MONTHYEARIR 05000458/20213012024-11-14014 November 2024 NRC Initial Operator Licensing Examination Approval 05000458/2021301 ML24289A0312024-11-0808 November 2024 – Issuance of Amendments Related to the Removal of License Condition 2.F as Part of the Consolidated Line-Item Improvement Process (CLIIP) IR 05000458/20240102024-10-31031 October 2024 Design Basis Assurance Inspection (Programs) Inspection Report 05000458/2024010 IR 05000458/20240032024-10-31031 October 2024 Integrated Inspection Report 05000458/2024003 RBG-48315, Reply to a Notice of Violation, NRC Inspection Report 05000458/2023003 Supplement2024-09-24024 September 2024 Reply to a Notice of Violation, NRC Inspection Report 05000458/2023003 Supplement RBG-48306, Report of Changes and Errors to 10CFR50.462024-09-24024 September 2024 Report of Changes and Errors to 10CFR50.46 ML24263A2712024-09-19019 September 2024 Application to Revise Technical Specifications to Adopt TSTF-592, Revise Automatic Depressurization System (ADS) Instrumentation Requirements ML24255A1192024-09-16016 September 2024 Notification of NRC Follow Up Inspection for One Severity Level (SL) III and Two SL IV or Three or More SL IV Violations and Request for Additional Information RBG-48311, Reply to a Notice of Violation, NRC Inspection Report 05000458/20240022024-08-28028 August 2024 Reply to a Notice of Violation, NRC Inspection Report 05000458/2024002 IR 05000458/20240052024-08-22022 August 2024 Updated Inspection Plan for River Bend Station (Report 05000458/2024005) ML24220A2642024-08-20020 August 2024 Entergy Operations, Inc. - Entergy Fleet Project Manager Assignment ML24185A1522024-08-13013 August 2024 Issuance of Amendment Nos. 334, 235, and 215, Respectively, to Revise TSs to Adopt TSTF-205 ML24214A2752024-08-0202 August 2024 Acknowledgement of Readiness for Supplemental Inspection RBG-48308, Notification of Readiness for Supplemental Inspection2024-07-31031 July 2024 Notification of Readiness for Supplemental Inspection IR 05000458/20240022024-07-30030 July 2024 Integrated Inspection Report 05000458/2024002 and Notice of Violation ML24164A0862024-06-12012 June 2024 Notification of Commercial Grade Dedication Inspection (05000458/2024010) and Request for Information 05000458/LER-2023-005-01, Manual Reactor Scram Due to Lowering Feedwater Temperature Following an Automatic Isolation of Feedwater Heater String2024-06-0404 June 2024 Manual Reactor Scram Due to Lowering Feedwater Temperature Following an Automatic Isolation of Feedwater Heater String ML24060A2192024-05-30030 May 2024 Authorization of Alternative to Use EN-RR-01 Concerning Proposed Alternative to Adopt Code Case N-752 ML24093A0892024-05-16016 May 2024 Issuance of Amendment No. 214 Adoption of 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, Systems, and Components for Nuclear Power Reactors ML24081A0072024-05-16016 May 2024 Issuance of Amendment No. 213 Revision to Technical Specifications to Adopt TSTF 505, Revision 2, Provide Risk-Informed Extended Completion Times – RITSTF Initiative 4b IR 05000458/20240012024-05-14014 May 2024 Integrated Inspection Report 05000458/2024001 ML24102A2842024-05-0707 May 2024 Summary of Regulatory Audit in Support of LARs to Revise Technical Specifications to Adopt Risk-Informed Completion Times and Implement the Provisions of 10 CFR 50.69 ML24128A0422024-05-0707 May 2024 License Amendment Request to Remove Obsolete License Conditions RBG-48276, 2023 Annual Radioactive Effluent Release Report2024-04-23023 April 2024 2023 Annual Radioactive Effluent Release Report IR 05000458/20244022024-04-15015 April 2024 Security Baseline Inspection Report 05000458/2024402 (Full Report) RBG-48288, Louisiana Pollutant Discharge Elimination System Permit Renewal2024-04-15015 April 2024 Louisiana Pollutant Discharge Elimination System Permit Renewal ML24106A0432024-04-11011 April 2024 June 2024 Emergency Preparedness Exercise Inspection Request for Information