IR 05000456/2025003

From kanterella
Jump to navigation Jump to search
Integrated Inspection Report 05000456/2025003 and 05000457/2025003 and Exercise of Enforcement Discretion
ML25344A058
Person / Time
Site: Braidwood  
Issue date: 12/10/2025
From: Dariusz Szwarc
NRC/RGN-III/DORS/RPB3
To: Mudrick C
Constellation Energy Generation, Constellation Nuclear
References
EAF-RIII-2025-0159 IR 2025003
Download: ML25344A058 (0)


Text

SUBJECT:

BRAIDWOOD STATION - INTEGRATED INSPECTION REPORT 05000456/2025003 AND 05000457/2025003 AND EXERCISE OF ENFORCEMENT DISCRETION

Dear Christopher H. Mudrick:

On September 30, 2025, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at Braidwood Station. On November 24, 2025, the NRC inspectors discussed the results of this inspection with A. Schuerman, Site Vice President, and other members of your staff. The results of this inspection are documented in the enclosed report.

Due to the temporary cessation of government operations, which commenced on October 01, 2025, the NRC began operating under its Office of Management and Budget-approved plan for operations during a lapse in appropriations. Consistent with that plan, the NRC operated at reduced staffing levels throughout the duration of the shutdown. However, the NRC continued to perform critical health and safety functions and make progress on other high-priority activities associated with the ADVANCE Act and Executive Order 14300.

On November 13, 2025, following the passage of a continuing resolution, the NRC resumed normal operations. However, due to the 43-day lapse in normal operations, the Office of Nuclear Reactor Regulation granted the regional offices an extension on the issuance of the calendar year 2025, third quarter integrated inspection reports normally issued by November 15, 2025, to December 31, 2025. The NRC will resume the routine cycle of issuing inspection reports on a quarterly basis beginning with the calendar year 2025, fourth quarter integrated inspection reports, which will be issued 45 days after the fourth quarter ends on December 31, 2025.

December 10, 2025 No findings or violations of more than minor significance were identified during this inspection.

This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations 2.390, Public Inspections, Exemptions, Requests for Withholding.

Sincerely, Dariusz Szwarc, Chief Reactor Projects Branch 3 Division of Operating Reactor Safety Docket Nos. 05000456 and 05000457 License Nos. NPF-72 and NPF-77 Enclosure:

As stated cc w/ encl: Distribution via LISTSERV Signed by Szwarc, Dariusz on 12/10/25

SUMMARY

The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees performance by conducting an integrated inspection at Braidwood Station, in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information.

List of Findings and Violations

No findings or violations of more than minor significance were identified.

Additional Tracking Items

Type Issue Number Title Report Section Status EDG EAF-RIII20250159 Failure to Comply with 10 CFR Part 37 71124.08 Closed

PLANT STATUS

Unit 1 began the inspection period at rated thermal power. On July 30, 2025, Unit 1 tripped due to a lightning strike (EN 57839/LER 202500101). All systems responded as designed. The unit was restarted on July 31, 2025, and achieved full power on August 2, 2025. The unit remained at or near rated thermal power until September 16, 2025, when the unit began coasting down for planned refueling outage A1R25. The unit was at approximately 90 percent rated thermal power at the end of the inspection period.

Unit 2 began the inspection period at rated thermal power. On July 10, 2025, the unit reduced rated thermal power to 89 percent to repair a condenser tube leak. The unit returned to full power on July 14, 2025. The unit remained at or near rated thermal power for the remainder of the inspection period.

INSPECTION SCOPES

Inspections were conducted using the appropriate portions of the inspection procedures (IPs)in effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with their attached revision histories are located on the public website at http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html. Samples were declared complete when the IP requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter (IMC) 2515, Light-Water Reactor Inspection Program - Operations Phase. The inspectors performed activities described in IMC 2515, Appendix D, Plant Status, observed risk significant activities, and completed on-site portions of IPs. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess licensee performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards.

REACTOR SAFETY

71111.04 - Equipment Alignment

Complete Walkdown Sample (IP Section 03.02) (1 Sample)

(1) The inspectors evaluated system configurations during a complete walkdown of the Unit 1 emergency diesel generators (EDGs) during the weeks ending September 6 through October 4, 2025.

