0.42 VOL 15 04C -0.81 -0.56 0.25 Array WAR TPR NBC 70 80 55 55 0.83 VOL 20 02C -0.64 0.73 1.37 Array WAR FLT 70 80 55 55 0.25 WAR 19 02C -0.39 Bobbin CBA 71 81 23 56 0.36 VOL 14 04H -0.93 -0.62 0.31 Array WAR TPR NBC 72 82 54 56 0.36 VOL 14 04H -0.93 -0.67 0.26 Array WAR TPR NBC 73 83 21 57 0.34 VOL 14 04H -0.72 -0.46 0.26 Array WAR TPR NBC 73 84 21 57 0.29 VOL 13 05H -0.78 -0.52 0.26 Array WAR TPR NBC Page 30 of 39

TABLE 6 Steam Generator 12 TSP Wear Tube # Ind # Row Col Volts Ind Pct Locn Inch1 Inch2 Length PType Util1 Util2 Util3 74 85 22 57 0.37 VOL 14 04H -0.75 -0.49 0.26 Array WAR TPR NBC 75 86 23 57 0.33 VOL 14 04H -0.72 -0.46 0.26 Array WAR TPR NBC 76 87 25 57 0.36 VOL 14 03H -0.72 -0.46 0.26 Array WAR TPR NBC 77 88 53 57 0.47 VOL 16 08C -0.94 -0.59 0.35 Array WAR TPR 77 88 53 57 0.12 WAR 10 08C -0.91 Bobbin CBA 77 89 53 57 0.39 VOL 15 06C -0.90 -0.59 0.31 Array WAR TPR NBC 78 90 54 57 0.47 VOL 16 08C -0.94 -0.53 0.41 Array WAR TPR NBC 79 91 55 57 0.35 VOL 14 06H -1.02 -0.68 0.34 Array WAR TPR NBC 79 92 55 57 0.61 VOL 18 04C -0.87 -0.56 0.31 Array WAR TPR 79 92 55 57 0.15 WAR 13 04C -0.64 Bobbin CBA 79 93 55 57 0.82 VOL 20 03C -0.78 -0.11 0.67 Array WAR TPR 79 93 55 57 0.21 WAR 16 03C -0.59 Bobbin CBA 79 94 55 57 0.44 VOL 16 02C -0.72 -0.28 0.44 Array WAR FLT 79 94 55 57 0.11 WAR 10 02C -0.50 Bobbin CBA 79 95 55 57 0.34 VOL 14 01C -0.75 -0.25 0.50 Array WAR TPR 79 95 55 57 0.09 WAR 8 01C -0.49 Bobbin CBA 80 96 47 58 0.34 VOL 14 05H -0.93 -0.73 0.20 Array WAR TPR NBC 81 97 22 59 0.37 VOL 15 03H -0.95 -0.72 0.23 Array WAR TPR 81 97 22 59 0.07 WAR 6 03H -0.81 Bobbin CBA 82 98 23 59 0.4 VOL 15 03H -1.01 -0.72 0.29 Array WAR TPR 82 98 23 59 0.07 WAR 6 03H -0.78 Bobbin CBA 83 99 54 59 0.29 VOL 13 02C -0.72 0.60 1.32 Array WAR FLT 83 99 54 59 0.11 WAR 10 02C -0.52 Bobbin CBA 84 100 55 59 0.59 VOL 18 04C -0.78 -0.36 0.42 Array WAR TPR 84 100 55 59 0.12 WAR 10 04C -0.62 Bobbin CBA 84 101 55 59 0.22 VOL 12 01C -0.61 -0.41 0.20 Array WAR TPR 84 101 55 59 0.09 WAR 8 01C -0.46 Bobbin CBA 85 102 43 60 0.39 VOL 15 04H -0.72 -0.46 0.26 Array WAR TPR NBC 86 103 48 60 0.38 VOL 15 04H -0.93 -0.70 0.23 Array WAR TPR NBC 86 104 48 60 0.51 VOL 17 05H -1.01 -0.65 0.36 Array WAR TPR NBC 87 105 53 60 0.34 VOL 14 05C 0.34 0.62 0.28 Array WAR TPR 87 105 53 60 0.16 WAR 13 05C 0.48 Bobbin CBA 88 106 54 60 0.32 VOL 14 04C -0.81 -0.48 0.33 Array WAR TPR NBC 88 107 54 60 0.16 WAR 13 01C -0.45 Bobbin CBA 88 107 54 60 0.27 VOL 13 01C -0.20 0.22 0.42 Array WAR TPR 89 108 55 61 0.53 VOL 11 05C 0.25 0.73 0.48 Array WAR TPR 89 108 55 61 0.11 WAR 10 05C 0.45 Bobbin CBA 90 109 51 62 0.35 VOL 14 08C -0.94 -0.64 0.30 Array WAR TPR NBC 91 110 55 62 0.41 VOL 15 04C -0.95 -0.36 0.59 Array WAR TPR 91 110 55 62 0.08 WAR 7 04C -0.64 Bobbin CBA Page 31 of 39

