JAFP-20-0087, Inservice Inspection Summary Report Cycle 24

From kanterella
Jump to navigation Jump to search
Inservice Inspection Summary Report Cycle 24
ML20363A181
Person / Time
Site: FitzPatrick Constellation icon.png
Issue date: 12/28/2020
From: Sullivan R
Exelon Generation Co
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
JAFP-20-0087
Download: ML20363A181 (6)


Text

Exelon Generation JAFP-20-0087 December 28, 2020 United States Nuclear Regulatory Commission Attn: Document Control Desk Washington, D.C. 20555 James A FitzPatrick NPP POBox110 Lycoming. NY 13093 Tel 315-342-3840 Richard Sullivan Regulatory Assurance Manager - JAF James A. FitzPatrick Nuclear Power Plant Renewed Facility Operating License No. DPR-59 NRC Docket No. 50-333

Subject:

Reference:

1)

Dear Sir or Madam:

lnservice Inspection Summary Report Cycle 24 Exelon letter, Fifth Ten-Year lnservice Inspection Interval Program Plan, JAFP-18-0113, dated December 17, 2018 This letter submits the James A. FitzPatrick Nuclear Power Plant (JAF) Owner's Activity Report, First Period, Fifth Interval which contains a summary of the lnservice Inspection (ISi) examinations conducted during the plant's 2020 Refuel Outage 24 (FP1 R24).

Table 1 of the enclosed report summarizes the items with flaws or relevant indications that required evaluation for continued service and Table 2 provides an abstract of repair/replacement activities required for continued service.

This report is being submitted in accordance with JAF's approved Fifth Interval lnservice Inspection Program Plan [Reference 1].

There are no new regulatory commitments contained in this letter. If you have any questions in this regard, please contact Mr. Michael Faivus, Programs Engineering Branch Manager, at (315) 349-1895.

Very truly yours, f =s:: I Richard Sullivan Regulatory Assurance Manager RS/hm

Enclosure:

JAF Owner's Activity Report (OAR) First Period, Fifth Interval cc:

NRC Region 1 Administrator NRC Project Directorate NRC Resident Inspector NYSERDA

JAFP-20-0087 ENCLOSURE JAF Owner's Activity Report (OAR)

First Period, Fifth Interval (3 Pages)

FORM OAR-1 OWNER'S ACTIVITY REPORT Report Number FP1 R24 Plant -------~J=am=es~A~. ~F~ilzP~a=tr~ic~k~N~u=c~le=a=r~P~o~w~e~r~P~la=n=t,~2=6=8~L=a~ke~R=d~.,~L-Y=Co=m~in-g~,~N=e~w~Y~o~rk~13-0~9=3 Plant Unit 1

Commercial Service Date July 28. 1975 Refueling Outage Number R24 Qf appllcabla)

Current Inspection Interval : ________

~F~i=fth~IS=l~ln~t=e,..,rv=a,,_I....,CO=B~/0~1=/2=0~1~7_-_0=6=/"'"'15=/2=0=2=7.,_) _____ _

(1st, 2nd, 3rd, 4th, Clthar)

Current Inspection Period : ____

~F~irs=t~ln=s""p=e=ctt=*o=n.,__,,,P,.a;e;--;ri;=-o:=,d.-,l,,-:0=8/=0~1/=2=0~17~-~12/=3~1/=20=2=0'-'-) ________________ _

(1st 2nd, 3rd)

Edition and Addenda of Section XI applicable to the Inspection Plan 2007 Edition. 2008 Addenda Date and Revision of Inspection Plan: ER-JF-330-1001, Rev. 2 (09/17/2020)

Edition and Addenda of ASME Section XI applicable to Repairs and Replacements, if different than the Inspection Plan: Same Code Cases used for inspection and evaluation: Code Cases used at James A. FitzPatrick. Unit 1, during the Fifth In service Inspection Interval are identified in Document#ER-AA-~30-1007, Revision 0.

f applicable)

CERTIFICATE OF CONFORMANCE I certify that (a) statements made in this report are correct; (b) the examination and tests meetthe Inspection Plan as required by the ASME Code,Section XI; and (c) the repair/replacement activities and evaluations supporting the completion of R24 conform to the requirements of Section XI.