71111.05 - Fire Protection

Fire Area Walkdown and Inspection Sample (IP Section 03.01) (3 Samples)

The inspectors evaluated the implementation of the fire protection program by conducting a walkdown and performing a review to verify program compliance, equipment functionality, material condition, and operational readiness of the following fire areas:

(1) Fire Zone FZ 11.3A1, auxiliary building, 364' elevation, safety injection pump 1A room during the week ending August 16, 2025
(2) Fire Zone FZ 11.2D1, auxiliary building, 346' elevation, residual heat removal pump 1B room during the week ending August 16, 2025
(3) Fire Zone FZ 11.4A2, auxiliary building, 383' elevation, Unit 2 auxiliary feedwater pump diesel room during the week ending August 16, 2025

71111.11A - Licensed Operator Requalification Program and Licensed Operator Performance

Requalification Examination Results (IP Section 03.03) (1 Sample)

(1) The inspectors reviewed and evaluated the licensed operator examination failure rates for the requalification annual operating exam administered between the weeks of August 19, 2025, and September 23, 2025, and the biennial written examinations completed in September 2024.

71111.11B - Licensed Operator Requalification Program and Licensed Operator Performance

Licensed Operator Requalification Program (IP Section 03.04) (1 Sample)

(1) Biennial Requalification Written Examinations The inspectors evaluated the quality of the licensed operator biennial requalification written examination administered on September 13, 2024.

Annual Requalification Operating Tests The inspectors evaluated the adequacy of the facility licensees annual requalification operating test administered during the week of August 25, 2025.

Administration of an Annual Requalification Operating Test The inspectors evaluated the effectiveness of the facility licensee in administering requalification operating tests required by 10 CFR 55.59(a)(2) and that the facility licensee is effectively evaluating their licensed operators for mastery of training objectives.

Requalification Examination Security The inspectors evaluated the ability of the facility licensee to safeguard examination material, such that the examination is not compromised.

Remedial Training and Re-examinations The inspectors evaluated the effectiveness of remedial training conducted by the licensee, and reviewed the adequacy of re-examinations for licensed operators who did not pass a required requalification examination.

Operator License Conditions The inspectors evaluated the licensees program for ensuring that licensed operators meet the conditions of their licenses.

Control Room Simulator The inspectors evaluated the adequacy of the facility licensees control room simulator in modeling the actual plant, and for meeting the requirements contained in 10 CFR 55.46.

71111.11Q - Licensed Operator Requalification Program and Licensed Operator Performance

Licensed Operator Performance in the Actual Plant/Main Control Room (IP Section 03.01) (2 Samples)

The inspectors observed and evaluated the following activities performed by licensed operators in the facility's main control room:

(1)various activities involving on-watch operations crews in the main control room during a downpower for a Unit 2 condenser tube leak during the week ending July 12, 2025 (2)various activities involving on-watch operations crews in the main control room during a restart of Unit 1 during the week ending August 2, 2025

Licensed Operator Requalification Training/Examinations (IP Section 03.02) (1 Sample)

The inspectors observed and evaluated the following licensed operator training activity, which included the administration of the annual requalification operating test required by 10 CFR 55.59(a)(2) in the facility's control room simulator:

(1)a complex casualty graded scenario involving a crew of licensed operators was observed in facilitys simulator during the conduct of the annual requalification operating test during the week ending September 6, 2025

71111.12 - Maintenance Effectiveness

Maintenance Effectiveness (IP Section 03.01) (2 Samples)

The inspectors evaluated the effectiveness of maintenance to ensure the following structures, systems, and components (SSCs) remain capable of performing their intended function:

(1) EDG emergency air supply bottles during the week ending August 30, 2025 (2)auxiliary feedwater air operated injection valves during the weeks ending September 6 through 20, 2025

Quality Control (IP Section 03.02) (1 Sample)

The inspectors evaluated the effectiveness of maintenance and quality control activities to ensure the following SSC remains capable of performing its intended function:

(1)main steam isolation valve (MSIV) air accumulator regulators during the weeks ending September 6 through 13, 2025

71111.13 - Maintenance Risk Assessments and Emergent Work Control

Risk Assessment and Management Sample (IP Section 03.01) (1 Sample)

The inspectors evaluated the accuracy and completeness of risk assessments for the following planned and emergent work activities to ensure configuration changes and appropriate work controls were addressed:

(1)review and evaluation of the risk associated with risk informed completion time (RICT)associated with instrument 1P0545 repairs and over temperature delta temperature (OTDT) needs calibration, as documented in OP-AA108118, Attachment 2, RICT record during the week ending August 9, 2025

71111.15 - Operability Determinations and Functionality Assessments

Operability Determination or Functionality Assessment (IP Section 03.01) (6 Samples)

The inspectors evaluated the licensees justifications and actions associated with the following operability determinations and functionality assessments:

(1)evaluation of the operability of the 1A diesel generator due to a fuel oil leak, as documented in Action Request (AR) 4878462 during the week ending July 12, 2025 (2)evaluation of the operability of the 1A diesel generator due to a lube oil leak, as documented in AR 4878458 during the week ending July 19, 2025 (3)evaluation of the operability of the 2A diesel generator due to a sheared piece of tubing, as documented in AR 4885105 during the week ending August 2, 2025 (4)evaluation of the operability of the 1A EDG due to a potential issue with EDG ventilation, as documented in AR 4895775 during the week ending September 13, 2025 (5)evaluation of the operability of 2P0457 pressurizer pressure loop, as document in AR 4891362 during the week ending September 13, 2025 (6)evaluation of the operability of the 2B EDG after a failed fast start, as documented in AR 4900643 during the week ending September 27, 2025

