IR 05000440/1986001

From kanterella
Jump to navigation Jump to search
SALP Rept 50-440/86-01 for Jul 1985 - Apr 1986
ML20206P593
Person / Time
Site: Perry FirstEnergy icon.png
Issue date: 06/27/1986
From:
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
To:
Shared Package
ML20206P571 List:
References
50-440-86-01, 50-440-86-1, NUDOCS 8607020163
Download: ML20206P593 (39)


Text

._

O-

SALP 6 i

'

SALP BOARD REPORT U. S. NUCLEAR REGULATORY' COMMISSION

REGION III

_

SYSTEMATIC ASSESSMENT OF LICENSEE PERFORMANCE i

50-440/86001

Inspection Report

Cleveland Electric Illuminating Company

Name of Licensee

-Perry Nuclear Power Plant, Unit 1

Name of Facility

l

July 1, 1985 through April 30, 1986

Assessment Period

S887RBheaSt8obo

G

.

_

_

_

_ _., _

.-

_

_ _,. -

,

- _.. _ _., _

.

.

I

l

I.

INTRODUCTION

The Systematic Assessment of Licensee Performance (SALP) program is an

integrated NRC staff effort to collect available observations and data on

a periodic basis and to evaluate licensee performance based upon this

information. SALP is supplemental to normal regulatory processes used to

ensure compliance to NRC rules and regulations.

SALP is intended to be

sufficiently diagnostic to provide a rational basis for allocating NRC

resources and to provide meaningful guidance to the licensee's management

to promote quality and safety of plant construction and operation.

An NRC SALP Board, composed of staff members listed below, met on June 20,

1986, to review the collection of performance observations and data to

assess the licensee's performance in accordance with the guidance in NRC

Manual Chapter 0516, " Systematic Assessment of Licensee Performance." A

summary of the guidance and evaluation criteria is provided in Section II

of this report.

This report is the SALP Board's assessment of the licensee's safety

performance at Perry Unit 1 for the period July 1, 1985, through April

30, 1986.

SALP Board for Perry 1 :

Name

Title

J. A. Hind

Director, DRSS

C. J. Paperiello

Director, DRS

C. E. Norelius

Director, DRP

R. F. Warnick

Chief, Reactor Projects

Branch 1, DRP

Walter R. Butler

Project Director, NRR/BWD-4

R. C. Knop

Section Chief, DRP

D. H. Danielson

Section Chief, M&PS, DRS

E. R. Schweibinz

Chief, Tech Support Staff, DRP

W. G. Snell

Section Chief, DRSS

G. L. Pirtle

Section Chief, Safeguards

Section, DRSS

L. G. McGregor

Chief, FRPS, DRSS

M. Schumacher

Chief, RECS, DRSS

John J. Stefano

Project Manager, NRR/BWD-4

J. A. Grobe

Perry Senior Resident

Inspector, DRP

K. A. Connaughton

Perry Resident Inspector, DRP

J. E. Foster

EP Analyst, DRSS

J. W. McCormick-Barger

Project Inspector, DRP

__

.

,

II. CRITERIA

Licensee performance is assessed in selected functional areas, depending

upon whether the facility is in a construction, preoperational, or

operating phase.

Functional areas normally represent areas significant

to nuclear safety and the environment.

Some functional areas may not

be assessed because of little or no licensee activities, or lack of

meaningful observations.

Special areas may be added to highlight

significant observations.

One or more of the following evaluation criteria were used to assess each

functional area:

1.

Management involvement and control in assuring quality.

'

2.

Approach to the resolution of technical issues from a safety

standpoint.

3.

Responsiveness to NRC initiatives.

4.

Enforcement history.

5.

Operational and Construction events (including response to, analysis

of, and corrective actions for).

6.

Staffing (including management).

However, the SALP Board is not limited to these criteria and others may

have been used where appropriate.

Based upon the SALP Board assessment, each functional area evaluated is

classified into one of three performance categories. The definitions of

these performance categories are:

Category 1:

Reduced NRC attention may be appropriate.

Licensee

,

'

management attention and involvement are aggressive and oriented toward

nuclear safety; licensee resources are ample and effectively used so that

a high level of performance with respect to operational safety and

construction is being achieved.

Category 2: NRC attention should be maintained at normal levels.

Licensee management attention and involvement are evident and are

concerned with nuclear safety; licensee resources are adequate and are

reasonably effective so that satisfactory performance with respect to

l

operational safety and construction is baing achieved.

!

l

Category 3: Both NRC and licensee attention should be increased.

Licensee management attention or involvement is acceptable and considers

nuclear safety, but weaknesses are evident; licensee resources appear to

,

!

be strained or not effectively used so that minimally satisfactory

'

performance with respect to operational safety or construction is being

achieved.

l

l

l

- - -

-

-

.

.

III. SUMMARY OF RESULTS

Overall, the licensee's performance was found to be acceptable. The

licensee was found to have aggressive management attention and a high

level of performance in the assessment areas of Electrical Power and

Instrumentation and Control Systems, Licensing Activities, Emergency

Preparedness, and Security. All other assessment areas were found to

be adequate and represented a licensee management team that was

sufficiently staffed and appropriately involved and concerned with

nuclear safety. The highly transitional stage that the plant is

undergoing as it moves from construction and preoperational testing to

icw power testing and eventual full power operation will require

increased management attention. Management involvement in assuring safe

operation must continue to be present with a particularly keen sense

of awareness of weaknesses that are identified through implementation of

their operational program.

Rating Last

Rating This

Functional Area

Period

Period

A.

Containment and Other

NR

Safety-Related

Structures

B.

Piping Systems

2

'

and Supports

C.

Heating, Ventilating,

NR

NR

and Air Conditioning

(HVAC)

D.

Electrical Power

NR*

and Instrumentation

and Control Systems

E.

Quality Programs and

2

Administrative Controls

Affecting Quality

F.

Licensing Activities

1

G.

Preoperational Testing

2

H.

Startup Testing

NR

NR

i

I.

Radiological Controls

2

J.

Fire Protection

2

K.

Emergency Preparedness

1

.

'

.

L.

Security

1

M.

Maintenance / Modifications

NR

N.

Surveillance and Inservice

NR

Testing

O.

Fueling

NR

P.

Operational Readiness / Plant

NR**

Operations

Q.

Training and Qualification

NR

Effectiveness

  • The licensee was rated in the two areas separately during the last

assessment period. A Category 2 was given for Electrical Power and a

Category I was given for Instrument and Control Systems.

    • The licensee was rated a Category 2 in Operational Readiness during the

previous assessment period but not rated in Plant Operations.

I

NR = Not Rated

!

!

I

l

l

.

- -

-

_-

.-

.-

.

....

.-

-

.

.

IV.

PERFORMANCE ANALYSIS

A.

Containment and Other Safety-Related Structures

1.

Analysis

The work activities in this functional area are essentially

complete.

Inspection activities by Region III inspectors

were limited to portions of seven inspections. Areas examined

included a review of activities related to the drywell

structural integrity test (SIT), structural steel as-built

drawing verifications, and allegations concerning the

misapplication of coatings in the containment, containment

iiner weld quality, voids in bioshield concrete, fuel transfer

pool integrity, Polar Crane box girder weld quality and

containment piping penetration seal defects.

For the areas examined, the inspectors determined that

activities were generally controlled through the use of well

stated and defined procedures. The approach used to conduct

the SIT was generally conservative, technically sound, and

thorough.

Records were found to be generally complete, well

maintained, and available.

Inspections into the concerns

contained in the allegations did not disclose any issues for

which the licensee had not already taken suitable corrective

actions.

No violations or deviations were identified.

2.

Conclusions

Due to the limited inspection activities performed in this area,

the licensee was not rated.

The licensee received a rating of

Category 1 during the last SALP period.

3.

Board Recommendations

None.

B.

Piping Systems and Supports

1.

