IR 05000461/2025002
| ML25209A151 | |
| Person / Time | |
|---|---|
| Site: | Clinton |
| Issue date: | 07/28/2025 |
| From: | April Nguyen NRC/RGN-III/DORS/RPB1 |
| To: | Rhoades D Constellation Energy Generation, Constellation Nuclear |
| References | |
| IR 2025002 | |
| Download: ML25209A151 (1) | |
Text
SUBJECT:
CLINTON POWER STATION - INTEGRATED INSPECTION REPORT 05000461/2025002
Dear David Rhoades:
On June 30, 2025, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at Clinton Power Station. On July 21, 2025, the NRC inspectors discussed the results of this inspection with A. Krukowski, Plant Manager, and other members of your staff. The results of this inspection are documented in the enclosed report.
No findings or violations of more-than-minor significance were identified during this inspection.
This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at https://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations 2.390, Public Inspections, Exemptions, Requests for Withholding.
Sincerely, April Nguyen, Team Leader Palisades Restart Team Division of Operating Reactor Safety Docket No. 05000461 License No. NPF-62
Enclosure:
As stated
Inspection Report
Docket Number:
05000461
License Number:
Report Number:
Enterprise Identifier:
I-2025-002-0053
Licensee:
Constellation Nuclear
Facility:
Clinton Power Station
Location:
Clinton, IL
Inspection Dates:
April 01, 2025, to June 30, 2025
Inspectors:
J. Cassidy, Senior Health Physicist
R. Farmer, Health Physicist
T. Hartman, Senior Resident Inspector
J. Hickey, Senior Project Engineer
M. Learn, Team Leader
A. Muneeruddin, Resident Inspector
J. Murphy, Illinois Emergency Management Agency
V. Rand, Project Engineer
N. Shah, Senior Project Engineer
J. Steward, Senior Resident Inspector
Approved By:
April Nguyen, Team Leader
Palisades Restart Team
Division of Operating Reactor Safety
SUMMARY
The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees performance by conducting an integrated inspection at Clinton Power Station, in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information.
List of Findings and Violations
No findings or violations of more-than-minor significance were identified.
Additional Tracking Items
None.
PLANT STATUS
Unit 1 began the inspection period at rated thermal power (RTP). On April 12, May 17, May 31, June 14, June 21, and June 28, 2025, Unit 1 lowered power to between 75 and 85 percent RTP to perform planned control rod sequence exchange and other rod adjustments to ensure an even fuel depletion. Following completion of these reactivity manipulations, the unit was returned to RTP and continued to operate at or near RTP for the remainder of the inspection period.
INSPECTION SCOPES
Inspections were conducted using the appropriate portions of the inspection procedures (IPs)in effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with their attached revision histories are located on the public website at http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html. Samples were declared complete when the IP requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter (IMC) 2515, Light-Water Reactor Inspection Program - Operations Phase. The inspectors performed activities described in IMC 2515, Appendix D, Plant Status, observed risk-significant activities, and completed on-site portions of IPs. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess licensee performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards.
REACTOR SAFETY
71111.01 - Adverse Weather Protection
Impending Severe Weather Sample (IP Section 03.02) (1 Sample)
- (1) The inspectors evaluated the adequacy of the overall preparations to protect risk-significant systems from impending severe weather including high winds and severe thunderstorms on April 2, 2025.
71111.04 - Equipment Alignment
Partial Walkdown Sample (IP Section 03.01) (5 Samples)
The inspectors evaluated system configurations during partial walkdowns of the following systems/trains:
(1)division 2 shutdown service water system on April 15, 2025 (2)division 1 shutdown service water system on April 25, 2025 (3)division 2 emergency diesel generator fuel oil transfer system on April 29, 2025 (4)division 1 emergency diesel generator fuel oil transfer system on April 29, 2025 (5)component cooling water system on May 6, 2025
71111.05 - Fire Protection
Fire Area Walkdown and Inspection Sample (IP Section 03.01) (5 Samples)
The inspectors evaluated the implementation of the fire protection program by conducting a walkdown and performing a review to verify program compliance, equipment functionality, material condition, and operational readiness of the following fire areas:
- (1) Fire Area A-3d, 762' auxiliary building non-safety related switchgear (west)on April 23, 2025
- (2) Fire Areas CB-3a through CB-3g, and CB-4, division 2 cable spreading room on April 23, 2025
- (3) Fire Area R-1c, 702' radwaste building basement north and south on May 8, 2025
- (4) Fire Area R-1h, 720' radwaste building intermediate floor north and south on May 14, 2025
- (5) Raw water treatment building on June 9, 2025
71111.07A - Heat Exchanger/Sink Performance
Annual Review (IP Section 03.01) (1 Sample)
The inspectors evaluated readiness and performance of:
(1)1vy03AB, residual heat removal (RHR) heat exchanger room cooler per work order (WO) 05409628-11 on April 24, 2025
71111.11Q - Licensed Operator Requalification Program and Licensed Operator Performance
Licensed Operator Performance in the Actual Plant/Main Control Room (IP Section 03.01) (1 Sample)
- (1) The inspectors observed and evaluated licensed operator requalification simulator training on April 8, 2025.