71111.18 - Plant Modifications

Temporary Modifications and/or Permanent Modifications (IP Section 03.01 and/or 03.02) (1 Sample)

The inspectors evaluated the following temporary or permanent modifications:

(1)permanent plant modification per Engineering Change (EC) 643635, Appendix J Local Leak Rate Scope Reduction - Penetrations P1, P16, and P41, Revision 0 during the week ending July 17, 2025

71111.24 - Testing and Maintenance of Equipment Important to Risk

The inspectors evaluated the following testing and maintenance activities to verify system operability and/or functionality:

Post-Maintenance Testing (PMT) (IP Section 03.01) (5 Samples)

(1)functional and operational testing of the 1D steam generator pressure indicator following replacement, as documented in Work Order (WO) 5701998 during the week ending August 16, 2025 (2)functional and operational testing of Unit 1, power range instrument N43 following 15-year replacement of power supplies, as documented in WO 1835382 during week ending August 30, 2025 (3)functional and operational testing of 2CC9412A following maintenance, as documented in WO 4921862 during week ending August 30, 2025 (4)functional and operational testing of 1PDS-VD044 DG vent system fan and 1VD01CA differential pressure switch following maintenance, as documented in WO 5720055 during week ending September 20, 2025 (5)functional and operational testing of 1FC8765 after maintenance, as documented in WO 5430031 during the week ending August 30, 2025

Surveillance Testing (IP Section 03.01) (2 Samples)

(1)1BwOSR 3.8.1.21; Unit One 1A Diesel Generator Operability Surveillance, as documented in WO 5683714 during the week ending July 5, 2025 (2)1BwOSR 5.5.8.CC6A; Group A IST Requirements for Component Cooling Pump (1CC01PA), as documented in WO 5660549 during the week ending July 12,

RADIATION SAFETY

71124.07 - Radiological Environmental Monitoring Program

Environmental Monitoring Equipment and Sampling (IP Section 03.01) (1 Sample)

(1) The inspectors evaluated environmental monitoring equipment and observed collection of environmental samples.

Radiological Environmental Monitoring Program (IP Section 03.02) (1 Sample)

(1) The inspectors evaluated the implementation of the licensees radiological environmental monitoring program.

GPI Implementation (IP Section 03.03) (1 Sample)

(1) The inspectors evaluated the licensees implementation of the Groundwater Protection Initiative (GPI) program to identify incomplete or discontinued program elements.

71124.08 - Radioactive Solid Waste Processing & Radioactive Material Handling, Storage,

& Transportation

Radioactive Material Storage (IP Section 03.01)

The inspectors evaluated the licensees performance in controlling, labeling and securing the following radioactive materials:

(1)snubbers stored in top loading sealand container

Radioactive Waste System Walkdown (IP Section 03.02) (1 Sample)

The inspectors walked down the following accessible portions of the solid radioactive waste systems and evaluated system configuration and functionality:

(1)radioactive waste building resin processing equipment

Waste Characterization and Classification (IP Section 03.03) (2 Samples)

The inspectors evaluated the following characterization and classification of radioactive waste:

(1) Dry Active Waste (DAW)

(2)0WX0ST resin

Shipping Records (IP Section 03.05) (3 Samples)

The inspectors evaluated the following non-excepted radioactive material shipments through a record review:

(1)radioactive waste shipment number RWS24014; resin liner in cask RT100 (2)radioactive waste shipment number RWS24019; DAW & metals in shielded seavan (3)radioactive waste shipment number RWS25001; resin liner PO71139886 in cask 14215H21

OTHER ACTIVITIES - BASELINE

===71151 - Performance Indicator Verification The inspectors verified licensee performance indicators submittals listed below:

MS08: Heat Removal Systems (IP Section 02.07)===

(1) Unit 1 (July 1, 2024, through June 30, 2025)
(2) Unit 2 (July 1, 2024, through June 30, 2025)

MS09: Residual Heat Removal Systems (IP Section 02.08) (2 Samples)

(1) Unit 1 (July 1, 2024, through June 30, 2025)
(2) Unit 2 (July 1, 2024, through June 30, 2025)

MS10: Cooling Water Support Systems (IP Section 02.09) (2 Samples)

(1) Unit 1 (July 1, 2024, through June 30, 2025)
(2) Unit 2 (July 1, 2024, through June 30, 2025)