TABLE 6 Steam Generator 12 TSP Wear Tube # Ind # Row Col Volts Ind Pct Locn Inch1 Inch2 Length PType Util1 Util2 Util3 92 111 54 63 0.62 VOL 12 04C 0.28 0.70 0.42 Array WAR TPR 92 111 54 63 0.12 WAR 10 04C 0.45 Bobbin CBA 93 112 55 63 0.33 VOL 14 05C -0.84 -0.45 0.39 Array WAR TPR 93 112 55 63 0.11 WAR 10 05C -0.62 Bobbin CBA 94 113 52 64 0.56 VOL 17 04H -0.95 -0.42 0.53 Array WAR TPR 94 113 52 64 0.14 WAR 12 04H -0.73 Bobbin CBA 95 114 55 64 0.35 VOL 14 04C -0.85 -0.60 0.25 Array WAR TPR 95 114 55 64 0.09 WAR 8 04C -0.80 Bobbin CBA 96 115 23 65 0.44 VOL 16 06H -0.99 -0.58 0.41 Array WAR TPR NBC 97 116 40 65 0.5 VOL 16 05H -0.83 -0.52 0.31 Array WAR TPR NBC 98 117 54 65 0.45 VOL 16 04C -0.83 -0.52 0.31 Array WAR TPR 98 117 54 65 0.17 WAR 14 04C -0.63 Bobbin CBA 99 118 50 69 0.57 VOL 17 03H -0.81 -0.38 0.43 Array WAR TPR NBC 100 119 53 69 0.47 VOL 16 04H -0.81 -0.37 0.44 Array WAR TPR 100 119 53 69 0.11 WAR 10 04H -0.75 Bobbin CBA 101 120 53 70 0.1 WAR 9 04H 0.39 Bobbin NCA 101 121 53 70 0.39 VOL 15 08C -0.99 -0.65 0.34 Array WAR TPR 101 121 53 70 0.12 WAR 10 08C -0.74 Bobbin CBA 102 122 51 71 0.26 VOL 13 06H -1.01 -0.65 0.36 Array WAR TPR NBC 103 123 41 72 0.49 VOL 16 05H -0.81 -0.49 0.32 Array WAR TPR NBC 104 124 52 73 0.13 WAR 11 05C 0.48 Bobbin NCA 105 125 50 74 0.45 VOL 16 03H -0.92 -0.45 0.47 Array WAR TPR NBC 106 126 31 76 0.29 VOL 13 04H -0.98 -0.70 0.28 Array WAR TPR 106 126 31 76 0.06 WAR 6 04H -0.79 Bobbin CBA 107 127 50 76 0.68 VOL 19 05C -0.95 -0.48 0.47 Array WAR TPR 107 127 50 76 0.1 WAR 9 05C -0.62 Bobbin CBA 108 128 11 77 0.39 VOL 15 04H -1.01 -0.73 0.28 Array WAR TPR 108 128 11 77 0.11 WAR 10 04H -0.81 Bobbin CBA 109 129 50 77 0.4 VOL 15 04C -0.85 -0.59 0.26 Array WAR TPR 109 129 50 77 0.12 WAR 10 04C -0.71 Bobbin CBA 110 130 26 82 0.35 VOL 14 04H -0.98 -0.75 0.23 Array WAR TPR 110 130 26 82 0.12 WAR 10 04H -0.86 Bobbin CBA 111 131 39 83 0.5 VOL 16 06H -1.07 -0.69 0.38 Array WAR TPR NBC 112 132 47 85 0.13 WAR 11 06H -0.63 Bobbin NCA 113 133 47 86 0.31 VOL 14 04C -0.91 -0.63 0.28 Array WAR TPR 113 133 47 86 0.11 WAR 10 04C -0.77 Bobbin CBA 114 134 48 86 0.37 VOL 15 05C -0.96 -0.68 0.28 Array WAR TPR 114 134 48 86 0.1 WAR 9 05C -0.79 Bobbin CBA 114 135 48 86 0.28 VOL 13 04C -1.01 -0.66 0.35 Array WAR TPR 114 135 48 86 0.07 WAR 6 04C -0.77 Bobbin CBA Page 32 of 39