Licensed Operator Requalification Training/Examinations (IP Section 03.02) (1 Sample)
- (1) The inspectors observed and evaluated a planned downpower to 85 percent RTP and performed a control rod pattern adjustment on April 12, 2025.
71111.12 - Maintenance Effectiveness
Maintenance Effectiveness (IP Section 03.01) (2 Samples)
The inspectors evaluated the effectiveness of maintenance to ensure the following structures, systems, and components (SSCs) remain capable of performing their intended function:
(1)failure of 1RIX-PR034, off-gas pretreatment radiation monitor sample pump per action request (AR) 4843986 and (WO) 5631787-01 on April 10, 2025 (2)systems and support equipment readiness to perform containment venting without AC power available. This sample utilized elements of the Operating Experience Smart Sample 2020/01 Flex Equipment Design Control, Maintenance, and Testing, performed on May 8, 2025
Quality Control (IP Section 03.02) (1 Sample)
The inspectors evaluated the effectiveness of maintenance and quality control activities to ensure the following SSC remains capable of performing its intended function:
(1)commercial grade dedication of parts utilized to restore the division 2 switchgear heat removal ventilation system compressor, 1VX06CB to service per WO 05555842 on June 16, 2025
71111.13 - Maintenance Risk Assessments and Emergent Work Control
Risk Assessment and Management Sample (IP Section 03.01) (2 Samples)
The inspectors evaluated the accuracy and completeness of risk assessments for the following planned and emergent work activities to ensure configuration changes and appropriate work controls were addressed:
(1)elevated risk (action green) due to a tornado warning issued for Dewitt County on April 2, 2025 (2)elevated risk (action green) due to planned work on the reserve auxiliary transformer B load tap controller during April 14, 2025, through April 19, 2025
71111.15 - Operability Determinations and Functionality Assessments
Operability Determination or Functionality Assessment (IP Section 03.01) (5 Samples)
The inspectors evaluated the licensees justifications and actions associated with the following operability determinations and functionality assessments:
(1)345 KV voltage transient caused a momentary spike, which resulted in the north bus voltage below the voltage band for reserve auxiliary transformer B load tap changer tap 1 position in manual per AR 4852085 on April 2, 2025 (2)division II emergency diesel generator fuel oil transfer pump failed surveillance test on low flow per AR 4860111 on April 28, 2025 (3)reactor recirculation jet pump number 9 indication failed high due to transmitter failure per AR 4864530 on May 15, 2025 (4)main turbine bypass valve number 1 fast acting solenoid actuated late per AR 487003487003on June 6, 2025
- (5) RHR pump minimum flow check valve, 1E12-F046B open exercise unsatisfactory per AR 4873782 on June 18, 2025
71111.18 - Plant Modifications
Temporary Modifications and/or Permanent Modifications (IP Section 03.01 and/or 03.02) (1 Sample)
The inspectors evaluated the following temporary or permanent modifications:
(1)temporary transfer water from containment floor drain sump to the containment equipment drain sump per engineering change (EC) 644014 on May 29, 2025
71111.24 - Testing and Maintenance of Equipment Important to Risk
The inspectors evaluated the following testing and maintenance activities to verify system operability and/or functionality:
Post-Maintenance Testing (PMT) (IP Section 03.01) (9 Samples)
- (1) RHR heat exchanger 1A cooling coil B, 1vy03AB leak testing following eddy current testing and plugging of one tube per WO 05409628 tasks 04 and 05 on April 16, 2025 (2)control room supply fan B testing following replacement of the fan blade and hub assembly per WO 5645427-04 on April 17, 2025 (3)condensate pump D minimum flow valve testing following replacement of the transducer per WO 05631661-03 on April 18, 2025 (4)division 2 4.16 KV degraded voltage trip functional testing following replacement of time delay relays per WO 05602069-01 on April 29, 2025 (5)reserve auxiliary transformer B post-maintenance test following replacement of the load tap changer motor and cam switches per WO 5588161-15 on April 21, 2025 (6)standby liquid control system pressure testing following replacement of the B pump discharge relief valve per WO 05605199-05 on May 7, 2025 (7)control room ventilation train A damper testing following maintenance on May 15, 2025 (8)control room ventilation train A supply fan, 0VC03CA testing following maintenance on May 20, 2025 (9)main steam line pressure low instrument line in service testing following failure and associated channel calibration of transmitter 1B21-N076A per WO 05555842-03 on June 6, 2025
Surveillance Testing (IP Section 03.01) (4 Samples)
(1)diesel generator 1C test mode override and load reject operability test per Clinton Power Station (CPS) 9080.26 on April 30, 2025.