BI01: Reactor Coolant System (RCS) Specific Activity Sample (IP Section 02.10) (2 Samples)

(1) Unit 1 (October 1, 2024, through June 30, 2025)
(2) Unit 2 (October 1, 2024, through June 30, 2025)

OR01: Occupational Exposure Control Effectiveness Sample (IP Section 02.15) (1 Sample)

(1) Unit 1 (October 1, 2024, through June 30, 2025)

PR01: Radiological Effluent Technical Specifications/Offsite Dose Calculation Manual Radiological Effluent Occurrences (RETS/ODCM) Radiological Effluent Occurrences Sample (IP Section 02.16) (1 Sample)

(1) Unit 1 (October 1, 2024, through June 30, 2025)

71152A - Annual Follow-up Problem Identification and Resolution Annual Follow-up of Selected Issues (Section 03.03)

The inspectors reviewed the licensees implementation of its corrective action program related to the following issues:

(1) Review and assessment of the stations corrective actions for an out of tolerance condition identified during testing as discussed in AR 4891362 during the week ending September 20, 2025.

71153 - Follow-up of Events and Notices of Enforcement Discretion Personnel Performance (IP Section 03.03)

(1) Review and assessment of licensee and plant response to the Unit 1 automatic reactor trip on July 30, 2025, due to an OTDT reactor protection system actuation as documented in NRC Event Notification57893, during the week ending August 2, 2025. No performance deficiency nor violation of NRC requirements was identified.

INSPECTION RESULTS

Enforcement Discretion Enforcement Action EAF-RIII20250159: Failure to Comply with 10 CFR Part 37 71124.08

Description:

On January 15, 2016, the licensee was issued NRC Inspection Report Nos.

05000456/2016407 and 05000457/2016407, which documented a licensee identified violation of 10 CFR Part 37, Physical Protection of Category 1 and Category 2, Quantities of Radioactive Material at Facilities with a 10 CFR Part 73, Physical Protection Program.

The violation met the criteria for Enforcement Discretion as described in Enforcement Guidance Memorandum (EGM) 14001, Interim Guidance for Dispositioning 10 CFR Part 37 Violations with Respect to Large Components or Robust Structures Containing Category 1 or Category 2 Quantities of Material at Power Reactor Facilities Licensed Under 10 CFR Parts 50 and 52.

Subsequently, the inspectors re-evaluated this activity and found that while a violation of regulatory requirements continues to exist, the conditions remain within the criteria for enforcement discretion established within the Interim Enforcement Policy (IEP) discussed within NRCs Enforcement Policy, Section 9.3.

Corrective Actions: As specified in the NRCs Enforcement Policy, Section 9.3, the application of discretion is authorized until the underlying technical issue is dispositioned through rulemaking or other regulatory action.

Enforcement:

Violation: On January 15, 2016, the licensee was issued NRC Inspection Report Nos.

05000456/2016407 and 05000457/2016407. The inspectors determined that the previously identified violation remains.

Basis for Discretion: This violation met all of the criteria for Enforcement Discretion as described in NRCs Enforcement Policy, Section 9.3, Enforcement Discretion for Physical Protection of Category 1 and Category 2 Quantities of Radioactive Material (10 CFR Part 37).

EXIT MEETINGS AND DEBRIEFS

The inspectors verified no proprietary information was retained or documented in this report.

  • On November 24, 2025, the inspectors presented the integrated inspection results to A. Schuerman, Site Vice President, and other members of the licensee staff.
  • On July 25, 2025, the inspectors presented the radiation protection inspection results to S. MacArtney, Maintenance Director, and other members of the licensee staff.
  • On August 29, 2025, the inspectors presented the 2025 licensed operators requalification program inspection results to A. Schuerman, Site Vice President, and other members of the licensee staff.

