January 17, 2018
SUBJECT:
COMANCHE PEAK NUCLEAR POWER PLANT, UNITS 1 AND 2 -
NRC EMERGENCY PREPAREDNESS ANNUAL INSPECTION
REPORT 05000445/2017501 AND 05000446/2017501
Dear Mr. Peters:
On December 31, 2017, the Nuclear Regulatory Commission (NRC) staff completed its annual inspection of the Emergency Preparedness Program at the Comanche Peak Nuclear Power Plant, Units 1 and 2. This inspection began on January 1, 2017. Issuance of this letter closes NRC Inspection Report 05000445/2017501 and 05000446/2017501. The inspection results associated with the 2017-501 reports are documented in Integrated Resident Inspection Reports 2017-001, 2017-002, 2017-003, and 2017-004.
In accordance with 10 CFR 2.390 of the NRCs Rules of Practice and Procedure, a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's Agencywide Documents Access and Management System (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
Sincerely,
/RA/
Heather J. Gepford, PhD, CHP Chief, Plant Support Branch 2 Division of Reactor Safety
Docket Nos. 50-445 and 50-446 License Nos. NPF-87 and NPF-89
cc: Electronic Distribution
ML18022B137 SUNSI Review ADAMS:
Non-Publicly Available Non-Sensitive Keyword:
By: PJElkmann Yes No Publicly Available Sensitive NRC-002 OFFICE SEPI:PSB2 BC:PSB2
NAME PElkmann HGepford
SIGNATURE
/RA/
/RA/
DATE 1/17/18 1/1718