Analysis

The inspection activities in this area were, for the most part,

limited to observation of completed work and a selected review

of records because construction was essentially complete at

the beginning of the assessment period.

Examination of this

functional area consisted of portions of ten inspections by

Region III inspectors. Areas examined included (1) visual

examination of selected piping welds and piping spools;

(2) review of radiographs and related reports for selected

field welds; (3) testing of pipe support and restraint systems;

(4) the inadvertent overpressurization of some non safety-related

--

.

High Pressure Core Spray pump test return line piping during

system vibration testing; (5) review of selected licensee " Call

for Quality" investigations and engineering technical evalua-

tions; (6) examination and field walkdowns of selected as-built

safety-related piping systems and supports; and (7) licensee

actions related to previous inspection findings, IE Bulletins,

IE Circulars, IE Information Notices, and 10 CFR 50.55(e)

deficiency reports.

One Severity Level IV violation was identified for

failure to adequately control the design of pipe

supports. The licensee's written response and

implementation of corrective actions were reviewed

and found to be acceptable. This violation is not

repetitive of violations identified during the

previous assessment period and it did not appear

to have generic or programmatic implications

(Inspection Report 50-440/85016).

For the areas examined, the inspectors determined that

activities were generally controlled through the use of well

stated and defined procedures. Visual observations indicate

personnel had an adequate understanding of work practices and

that procedures were generally adhered to.

The licensee's

actions in response to previous inspection findings, NRC

initiatives,10 CFR 50.55(e) deficiency reports, were generally

timely, thorough, and technically sound. With the exception

noted above, the control of design was viable, generally sound,

and thorough.

Their approach used to evaluate and analyze

piping system vibration and thermal expansion preoperational

testing was generally conservative, technically sound, and

thorough. The " Call for Quality" investigations and resulting

technical evaluations were technically sound and acceptable

resolutions were generally implemented. Records were found

to be generally complete, well maintained, and available.

2.

Conclusions

The licensee is rated Category 2 in this area. The licensee

received a rating of Category 2 in the last SALP period.

3.

Board Recommendations

None.

f

7

___

,-

,

C.

Heating, Ventilating, and Air Conditioning (HVAC)

1.

Analysis

Examination of this functional area consisted of one inspection

during which the Region III inspector reviewed the HVAC

contractors installation activities. Areas examined included

(1) a review of the design specification and applicable

installation and quality control procedures; (2) a review of

certification and qualification records for selected QC

technicians (inspectors) and welders; (3) a walkdown of

portions of selected systems which included examination of

installations for conformance to design drawings, fabrication

sketches and duct installation procedures, and (4) a review

of selected installation packages and testing records.

For the areas examined, the inspector concluded that activities

were generally controlled through the use of well stated and

defined procedures. Observations of HVAC activities indicate

the personnel had an adequate understanding of work practices

and that procedures and drawings were adhered to.

Records were

found to be generally complete, well maintained, and available.

The records also indicated that personnel performing welding and

QC inspection activities were trained and certified. No

violations or deviations were identified.

2.

Conclusions

Due to the limited inspection activities performed in this

area, the licensee was not rated. The licensee was not

assessed in this area during the last SALP period.

3.

Board Recommendations

None.

D.

Electrical Power and Instrument and Control Systems

1.

Analysis

The examination of this functional area included portions of 25

inspections by Region III inspectors. The inspections included

(1) examination of control of activities involving the

installation of materials and components including direct

inspection of in process and completed work; (2) walkdown

inspection of instrumentation systems and electrical circuits;

(3) review of welding processes; (4) inspection of instrument

and electrical cable terminations; (5) examination of quality

-__

.

.

assurance records including equipment and materials qualifica-

tion; (6) as-built drawing verification; and (7) examination of

quality control activities.

No violations of NRC requirements

or deviations from commitments were identified in this functional

area.

The inspectors identified no programmatic or procedural

weaknesses in this functional area during the appraisal period.

With one minor exception, issues identified by the inspectors

and/or licensee were promptly and adequately resolved. The

single exception involved incomplete evaluation of susceptibility

of installed plant instrumentation to radio frequency

interference as recommended by IE Information Notice 80-09.

Once this matter was brought to the licensee's attention,

additional actions were implemented in a thorough manner and

resolution was achieved prior to operating license issuance.

Significant deficiencies were promptly reported in accordance

with 10 CFR 50.55(e). Analyses were thorough and included

comprehensive corrective actions.

The Perry construction quality assurance organization was

adequately staffed with well qualified personnel as

demonstrated by the quality of their overview inspections,

surveillances, audits of contractor activities,

and their responsiveness to regulatory issues. The

inspections, surveillances, and audits were timely, thorough,

and in-depth to determine the root cause(s) of identified

problems.

Corrective actions were timely and directed toward

preventing the recurrence of problems.

Management involvement in assuring a high degree of quality was

evident throughout the assessment period. An example of this

was reflected in their final inspections /walkdowns of systems

prior to turnover. These activities were found to be thorough

and served to present the carry over of construction

deficiencies into the testing and operating phases of the

plant.

In addition, outstanding licensee performance was

evident from the lack of violations or deviations issued

during this rating period and the quality of the overview

provided by the licensee's quality assurance organization.

2.

Conclusions

The licensee is rated a Category 1 in this area.

The licensee

was rated separately a Category 1 in Instrument and Control

Systems and a Category 2 in Electrical Power Supply and

Distribution during the previous assessment period.

3.

Board Recommendations

None.

.

E.

Quality Programs and Administrative Controls Affecting Quality

1.

Analysis

One region based inspection was performed to determine the

adequacy of the Operational Quality Assurance Program in the

following areas:

safety committee activities; tests and

experiments; operating staff training; surveillance testing;

and calibration control.

No violations or deviations were

identified.

Another region based inspection consisted of an NRC Augmented

Investigation Team (AIT) and a support team walkdown inspection

following the January 31, 1986, earthquake to determine its

effect on the Perry plant.

Following the January 31, 1986, earthquake, a Confirmatory

Action letter (CAL-RIII-86-01) was issued on January 31, 1986,

to document an agreement to maintain all affected equipment in

the "as found" condition until the NRC AIT could jointly with

the licensee evaluate any evidence to determine the effects of

this event. The AIT inspection included confirmation of the

data gathered by the Perry staff during their plant walkdowns,

the review and the validation of the data captured by the plant's

seismic instruments, and conduct of a detailed inspection of

selected safety-related systems including piping and associated

mechanical and electrical support systems.

Based on AIT observations, it was determined that activities

were generally controlled through the use of well stated and

defined procedures and that personnel demonstrated a general

understanding of the actions required to respond to an off-

normal event.

The licensee's approach to evaluating the event

was conservative, technically sound, and thorough. The

licensee's actions in response to the CAL were prompt and

effective.

Records were found to be complete and reasonable

steps were taken to preserve and validate the data.

Considerable resident inspection effort was expended to examine

licensee activities in this functional area in the course of

fourteen inspections. This inspection effort focused upon (1)

development and staffing of the plant operating organization;

(2) development and implementation of administrative procedures

required for plant operation; (3) implementation of

administrative controls for the tracking and resolution of

outstanding construction items and establishment of equipment

operability; (4) independent review programs; (5) procedures

and activities addressing housekeeping and care and preservation

of safety related components; (6) implementation of the

licensee's program for the handling of employee concerns and

.

.

_

.

.

-

.

allegations; (7) review and investigation of~ allegations dealing

with employee fitness for duty; (8) development and implementa-

tion of the licensee's program for the tracking and resolution

of NRC inspector-identified items; (9) the licensee's program

for performing evaluations required by 10 CFR 50.59; and (10) the

'

l

processing of FSAR changes prior to operating license issuance.

Two violations were identified, as follows:

a.

Severity Level IV - failure to establish and implement

adequate administrative controls for housekeeping and

material control (Inspection Report 50-440/86006).

b.