DOCUMENTS REVIEWED

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

4899212

1DG5168B Valve Handle Comes Off

09/19/2025

4899221

1HS-DG223 Needs EPN

09/19/2025

4899235

1B DG Left Air Manifold High

09/19/2025

Corrective Action

Documents

4900339

1B EDG DO Supply Pipe Clamp Dampening Material

Degraded

09/24/2025

Corrective Action

Documents

Resulting from

Inspection

4899608

DG Valve Tag Description Typos

09/22/2025

BwOP DG-E1

Electrical Lineup - Unit 1 1A Diesel Generator

BwOP DG-E2

Electrical Lineup - Unit 1 1B Diesel Generator

BwOP DG-M1

Operating Mechanical Lineup Unit 1 1A D/G

71111.04

Procedures

BwOP DG-M2

Operating Mechanical Lineup Unit 1 1B D/G

Pre-Fire Plan

  1. 109

FZ 11,2D-a, AB 346' RHR Pump 1B Room

Pre-Fire Plan

  1. 118

FZ 11.3A-1, AB 364' Safety Injection Pump 1A Room

71111.05

Fire Plans

Pre-Fire Plan

  1. 138

FZ 11.4A-2, AB 383' Unit 2 Aux. Feedwater Pump Diesel

Room

71111.11A

Miscellaneous

TQ-AA-150F25

LORT Annual Exam Status Report

Rev. 007

Calculations

1BwGP 1007T4

Calculation of Estimated Critical Condition from Nuclear

Fuel, Westinghouse, or Beacon Supplied Values

Root Cause Evaluation for IR#4772085

05/24/2024

AR 04893981

LORT Annual Exam Security Procedure Non-Compliance

08/28/2025

Corrective Action

Documents

PA-240124-001

Performance Analysis for Shear Pin Replacement

01/24/2024

Braidwood 24-month Requalification Program (2023-2025)

Training Cycle 23-6 Licensed Operator Attendance Records

Training Cycle 24-4 Licensed Operator Attendance Records

BwVS 500-6

Low Power Physics Test Program

OP-AA-105-102

Reactivation of License Log

71111.11B

Miscellaneous

OP-AA-105-102

Reactivation of License Log (Completed for two operators)

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

SRB 24-1

Simulator Review Board

03/05/2024

SRB 24-2

Simulator Review Board

11/05/2024

TQ-AA-150-F25

LORT Annual Examination Status Report

09/27/2024

TQ-AA-155-F04

Simulator Evaluation Form - Individual (Completed)

TQ-AA-155-F05

Simulator Evaluation Form - CREW (Completed)

TQ-AA-306 ATT

PWR Moderator Temperature Coefficient of Reactivity

Post-Outage

06/20/2024

TQ-AA-306 ATT

PWR Moderator Temperature Coefficient of Reactivity

Pre-Outage

11/04/2023

TQ-AA-306 ATT

PWR Rod Worth Coefficient of Reactivity Pre-Outage

11/04/2023

TQ-AA-306 ATT

PWR Rod Worth Coefficient of Reactivity Post-Outage

06/20/2024

TQ-AA-306 ATT

PWR Boron Coefficient of Reactivity Pre-Outage

11/04/2023

TQ-AA-306 ATT

PWR Xenon Worths Pre-Outage

11/04/2023

TQ-AA-306 ATT

PWR Approach to Criticality Using Boric Acid Pre-Outage

11/04/2023

TQ-AA-306 ATT

PWR Approach to Criticality Using Control Rods Pre-Outage

11/04/2023

TQ-AA-306 ATT

PWR Approach to Criticality Using Control Rods Post-

Outage

06/20/2024

TQ-AA-306-F-03

POST EVENT SIMULATOR TEST: Steam Generator

Lo-2 Reactor Trip

07/02/2024

TQ-AA-306-F-03

Post Event Simulator Test: Grid Transient AR 04799109

10/09/2024

TQ-AA-306-F-03

POST EVENT SIMULATOR TEST: 16B Heater Normal

Level Control Valve 1HD011B Sticking

06/03/2025

TQ-AA-306-F-03

Braidwood Real Time Test, Rt-1 Cycle 25 Core Load Testing

07/17/2025

TQ-AA-306-F-03

Braidwood Transient Test 1 - Manual Reactor Trip

07/17/2025

TQ-AA-306-F-03

Braidwood Transient Test 2 - Simultaneous Trip of All Main

Feedwater Pumps

07/17/2025

TQ-AA-306-F-03

Braidwood Transient Test 3 - Simultaneous Closure of All

07/17/2025

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Main Steam Isolation Valves

TQ-AA-306-F-03

Braidwood Transient Test 4 - Simultaneous Trip of All

Reactor Coolant Pumps

07/17/2025

TQ-AA-306-F-03

Braidwood Transient Test 5 - Trip of Any Single Reactor

Coolant Pump

07/17/2025

TQ-AA-306-F-03

BRAIDWOOD TRANSIENT TEST 6 - TURBINE TRIP < P-8

07/17/2025

TQ-AA-306-F-03

Braidwood Transient Test 7 - Maximum Rate Ramp 100%

To 75% To 100%

07/17/2025

TQ-AA-306-F-03

Braidwood Transient Test 8 - Lbloca with Loop

07/16/2025

TQ-AA-306-F-03

Braidwood Transient Test 9 - Maximum Size Main Steam

Line Rupture

07/17/2025

TQ-AA-306-F-03

Braidwood Transient Test 10 - Slow Primary Depress Due

to Open Porv Without Charging Pumps

07/17/2025

TQ-AA-306-F-03

Braidwood Transient Test 11 - Maximum Design Load

Rejection

07/17/2025

TQ-AA-306-F-20

Simulator Scenario Based Testing Checklist

(LORT Scenario Number 2531)