(refueling 01Jage number)

Graham Jacquell*ne T1"tus DigitallysignedbyGraham,Jacquelinentus Date: 2020.12.23 09:08:12 -05'00' Signed ______ ~-~--~~--------------- Date Owner d Owner's Deslgnee, TIUe: Engineer 12/23/2020 ____

CERTIFICATE OF INSERVICE INSPECTION I, the undersigned, holding a valid commission issued by the National Board of Boiler and Pressure Vessel Inspectors and the State or Province of New York and employed by The Hartford Steam Boiler Inspection and Insurance Company of Hartford, CT have inspected the items described in this Owner's Activity Report and state that to the best of my knowledge and belief, the Owner has performed all activities represented by this report in accordance with the requirements of Section XI.

By signing this certificate neither the Inspector nor his employer makes any warranty, expressed or implied, concerning the repair/replacementactivities and evaluations described in this report. Furthermore, neither the Inspector nor his employer shall be liable in any manner for any personal injury or property damage or a loss of any kind arising from or connected with this inspection.

powers, Brand On Digitally signed by Powers, Brandon D_at_e:_2_02_0_*1_2*_23_0_9

_=1_3:_s,_-o_s_*o_o_* _Commissions_~16=1=5~8~A~N~IR~N~Y5=5~70-=----~----

1nspec1or's Slgnalu"e Natlonal Boa-d, Stale, Pravlrce, aid Erdorsemenls Date ________ _

Table 1:

Items with Flaws or Relevant Conditions That Required Evaluation for Continued Service Examination Category Item Description Evaluation Description and Item Number D-B/D2.10 Through-wall leak in 46-10"-

IR 04351640 - Through wall leak on line WES-151-37 46-1 0"-WES-151-37 ASME Section XI Code Case N-513-3 was employed and concluded the flaw was caused by a combination of MIC and a weld defect.

Extent-of-condition examinations were performed on 5 comparable locations. The section of pipe was replaced during the R24 refueling outage.

Table 2:

Abstract of Reoair/Rec lacement Activities Reouired for Continued Service CODE ITEM DESCRIPTION DATE REPAIR/

CLASS DESCRIPTION OF COMPLETED REPLACEMENT WORK PLAN NUMBER 3

Repair Repair thinned section of 9/19/2019 19-010 46STR-581 Basket Housing 3

Replace Replace valve 70PCV-7/2/2019 19-015 100A1 3

Replace Contingency - 10EXJ-4C 9/10/2019 19-016 expansion joint 3

Replace Replace 46EXJ-10D 9/17/2019 19-018 3

Replace Replace elbow and piping 7/20/2019 19-019 66UC-22E supply line 66-2.5"-WES-151-13 2

Replace Contingency - 10EXJ-4D 10/21/2019 19-020 expansion joint 2

Replace Replace 03TK-125(HCU-9/22/2020 19-024 42-43) 3 Repair Weld repair discharge 5/9/2020 19-028 head on 10P-1B 2

Replace Remove snubber JAF-8/28/2020 19-066 45355 and replace with new@ location 10-158-MS-1258 2

Replace Remove snubber JAF-9/9/2020 19-067 45776 and replace with new @ location 10-15A-MS-304 1

Replace IST-Perform (RLF) Testing 9/30/2020 19-068 of 02RV-71A 1

Replace IST-Perform (RLF) Testing 9/30/2020 19-069 of 02RV-71J 1

Replace IST-Perform (RLF) Testing 9/30/2020 19-071 of 02RV-71E 1

Replace IST-Perform (RLF) Testing 9/30/2020 19-076 of 02RV-71K 1

Repair Seal Weld 12MOV-15 2/21/2020 20-002 1

Replace R24 CRDM Exchange 9/24/2020 20-012

-- ---- - - ---------- -- --- -- --- ---------- ------