Severity Level IV - failure to develop and implement

adequate procedures for establishing and documenting the

operating status of plant instruments (Inspection Report

50-440/86008).

The housekeeping violation resulted following a turnover of

housekeeping responsibilities from the construction

organization to the operating organization. Corrective actions

,

in response to earlier violations involving housekeeping were

'

not adequately translated into the administrative procedures

,

governing housekeeping for the facility operating phase.

Licensee response to this violation was prompt and thorough.

?

Interim and permanent corrective actions taken included

i

training of responsible personnel to revised administrative

'

procedures.

The violation concerning plant instruments represented a

i

breakdown in administrative controls which, had it gone

undetected, would have seriously threatened the operability

of a number of safety related instruments.

Following

,

!

identification of this deficiency by the licensee, a program

of corrective action was formulated in consultation with NRC

Region III management. This program was formally submitted

to the NRC and incorporated as a condition of the Perry

operating license.

Followup inspections by the resident

inspectors confirmed, prior to fuel load and initial

,

criticality, that required portions of the corrective action

program were acceptably completed.

Licensee actions in

i

response to this matter were generally timely and thorough;

however, the corrective action plan initially formulated by

the licensee was deficient in a number of respects.

It did

not include evaluation of the effects of mispositioned

instrument valves on preoperational and surveillance test

i

results nor did it include review to determine if instrument

l

valves were mispositioned by unauthorized personnel (i.e.

i

tampering).

Finally, the schedule for providing valve

identification tags was untimely.

Following discussions among

'

I

l

l

l

l

.-

_-

.

..

-.

.

.

..

.

-

- - -

.-

-

.

the licensee, Region III management, and inspection personnel,

the deficiencies were resolved and incorporated into the

licensee's formal submittal.

The significance of this matter was mitigated by the fact that

a licensee initiative to assess operational readiness had

identified the problems and corrective actions were accomplished

before plant operating conditions required operability of

affected instruments.

Throughout the assessment period licensee management

involvement in the implementation of quality programs and

administrative controls has been highly visible. This

involvement was evidenced by the establishment of a formal

and comprehensive program for the completion of plant licensing,

construction, testing, and operational program development

activities. The program was well formulated and provided a

high level of assurance that these activities were completed in

a thorough and timely manner to support plant operations.

By management direction, operational administrative controls

and procedures were implemented on November 1, 1985. This has

proven to be invaluable in that it resulted in the early

detection of programmatic weaknesses, inconsistencies and areas

where additional personnel training was needed. By the time of

operating license issuance, the licensee had demonstrated the

capability to implement a viable system of operational programs

and administrative controls to support plant operations.

Throughout the assessment period the licensee exhibited a high

level of responsiveness to NRC identified concerns and their

resolution of technical issues were generally found to be

adequate. This was evidenced by numerous refinements to

operational programs and procedures, enhanced personnel

training, and self assessments of operational readiness

conducted to resolve NRC identified weaknesses.

Staffing

was found to be ample and well trained.

In summary, quality programs and administrative controls

affecting quality were determined to be adequate and acceptably

implemented throughout the difficult pre-licensing and initial

operations phases included in this assessment period.

2.

Conclusion

The licensee is rated Category 2 in this area. The licensee

was rated Category 2 in this area during the previous

assessment period.

3.

Board Recommendations

None.

.

..

-._

..

'

.

F.

Licensing Activities

1.

Analysis

Evaluation of the licensee's performance for this rating

period was predicated on how the licensee fared in the

areas of management involvement and control in assuring

quality; how the licensee approached the resolution of

technical issues; the licensee's responsiveness to NRC

initiatives; and project staffing in the emergency planning,

licensing, and plant operating organizations.

During this review period, the licensee's management

demonstrated an active participation and thorough working

knowledge of the technical issues involved in licensing

activities, and has kept abreast of current and anticipated

NRR licensing actions. This was especially evident by actions

taken by the licensee's management in directing his staff to

ensure that the physical plant was designed and built in

conformance with regulatory requirements, and in the finaliza-

tion of plant technical specifications. With respect to the

NRC technical concerns over the use of silicone sealants on

HVAC ductwork, it is the staff's opinion that the licensee's

management enabled its technical personnel to institute a

comprehensive testing program to address long-standing generic

NRC staff concerns relative to the integrity of silicone

sealants used in HVAC ductwork under postulated accident

environmental conditions. This testing program is unique in

the industry and has the potential for solving this long-standing

generic issue. More recently, the licensee's management

direction and direct involvement in assessing the effects of

the 1986 Ohio earthquake on the plant design, as well as in the

re-review of the site area geology / seismology design bases, was

instrumental in obtaining the Perry Unit I low power operating

license in March 1986. Wecknesses reported for the last SALP

'

period in the area of the licensee's management involvement and

control in assuring quality with respect to plant test and plant

operation organizational interfaces, control and overview of FSAR

amendments, the oversight of in-house and Architect Engineer

'

engineering work to preclude deficiencies found during the

Independent Design Inspection (IDI) Team audit of the licensee's

technical documentation file, and the workload problems in the

Licensing organization which resulted in missed commitments,

have all been corrected to the NRR staff's satisfaction. On

being notified of these performance weaknesses, the licensee's

senior management took prompt remedial action and instituted

more rigorous controls and made personnel changes which corrected

problems in the oversight of engineering work and organizational

interfaces.

_.

.

The licensee's understanding of technical issues, which needed

to be resolved prior to obtaining an operating license for

Perry 1, and their approach to resolving technical issues was

found to be thorough and competent.

Performance of the

licensee's technical staff was better than average in

addressing such difficult SER open issues as:

reliability of

TDI diesel engines; the detailed control room design review;

Reactor Coolant Pressure Boundary (RCPB) leak detection design;

Mark III (Humphrey) containment design issues; completion of

the fire protection program; use of silicone sealant in HVAC

ductwork; post accident sampling system design; and the

completion of plant equipment seismic / dynamic qualifications.

It is particularly noted that the work performed by the

licensee contributed to making Perry the only Mark III plant to

date which has satisfactorily resolved every containment design

issue, alleged by John Humphrey (a former GE engineer) at the

time the initial SER was issued in May 1982.

Responsiveness to NRC initiatives has been most satisfactory in

that the licensee is always ready to meet with the staff (often

generating meetings themselves) to ensure a correct response to

NRC needs. Examples of this were most evident from the

licensee's performance in the resolution of the technical issue

>

discussed above, responding to TMI Action Items, requests for

additional information, and NRC Generic Letters during this

performance appraisal period.

The licensee's staffing for the operation of Perry 1 is

considered by NRR to be qualified and adequate for Perry 1

operation. At the time of Perry I licensing, there was a

sufficient number of licensed SR0s, R0s, and STAS to man six

operating shifts. The licensee has chosen to operate the

facility with four rotating shifts throughout the startup

test program. The licensee's plan to have every General

Engineering Supervisor licensed as SR0s as a matter of policy

is a distinctive plus.

An inspection was performed by region based personnel to

'

determine the level of consistency and compatibility between

plant Technical Specifications (DRAFT), Final Safety Analysis

Report (FSAR), Safety Evaluation Report (SER), as-built

i

configurations, surveillance requirements, and preoperational

test acceptance criteria. The inspection revealed no

violations of NRC requirements and documents reviewed exhibited

a high degree of consistency.

2.

Conclusions

An overall Category 1 rating is assigned for the licensee's

performance for this rating period. The licensee was rated

Category 2 in this area during the previous assessment period.

_

._

.-.

-- _.

-

.-

.-

_-

-

. _ _ _ - -

.

3.

Board Recommendations

None.

G.

Preoperational Testing

1.