ML24101A3882024-04-10010 April 2024 Response to Request for Confirmation of Information by the Office of Nuclear Reactor Regulation Proposed Alternative Request EN-RR-22-001 Risk-Informed Categorization and Treatment for Repair RBG-48277, 2023 Annual Radiological Environmental Operating Report2024-04-10010 April 2024 2023 Annual Radiological Environmental Operating Report IR 05000458/20243012024-04-0202 April 2024 Notification of NRC Initial Operator Licensing Examination 05000458/2024301 ML24089A2262024-03-29029 March 2024 Entergy Response to Regulatory Issue Summary 2024-01, Preparation and Scheduling of Operator Licensing Exams IR 05000458/20240402024-03-15015 March 2024 – 95001 Supplemental Inspection Report 05000458/2024040 and Follow-Up Assessment ML24075A1712024-03-15015 March 2024 Nuclear Onsite Property Damage Insurance (10 CFR 50.54(w)(3)) ML24074A2892024-03-14014 March 2024 Proof of Financial Protection (10 CFR 140.15) ML24066A1802024-03-0707 March 2024 Notification of NRC Follow-Up Inspection for Any Severity Level I or II Traditional Enforcement Violation IR 05000458/20230062024-02-28028 February 2024 Annual Assessment Letter for River Bend Station - Report 05000458/2023006 RBG-48286, Revision to Owners Activity Report Form (OAR) for Cycle 222024-02-27027 February 2024 Revision to Owners Activity Report Form (OAR) for Cycle 22 RBG-48278, 2023 Spent Fuel Storage Radioactive Effluent Release Report2024-02-27027 February 2024 2023 Spent Fuel Storage Radioactive Effluent Release Report ML24031A0042024-02-21021 February 2024 Exemption from Select Requirements of 10 CFR Part 73 (EPID L-2023-LLE-0052 (Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting)) 05000458/LER-2023-006, Automatic Reactor Scram Due to a Turbine Trip Following a Disconnect Failure at Switchyard2024-02-0808 February 2024 Automatic Reactor Scram Due to a Turbine Trip Following a Disconnect Failure at Switchyard RBG-48274, Notification of Readiness for Supplemental Inspection2024-02-0505 February 2024 Notification of Readiness for Supplemental Inspection IR 05000458/20230042024-01-30030 January 2024 Integrated Inspection Report 05000458/2023004 IR 05000458/20230402024-01-18018 January 2024 – 95001 Supplemental Inspection Supplemental Report 05000458/2023040 and Follow-Up Assessment Letter 05000458/LER-2023-005, Manual Reactor Scram Due to Lowering Feedwater Temperature Following an Automatic Isolation of Feedwater Heater String2024-01-16016 January 2024 Manual Reactor Scram Due to Lowering Feedwater Temperature Following an Automatic Isolation of Feedwater Heater String ML24012A1962024-01-12012 January 2024 Response to 2nd Round Request for Additional Information Concerning Relief Request Number EN-RR-22-001 – Proposed Alternative to Use ASME Code Case N-752, Risk-Informed Categorization and RBG-48271, Supplement to License Amendment Request to Adopt Risk Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times – RITSTF Initiative 4b and Application to Adopt 10 CFR 50.69, Risk2024-01-12012 January 2024 Supplement to License Amendment Request to Adopt Risk Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times – RITSTF Initiative 4b and Application to Adopt 10 CFR 50.69, Risk ML24011A1742024-01-11011 January 2024 Security Baseline Inspection Report (Cover Letter) 05000458/LER-2023-004, Drywall Post Accident Radiation Monitor Inoperable Due to Unrecognized Surveillance Failure2023-12-28028 December 2023 Drywall Post Accident Radiation Monitor Inoperable Due to Unrecognized Surveillance Failure ML23349A1672023-12-21021 December 2023 Request for Withholding Information from Public Disclosure ML23348A3572023-12-14014 December 2023 Application to Revise Technical Specifications to Use Online Monitoring Methodology – Slides and Affidavit for Pre-Submittal Meeting 2024-09-24
[Table view] Category:Inspection Report