04/30/2025

TQ-AA-306-F-20

Simulator Scenario Based Testing Checklist

(LORT Scenario Number 2541)

06/26/2025

TQ-AA-306-F-20

Simulator Scenario Based Testing Checklist (ILT NRC 2023

Exam Scenario 1)

10/16/2023

TQ-AA-306-F-20

Simulator Scenario Based Testing Checklist (NRC 2023

Exam Scenario 2)

10/16/2023

TQ-AA-306-F-20

Simulator Scenario Based Testing Checklist (NRC 2023

Exam Scenario 3)

10/17/2023

TQ-BR-302-0103

Braidwood Simulator Steady State Testing Ss-1 (100%)

06/17/2025

TQ-BR-302-0103

Braidwood Simulator Steady State Testing Ss-1 (75%)

06/24/2025

TQ-BR-302-0103

Braidwood Simulator Steady State Testing Ss-1 (54%)

06/24/2025

NF-AP-181

Byron and Braidwood Rod Worth Testing Scope Decision

Review Form

NF-AP-181

PWROG-19014-P HZP BOL MTC Testing Scope Decision

Review Form for Byron and Braidwood

TQ-AA-150

Operator Training Programs

Procedures

TQ-AA-306

Simulator Management

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

TQ-BR-150-F31

(LORT)

Training Program Description: Licensed Operator

Requalification Training Program (LORT)

TQ-BR-201-0113

Braidwood Training Department Simulator Examination

Security Actions

Self-Assessments AR 04845283

Pre-71111.11 & Annual Simulator Compliance

05/14/2025

05303923

Perform Low Power Physics Test Program

05/05/2024

SWR 0138723

Nuclear Instrument cabinet power supply failure

11/08/2023

SWR 0138802

Add PPC points for PZR PORV/Safety Tailpipe Temps and

Rate of Change

2/19/2023

SWR 0138900

Adjust Refueling Water Storage Tank Low Setpoint

2/15/2024

SWR 0139079

Hour Lost Time Due to ECCS Reset Buttons Not

Functioning

05/14/2024

SWR 0139092

OA WS Pump Stator Temperature Reaches Alarm Setpoint

05/20/2024

SWR 0139240

Must reset MST With Each IC Reset To Prevent Partial

Simulator Failure

08/07/2024

SWR 0139300

Exam Related

09/06/2024

SWR 0139341

STC Simulator Firewall Ruleset Consolidation

10/03/2024

SWR 0139486

H2 Temperature Meter Sticking

01/30/2025

SWR 0139596

SG 1A/1B WR SGWL Yokogawa Fails Intermittently

03/24/2025

Work Orders

SWR 0139786

Add PPC Alarm for Feedwater Regulating Valves

06/25/2025

HU-AA-104-101

Procedure Use and Adherence

OP-AA-101-111-

1001

Operations Standards and Expectations

OP-AA-101-113

Operator Fundamentals

71111.11Q

Procedures

OP-AA-101-113-

1006

4.0 Crew Critique Guidelines

4815722

2A MSIV Air Pump Regulator Seems to be Degraded

11/06/2024

27290

MSIV Air Regulator Trend

01/03/2025

4837397

1AF005F in Mid Position Following Stroke from RSDP

2/14/2025

4866722

TRM 3.7.g to Go Past 30 Days for 1AF005F

05/18/2025

4867669

1AF005E Did Not Go Full Open

05/21/2025

4869010

2AF005D Exceeds Stroke Closed Alert Time Limit

05/25/2025

71111.12

Corrective Action

Documents

4876951

2D MSIV Air Pump Regulator Degraded

06/27/2025

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

4888258

2D MSIV Air Pump Regulator Degraded

08/04/2025

4892892

2D MSIV Air Pump Regulator Degraded

08/24/2025

Drawings

D-10239

Schematic for A/DV Self Contained Hydraulic Acutator

K

0BwOS OALE-Q1

Operating Abnormal Procedures Local Equipment Check

Surveillance

1BwOSR

3.6.3.5.AF-1B

Unit One Train B Auxiliary Feedwater Valve Stroke

Surveillance

ER-AA-2030

Conduct of Equipment Reliability Manual

Procedures

SM-AA-3019

Parts Quality Initiative (PQI)