Analysis

During this assessment period six inspections were performed

in this functional area. The inspection effort included:

(1) review of administrative controls and implementing

procedures; (2) detailed reviews of preoperational test

procedures and results; (3) preoperational test witnessing;

(4) verifications of preoperational test procedures and results;

(5) independent inspection; and (6) followup of previous

inspection items.

Six violations were identified as follows:

a.

Severity Level IV - Preoperational Test Procedures TP

1C71-P001, " Reactor Protection System (RPS)" and TP

IC71-P002, " Reactor Protection System Motor-Generator

Sets" were inadequate because they did not adequately

test design features.

Preoperational Test Procedure

TP 1M51-P001, " Combustible Gas Control System" was

inadequate because it was inconsistent with the

licensee's administrative requirements (Inspection

Report No. 50-440/85042).

,

b.

Severity Level IV - Inadequate measures to ensure

that the System Test Engineer is aware of the status

of his system with respect to temporary alterations

while undergoing testing (Inspection Report

No. 50-440/85042).

c.

Severity Level V - Inadequate measures to indicate

jurisdictional status of equipment in the control

room (Inspection Report No. 50-440/85042).

d.

Severity Level IV - Preoperational Test Procedure

TP IP57-P001, " Safety-Related Instrument Air," was

determined to be inadequate for not properly

controlling the sequence of testing (Inspection

Report No. 50-440/85053).

._

_.

. _ -.

.-

~

.

e.

Severity Level IV - Testing was not accomplished in

accordance with applicable procedure requirements for

TP 1R76-P001, "ECCS Initiation / Loss of Offsite Power,"

TP 1C71-P001, " Reactor Protection System," and TP

1M51-P001, " Combustible Gas Control System" (Inspection

Report No. 50-440/85053).

f.

Severity Level V - Resolutions of failures to meet

acceptance criteria in Preoperational Test Procedures

TP 1G43-P001, " Suppression Pool Makeup (SPMU) System"

and TP 1C71-P002, "RPS Motor Generator Sets" represent

inadequate documentation and evaluation to assure test

requirements had been satisfied (Inspection Report

No. 50-440/85081).

These violations can be categorized into four general areas of

(1) inadequate administrative controls, (2) inadequate documen-

tation and evaluation of failures to meet acceptance criteria,

(3) inadequate test procedures and (4) failure to follow

procedures.

The identified violations are in either random areas or areas

of the test program that have been corrected before the end of

this assessment period, and therefore do not appear to indicate

any significant problems.

As a result of 13 violations identified in the previous 18 month

SALP period, a management meeting was conducted on June 3, 1985,

to discuss NRC concerns.

The licensee was very responsive to

NRC initiatives and implemented aggressive corrective actions

to address those concerns. The licensee exhibited increased

initiative in identifying and implementing self-imposed

corrective actions. The effectiveness of those actions was

evaluated during this assessment period and found to satisfac-

torily remedy the concerns.

Five of the six violations

identified in this SALP period were identified in the first

three months of the period. These were primarily attributable

to causes which actually occurred prior to the management

meeting or prior to complete implementation of the resulting

corrective actions. Therefore, the six violations of this 10

month SALP period represent a substantial reduction in both

frequency and significance from the 13 violations of the

previous 18 month SALP period.

The licensee displayed evidence of prior planning and

assignment of priorities by forming a Management Procedure

Review Team (MPRT) to determine the extent of the problems and

to present recommendations for corrective actions, in that the

MPRT was well staffed technically and received upper management

support. Corporate management was involved with the creation,

_

.

recommendations, and other activities of the MPRT which ensured

adequate management review of site activities. Personnel

appeared to understand and be operating in compliance with

adequately stated policy.

In implementing the MPRT recommendations, the licensee

developed Special Project Plan 1102, " Test Procedure Assurance

Review." This plan ensured preoperational test procedure

adequacy by providing a generally sound review of all

preoperational and selected acceptance test procedures. The

plan's reinforcement of attention to detail to ensure technical

adequacy of test procedures was found to be effective.

At the time of the NRC review, the preoperational test

procedures TP IC71-P001, TP 1C71-P002 and TP IM51-P001 had not

yet received the MPRT additional review, therefore, violation

'

a. does not reflect on the corrective actions. The sequencing

'

problem of Violation d. identified in TP IP57-P001 (a

post-MPRT-reviewed procedure) probably would have been

corrected during performance of the test and was the only

procedure inadequacy identified in a post-MPRT-reviewed

procedure. Generally, the procedure review seemed to have

prevented recurrence of any procedure inadequacies due to

omission of design feature testing. The plan was eventually

effective in preventing failures to follow procedures by

increased supervisory involvement during the evolution and

conduct of test procedures and revisions and additional

training for test personnel.

The failure to fcilow procedures

documented in Violation e. occurred in the first three months

of this assessment period. No recurrences were identified in

the subsequent months and it appears the corrective actions of

additional training finally became ef fective. Violations b.

and c. document failure to meet administrative controls that

occurred before the corrective actions of June 3,1985, became

effective.

There were no subsequent administrative require-

ment violations identified in the following 11 months;

therefore, the corrective actions appear effective. The re-

review of licensee requirements was effective because no

omissions of required testing were identified subsequent to

MPRT review. Generally the licensee was very responsive to NRC

initiatives and the corrective actions took a long time to

manifest their effectiveness only because of the vast amount of

work undertaken by the licensee to ensure preoperational test

program adequacy. Therefore, in that context, the corrective

actions were generally timely and effective.

The licensee generally understood technical issues exhibiting

conservatism in the resolution of approximately 2000 problems

encountered during testing commonly called test exceptions.

I

Violation f. documented only two test exceptions that were

inadequately resolved.

Licensee management adequately resolved

i

.

_m

-

-

__

~

.

those after citation. Based upon the large sample determined

to be adequate, these are considered isolated occurrences and

represent no significant problem.

Occasional significant construction events attributable to

causes under the licensee's control, have occurred that are

relevant to preoperational testing but they were reported and

analyzed properly.

Staffing, including management, appears adequate.

2.

Conclusions

The licensee is rated Category 2 in this area. This is an

improvement from the previous SALP period rating of Category 3.

The improvement is largely attributable to the effective

management initiatives taken by the licensee following the

June 3,1985, management meeting with the NRC.

3.

Board Recommendations

None.

H.

Startup Testing

1.

Analysi s

Region based inspectors performed three inspections in this

functional area. The inspection effort included overall

startup test program review and startup test procedure review.

There have been no violations identified in this area.

The inspections showed that the overall program is comprehen-

sive and adequate.

In addition, the startup test procedures

are adequate in meeting administrative requirements and regula-

tory commitments and exemplify good technical methodology. The

inspectors feel that overall the procedures for control of

activities were well stated, controlled, and explicit.

The licensee has proved to be responsive to NRC initiatives in

that an additional final review by quality assurance was

provided to ensure correction of some minor procedural problems

and prevent recurrence. All startup test procedures are to be

revised under this modified review process prior to their actual

use. The licensee was not rated in this functional area during

the previous SALP assessment period because of no work being done

in this area.

Inspections in this assessment period have covered

a limited portion of this functional area.

i

j

'

.

2.

Conclusions

No rating is recommended in this area due to limited licensee

and inspection activity. The licensee was not assessed in this

area during the previous SALP period.

3.

Board Recommendations

None.

I.

Radiological Controls

1.

Analysis

Five preoperational inspections were conducted during the

assessment period. These inspections covered radiation

protection, radwaste, chemistry, confirmatory measurements, and

environmental monitoring. No violations were identified.

The licensee has satisfactorily completed activities essential

to load fuel. Organization, staffing, and training meet FSAR

requirements. Capabilities of staff and technicians were

judged adequate to proceed with fuel load and startup, and the

qualified staff is large enough to provide coverage on all

shifts. The licensee is seeking to retain a qualified

chemistry consultant to assist the Plant Chemist during early

plant operation in accordance with their commitments.