MONTHYEARIR 05000458/20213012024-11-14014 November 2024 NRC Initial Operator Licensing Examination Approval 05000458/2021301 IR 05000458/20240032024-10-31031 October 2024 Integrated Inspection Report 05000458/2024003 IR 05000458/20240102024-10-31031 October 2024 Design Basis Assurance Inspection (Programs) Inspection Report 05000458/2024010 IR 05000458/20240052024-08-22022 August 2024 Updated Inspection Plan for River Bend Station (Report 05000458/2024005) IR 05000458/20240022024-07-30030 July 2024 Integrated Inspection Report 05000458/2024002 and Notice of Violation ML24164A0862024-06-12012 June 2024 Notification of Commercial Grade Dedication Inspection (05000458/2024010) and Request for Information IR 05000458/20240012024-05-14014 May 2024 Integrated Inspection Report 05000458/2024001 IR 05000458/20244022024-04-15015 April 2024 Security Baseline Inspection Report 05000458/2024402 (Full Report) IR 05000458/20243012024-04-0202 April 2024 Notification of NRC Initial Operator Licensing Examination 05000458/2024301 IR 05000458/20240402024-03-15015 March 2024 – 95001 Supplemental Inspection Report 05000458/2024040 and Follow-Up Assessment IR 05000458/20230062024-02-28028 February 2024 Annual Assessment Letter for River Bend Station - Report 05000458/2023006 IR 05000458/20230042024-01-30030 January 2024 Integrated Inspection Report 05000458/2023004 IR 05000458/20230402024-01-18018 January 2024 – 95001 Supplemental Inspection Supplemental Report 05000458/2023040 and Follow-Up Assessment Letter IR 05000458/20230102023-12-12012 December 2023 Biennial Problem Identification and Resolution Inspection Report 05000458/2023010 IR 05000458/20230032023-11-13013 November 2023 Integrated Inspection Report 05000458/2023003 IR 05000458/20234012023-09-26026 September 2023 Cyber Security Inspection Report 05000458/2023401 IR 05000458/20234032023-09-21021 September 2023 NRC Security Inspection Report 05000458/2023403 (Cover Letter) IR 05000458/20230122023-09-0101 September 2023 – Comprehensive Engineering Team Inspection Report 05000458/2023012 IR 05000458/20230052023-08-21021 August 2023 Updated Inspection Plan for River Bend Station (Report 05000458/2023005) - Mid Cycle Letter IR 05000458/20230922023-08-15015 August 2023 Final Significance Determination of a White Finding, Notice of Violation, and Follow-Up Assessment Letter; NRC Inspection Report 05000458/2023092 IR 05000458/20230022023-08-0909 August 2023 Integrated Inspection Report 05000458/2023002 IR 05000458/20230912023-07-20020 July 2023 Final Significance Determination of a White Finding, Notice of Violation, and Follow-Up Assessment Letter; NRC Inspection Report 05000458/2023091 IR 05000458/20234042023-07-11011 July 2023 NRC Security Inspection Report 05000458/2023404 (Cover Letter Only) IR 05000458/20230902023-06-26026 June 2023 NRC Inspection Report 05000458/2023090 and Preliminary White Finding IR 05000458/20230012023-05-0101 May 2023 Integrated Inspection Report 05000458/2023001 IR 05000458/20230112023-04-12012 April 2023 NRC License Renewal Phase 1 Inspection Report 05000458/2023011 IR 05000458/20220062023-03-0101 March 2023 Annual Assessment Letter for River Bend Station Report 05000458/2022006 IR 05000458/20220042023-02-0101 February 2023 Integrated Inspection Report 05000458/2022004 IR 05000458/20220102022-12-12012 December 2022 Triennial Fire Protection Inspection Report 05000458/2022010 IR 05000458/20220032022-11-0303 November 2022 And Independent Spent Fuel Storage Installation Integrated Inspection Report 05000458/2022003 and 07200049/2022001 IR 05000458/20224022022-09-12012 September 2022 NRC Security Inspection Report 05000458/2022402 (Full Report) IR 05000458/20220022022-08-0909 August 2022 Integrated Inspection Report 05000458/2022002 IR 05000458/20220112022-06-0202 June 2022 Design Basis Assurance Inspection (Programs) Inspection Report 05000458/2022011 IR 05000458/20220012022-04-27027 April 2022 Integrated Inspection Report 05000458/2022001 IR 05000458/20210062022-03-0202 March 2022 Annual Assessment Letter (Report 