TABLE 6 Steam Generator 12 TSP Wear Tube # Ind # Row Col Volts Ind Pct Locn Inch1 Inch2 Length PType Util1 Util2 Util3 115 136 37 87 0.34 VOL 14 03H -0.95 -0.69 0.26 Array WAR TPR 115 136 37 87 0.1 WAR 9 03H -0.69 Bobbin CBA 115 137 37 87 0.11 WAR 10 05H 0.32 Bobbin CBA 115 137 37 87 0.24 VOL 12 05H 0.35 0.49 0.14 Array WAR TPR 116 138 33 88 0.52 VOL 17 06H -1.10 -0.49 0.61 Array WAR TPR 116 138 33 88 0.07 WAR 6 06H -0.84 Bobbin CBA 117 139 38 89 0.56 VOL 17 05C -0.80 -0.49 0.31 Array WAR TPR NBC 118 140 40 90 0.41 VOL 15 04H -0.98 -0.72 0.26 Array WAR TPR NBC 119 141 28 92 0.25 VOL 13 04H -0.98 -0.75 0.23 Array WAR TPR NBC 120 142 40 92 0.13 WAR 11 05C 0.49 Bobbin NCA 121 143 43 92 0.56 VOL 17 06H -1.04 -0.66 0.38 Array WAR TPR NBC 122 144 37 94 0.25 VOL 12 04C -0.89 -0.63 0.26 Array WAR TPR 122 144 37 94 0.12 WAR 10 04C -0.66 Bobbin CBA 123 145 39 94 0.29 VOL 13 03H -0.96 -0.67 0.29 Array WAR TPR 123 145 39 94 0.07 WAR 6 03H -0.69 Bobbin CBA 124 146 34 96 0.34 VOL 14 03H -0.93 -0.72 0.21 Array WAR TPR NBC 125 147 36 97 0.37 VOL 15 03H -0.95 -0.52 0.43 Array WAR TPR NBC 126 148 34 99 0.37 VOL 14 03H -0.96 -0.64 0.32 Array WAR TPR NBC 126 149 34 99 0.42 VOL 15 06H -1.01 -0.72 0.29 Array WAR TPR NBC 127 150 36 99 0.32 VOL 14 06H -1.07 -0.69 0.38 Array WAR TPR 127 150 36 99 0.11 WAR 10 06H -0.78 Bobbin CBA 128 151 35 100 0.45 VOL 16 06H -1.07 -0.72 0.35 Array WAR TPR 128 151 35 100 0.12 WAR 10 06H -0.87 Bobbin CBA 129 152 32 101 0.74 VOL 19 05C -0.83 -0.46 0.37 Array WAR TPR 129 152 32 101 0.14 WAR 12 05C -0.66 Bobbin CBA 129 153 32 101 0.39 VOL 15 04C -0.89 -0.46 0.43 Array WAR TPR NBC 130 154 31 102 0.28 VOL 13 04C -0.86 -0.52 0.34 Array WAR TPR 130 154 31 102 0.1 WAR 9 04C -0.69 Bobbin CBA 131 155 33 102 0.35 VOL 14 04C -0.84 -0.52 0.32 Array WAR TPR 131 155 33 102 0.08 WAR 7 04C -0.69 Bobbin CBA 132 156 30 103 0.33 VOL 14 04H -0.95 -0.72 0.23 Array WAR TPR NBC 133 157 27 105 0.52 VOL 17 05C -0.95 -0.46 0.49 Array WAR TPR 133 157 27 105 0.11 WAR 10 05C -0.66 Bobbin CBA 134 158 25 106 0.5 VOL 16 04C -0.86 -0.55 0.31 Array WAR TPR 134 158 25 106 0.09 WAR 8 04C -0.63 Bobbin CBA 135 159 26 106 0.6 VOL 18 05C -0.78 -0.52 0.26 Array WAR TPR 135 159 26 106 0.11 WAR 10 05C -0.66 Bobbin CBA 135 160 26 106 0.29 VOL 13 04C -0.81 -0.58 0.23 Array WAR TPR 135 160 26 106 0.09 WAR 8 04C -0.72 Bobbin CBA 136 161 28 106 0.38 VOL 15 05C -0.81 -0.49 0.32 Array WAR TPR Page 33 of 39