Facilities

and equipment for health physics and chemistry were generally

satisfactory.

Overcrowded office space identified in the previous SALP was

alleviated and now appears adequate.

Laboratory and counting

room instruments are of good quality, adequate to perform the

required analyses, and have been calibrated in accordance with

approved procedures. The licensee established a water

chemistry control program addressing the important elements

l

presented in the BWR Owners Group guidelines with provision for

monitoring and trending important parameters and for suitable

administrative limits. The licensee has agreed to issue a

corporate policy on water chemistry control within six months

after issuance of the fuel load license. The licensee also

completed the preoperational requirements for the Radiological

Environmental Monitoring Program (REMP) and demonstrated

satisfactory capability in performing analyses of radiological

samples. Management involvement in these areas has been

evident during the assessment period.

.

,

, - -

.

Adequate management involvenent and technical issue resolution

has been exhibited by the licensee in assigning priorities for

completing critical preoperational activities and documenting

necessary deferrals. Several activities, not essential for

'

fuel loading, have been deferred with appropriate schedule

priorities. These activities include:

testing and correction

of deviations for the liquid radwaste processing, solid radwaste,

and offgas systems, which were deferred until initial

criticality; operability of the Post Accident High Range

Radiation Monitoring System, which has been deferred to five

percent power; investigation of use of silicone sealant on

certain HVAC systems and representativeness of gaseous effluent

sampling systems, which are scheduled for resolution by the first

refueling outage; work on the Turbine Plant Sampling System

(TPSS), including replacement of extraction pumps and calibration

of dissolved oxygen monitors, which is scheduled for completion

by turbine roll; and completion of a small tool decontamination

and storage facility, tentatively scheduled for mid-1986.

Management responsiveness and resolution of NRC identified

technical issues were adequate during this assessment period.

The licensee's initiation of a program to test silicone

sealants used in HVAC ductwork under postulated accident

environmental conditions is an example of good responsiveness.

Conversely, weaknesses are evident in laboratory Quality

Control (QC) where the program for testing of technician

proficiency with unknowns is limited to analyses required by

technical specifications; not included are sulfate, fluoride,

silica, and copper which are important for chemical control

<

and recommended by the BWR Owners Group. The licensee has

been reluctant to make specific commitments for improvements

in laboratory QC but has indicated a willingness to extend

the scope of the QC program at a later time. The licensee's

policy and plans for a quality assurance audit program for

radiological controls appears adequate.

2.

Conclusions

The licensee is rated Category 2 in this area. This is the

same rating as the previous assessment period.

3.

Board Recommendations

None.

'

.

J.

Fire Protection

1.

Analysis

During this assessment period, two inspections by Region III

based inspectors and their consultants were performed to

determine the status of outstanding fire protection issues

including a continuing assessment of the licensee's fire

protection program implementation and a review of allegations

received by the NRC relative to penetration seals. No

violations or deviations from NRC guidelines or other

commitments were identified during these two inspection visits.

Based on these two regional inspections, it was determined that

the licensee was continuing to make satisfactory progress in

implementing the applicable fire protection requirements and

the fire protection preoperational test program. The outstanding

items remaining open from the initial fire protection team

inspection (Inspection Report 440/85015), discussed during the

last assessment period, were all addressed adequately by the

licensee's staff and the majority closed out in these two

inspection reports.

A review of three allegations concerning penetration seals was

completed. They were closed based on supporting test data and

the technical adequacy of procedures including an in-office

review of certain information provided by the licensee.

Management was found to be sufficiently involved in this

functional area as evident by the licensee's responsiveness in

addressing the inspectors' outstanding items.

Staffing

appeared to be adequate and personnel were found to be

knowledgeable and well trained.

2.

Conclusions

The licensee is rated Category 2 in this area. The licensee

was rated Category 2 in this area during the previous

assessment period.

3.

Board Recommendations

None.

K.

Emergency Preparedness

1.

Analysis

Four inspections were conducted during the assessment period to

evaluate the licensee's performance with regard to emergency

preparedness. These included a followup inspection to the

Emergency Preparedness Implementation Appraisal (EPIA) to

-

___

_-

.

assess the progress in addressing NRC concerns raised as a

result of the EPIA; observation of the annual emergency

preparedness exercise in 1985; an inspection to assess the

actions associated with the activation of the Emergency Plan as

a result of a January 31, 1986, earthquake; and an inspection

of the 1986 annual exercise. No violations or deviations were

identified during the SALP period.

No weaknesses were

identified during the 1985 annual exercise; no additional NRC

concerns were raised during the followup to the EPIA; only two

NRC concerns were tracked as open items as a result of the

licensee's performance in regards to activating their Emergency

Plan due to the earthquake.

The scenario for the 1986 exercise was considered challenging

and difficult, and adequately exercised all aspects of the

Emergency Plan. While three Open Items were identified as a

result of this exercise, the items were considered minor.

In almost all cases, the licensee has been responsive to NRC

concerns by providing viable, sound, and thorough responses in

a timely manner. When resolving weaknesses from a safety

standpoint, the licensee has demonstrated a clear understanding

of the issues involved.

Management involvement in emergency preparedness has been very

strong as evidenced by their participation in the exit meetings

following each inspection, and their timeliness in addressing

WRC concerns.

Staffing of key emergency response positions has been adequate,

with the authorities and responsibilities of personnel well

r

identified.

Knowledge and capability of personnel to carry out

their assigned emergency response duties and responsibilities

was demonstrated during both annual emergency preparedness

exercises and the actual activation of the Emergency Plan due

to the earthquake. The licensee's performance related to these

two items is indicative of an effective training program that

has adequately prepared personnel to carry out their emergency

response assignments.

2.

Conclusions

The licensee is rated Category 1 in this area, and was also

rated a Category 1 in this area in the last SALP period.

3.

Board Recommendations

None.

'

.

L.

Security

1.

Analysis

Four preoperational safeguards inspections were conducted by

regional based inspectors during the assessment period and

one routine safeguard startup inspegtion was i,e! formed

subsequent to the assessment period to determine the licensee's

progress in implementing the security program. The resident

inspectors also made periodic inspections of security activities,

and assessed routine program implementation.

One Severity Level IV violation was identified

subsequent to the assessment period because

portions of the licensee's vital area barriers

were found unsecured (Inspection Report 50-440/86013).

The licenses's immediate actions resolved the issue

and a written response to the violations was not

required.

This violation is not included in Paragraph V.B.1, Table 1,

of this report, but is addressed here because it reflects on

performance during this assessment period.

The licensee's Physical Security Plan, Safeguards Contingency

Plan, and Training and Qualification Plan became effective

on March 18, 1986, upon issuance of their operating license.

Therefore, no violations were cited during the preoperational

security inspections. During the preoperational inspections,

numerous items were identified and were satisfactorily corrected

and/or resolved prior to issuance of the operating license.

The 1fcensee has been very responsive to the concerns identified

by the NRC and extremely aggressive in self-identifying and

correcting problems.

During the preoperational phase in anticipation of initial

activation of the security program needed prior to license

issuance, the licensee requested and received an extensive

security audit conducted by the security managers from nuclear

plants of another large Region III utility which assisted in

establishing priorities for implementation and problem areas.

The licensee's preoperational planning and scheduling program

was aggressive and proved effective, and as a result, all

preoperational inspection findings / concerns were resolved prior

to licensing.

The licensee's senior management appears to have an awareness

of security issues and are effective and responsive to

resolving security issues as demonstrated by the extensive

.

.

--

'

.

resources devoted to completion of the background screening

program. The senior security personnel represent broad

technical disciplines, have a high degree of expertise, and

have been effective in identifying problem areas and

-

recommending solutions.

Concerns and observations receive the

same exceptionally high level of management attention normally

associated with violations. The security management is

responsive to all findings that can strengthen their program,

rather than concentrating on just minimum compliance required

by the security plan.