05000458/2021006) IR 05000458/20210042022-01-25025 January 2022 Integrated Inspection Report 05000458/2021004 ML22011A0992022-01-14014 January 2022 IR 2021012 EOI CO3 IR 05000458/20214022021-12-15015 December 2021 Security Baseline Inspection Report 05000458/2021402 IR 05000458/20214042021-12-0707 December 2021 Material Control and Accounting Program Inspection Report 05000458/2021404, Publicly Available IR 05000458/20214012021-12-0303 December 2021 Security Baseline Inspection Report 05000458/2021401 IR 05000458/20223012021-11-30030 November 2021 Notification of NRC Initial Operator Licensing Examination 05000458/2022301 IR 05000458/20210032021-11-0404 November 2021 Integrated Inspection Report 05000458/2021003 IR 05000458/20210912021-09-30030 September 2021 Notice of Violation and Proposed Imposition of $150,000 Civil Penalty, NRC Inspection Report 05000458/2021091 and Investigation Reports 4-2020-008, 4-2020-009, and 4-2020-019 IR 05000458/20210022021-08-11011 August 2021 Integrated Inspection Report 05000458/2021002 IR 05000458/20210902021-07-0101 July 2021 NRC Inspection Report 05000458/2021090 and Investigation Reports 4-2020-008, 4-2020-009, and 4-2020-019 IR 05000458/20210132021-05-25025 May 2021 Rriver Bend Station - NRC Baseline Inspection Report 05000458/2021013 IR 05000458/20214032021-05-24024 May 2021 Security Baseline Inspection Report 05000458/2021403 IR 05000458/20210012021-05-0505 May 2021 RBS2021001-RP-RJK, River Bend Station - Integrated Inspection Report 05000458/2021001 IR 05000458/20210102021-03-18018 March 2021 2021 River Bend Station - Biennial Problem Identification and Resolution Inspection Report 05000458/2021010 and Notice of Violation IR 05000458/20200042021-02-11011 February 2021 RBS2020004-RP-RJK, River Bend Station - Integrated Inspection Report 05000458/2020004 2024-08-22
[Table view] |
Text
UNIT ED STAT ES NU C LE AR RE G UL AT O RY C O M M I S S I O N May 17, 2010
SUBJECT:
RIVER BEND STATION - NRC SECURITY INSPECTION REPORT 05000458/2010405
Dear Mr. Perito:
On April 22, 2010, the U.S. Nuclear Regulatory Commission (NRC) completed an Independent Spent Fuel Storage Installation (ISFSI) security Inspection at your River Bend Station. The inspection covered the NRCs Additional Security Measures (ASMs) for the Physical Protection of Dry Independent Spent Fuel Storage Installation. The enclosed inspection report documents the inspection results, which were discussed on April 22, 2010, with you and other members of your staff.
The inspection examined activities conducted under your license as they relate to security and compliance with the Commissions rules and regulations and with the conditions of your license.
The inspector reviewed selected procedures and records, observed activities, and interviewed personnel.
Based on the results of this inspection, no findings of significance were identified.
In accordance with 10 CFR 2.390 of the NRCs Rules of Practice, a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of the NRCs document system, ADAMS.
ADAMS is accessible from the NRC Website at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room). However, because of the security-related concerns contained in the enclosure, and in accordance with 10 CFR 2.390, a copy of this letters enclosure will not be available for public inspection. Entergy Operations, Inc. 1 In accordance with 10 CFR 2.390(b)(1)(ii), the NRC is waiving the affidavit requirements for your response, if any. This practice will ensure that your response will not be made available electronically for public inspection in the NRC Public Document Room or from the NRCs document system, ADAMS. If Safeguards Information is necessary to provide an acceptable response, please provide the level of protection described in 10 CFR 73.21. Otherwise, mark your entire response "Security-Related Information-Withhold Under 10 CFR 2.390" and follow the instructions for withholding in 10 CFR 2.390(b)(1).
