Entergy Nuclear Northeast Entergy Nuclear Operations, Inc.

James A. Fitzpatrick NPP

-P.O. Box I"1-Lycoming, NY 13093 Tel 315-342-3840 January 10, 2009 JAFP-09-0004 United States Nuclear Regulatory Commission Attn: Document Control Desk Washington, D.C. 20555

Subject:

James A. FitzPatrick Nuclear Power Plant Docket No. 50-333 License No. DPR-59 Inservice Inspection Summary Report 2008 Refuel Outage (Reload 18/Cycle 19)

Reference:

1. Entergy letter to USNRC (JAFP-07-0030), "Fourth Inservice Inspection Interval Inspection Program Plan", dated February 27, 2007

Dear Sir or Madam:

This letter submits the James A. FitzPatrick (JAF) Owner's Activity Report, JAF-RPT 00019, Rev. 0 (Enclosure 1) which contains a'summary of the Inservice Inspection (ISI) examinations conducted during the plant's fall 2008 Refuel Outage (Reload1 8/Cycle 19).

Table 1 of the enclosed report summarizes the items with flaws or relevant indications that required evaluation for continued service and Table 2 provides an abstract of repair/replacement activities required for continued service. This Report is being submitted in accordance with JAF's approved Fourth Inservice Inspection Interval Inspection Program Plan (Reference 1).

Should you have any questions concerning this letter, please contact Mr. Joseph Pechacek at (315) 349-6766.

This letter contains no new commitments.

Very truly yours, Joseph Pechacek Licensing Manager JP:ed Enclosure I: JAF Owner's Activity Report (OAR), First Outage, First Period, Fourth Interval (Report No. JAF-RPT-08-00019, rev.0) cc: Next page / 3 4f,7 Page 1 of 5

JAFP-09-0004 Page 2 of 2 cc: Regional Administrator, Region 1 U.S. Nuclear Regulatory Commission 475 Allendale Road King of Prussia, PA 19406-1415 Office of the Resident Inspector U.S. Nuclear Regulatory Commission James A. FitzPatrick Nuclear Power Plant P.O. Box 136 Lycoming, NY 13093 Mr. Bhalchandra Vaidya, Project Manager Plant Licensing Branch I I Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation U.S. Nuclear Regulatory Commission Mail Stop O-8-C2 Washington, DC 20555-0001 Mr. Paul Tonko, President NYSERDA 17 Columbia Circle Albany, NY 12203-6399

Enclosure I to JAFP-09-0004 Entergy Nuclear Operations, Inc. - J. A. FitzPatrick Docket No. 50-333 JAF Owner's Activity Report (OAR), First Outage, First Period, Fourth Interval (Report No. JAF-RPT-08-00019, Rev. 0)

ATTACHMENT 9.1 ENGINEERING REPORT COVER SHEET & INSTRUCTIONS SHEET 1 OF 2 Engineering Report No. JAF-RPT-08-00019 Rev. 0 Page 1 of 6

? Entergy ENTERGY NUCLEAR Engineering Report Cover Sheet Engineering Report

Title:

JAF Owner's Activity Report (OAR) First Outage, First Period, Fourth Interval Engineering Report Type:

New [ Revision 13 Cancelled 11 Superseded E3 Applicable Site(s)

IP 1 El IP2 13 IP3 E3 JAF E PNPS El vy El wpo EI ANO1 El ANO2 13 ECH El GGNS F] RBS El WF3 F1 PLP [I DRN No. ON/A; 13 Report Origin: [ Entergy 13 Vendor Vendor Document No.:

Quality-Related: Z Yes [] No Prepared by: Scott Reed Date: 12/30/2008 Responsible Engineer (Print Name/Sign)

Design Verified/ Design Verification is not required Date: N/A Design Verifier (if required) (Print Name/Sign)

Reviewed by:

Neal Chapman "4 - -- _- Date: 12/30/2008 Reviewer (Print Na mý/Sign)

Reviewed by*: Ron Fabiny Date: 12/30/2008 ANII (if*ud)(#

e int men )

Approved by: Joe Pechacek'... , Date: 12/30/2008 Supervis (Print Name/Sign)