The licensee's staffing levels appear adequate to fulfill

security plan commitments. There have been no licensee reports

of Safeguards events and no known events that would require a

report. The licensee is fully aware of the reporting require-

ments and the importance of timely and detailed reports.

The licensee's training and qualification program is well

defined and implemented with dedicated resources which make a

positive contribution to overall implementation of the security

program. Understanding of and adherence to procedures resulted

in few personnel errors during the rating period.

The site Quality Assurance (QA) Department, which lacked

experience in the security field, will have to demonstrate

through involvement in site security activities, that they can

effectively audit the security program, and identify security

weaknesses.

In summary, the licensee's security staff has been effective in

the planning and implementation of the security program.

The

security staffing is adequate and departmental support for the

security program has been effective.

2.

Conclusions

The licensee is rated a Category 1 in this area. The licensee

was rated Category 2 in this area during the previous

assessment period.

3.

Board Recommendations

None.

1

.

M.

Maintenance / Modifications

1.

Analysis

The operational maintenance program was reviewed in detail in

portions of 10 inspections during this assessment period.

These inspections included the review of related IE Circulars

and Bulletins, maintenance procedures, staffing, work control,

work package implementation, and the overall effectiveness of

the maintenance program. One violation was identified in

this area as follows:

Severity Level IV - Work Order No. 86-2829 for

filling and venting the suppression pool level

instruments was not prepared, controlled, or

accomplished in accordance with instructions and

administrative procedures in that uncontrolled

non as-built drawings were being used to perform

safety related work; work was performed out of

required sequence; incorrect instructions were

not properly corrected; independent restoration

verifications were not properly accomplished; and

the work order did not include the purpose, as

required (Inspection Report 50-440/86006). Another

example of this violation is identified in Section P.

This violation identified weaknesses in Instrumentation and

Control (I&C) implementation of the maintenance program.

In

addition, a major undertaking by the licensee to provide

controlled "as-built" drawings of instrument lines occurred as

a result of the identification of the lack of "as-built"

drawings used to perform the I&C Work Order. The licensee took

prompt corrective actions to assure that personnel were

counseled on the importance of following established

procedures. A site-wide compliance training program was also

established.

The licensee's program for implementation of maintenance

activities was found to be generally adequate and amply

staffed. Maintenance personnel were found to meet FSAR and

ANSI qualification requirements but did not always meet the

requirements specified by the licensee's more conservative

administrative procedures. The licensee has committed to

have these personnel qualified to their own program by

December 31, 1986.

Region III has found this implementation

schedule to be acceptable.

Management was four.d to be committed to improving their

established program as deficiencies are identified during

actual implementation. This was apparent when, during a recent

NRC review of their maintenance program, three weaknesses in

the licensee's program were brought to their attention, and

.

the inspector was shown evidence that the weaknesses had been

previously self-identified and procedural changes had already

been prepared and were being reviewed to correct the

weaknesses. Utilizing a state-of-the-art ccmputerized

information storage and scheduling system, the licensee's

periodic maintenance (PM) program appeared to adequately

identify and direct the conduct of safety related PM

activities.

As described above, management appears to be adequately

involved in assuring quality.

Their approach to resolving

technical problems, once identified, appears to be

comprehensive, and their responsiveness to NRC identified

concerns were found to generally be prompt and thorough.

However, weaknesses in the implementation of maintenance

activities as identified in the above violation, and licensee

self-identified maintenance discrepancies have required, and

will continue to require management attention and involvement.

2.

Conclusions

The licensee is rated Category 2 in this area. The licensee

was not assessed in this area in the previous SALP period.

3.

Board Recommendation

None.

N.

Surveillance and Inservice Testing

1.

Analysis

The examination of this functional area included portions of

twelve inspections by Region III inspectors. The inspections

included the review of Local Leak Rate Testing (LLRT),

applicable IE Bulletins, numerous surveillance instructions

(as part of the NRC's preoperational phase inspection program),

observations of surveillance test performance, and review of

programmatic aspects of surveillance testing including the

computerized scheduling system (r2petitive task program). No

violations of NRC requirements or deviations from commitments

were identified in this functional area.

During the review of LLRTs, procedures were generally

well-defined and accurate. Technical issues raised as a result

of an earlier Integrated Leak Rate Test inspection (conducted

during the previous SALP period) were found to have been

resolved satisfactorily. Management's responsiveness to

inspector identified concerns was excellent and staffing was

found to be well qualified and adequate for LLRT activities.

__,

.

Review of surveillance instructions (SVIs) revealed that, in

general, they were prepared in accordance with administrative

procedures, technically adequate, and met the requirements of

the initiating documents (i.e., Technical Specifications, FSAR,

etc.).

During the licensee's preparation of the SVIs, several

program actions were initiated by management to ensure quality

and technical adequacy. These actions included initial

development, SVI walkdown/dryrun, rewrite, and run for credit.

By performing these functions, many of the minor errors

associated with the development of this massive SVI program

were identified and corrected prior to the "run for credit."

However, problems were encountered during the "run for credit"

phase that could have been avoided had there been a trial run

of the SVIs prior to their run for credit. These problems,

which required initiation of procedure changes, may have resulted

in some plant delays, but did not have any direct safety

implications.

A sample review of surveillance procedures required by Technical

Specifications was conducted and found, in general, to be in

agreement with the Technical Specifications. However, when

reviewing the licensee's program for ensuring that non-routine

surveillances were conducted as required by Technical

Specifications, it was discovered that the SVI for determining

,

the shutdown margin prior to or during the first startup after

'

each refueling, was not included in their " repetitive task"

program or any other written program. Subsequently, the

licensee performed a review of all non-routine surveillances

specified in the Technical Specifications to ensure that they

were included in their operating procedures. No other examples

of SVIs were found t.o be missing from the licensee's operating

procedures.

During this assessment period, some SVI performance observations

were conducted which included SVIs associated with the fueling

activities. These observations determined that the SVIs were

being conducted as specified by administrative procedures and

those performing the work were knowledgeable and followed the

instructions as required.

Management's responsiveness to and resolution of NRC identified

issues were adequate during this assessment period. The

licensee's staff appeared to be adequate, knowledgeable and

well trained for both the preparation and implementation of the

SVI program.

- _ _ _ - - - _ _ _ _ _ _ _

-__

'

.

2.

Conclusion

The licensee is rated a Category 2 in this area. The licensee

was not assessed in this area during the previous SALP period.

3.

Board Recommendations

None.

O.

Fueling

1.

Analysis

The licensee received an operating license on March 18, 1986,

and fuel loading commenced on March 21, 1986.

Fueling was

completed on April 24, 1986, approximately two weeks behind

schedule.

Region III inspectors provided 24 hour2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> / day coverage

of the initial fueling process and performed extensive

inspection activities associated with Technical Specification

compliance, nuclear instrumentation calibration, core physics

testing, shift turnover activities, refueling floor access

control, and other associated fuel loading activities. No

violations of regulatory requirements or deviations from

commitments were identified.

Fuel loading activities were suspended on several occasions

due to the refueling machine main hoist drive motor supply

breaker tripping on overcurrent on numerous occasions and

spurious high neutron flux signals due to electrically

induced " noise" on the intermediate range neutron flux

monitoring (IRM) system which resulted in trips of the reactor

protection system which were properly reported.

The licensee's

actions to repair the hoist included, among others, the

replacement of the supply breaker, fuses, power supply, and

control circuitry components.

Initially, licensee corrective

actions to resolve this equipment problem were slow to be

l

formulated and not well organized.

Late in the fueling process

l

it was determined that a silicon controlled rectifier (SCR) in

l

the power supply to the main hoist was the cause of the tr.ps.

l

This SCR had been previously replaced, and therefore, not

suspect.

Following re-replacement of the defective SCR, the

main hoist drive operated normally.