(2)diesel generator 1C monthly operability test per CPS 9080.03 on May 7, 2025
- (3) RHR pump B operability test per CPS 9053.07 on June 18, 2025 (4)division 1 shutdown service water operability test per CPS 9069.01P001 on June 25, 2025
Inservice Testing (IST) (IP Section 03.01) (2 Samples)
(1)standby liquid control pump B operability test per CPS 9015.01 on May 13, 2025
- (2) RHR pump A operability/waterleg pump double check valve test per CPS 9052.01P002 on May 20, 2025
71114.06 - Drill Evaluation
Required Emergency Preparedness Drill (1 Sample)
- (1) Clinton 2025 pre-exercise emergency plan drill on June 17,
RADIATION SAFETY
71124.07 - Radiological Environmental Monitoring Program
Environmental Monitoring Equipment and Sampling (IP Section 03.01) (1 Sample)
- (1) The inspectors evaluated environmental monitoring equipment and observed collection of environmental samples.
Radiological Environmental Monitoring Program (IP Section 03.02) (1 Sample)
- (1) The inspectors evaluated the implementation of the licensees radiological environmental monitoring program.
GPI Implementation (IP Section 03.03) (1 Sample)
- (1) The inspectors evaluated the licensees implementation of the Groundwater Protection Initiative (GPI) program to identify incomplete or discontinued program elements.
71124.08 - Radioactive Solid Waste Processing & Radioactive Material Handling, Storage,
& Transportation
Radioactive Material Storage (IP Section 03.01)
The inspectors evaluated the licensees performance in controlling, labeling and securing the following radioactive materials:
(1)shepherd calibrator and shipping pad (2)large fab shop, old resin storage building, and nuclear materials cage
Radioactive Waste System Walkdown (IP Section 03.02) (2 Samples)
The inspectors walked down the following accessible portions of the solid radioactive waste systems and evaluated system configuration and functionality:
(1)radioactive waste truck bay and associated waste processing areas (2)radwaste mixed storage area
Waste Characterization and Classification (IP Section 03.03) (3 Samples)
The inspectors evaluated the following characterization and classification of radioactive waste: (1)irradiated hardware (2)dry activated waste (3)suppression pool resin
Shipment Preparation (IP Section 03.04) (1 Sample)
- (1) The inspectors observed the preparation of radioactive shipment W25-005 of irradiated hardware on May 23, 2025.
Shipping Records (IP Section 03.05) (4 Samples)
The inspectors evaluated the following non-excepted radioactive material shipments through a record review:
- (1) W24-018, Dry Activated Waste, Bear Creek, December 5, 2024
- (2) W24-013, Suppression Pool Resin, Clive, September 3, 2024
- (3) W25-001, Waste Sludge Resin, Clive, April 15, 2025
- (4) W25-005, Irradiated Hardware, WCS, May 23,
OTHER ACTIVITIES - BASELINE
===71151 - Performance Indicator Verification The inspectors verified licensee performance indicators submittals listed below:
MS06: Emergency AC Power Systems (IP Section 02.05)===
- (1) April 1, 2024, through March 31, 2025
MS07: High Pressure Injection Systems (IP Section 02.06) (1 Sample)
- (1) April 1, 2024, through March 31, 2025
MS08: Heat Removal Systems (IP Section 02.07) (1 Sample)
- (1) April 1, 2024, through March 31, 2025
71152A - Annual Follow-up Problem Identification and Resolution Annual Follow-up of Selected Issues (Section 03.03)
The inspectors reviewed the licensees implementation of its corrective action program related to the following issues:
(1)nuclear fleet wide action 04787989-23 to risk rank all small-bore vent and drain pipes in the drywell that see primary system pressure that would prevent recurrence of a forced outage similar to what resulted from the C1F64 Clinton Power Station Forced Outage due to excessive drywell leakage event on May 23, 2023. Inspectors reviewed the site completed corrective actions for this issue on June 30, 2025.