TABLE 6 Steam Generator 12 TSP Wear Tube # Ind # Row Col Volts Ind Pct Locn Inch1 Inch2 Length PType Util1 Util2 Util3 136 161 28 106 0.09 WAR 8 05C -0.60 Bobbin CBA 136 162 28 106 0.46 VOL 16 04C -0.78 -0.46 0.32 Array WAR TPR 136 162 28 106 0.11 WAR 10 04C -0.64 Bobbin CBA 137 163 25 107 0.29 VOL 13 04C -0.83 -0.43 0.40 Array WAR TPR 137 163 25 107 0.14 WAR 12 04C -0.66 Bobbin CBA 138 164 26 107 0.55 VOL 17 04C -0.84 -0.52 0.32 Array WAR TPR 138 164 26 107 0.07 WAR 7 04C -0.58 Bobbin CBA 139 165 23 108 0.38 VOL 15 04C -0.87 -0.39 0.48 Array WAR TPR 139 165 23 108 0.11 WAR 10 04C -0.65 Bobbin CBA 140 166 24 108 0.44 VOL 16 05C -0.93 -0.59 0.34 Array WAR TPR NBC 141 167 25 108 0.5 VOL 16 04C -0.90 -0.20 0.70 Array WAR TPR 141 167 25 108 0.16 WAR 13 04C -0.62 Bobbin CBA 142 168 21 109 0.4 VOL 15 04C -0.82 -0.45 0.37 Array WAR TPR 142 168 21 109 0.11 WAR 10 04C -0.65 Bobbin CBA 143 169 11 111 0.31 VOL 14 06C -0.98 -0.61 0.37 Array WAR TPR 143 169 11 111 0.12 WAR 10 06C -0.75 Bobbin CBA 144 170 4 113 0.56 VOL 17 05C -0.99 -0.36 0.63 Array WAR TPR 144 170 4 113 0.15 WAR 13 05C -0.74 Bobbin CBA 145 171 6 113 0.37 VOL 15 05C -0.83 -0.58 0.25 Array WAR TPR 145 171 6 113 0.09 WAR 8 05C -0.74 Bobbin CBA 146 172 5 114 0.27 VOL 13 05C -0.88 -0.63 0.25 Array WAR TPR 146 172 5 114 0.1 WAR 9 05C -0.77 Bobbin CBA TABLE 7 Steam Generator 11 Tube Plugging Tube # Ind # Row Col Volts Ind Pct Locn Inch1 Inch2 Length PType Util1 Util2 Util3 1 1 55 60 0.82 VOL 20 03H -0.76 -0.36 0.40 Array WAR TPR 1 1 55 60 0.3 WAR 21 03H -0.56 Bobbin CBA 1 2 55 60 0.42 VOL 15 07H -0.85 -0.48 0.37 Array WAR TPR NBC 1 3 55 60 0.29 VOL 13 08C -1.04 -0.73 0.31 Array WAR TPR NBC 2 4 47 87 0.87 VOL 20 03H -0.75 -0.47 0.28 Array WAR TPR 2 4 47 87 0.32 WAR 22 03H -0.61 Bobbin CBA TABLE 8 Steam Generator 12 Tube Plugging Tube # Ind # Row Col Volts Ind Pct Locn Inch1 Inch2 Length PType Util1 Util2 Util3 1 1 42 54 0.87 VOL 14 AV2 -0.20 0.34 0.54 Array WAR FLT 1 1 42 54 0.3 VOL 9 AV2 -0.11 0.22 0.33 Array WAR FLT 1 1 42 54 0.35 AVB 11 AV2 0.06 Bobbin CBA 1 2 42 54 1.26 VOL 17 AV3 -0.25 0.31 0.56 Array WAR FLT Page 34 of 39