Work Orders

5658148

Operating Abnormal Procedures Local Equipment Check

Quarterly Surveillance

07/22/2025

Corrective Action

Documents

4888466

1TY-0421G & 1TY-0421A3 Cards Found Defective

1T-0421 Loop

08/05/2025

None

PARAGON RMTS Report for 1P-0545

08/01/2025

OP-AA-108-118,

Initial RICT Record for 1PT-0545 and 1B OTDT requires

Calibration

08/01/2025

Miscellaneous

OP-AA-108-118,

Final RICT Record for 1P-0545 and 1B OTDT Requires

Calibration

08/05/2025

71111.13

Procedures

OP-AA-108-118

Risk Informed Completion Time

4878458

1A DG Lower Lube Oil Cooler Oil Leak

07/02/2025

4878462

Fuel Oil Leak from 1PY-DG8035A Diaphragm

07/02/2025

4885105

2A DG Starting Air Compressor #1 Running Continuously /

Air Leak

07/24/2025

4891362

2PB-0457B 0-10 V Signal Found OOT During WO 5439299

08/19/2025

4895775

Unexpected Annunciator 1VD01JA-1-A6

09/06/2025

Corrective Action

Documents

4900643

2B EDG Failed Fast Start

09/25/2025

20E-1-4030VD01

Diesel Generator Room 1A HVAC System Ventilation Fan

1A 1VD01CA

M

20E-1-4030VD03

Diesel Generator Room 1A HVAC System Ventilation &

Exhaust Fans Auxiliary Relays, Switches & Alarms - Part 1

P

Drawings

20E-1-4030VD15

Diesel Generator Room HVAC System Ventilation

Annunciator Panel 1VD01JA

G

71111.15

Engineering

Evaluations

EC 405348

DG Closed System Leak Guidance (Lube Oil, Jacket Water,

and Fuel Oil)