71152S - Semiannual Trend Problem Identification and Resolution Semiannual Trend Review (Section 03.02)
- (1) The inspectors reviewed the licensees corrective action program to identify potential trends in content and disposition of items listed in degraded equipment/operations concerns list, which is included in every plan of the day that might be indicative of a more significant safety issue. For this sample the inspectors focused on a snapshot of the 22 items contained in the degraded equipment/operations concerns list on May 7,
INSPECTION RESULTS
Observation: Review of the Plan of the Day Degraded Equipment/Operations Concerns List 71152S The inspectors noted the degraded equipment/operations concerns list contained 22 work orders and is included in each plan of the day. The inspectors organized the 22 items into 4 categories related to the degraded conditions potential impact on the operating unit. There were 6 items associated with balance of plant-support, 4 items in balance of plant-electrical, 2 items in balance of plant-auxiliary, and 11 items in reactor-support. The inspectors reviewed the items for length of time on the list, potential for plant impacts if the identified condition worsened before correction, and potential cumulative impacts of all 22 items.
One item of note the inspectors evaluated was the item titled, Sudden drops in service air header pressure, added to the list on September 15, 2024. The issue was documented under AR 04801875 and work request (WR) 01567135. The licensees impact assessment states a loss of service air can result in undesired control rod insertion and a plant scram.
The inspectors noted the service air system was the subject of a previous problem identification and resolution trend sample in the third quarter of 2024, as documented in Inspection Report 2024003. In that report, the inspectors noted similar performance issues that did not result in a plant transient. The inspectors reviewed the service air system health report and noted multiple component deficiencies being tracked. Items include corrective actions for issues such as component leak by, overdue preventive maintenance, and unusual noises/indications.
The inspectors also evaluated three items associated with shutdown service water piping issues, including a code case repair, low ultrasonic thickness readings, and a through wall leak added from August to October of 2024. The inspectors reviewed the interim corrective actions and planned corrective actions to resolve the identified conditions.
Finally, the inspectors evaluated plant chiller WO-D which tripped due to low oil pressure caused by an oil leak, added to the list on April 17, 2025. The licensees impact assessment notes the loss of redundancy for the chilled water system and impact to temperature sensitive areas which may result in a scram. The inspectors reviewed the corrective actions and planned return to service schedule.
The inspectors did not identify any findings or violations of NRC requirements in the course of this review.
EXIT MEETINGS AND DEBRIEFS
The inspectors verified no proprietary information was retained or documented in this report.
- On July 21, 2025, the inspectors presented the integrated inspection results to A. Krukowski, Plant Manager, and other members of the licensee staff.
- On May 29, 2025, the inspectors presented the radiation protection inspection results to A. Krukowski, Plant Manager, and other members of the licensee staff.