FORM OAR-i OWNER'S ACTIVITY REPORT Report Number JAF-RPT-08-00019 Plant James A. FitzPatrick Nuclear Power Plant, 268 Lake Road East, Lycominc New York 13093 Unit No. 1 Commercial Service Date July 28, 1974 Refueling Outage Number R18 (if applicable)

Current Inspection Interval 4th (1st, 2nd, 3", 4-, other)

Current Inspection Period 1st (1st, 2"d, 3rd)

Edition and Addenda of Section XI applicable to the Inspection Plans 2001 Edition, 2003 Addenda Date / Revision of Inspection Plans March 1, 2007 / ISI Proqram Plan, Rev. 1 No. JAF-RPT-06-001 Edition and Addenda of Section XI applicable to repair/replacement activities, if different than the inspection plans Same Code Cases used: N-416-3, N-532-4 CERTIFICATE OF CONFORMANCE I certify that (a) the statements made in this report are correct; (b) the examinations and tests, meet the Inspection Plan as required by the ASME Code,Section XI; and (c) the repair/replacement activities and evaluations supporting the completion of R18 conform to the requirements of Section XI (refueling outage number)

Signed Scott Reed ' 1 / jz . Date 12/30/2008 (Owner or Owner's designee.

Title:

Sr Lead Technical Spec (Nuc))

CERTIFICATE OF INSERVICE INSPECTION I, the undersigned, holding a valid commission issued by the National Board of Boiler and Pressure Vessel Inspectors and the State or Province of . New York and employed by HSB CT of Hartford, CT have inspected the items described in this Owner's Activity Report, and state that to the best of my knowledge and belief, the Owner has performed all activities represented by this report in accordance with the requirements of Section XI By signing this certificate neither the Inspector nor his employer makes any warranty expressed or implied concerning the repair/

replacement activities and evaluation described in this report. Furthermore, neither the Inspector nor his employer shall be liable in any manner for any personal injLor property damage or a loss of any kind arising from or connected with this inspection Ron Fabiny \ Commissions NY3061 (Inspector's Signaturaizý National Board, State, Province, and Endorsements Date 12/30/2008 Engineering Report No. JAF-RPT-08-00019 Rev.0 Page 2 of 6

TABLE 1 ITEMS WITH FLAWS OR RELEVANT CONDITIONS THAT REQUIRED EVALUATION FOR CONTINUED SERVICE Examination Category and Item Number Item Description Evaluation Description B-F / B5.10 Nozzle to Safe End Weld / N-2C-SE CR-JAF-2008-03311 - ISI examination of the N2C-SE identified an axial indication requiring repair.

Weld overlay repair performed per ISI program plan Relief Request #7 (RR-7) and Work Order 00166023.

C-A / C1.20 Head to Shell Weld / TH1-A CR-JAF-2008-02724 - ISI examination identified two subsurface planar indications requiring further evaluation per ASME Section XI requirements.

Evaluation of the indications was performed and acceptable per ASME Section XI Table IWC-3510-1 requirements.

E-A /E1.11 Torus Saddle Support/ CR-JAF-2008-02842 - IWE General Visual examination of the primary containment SC-SD-Azm @ 100-54' (Torus) saddle support assembly identified hold down brackets exhibiting SC-SD-Azm @ 1000-54' recordable conditions per the ASME Section XI program.

SC-SD-Azm @ 1240-6' SC-SD-Azm @ 1450-54' Engineering evaluation identified the degraded condition of the saddle hold-down SC-SD-Azm @ 2350-54' anchor bracket locations are capable of performing their design function of SC-SD-Azm @ 2590-6' restraining the torus when subjected to all required design loading conditions.

SC-SD-Azm @ 2800-54' Work Order 00167052 generated to reposition the torus saddle hold down bracket SC-SD-Azm @ 3040-6' shim plates identified.

SC-SD-Azm @ 3490-6' E-A / E1.11 Torus Shell Plates / SC-PL-Bay (A CR-JAF-2008-03439 - ASME Section XI, IWE, General Visual examination of the through P) Torus exterior surfaces identified coating (paint) was either missing or had minor degradation in various locations.

Engineering evaluated the condition and the indication was accepted as is. The integrity of the Torus Shell remains intact as there is no degradation of the steel Torus shell and it is capable to perform its intended design function.