TABLE 8 Steam Generator 12 Tube Plugging Tube # Ind # Row Col Volts Ind Pct Locn Inch1 Inch2 Length PType Util1 Util2 Util3 1 2 42 54 1.38 VOL 18 AV3 -0.20 0.34 0.54 Array WAR FLT 1 2 42 54 0.72 AVB 20 AV3 -0.08 Bobbin CBA 1 3 42 54 2.42 VOL 24 AV4 -0.25 0.34 0.59 Array WAR FLT 1 3 42 54 1.51 VOL 19 AV4 -0.20 0.37 0.57 Array WAR FLT 1 3 42 54 1.18 AVB 27 AV4 -0.11 Bobbin CBA 1 4 42 54 1.9 VOL 21 AV5 -0.25 0.37 0.62 Array WAR FLT 1 4 42 54 1.02 VOL 15 AV5 -0.22 0.39 0.61 Array WAR FLT 1 4 42 54 0.83 AVB 22 AV5 -0.06 Bobbin CBA 1 5 42 54 2.5 VOL 25 AV6 -0.22 0.34 0.56 Array WAR FLT 1 5 42 54 0.86 VOL 14 AV6 -0.17 0.42 0.59 Array WAR FLT 1 5 42 54 0.91 AVB 23 AV6 -0.08 Bobbin CBA 1 6 42 54 1.23 VOL 17 AV7 -0.17 0.37 0.54 Array WAR FLT 1 6 42 54 0.84 VOL 13 AV7 -0.14 0.37 0.51 Array WAR FLT 1 6 42 54 0.62 AVB 18 AV7 -0.06 Bobbin CBA 1 7 42 54 0.56 VOL 11 AV8 -0.17 0.34 0.51 Array WAR FLT 1 7 42 54 0.48 VOL 10 AV8 -0.14 0.31 0.45 Array WAR FLT 1 7 42 54 0.41 AVB 13 AV8 0.08 Bobbin CBA 2 8 39 56 1.03 VOL 15 AV2 -0.12 0.43 0.55 Array WAR FLT 2 8 39 56 0.31 AVB 10 AV2 0.03 Bobbin CBA 2 9 39 56 1.82 VOL 21 AV3 -0.09 0.43 0.52 Array WAR FLT 2 9 39 56 0.4 AVB 13 AV3 0.09 Bobbin CBA 2 10 39 56 0.82 VOL 13 AV4 -0.17 0.35 0.52 Array WAR FLT 2 10 39 56 0.24 AVB 8 AV4 -0.03 Bobbin CBA 2 11 39 56 1.12 VOL 16 AV5 -0.17 0.38 0.55 Array WAR FLT 2 11 39 56 0.4 AVB 13 AV5 -0.06 Bobbin CBA 2 12 39 56 0.82 VOL 13 AV6 -0.17 0.35 0.52 Array WAR FLT 2 12 39 56 0.48 VOL 10 AV6 -0.14 0.40 0.54 Array WAR FLT 2 12 39 56 0.4 AVB 13 AV6 0.06 Bobbin CBA 2 13 39 56 0.3 VOL 9 AV7 -0.14 0.23 0.37 Array WAR FLT 2 13 39 56 0.15 AVB 5 AV7 -0.06 Bobbin CBA 2 13 39 56 0.31 VOL 9 AV7 0.06 0.32 0.26 Array WAR FLT 2 14 39 56 0.46 VOL 10 AV8 -0.09 0.32 0.41 Array WAR FLT 2 14 39 56 0.13 AVB 5 AV8 -0.06 Bobbin CBA 2 15 39 56 0.14 AVB 5 AV9 -0.09 Bobbin CBA 2 15 39 56 0.37 VOL 9 AV9 -0.09 0.30 0.39 Array WAR TPR 3 16 46 56 0.24 VOL 8 AV1 -0.23 0.14 0.37 Array WAR FLT NBC 3 17 46 56 0.29 VOL 9 AV2 -0.23 0.08 0.31 Array WAR FLT NBC 3 18 46 56 0.69 VOL 12 AV3 -0.34 0.17 0.51 Array WAR FLT 3 18 46 56 0.23 AVB 8 AV3 -0.03 Bobbin CBA 3 19 46 56 0.31 VOL 9 AV4 -0.31 0.08 0.39 Array WAR FLT Page 35 of 39