DOCUMENTS REVIEWED
Inspection
Procedure
Type
Designation
Description or Title
Revision or
Date
4302.01
Tornado/High Winds
23d
Procedures
Severe Weather and Natural Disaster Guidelines
M05-1036 sheet
001
P&ID Diesel Generator Fuel Oil System
T
M05-1036 sheet
2
P&ID Diesel Generator Fuel Oil System
T
M05-1052 sheet 2
P&ID Shutdown Service Water
M05-1052 sheet 4
P&ID Shutdown Service Water
X
M05-1052 sheet 5
P&ID Shutdown Service Water
AH
Drawings
M05-9036 sheet 1
P&ID Div-1 Fuel Oil Tandem EMD 3869KW Diesel
Generator Set 1DG01KA
G
211.01E001
Shutdown Service Water Electrical Lineup
18a
211.01V001
Shutdown Service Water Valve Lineup
3506.01
Diesel Generator and Support Systems
41b
3506.01E001
Diesel Generator and Support Systems Electrical Lineup
18d
3506.01V001
Diesel Generator and Support Systems Valve Lineup
13a
Procedures
3506.01V002
Diesel Generator and Support Systems Instrument Valve
Lineup
11b
1893.04M122
2' Auxiliary Building Non-Safety Related Switchgear
(West)
5a
1893.04M350
781 Control: Div 2 Cable Spreading Room Prefire Plan
5d
1893.04M600
2 Radwaste: Basement (South) Prefire Plan
5b
1893.04M601
2 Radwaste: Basement (North) Prefire Plan
5b
1893.04M610
20 Radwaste: Intermediate Floor (South) Prefire Plan
7a
1893.04M611
20-725 Radwaste: Intermediate Floor (North) Prefire Plan
Fire Plans
1893.04M912
Raw Water Treatment Building Prefire Plan
1019.05
Transient Equipment/Materials
26c
22.11
Fire Extinguisher Maintenance
22.13
Visual Inspections of Portable Fire Extinguishers
Procedures
22.13C001
Visual Inspection of Portable Fire Extinguishers Checklist -
4a
Inspection
Procedure
Type
Designation
Description or Title
Revision or
Date
Power Block and Essential Areas Within Protected Area
Engineering
Evaluations
VY-45
Performance Evaluation of VY System Cooling Coils
Under SX Flow Testing Limits
3005.01
Unit Power Changes
3302.01
Reactor Recirculation (RR)
39e
3304.01
Control Rod Hydraulic & Control (RD)
3304.02
Rod Control and Information System (RC&IS)
ESG-LOR-OBE-
001
Clinton Power Station Licensed Operator Training Simulator
Exercise Guide
Procedures
Conduct of Simulator Training and Evaluation
Corrective Action
Documents
04458706,
04505554,
04538194,
2464340,
04045129,
04352392,
04015784,
221389,
04136932
Various ARs Associated with the System and Components
Manipulated During the Activity
05/08/2025
Clinton Power Station Plant Status Report
03/11/2025
01479190
Purchase Order for 1VX06CB compressor component
10/07/2024
20626200
Commercial Grade Dedication Quality Receipt Inspection
Package
09/09/2024
91010190
Commercial Grade Dedication Plan Evaluation
09/09/2024
91011720
Commercial Grade Dedication Plan Evaluation
10/04/2024
Miscellaneous
91011721
Commercial Grade Dedication Plan Evaluation
10/04/2024
Procedures
4303.01P0001
Containment Venting Without AC Power Available
08/30/2013
Work Orders
5315952,
292551,
5194798,
4945309,
1797187,
1635009,
Various Work Orders on System Components Incorporated
as Part of the Activity Under Review
05/08/2025
Inspection
Procedure
Type
Designation
Description or Title
Revision or
Date
1557859,
5106920,
1400874,
1300882,
4990640,
5388728,
Miscellaneous
RICT Record for Reserve Auxiliary Transformer B
Inoperability
04/16/2025
4302.01
Tornado/High Winds
23d
Procedures
Risk Informed Completion Time
Corrective Action
Documents
04843283
Enhancement IR for RHR B Observations
06/17/2025
Engineering
Changes
2554
Evaluation of RHR B Pump Minimum Flow Acceptance
PTP-RH-1
RHR B Pump Curve
09/27/1985
Miscellaneous
Clinton Technical Specifications and Bases
04/02/2025
9041.01
Jet Pump Operability Test
05/15/2025
Procedures
9082.01
Offsite Source Power Verification
Engineering
Changes
644014
Temporary Transfer Water from Containment RF to
Containment RE
04833675
SX Piping Shaking 737' CB
01/30/2025
04856663
1VY03AB - Eddy Current Test Results
04/15/2025
04865169
0VC03CA crack found in removed hub
05/13/2025
04868124
Low UT Reading Obtained on 1SX93EA-3"
05/23/2025
Corrective Action
Documents
4857731
04/16/2025
640989
As Built Document Changes for RAT B MSC