The refueling equipment

is non-safety related and the associated problem did not pose

a safety concern. The IRM noise problem was attributed to

i

grounding and/or cabling deficiencies which were identified

i

by exhaustive troubleshooting and corrective maintenance

t

activities.

l

Inspector observations indicated fuel loading activities were

well coordinated and that licensee personnel proceeded in a

i

cautious and deliberate manner.

I

i

l

,

l

l

-

.

Management was actively involved in assuring quality and

,

adequate but sometimes slow resolution of technical issues

during fuel loading activities. Management ensured that no

undue scheduling pressure, which may have resulted in opera-

,

tional/ technical specification errors, was placed on the

<

operators during this initial post license activity. There

were sufficient numbers of operators on duty and they appeared

to be well trained and performed in a professional manner

'

commensurate with the positions they held.

2.

Conclusions

The licensee is rated Category 2 in this area. The licensee

was not assessed in this area during the previous SALP period.

3.

Board Recommendations

None.

,

P.

Operational Readiness / Plant Operations

1.

Analysis

'

Inspection of this functional area during the assessment period

consisted of portions of ten inspections and one inspection

subsequent to the assessment period by the resident and project

inspection staff. These inspections included examinations of

(1) normal operating procedures; (2) abnormal operating proce-

dures; (3) emergency operating procedures; (4) annunciator

i

response procedures; (5) system status control; (6) operating

logs and records; (7) control of work activities; (8) rountine.

operations; and, (9) reportable events.

One violation and one example from a violation contained in

section M were identified, as follows:

a.

Severity Level IV (one of two examples) - System Operating

Instructions (SOIs) were found to be technically inadequate.

j

This example is part of a violation identified in

Section M (Inspection Report 50-440/86006).

b.

Severity Level V - Inadequate review of a tag-out prior

to authorization and attempted performance of associated

work (Inspection Report 50-440/86008).

Subsequent to the assessment period, we issued Report

No. 50-440/86011, which identified three additional violations

,

as set forth below. While these violations are not included

.

in Paragraph V.B.1, Table 1 of this report, they are addressed

here because they reflect on performance during this assessment

period.

1

.

.. -

.

.

_ _ -

.. _ _. _.

.,

. _ -.

-

-

,

-...

_

.

a.

Severity Level IV - Failure to suspend containment /drywell

purge with inoperable plant vent radiation monitor

(Inspection Report 50-440/86011).

.

b.

Severity Level'IV - Two examples of failure to maintain

containment integrity during core alterations (Inspection

Report 50-440/86011).

c.

Severity Level IV - Failure to take compensatory actions

for inoperable carbon dioxide fire suppression system

(Inspection Report 50-440/86011).

Licensee management has been actively involved in adequately

resolving technical issues and assuring quality. As a result

of the violation concerning SOIs, the licensee proposed a

program of detailed re review to assure technical adequacy.

The licensee committed to conducting re-reviews and making

necessary corrections prior to the use of each SOI under the

operating license.

Followup inspections of S0Is subjected to

the re-review prior to fuel load and initial criticality

determined that the licensee's corrective actions were

responsive and effective in resolving the identified concern.

The other four violations all resulted from personnel errors,

including failures to comply with established administrative

controls. While these violations were licensee identified, and

corrective actions were taken to address each occurrence, they

collectively suggested a need for further evaluation to

determine whether or not they resulted from a lack of

understanding of administrative controls, excessive workloads,

or inattention to detail by operating personnel. These matters

were discussed with the licensee in a management meeting

conducted subsequent to the assessment period on June 5, 1986.

Licensee management personnel exhibited an understanding of the

significance of these items and informed NRC management that

additional evaluations of the events had resulted in changes to

personnel work assignments. The licensee also indicated that

future performance would be closely monitored such that any

need for additional actions would be promptly identified and

acted upon.

Licensee management, supervisory and non-supervisory operating

personnel have exhibited an understanding of the high level of

performance which must be achieved and maintained in this

functional area. Throughout the approach to operating license

issuance the licensee exhibited a good deal of caution in

assuring the readiness of personnel, equipment, procedures, and

programs for plant operations. Concerns identified by licensee

self-assessment as well as NRC inspection personnel were

responded to in a thorough and timely manner. Following

operating license issuance, the licensee continued with this

same caution and responsiveness to identified concerns.

. _.

.__

_

-

.-.

_._

__

.

A single programmatic concern remained at the close of the

assessment period. Based upon inspector review of the

licensee's response to a number of technical problems which

arose following operating license issuance, it appeared that

operating management personnel had neither demanded nor

received rigorous and coordinated technical support.

Subse-

quent to the assessment period the licensee made a number

of personnel and organizational changes intended, in part, to

address this identified weakness.

Notwithstanding the identified violations and concern, the

conduct of day-to-day activities under the operating license

has been generally found to be well controlled by knowledgeable

operating personnel and in accordance with technically adequate

procedures.

2.

Conclusions

The licensee is rated Category 2 in this area. The licensee

was rated Category 2 in the Operational Readiness assessment

area during the last SALP period but was not assessed in the

Plant Operations area.

3.

Board Recommendations

None.

Q.

Training and Qualification Effectiveness

1.

Analysis

Evaluations of the licensee's training and qualification

effectiveness has been and is an ongoing activity by Region III

inspectors in all areas of the plant's construction,

preoperational, and operational phases.

No violations were

identified in this assessment area.

Specific training programs reviewed included observations of

the general employee training program, the radiological

controls training course, and portions of maintenance and

operating personnel training programs. These reviews indicated

that the instructors followed prescribed training plans and met

the training objectives.

In addition, the training courses,

attended by inspectors, appeared to adequately cover the subject

matter in sufficient detail to ensure co-the-job training

requirements were being met.

'

.

During an inspection, a deficiency was identified concerning

the untimely distribution and training for temporary changes to

plant procedures. Procedure changes were being issued without

providing training to plant personnel. To resolve this issue,

the licensee changed applicable procedures to require training

of appropriate personnel when a temporary change to a Plant

Administrative Procedure is issued.

During the review of FSAR Chapter 13 " Conduct of Operations,"

specifically, the licensee's staff qualifications and training,

several discrepancies were identified where the qualifications

of incumbent operational staff did not agree with the

requirements delineated in ANSI N18.1 and/or Regulatory Guide 1.8.

To resolve these discrepancies, the licensee undertook a

comprehensive review of their operational staff qualifications

and requirements and subsequently amended (Amendment 21) the

FSAR to update and clarify the plant organization.

In

addition, the licensee replaced one individual with one that

met qualification requirements and provided additional

information for the other individuals that had discrepant

qualifications. The amendment and additional information

resolved the discrepancies.

As identified above, management is very responsive to NRC

identified issues and generally resolves them with comprehensive

corrective actions. When deficiencies are either NRC or self-

identified in various areas of the plant organization, enhanced

training is a method often incorporated into their corrective

actions to ensure that plant personnel are informed of the

deficiencies and management's planned and implemented

resolutions. Generally, plant staff training and qualifications

have been found to be above average; however, due to the change

from the construction and preoperational phases to the plant

operattsnal phase, increased management attention to training

is warranted to ensure that all personnel are kept abreast of

plant procedures that are undergoing fine-tuning as a result of

implementation experience.

'

The licensee is currently planning to achieve full INPO

accreditation of their training program by October 1987. This

is an approximate one year slip from their previous estimate of

October 1986. However, if accomplished as currently scheduled,

this will comply with industry commitments.

2.

Conclusions

The licensee is rated a Category 2 in this area. The licensee

was not assessed in this area in the previous SALP period.

3.

Board Recommendations

.

I

None.

-

_

-

._

._

=_,

.

V.

SUPPORTING DATA AND SUMMARIES

A.

Licensee Activities

For the first nine months of the assessment period, Perry Unit I was

considered to be in the construction /preoperational testing phases.