TABLE 8 Steam Generator 12 Tube Plugging Tube # Ind # Row Col Volts Ind Pct Locn Inch1 Inch2 Length PType Util1 Util2 Util3 3 19 46 56 0.13 AVB 5 AV4 -0.08 Bobbin CBA 3 20 46 56 1.69 VOL 20 AV5 -0.37 0.20 0.57 Array WAR FLT 3 20 46 56 0.41 VOL 10 AV5 -0.28 0.20 0.48 Array WAR FLT 3 20 46 56 0.6 AVB 18 AV5 0.08 Bobbin CBA 3 21 46 56 1.54 VOL 19 AV6 -0.37 0.23 0.60 Array WAR FLT 3 21 46 56 0.73 VOL 13 AV6 -0.31 0.23 0.54 Array WAR FLT 3 21 46 56 0.61 AVB 18 AV6 -0.14 Bobbin CBA 3 22 46 56 2.16 VOL 23 AV7 -0.34 0.23 0.57 Array WAR FLT 3 22 46 56 0.61 AVB 18 AV7 0.08 Bobbin CBA 3 23 46 56 1.06 VOL 15 AV8 -0.31 0.23 0.54 Array WAR FLT 3 23 46 56 0.31 AVB 10 AV8 0.03 Bobbin CBA 3 24 46 56 0.36 VOL 9 AV9 -0.25 0.06 0.31 Array WAR FLT NBC 4 25 55 56 0.51 VOL 17 06H -0.98 -0.62 0.36 Array WAR TPR NBC 4 26 55 56 0.51 VOL 11 AV4 -0.28 0.20 0.48 Array WAR FLT 4 26 55 56 0.17 AVB 6 AV4 0.03 Bobbin CBA 4 27 55 56 2.17 VOL 23 AV5 -0.34 0.22 0.56 Array WAR FLT 4 27 55 56 0.67 AVB 19 AV5 0.06 Bobbin CBA 4 28 55 56 1.63 VOL 19 AV6 -0.34 0.25 0.59 Array WAR FLT 4 28 55 56 0.51 AVB 16 AV6 0.11 Bobbin CBA 4 29 55 56 1.88 VOL 21 AV7 -0.39 0.31 0.70 Array WAR FLT 4 29 55 56 0.4 AVB 13 AV7 -0.08 Bobbin CBA 4 30 55 56 0.39 VOL 15 07C -0.87 -0.53 0.34 Array WAR TPR NBC 4 31 55 56 0.37 VOL 15 04C -0.81 -0.56 0.25 Array WAR TPR NBC 4 32 55 56 0.09 WAR 8 03C -0.98 Bobbin CBA 4 32 55 56 0.45 VOL 16 03C -0.76 -0.50 0.26 Array WAR TPR 5 33 55 60 0.54 VOL 17 07C -0.84 -0.48 0.36 Array WAR TPR 5 33 55 60 0.14 WAR 12 07C -0.67 Bobbin CBA 5 34 55 60 0.35 VOL 14 06C -0.82 -0.56 0.26 Array WAR TPR 5 34 55 60 0.13 WAR 11 06C -0.73 Bobbin CBA 5 35 55 60 0.9 VOL 21 02C -0.73 0.76 1.49 Array WAR TPR 5 35 55 60 0.14 WAR 12 02C 0.48 Bobbin CBA 5 36 55 60 0.52 VOL 17 01C -0.63 -0.11 0.52 Array WAR TPR 5 36 55 60 0.16 WAR 13 01C -0.42 Bobbin CBA