E-A / E1.11, E1.30 Primary Containment Moisture CR-JAF-2008-03508 - During scheduled IWE inspection of drywell 256' elevation, Barrier Area degraded conditions at the carbon steel drywell liner interface were recorded per the ASME Section XI program.

These conditions were evaluated and acceptable to Engineering for continued operational service. Work Order 00166758 was initiated for repairof concrete and coatings in the area of interest.

Engineering Report No. JAF-RPT-08-00019 Rev.0 Page 3 of 6

TABLE 1 ITEMS WITH FLAWS OR RELEVANT CONDITIONS THAT REQUIRED EVALUATION FOR CONTINUED SERVICE F-A / F1.10 Class 1 Piping Supports / 12-14-NS-3 CR-JAF-2008-02959 - ISI examination of piping box support 12-14-NS-3 / PFSK 1896 identified an approximate 1/4" gap between the support and bottom side of the pipe.

A shim or spacer plate was installed to correct the condition per Work Order 00167099.

N/A Whip Restraint / 02-2-6A-NN-1E CR-JAF-2008-03738 - VT-3 examination identified clearances not in accordance with the drawing.

___Engineering evaluated the condition and the indication was accepted as is.

N/A Hydraulic Snubber / 10-32B-HS-277 CR-JAF-2008-04139 - ISI examination of snubber 10-32B-HS-277 identified settings not in accordance with the design drawing.

Engineering evaluation accepted all conditions identified.

N/A 15-3"-WES-151-136 Piping CR-JAF-2007-03665 - Small Bore Piping Leak Replacement Pinhole leak was evaluated and acceptable to Engineering for continued service.

Piping replacement performed per Work Order 00127395, reference repair replacement plan #07-025.

N/A 67-2-3"-WS-151-1 Piping CR-JAF-2007-03693 - Small Bore Piping Leak Replacement Pinhole leak was evaluated and acceptable to Engineering for continued service.

Piping replacement performed per Work Order 00127709, reference repair replacement plan #07-026.

N/A 15-8"-WES-151-100 Piping CR-JAF-2008-01914 - Piping Leak Replacement Pinhole leak was evaluated and acceptable to Engineering for continued service.

Piping replacement performed per Work Order 00155590, reference repair replacement plan #08-052.

N/A 29AOV-80D Repair CR-JAF-2008-03062 - MSIV 29AOV-80D LLRT failure.

Valve seats repaired per Work Order 00165300, reference repair replacement plan

  1. 08-058.

Engineering Report No. JAF-RPT-08-00019 Rev.0 Page 4 of 6

TABLE 2 ABSTRACT OF REPAIR/REPLACEMENT ACTIVITIES REQUIRED FOR CONTINUED SERVICE Code Class Item Description Date Repair/Replacement Description Of Work Completed Plan Number 1 02-2P-1B Seal Replacement 07/08/2005 05-019 3 46EXJ-7A Expansion Joint Replacement 12/06/2005 05-024 3 46EXJ-7B Expansion Joint Replacement 10/28/2006 06-040 3 70TCV-120A Valve Replacement 10/23/2007 07-003 3 70TCV-121A Valve Replacement 10/25/2007 07-004 3 70TCV-121B Valve Replacement 04/19/2007 07-005 3 70TCV-120B Valve Replacement- 04/20/2007 07-006 3 02RV-71F Valve Replacement 08/21/2007 07-007 3 70RWC-2B(CND) Tube Sheet Replacement 07/16/2007 07-010 3 BFSK-457 (66UC-22D) Support Repair (Removal and replacement 12/11/2008 07-019 for maintenance) 3 46P-2A Pump Replacement 12/14/2007 07-020 2 11P-2B Pump Replacement 01/03/2008 07-024 3 15-3"-WES-151-136 Piping Replacement -- 10/26/2007.07-025 3 67-2-3"-WS-151-1 Piping Replacement 10/31/2007 07-026 2 10-2B-HS-162 Snubber Replacement 02/20/2008 07-027 3 46RO-101A1 Repair Flange (weld Buildup) 12/12/2007 07-028 3 46(70)SWS-50A Valve Replacement 12/14/2007 07-029 2 1ORHR-51A AND 10RHR-52A Valve Replacement 04/29/2008 08-003 2 13RCIC-3 Valve Replacement 10/03/2008 08-004 2 10-9B-HS-287 Snubber Replacement 09/08/2008 08-005 1 02RV-71B Valve Replacement 10/05/2008 08-008 1 02RV-71F Valve Replacement (Main Body) 10/03/2008 08-010 1 02RV-71A Valve Replacement 10/05/2008 08-011 1 02RV-71C Valve Replacement 10/05/2008 08-012 1 02RV-71D Valve Replacement 10/05/2008 08-013 1 02RV-71F Valve Replacement 10/05/2008 08-014 1 02RV-71E Valve Replacement 10/05/2008 08-015 1 02RV-71G Valve Replacement 10/05/2008 08-016 1 02RV-71H Valve Replacement 10/05/2008 08-017 1 02RV-71J Valve Replacement 10/05/2008 08-018 1 02RV-71K Valve Replacement 10/05/2008 08-019 1 02RV-71L Valve Replacement 10/05/2008 08-020 2 27-2"-N-152A-23 Piping Replacement 09/29/2008 08-021 Engineering Report.No. JAF-RPT-08-00019 Rev.0 Page 5 of 6