Sincerely,
/RA/ James Larsen for Michael P. Shannon, Chief Plant Support Branch-1 Division of Reactor Safety Docket Nos.: 50-458 License Nos.: NPF-47 Nonpublic Enclosure:
NRC Inspection Report 05000458/2010405 w/Attachment: Supplemental Information cc w/o enclosure:
Senior Vice President Entergy Nuclear Operations P. O. Box 31995 Jackson, MS 39286-1995 Senior Vice President and COO Entergy Operations, Inc.
P. O. Box 31995 Jackson, MS 39286-1995 Vice President, Oversight Entergy Operations, Inc.
P. O. Box 31995 Jackson, MS 39286-1995 Senior Manager, Nuclear Safety & Licensing Entergy Nuclear Operations P. O. Box 31995 Jackson, MS 39286-1995 Manager, Licensing Entergy Operations, Inc.
River Bend Station 5485 US Highway 61N St. Francisville, LA 70775 Associate General Counsel Entergy Nuclear Operations P. O. Box 31995 Jackson, MS 39286-1995 Distribution w/enclosure:
Ronald Albert (Ronald.Albert@nrc.gov), Chief, Reactor Security Oversight Branch Shyrl Coker, (Shyrl.Coker@nrc.gov) NSIR/DSO/DDSO, TWFN Mail Stop: T-3A5M Senior Resident Inspector (Grant.Larkin@nrc.gov)
Douglas Garner (Douglas.Garner@nrc.gov), NSIR/DSP/DDMS/MW, TWFN Mail Stop: 4F14 Clay Johnson, (Clay.Johnson@nrc.gov), NSIR/DSO/DDSO/SPEB, TWFN 3D43 Branch Chief, RI DRS (James.Trapp@nrc.gov)
Branch Chief, RII DRS/PSB2 (Michael.Ernstes@nrc.gov)
Branch Chief, RIII DRS/PSB (Eric.Duncan@nrc.gov)
Electronic distribution by RIV:
bcc w/o enclosure:
Regional Administrator (Elmo.Collins@nrc.gov)
Acting Deputy Regional Administrator (Art.Howell@nrc.gov)
DRP Director (Dwight.Chamberlain@nrc.gov)
DRP Deputy Director (Anton.Vegel@nrc.gov)
DRS Director (Roy.Caniano@nrc.gov)
DRS Deputy Director (Troy.Pruett@nrc.gov)
Senior Resident Inspector (Grant.Larkin@nrc.gov)
Resident Inspector (Charles.Norton@nrc.gov)
Branch Chief, DRP/C (Vincent.Gaddy@nrc.gov)
RBS Administrative Assistant (Lisa.Day@nrc.gov)
Senior Project Engineer, DRP/C (Bob.Hagar@nrc.gov)
Public Affairs Officer (Victor.Dricks@nrc.gov)
Public Affairs Officer (Lara.Uselding@nrc.gov)
Project Manager (Alan.Wang@nrc.gov)
Branch Chief, DRS/TSB (Michael.Hay@nrc.gov)
RITS Coordinator (Marisa.Herrera@nrc.gov)
Regional Counsel (Karla.Fuller@nrc.gov)
Congressional Affairs Officer (Jenny.Weil@nrc.gov)
OEMail Resource DRS STA (Dale.Powers@nrc.gov)
OEDO RIV Coordinator (Leigh.Trocine@nrc.gov)
RidsNsirDso@nrc.gov Security Related Complete Report - OUO:
SUNSI Review Completed: PRF ADAMS: Yes Initials: PRF Non-Publicly Available Sensitive Letter Only: SUNSI Review Completed: PRF ADAMS: Yes Initials: PRF Publicly Available Non-Sensitive PSI:PSB PSI:PSB C:PSB C:PBC C:PSB PFrechette JLarsen MPShannon VGaddy MPShannon
/RA/ /RA/ /RA/J. Larsen for /RA/ /RA/J. Larsen for 5/17/2010 5/17/2010 5/17/2010 5/17/2010 5/17/2010 OFFICIAL RECORD COPY T=Telephone E=E-mail F=Fax