3. A description of the condition monitoring assessment and results, including the margin to the tube integrity performance criteria and comparison with the margin predicted to exist at the inspection by the previous forward-looking tube integrity assessment; and The deepest AVB wear indication reported during 1R31 was 27%TW as reported from the bobbin probe and confirmed as flat wear with the X-Probe'. The condition monitoring Page 36 of 39

(CM) limit (probabilistically determined, using Monte Carlo simulations to apply tube material, relation, and ETSS depth uncertainties at 0.95 probability and 50% confidence level (95/50)) for flat (uniformly deep) AVB wear is 50%TW with the bobbin coil, which slightly bounds indications measured by the array coil. As the deepest indication is of lesser depth than the CM limit, CM is satisfied.

The deepest TSP wear indication reported during 1R31 was 22%TW as reported from the bobbin probe and confirmed as tapered wear with the X-Probe'. The tapered wear CM limit (probabilistically determined, using Monte Carlo simulations to apply tube material, relation, and ETSS depth uncertainties at 0.95 probability and 50% confidence level (95/50)) for TSP wear is 44%TW with the bobbin coil, which slightly bounds indications measured by the array coil. As the deepest indication is of lesser depth than the CM limit, CM is satisfied.

Visual inspections were performed of the SG channel head bowl in both SGs. These inspections are performed based on industry operating experience and guideline requirements. Visual inspections of the SG hot leg and cold leg divider plate, inclusive of the entire divider plate to channel head weld and all visible clad surfaces, were performed in accordance with the latest revision of Westinghouse NSAL-12-1. This inspection was performed using the SG manway channel head bowl cameras. Satisfactory inspection results were observed in both SGs with no indications of corrosion or cladding damage observed. Further, all previously installed tube plugs were also visually inspected by remote video camera from the primary side in each SG. The inspection results were satisfactory and showed no indication of tube plug leakage or failure.

4. The number of tubes plugged during the inspection outage.

Table 9 provides the number of tubes plugged during 1R31.

TABLE 9 MECHANISM SG 11 SG 12 AVB Wear 0 4 TSP Wear 2 1

d. An analysis summary of the tube integrity conditions predicted to exist at the next scheduled inspection (the forward-looking tube integrity assessment) relative to the applicable performance criteria, including the analysis methodology, inputs, and results; Additionally, an operational assessment (OA) was performed that provides reasonable assurance that the performance criteria will not be exceeded until the next planned SG inspection.

The OA predicts a projected depth of:

  • 37% for the largest AVB wear indication returned to service,
  • 48% for the largest TSP wear indication returned to service, Page 37 of 39

all based on the array coil after an 8.0 EFPY operating interval. Since the largest indication returning to service is greater than the 95th percentile detection threshold for the inspection for both AVB and TSP wear, this conclusion also applies to the assumed undetected indications. The OA also concludes that the structural and leakage integrity performance criteria will be maintained for both a 3- and 4-cycle inspection interval for all degradation mechanisms observed.