TABLE 2 ABSTRACT OF REPAIR/REPLACEMENT ACTIVITIES REQUIRED FOR CONTINUED SERVICE 1 02RV-71D Valve Replacement (Main Body) 10/05/2008 08-022 1 02RV-71E Valve Replacement (Main Body) 10/05/2008 08-023 1 34-4B-HS-36 Snubber Replacement 09/23/2008 08-024 1 34-4A-HS-16 Snubber Replacement 09/26/2008 08-025 1 29-1D-HS-41 Snubber Replacement 09/26/2008 08-026 1 29-1D-HS-36 Snubber Replacement 09/27/2008 08-027 1 29MOV-102 Valve Replacement 09/23/2008 08-028 1 02-2-1B-HS-20 Snubber Replacement 09/20/2008 08-029 1 03CRDU-(26-11, 26-43, 02-23, 02-31, 10- CRDM Replacement 09/26/2008 08-030 11, 10-15, 10-19, 18-07, 22-39, 22-51,

.26-35, 30-19, 34-23, 34-27, 42-11, 46-39) 2 23-19-HS-17 Snubber Replacement 09/02/2008 08-032 2 10-17-HS-57 Snubber Replacement 07/24/2008 08-033 2 23-1-HS-92 Snubber Replacement 08/18/2008 08-034 2 10-12A-HS-117 Snubber Replacement 07/23/2008 08-035 1 29-1B-HS-15 Snubber Replacement 09/20/2008 08-037 2 10-9B-HS-8 Snubber Replacement 09/08/2008 08-038 1 02-2-2A-HS-3 Snubber Replacement 09/24/2008 08-039 1 02-2-2B-HS-4 Snubber Replacement 09/19/2008 08-040 1 02-2-2A-HS-4 Snubber Replacement 09/24/2008 08-041 1 02-2-2B-HS-3 Snubber Replacement 09/19/2008 08-042 1 10-1-HS-208 Snubber Replacement 09/22/2008 08-043 1 14-5B-HS-43 Snubber Replacement 09/22/2008 08-044 1 14-5B-HS-44 Snubber Replacement 09/22/2008 08-045 1 34-5D-HS-27 Snubber Replacement 09/19/2008 08-046 3 BFSK-915 Support Repair (Removal and replacement 07/09/2008 08-047 for maintenance) 2 10-15A-MS-307 Snubber Replacement 08/11/2008 08-049 2 10-15A-MS-303 Snubber Replacement 08/18/2008 08-050 3 15-8"-WES-151-100 Piping Replacement 08/05/2008 08-052 1 29AOV-80D Repair 29AOV-80D LLRT Failure 10/01/2008 08-058 1 10-14B-HS-245A Snubber Replacement 09/26/2008 08-061 1 29-1C-HS-26 Snubber Replacement 09/26/2008 08-062 1 N2C-SE N2C Weld Overlay Repair 10/05/2008 08-063 Engineering Report No. JAF-RPT-08-00019 Rev.0 Page 6 of 6