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

406445

Appendix J Scope Reduction for Type C Local Leak Rate

Testing Penetration P-28

Engineering

Changes

643635

Appendix J Local Leak Rate Scope Reduction -

Penetrations P-1, P-16, and P-41

71111.18

Miscellaneous

NEI 94-01

Industry Guideline for Implementing Performance-Based

Option of 10 CFR Part 50, Appendix J

3-A

1012028

Verify Sealtight Conduit Connectors Tight for 2CC9412A

01/04/2010

1019847

Replace Fuse for Extent of Condition - 2AP21E-K3

01/22/2010

1397634

MCC Bucket as found wiring does not match EC Prints

08/06/2012

1502004

Replace 2CC9412A R/C Contactor - 2AP21E-K3

04/15/2013

4546249

WO 5137542-01 1CC01PA Coupling Issue Expanded Scope

01/03/2023

4546832

1CC01PA Work Delays

01/05/2023

4546923

1CC01PA Work Delays

01/06/2023

4546989

1CC01PA coupling gap issue

01/06/2023

4549595

4.0 Critique 1CC01PA

01/20/2023

4690196

1CC9412B Leak-by Prevented Relief Valve Replacement

07/12/2023

4759610

1CC9507B Leak-by Identified During Troubleshooting

03/20/2024

4762995

Roll-up of Troubleshooting to Isolate 1CC9422B

04/02/2024

24693

Fuel Transition Impact: 18 Month PR NIs Surveillance

Timing

2/18/2024

4869447

Unexpected Alarm 1-10-B4, PWR Rng Lower Det Flux Dev

High

05/30/2025

4875425

Unexpected Alarm 1-10-C4

06/23/2025

4878458

1A DG Lower Lube Oil Cooler Oil Leak

07/02/2025

4878465

Damaged Cable Insulation for 1PT-DG704A

07/02/2025

4878468

Unidentified Fuel Oil Leak 1A DG Top, West Side

07/02/2025

4878558

NI Related Ovation Alarms

07/03/2025

Corrective Action

Documents

4884475

Unexpected alarm 1-10-C4, PWR RNG Channel Dev

07/23/2025

Drawings

1F-FC-01

Fuel Pool Cooling System

E

1BwOSR 0.1-

1,2,3

Unit One Modes 1, 2, and 3 Shiftly and Daily Operating

Surveillance

104

71111.24

Procedures

ER-AA-335-004

Ultrasonic (UT) Measurement of Material Thickness and

Interfering Conditions

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

1835382

1N-NR4083 Replace All Power Supplies

08/14/2025

21862

2AP21E-K3 Starter Diagnostic Test and Control Power Fuse

Replacement

08/07/2025

5430031

1FC8765 Found to Have Internal Leak-by

08/27/2025

5660549

IST - For 1CC9463A/B 0CC9464 - ASME SRV RQMTS for

1CC01PA

07/08/2025

5683714

LRIST-1A D/G Operability Monthly

07/02/2025

5701998

1D SG Steam Pressure Indicator Failed High

08/04/2025

Work Orders

20055

Unexpected Annunciator 1VD01JA-1-A6

09/11/2025

04417340

1st Quarter 2021 Radiochemistry Crosscheck

04/18/2021

04483926

21 Control Dose OSLDs

03/10/2022

04532907

Power Supply Issue at BD-03

10/28/2022

04666583

NOS ID: Provide Explanation in the ODCM

03/31/2023

04733327

2nd QTR OSLDs

01/19/2024

04734642

5-Year OSLD Baseline Anomalies

01/22/2024

04852827

Change to ODCM Process and Procedure

04/03/2025

Corrective Action

Documents

04880690

ODCM Remp Provider

07/11/2025

Braidwood Sampling Anomalies

various

Annual Radiological Environmental Operating Report

various

Annual Radiological Groundwater Protection Program

Report

various

Land Use Census

various

Miscellaneous

Well Sample Analyses

various

CY-AA-170-000

Radioactive Effluent and Environmental Monitoring

Programs

CY-AA-170-100

Radiological Environmental Monitoring Program

CY-AA-170-1000

Radiological Environmental Monitoring Program and

Meteorological Program Implementation

CY-AA-170-1001

Environmental Dosimetry - Performance Specifications,

Testing, and Data Analysis

CY-AA-170-1100

Quality Assurance for Radiological Monitoring Programs

CY-BR-170-301

Offsite Dose Calculation Manual

71124.07

Procedures

EN-AA-408

Radiological Groundwater Protection Program

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

EN-AA-408-4000

Radiological Groundwater Protection Program

Implementation

Self-Assessments NOSA-BRW-23-

Chemistry, Radwaste, Effluent and Environmental

Monitoring Audit Report

04/05/2023

Corrective Action

Documents

Resulting from

Inspection

AR 04884453

NRC ID: No locks on Radioactive Materials Trailers

07/22/2025

DAW

DAW Ave

06/01/2022

DAW

DAW Ave

04/05/2024

DAW

DAW Ave

03/11/2025

DAW

Waste Stream Review and Scaling Factor Determination

03/11/2025

Memo #2018-02

Radiological Controls for Condensate Polisher Resin B-25

Boxes

08/02/2021

Miscellaneous

SRRS ID 2B.127

RP-AA-800 2025 Semi-annual Source Inventory and Leak

Test

01/16/2025

RP-AA-500-1001

Control of RAM Storage Areas and Containers Stored

Outside

RP-AA-600

Radioactive Material/Waste Shipments

RP-AA-602-1002

Loading Dry Active Waste and Other Waste Forms for

Energy Solutions Waste Acceptance Guide (WAG-501)

RP-AA-605

CFR 61 Program

RW-AA-100

Process Control Program for Radioactive Wastes

Procedures

RW-AA-100

Process Control Program for Radioactive Wastes

AR 04710974

Part 37 Implementation and Part 37 Security Plan

Compliance

01/15/2024

AR 04716439-01-

Radioactive Solid Waste Processing and Radioactive

Material Handling, Storage, and Transportation

11/08/2024

Self-Assessments

AR 04755696

Part 37 Implementation and Part 37 Security Plan

Compliance

2/10/2025

71124.08

Shipping Records

Radioactive

Waste Shipment

Number RWS24-

014

Resin Liner in Cask RT-100

2/23/2024

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Radioactive

Waste Shipment

Number RWS24-

019

DAW & Metals in Shielded Seavan

10/25/2024

Performance Indicator Data for MS09: Residual Heat

Removal Systems for Units 1 and 2

07/01/2024 -

06/30/2025

Performance Indicator Data for MS10: Cooling Water

Systems for Units 1 and 2

07/01/2024 -

06/30/2025

Performance Indicator Data for MS08: Heat Removal

Systems for Units 1 and 2

07/01/2024 -

06/30/2025

LS-AA-2090

Monthly Data Elements for NRC ROP Indicator -

Reactor Coolant System (RCS) Specific Activity

various

LS-AA-2140

Monthly Data Elements for NRC ROP Indicator -

Occupational Exposure Control Effectiveness

various

71151

Miscellaneous

LS-AA-2150

Monthly Data Elements for NRC ROP Indicator -

RETS/ODCM Radiological Effluent Occurences

various

4101654

Trend 7300 NAL Cards

2/07/2018

4366128

WO 4890866 2PB-0457B OOT 0-10 V signal

08/28/2020

4509290

2PB-0457A/B 0-10 V Signal OOT during WO 5084086

07/05/2022

Corrective Action

Documents

4891362

2PB-0457B 0-10 V Signal found OOT during WO 5439299

08/19/2025

Drawings

20E-2-4031RY03

LOOP Schematic Diagram Pressurizer Pressure Protection

III (2PT0457) Protection Cabinet 3 (2PA03J)

K

Miscellaneous

Westinghouse IB-

NLP 7300

7300 Isolator and Loop Power Supply Instruction Bulletin

71152A

Procedures

BwISR 3.3.1.10-

M239

Operational Test and Channel Verification / Calibration for

LOOP P-0457, Pressurizer Pressure Protection Channel III

Cabinet 3

2