The OA calculations are developed using the computer code Single Flaw Model (SFM)

Version 2.2, wherein the burst pressure of projected flaws is determined through the Monte Carlo simulation method described in the EPRI Steam Generator Integrity Assessment Guideline, Rev. 4. Wear projections use the degradation growth normal distribution (AVB only) and beta distributions along with the single largest growth rate observed in both existing and new indications during U1R31. The OA assessment considers 95th percentile 50% confidence level contributions from depth, relation, material and growth in the reduction in tube burst pressure. Undetected flaws are considered in the OA with an assumed depth equal to the 95th percentile using MAPOD software with EPRI ETSS specific voltage-depth correlation and bounding site-specific noise measurements from the current inspection inputs.

e. The number and percentage of tubes plugged to date, and the effective plugging percentage in each SG; and Table 10 provides the total number and percentage of tubes plugged to date.

TABLE 10 PLUGGING SG 11 SG 12 TOTAL 8 12 PERCENT 0.16% 0.25%

f. The results of any SG secondary side inspections.

Upper Bundle - Minor downcomer LPTS screen grid degradation, on two screen segments, was discovered during 1R30 and dispositioned in the CAP program for one cycle operation without repair. During 1R31 one additional grid with degradation was discovered. All three degraded grids were subsequently replaced during 1R31.

Top-of-Tubesheet - During post sludge lancing and post eddy current FOSAR inspections, no tube degradation was observed that was associated with foreign objects visually observed or eddy current PLP indications recorded.

A top of tubesheet deposit cleaning process was performed in all SGs during Prairie Island U1R31. There are two main purposes of the cleaning process. The first is to remove hardened deposits that tend to form at the top of the tubesheet and the second is to force and filter out any loose parts or foreign objects that have migrated to the SG secondary side during operation. The mass of deposit material and debris removed by the top of tubesheet cleaning process was 12.0 lbs. in SG11 and 13.0 lbs. in SG12. Review of the system in-line filters was performed following the tubesheet cleaning process. This confirmed that the cleaning process was successful at removing a very small number of foreign objects and agglomerated deposit material from the RSG secondary side. The Page 38 of 39

subsequent secondary side visual inspections showed the tubesheet to be essentially free of deposits with only limited hard sludge piles. Hard sludge piles spanning several tubes were observed in the RSGs including SG11 near hot leg columns 42 and 54, SG12 hot leg columns 48 and 54 and SG12 cold leg column 36.

LEGEND OF FIELDS AND CODES FIELD EXPLANATION Tube # Distinct ROW/COL combination within each Table Ind # Distinct ROW/COL/LOCATION combination within each Table Row Row number of tube location Col Column number of tube location Volts Measured Voltage Ind Three Digit Code - see below Pct Measured percent through wall Locn Location of landmark - see below Inch1 Measurement in inches from the center of the landmark to the center of the indication for Bobbin records or Measurement in inches from the center of the landmark to the lower edge of the indication for Array records Inch2 Measurement in inches from the center of the landmark to the upper edge of the indication for Array records Length Inch1 minus Inch2 PType Probe Coil Type - Array or Bobbin Util1 Clarifying Codes - see below Util2 Clarifying Codes - see below Util3 Clarifying Codes - see below FIELD CODE EXPLANATION Ind AVB Anti-Vibration Bar VOL Volumetric WAR Wear Locn 0?H  ? = First through Eighth tube support plate on hot leg side AV?  ? = First through Ninth anti-vibration bar 0?C  ? = First through Eighth tube support plate on cold leg side Util1 TPR Tapered wear WAR Wear Util2 CBA Confirmed By Array coil FLT Flat (non-tapered) wear NBC No Bobbin Call NCA Not Confirmed by Array coil TPR Tapered wear Util3 NBC No Bobbin Call TPR Tapered wear Page 39 of 39