Engineering
Changes
641286
Tube Repair for Room Cooler Coils, 1VY03AA/AB
Engineering
Evaluations
VY-45
Performance Evaluation of VY System Cooling Coils Under
SX Flow Acceptance Limits
211.01
Shutdown Service Water
33d
9015.01
Standby Liquid Control System Operability
Procedures
9052.01P002
RHR Pump A Operability/WLP Double Check Valve Test
000
Inspection
Procedure
Type
Designation
Description or Title
Revision or
Date
9080.03
Diesel Generator 1C Operability - Manual and Quick Start
Operability
9080.26
DG 1C Test Mode Override and Load Reject Operability
7b
9866.02
VG/VC Charcoal Adsorber Leak Test
9069.01P001
Division 1 Shutdown Service Water Operability Test
MA-AA-716-230-
1002
Vibration Analysis/Acceptance Guideline
01708072-02,
01871691-02,
04595054-02,
04595055-02,
04946944-02,
01661475-02,
01661475-03
Various Work Orders Associated with Post-Maintenance
Testing of Control Room Train A Ventilation Dampers
05/15/2025
289122-02,
05548656-03,
239963-02
Various Work Orders Associated with 0VC03CA, Main
Control Room Ventilation Supply Fan Maintenance and
Testing
05/20/2025
05631329-01
9053.07B21 OP RHR Pump OPER Test (B Pump)
06/17/2025
Work Orders
05635953
OP SLC Pump B Operability
05/13/2025
Miscellaneous
25 Clinton Pre-Exercise Emergency Drill Package
06/17/2025
91W506166
Field Rotameter Calibration
11/04/2024
CL-90, CL-91,
CL-99
Water Compositor Calibration
10/23/2024
Calibration
Records
Contract
01370443
Clinton Meteorological Calibration
08/13/2024
NRC ID: Missed ODCM Sample
09/22/2022
REMP/ODCM CL-14 Sampling Anomaly
01/08/2024
0UIXPR050 All Channels Failed Primary Met Tower
2/20/2024
ODCM/REMP - CL-99 Pipe Needs Extended
10/23/2024
ODCM Sampling Anomalies CL-14
03/19/2025
Corrective Action
Documents
REMP Location CL-02 Timer Anomalies for 1Q2025
04/09/2025
Inspection
Procedure
Type
Designation
Description or Title
Revision or
Date
05/22/2025
Corrective Action
Documents
Resulting from
Inspection
NRCID: Potential Enhancements in the AREOR
05/22/2025
Annual Report on the Meteorological Monitoring Program at
the Clinton Power Station 2024
05/10/2025
2604558-RPT-1
23 Hydrogeologic Investigation Report (HIR)
08/06/2024
Clinton Power Station 2023 Annual Radiological
Environmental Operation Report
04/15/2024
Miscellaneous
Clinton Power Station 2024 Annual Radiological
Environmental Operation Report
04/29/2025
EIML-SPM-1
Sampling Procedures Manual
Radiological Groundwater Protection Program
Radiological Groundwater Protection Program
Procedures
EN-CL-408-4160
RGPP Reference Material for Clinton Power Station
Self-Assessments AR 04795557
NRC Inspection: Radiological Environmental Monitoring
Program (IP 71124.07)
03/19/2025
Work Orders
05012252
Radiological Groundwater Protection Program Risk
Reassessment
10/19/2023
Corrective Action
Documents
Resulting from
Inspection
NRC ID Water on Floor of Old Resin Storage Building
05/21/2025
AS5-AS5B
Dimensional/Visual Inspection Form
04/08/2025
D462939
CFR 61 DAW 2024 Waste Stream Review and Scaling
Factor Determination Report
07/08/2024
D464242
CFR 61 Suppression Pool Resin Waste Stream Review
and Scaling Factor Determination Report
09/03/2024
D464927
RP-AA-600-1005 Radioactive Shipment Notification Form,
09/03/2024
Miscellaneous
ES-WM-QA-
25-7
Certificate of Conformance, Energy Solutions 3-60B
Transport Cask
04/16/2025
Inspection
Procedure
Type
Designation
Description or Title
Revision or
Date
W24-018
RP-AA-600-1005 Radioactive Shipment Notification Form
2/05/2024
Miscellaneous
Regulatory Assessment Performance Indicator Guideline
71151
Procedures
71151
Performance Indicator Verification
01/01/2025
Corrective Action
Documents
4846474,
0486048401,
0485747501,
0486100401,
0485870901,
0485878201,
04862659,
Miscellaneous System and component ARs
05/01/2025
Work Orders
05650684-01,
05555842-02,
05658568-02,
05622558-01,
05627505-01,
01578152,
05104350-01,
05586848-01,
05586261-01,
05613518-01,
05661214-01,
05661214-03,
05662245-01,
05651611-01,
05588697-01,
01581550,
05608939-02,
05655934-01
Miscellaneous System and Component WOs
05/01/2025