On March 18, 1986, a low power operating license was issued by the

NRC.

Initial fuel loading began on March 21, 1986, and was completed

on April 24, 1986.

Fueling progressed slower than anticipated due

to recurring problems with the re-fueling machine and associated fuel

bundle lifting hoist.

During and subsequent to fuel loading, a

number of operational events occurred, including some which required

NRC notifications per 10 CFR 50.72 and 50.73. These events have

required and are requiring extensive licensee investigation as to

their causes and development of adequate corrective actions.

Initial

criticality occurred on June 6, 1986. For the remainder of the time

prior to issuance of this report, the unit has operated at less than

5% power with the low power testing portion of the startup program

continuing.

B.

Inspection Activities

1.

Inspection Data

Facility Name:

Perry Nuclear Power Plant, Unit 1

Docket No. 50-440

Inspections:

No. 50-440/85016; No. 50-440/85027;

No. 50-440/85031; No. 50-440/85034;

No. 50-440/85040 through No. 50-440/85042;

No. 50-440/85044; No. 50-440/85047

through No. 50-440/85051; No. 50-440/85053

through No. 50-440/85085; No. 50-440/85087

through No. 50-440/85090; No. 50-440/86001;

50-440/86002; No. 50-440/86004 through

No. 50-440/86010; No. 50-440/86011* and

No. 50-440/86013*.

  • Inspections performed subsequent to this assessment period

but included in the assessment.

'

- - - -

.

_

.

. -

-

.

-.

_

_

_

.

TABLE 1

ENFORCEMENT ACTIVITY

This table includes those violations issued during the

assessment period. Not iacluded are the violations

discussed in Paragraphs IV.L and IV.P which occurred

after the assessment period.

No. of Violations in Each

Severity Level

Functional Areas

I

II

III

IV

V

DEV

A.

Containment and other

Safety-Related Structures

B.

Piping System and Supports

C.

Heating, Ventilating, and

Air-conditioning

D.

Electrical Power and

Instrument and Control

Systems

E.

Quality Programs and

Administrative Controls

Affecting Quality

F.

Licensing Activities

G.

Preoperational Testing

2

H.

Startup Testing

I.

Radiological Controls

J.

Fire Protection

K.

Emergency Preparedness

L.

Security

M.

Maintenance

N.

Surveillance

_

-

.-- -

-- - --

._.

..

-.

.-

-

_

_.. -.

'

.

Functional Areas

I

II

III

IV

V

DEV

0.

Fueling

P.

Operational Readiness /

Plant Operations

Q.

Training and Training

Effectiveness

TOTALS

3

2.

Inspection Summary

Throughout the assessment period, NRC Region III conducted

inspections to assess the readiness of Perry Unit 1 for power

operations.

Included were reviews of the plant fire protection

program, procedures, Technical Specifications, Final Safety

Analysis Report (FSAR) and as-built configuration comparison,

adequacy of operating shifts, preoperational testing, startup

testing, and adequacy of management and engineering support

activities.

In addition, an Augmented Investigation Team and

support team walkdown inspection was conducted to assess the

effect of the January 31, 1986, earthquake.

C.

Allegation Review

Region III received 18 allegations during the assessment period that

resulted in inspections by resident and/or region based inspectors.

None of the findings involved significant safety issues.

D.

Escalated Enforcement Action

None.

E.

Management Conferences Held During the Appraisal Period

1.

September 12, 1985, Perry plant site - Meeting to discuss the

NRC fuel load requirements.

2.

September 26, 1985, Perry plant site - Meeting to discuss the

SALP 5 results.

3.

October 11, 1985, Perry plant site - Meeting to discuss items

required for fuel load.

4.

November 6, 1985, Perry plant site - Meeting to discuss

Preoperational Test Program problems and items required for

fuel load.

5.

December 3,1985, Perry plant site - Meeting to discuss the

status of items required for fuel load.

.

6.

December 17, 1985, NRC offices, Bethesda, Maryland - Meeting to

determine readiness of Perry Unit 1 for operating license.

7.

February.11, 1986, Perry plant site - Meeting to discuss review

of the January 31, 1986, earthquake and operational readiness

to load fuei.

F.

Confirmatory Action Letters

On January 31, 1986, Region III issued a Confirmatory Action

Letter (CAL-RIII-86-01) to document an agreement with the. licensee

for them to maintain all affected equipment in the "as found"

condition until the NRC Augmented Investigation Team (AIT) could

examine any evidence.which would be needed to evaluate the effects

of the January 31, 1986, earthquake that occurred near' Perry.

Licensee's cooperation with the NRC in response to the earthquake

event and their own immediate and subsequent followup of the event

were found to be excellent. Their response to the CAL provided the

NRC with valuable data that enabled the staff to better evaluate

the impact of the earthquake on the plant.

G.

Review of Licensee Event Reports, Construction Deficiency Reports,

and 10 CFR 21 Reports Submitted by the Licensee

1.

10 CFR 50.55(e) Reports (Construction Deficiency Reports)

During this SALP period, three 10 CFR 50.55(e) items were

reported by the licensee. The formal reports were timely,

well stated, and complete.

Corrective actions were promptly

initiated and all were documented as closed.

2.

10 CFR 21 Reports

There have been five 10 CFR 21 reports received concerning the

Perry plant. All but one of these reports have been reviewed

~

by the licensee and no modifications to the plant were necessary.

Only one, concerning Kaman high voltage power supply in the post

accident monitoring system, appears to have safety significance,

and it must be resolved prior to exceeding 5% power.

3.

Licensee Event Reports (LERs)

.

The licensee received their license on March 18, 1986, which

!

requires them to submit LERs to the NRC in accordance with

!

10 CFR 50.73. Subsequently, three LERs were received from

'

the licensee by closure of the SALP assessment period. The

i

reports were found to be complete, well written, and followup /

i

corrective actions were generally adequate. The events were

j

found to be primarily caused by hardware and/or design problems.

<

i

l

-

'

.

H.

Licensing Activities

1.

NRR/ Licensee Meetings

November 12, 1985 -

NRC Management visit to Perry plant

site to discuss readiness for

licensing.

December 17, 1985 -

NRC/CEI meeting in Bethesda to discuss

Perry I readiness for licensing.

February 11, 1986 -

NRC visit to plant site during which

CEI presented earthquake findings -

plant readiness for licer. sing.

March 12/13, 1986 -

NRC/CEI presented details of

evaluations of findings on

January 31, 1986, earthquake.

2.

Commission Meetings

None.

3.

FSAR Amendments

July 19, 1985

CEI issued FSAR Amendment 20

October 4, 1985

CEI issued FSAR Amendment 21

November 20, 1985

CEI issued FSAR Amendment 22

November 22, 1985

CEI issued FSAR Amendment 23

December 17, 1985

CEI issued FSAR Amendment 24

4.

NRR Issuance of SER Supplements

November 20, 1985

NRC issued SER Supplement No. 7

January 15, 1986

NRC issued SER Supplement No. 8

March 4, 1986

NRC issued SER Supplement No. 9

5.

Other Activities

July 17, 1985

NRC Commissioner Asselstine toured

plant.

September 3, 1985

ASLB concluded partial initial

decision on Emergency Planning,

Hydrogen Control, and TDI Diesel

Generator Issue.

.

September 20, 1985

NRC accepts CEI schedule for meeting

the Hydrogen Control Rule - 10 CFR 50.44(3)(c)(vii)(A).

October 29, 1985

CEI requested extension of CPPR-148 to

December 21, 1985.

NRC Chairman Palladino toured plant.

October 31, 1985

NRC transmitted the draft low power

operating license for Perry 1 to CEI

for comment.

November 13, 1985

NRC Commissioner Zech toured plant.

November 19, 1985

NRC issued final draft of Perry 1

technical specifications for CEI

certification.

November 29, 1985

CEI requested extension of CPPR-148 to

January 31, 1986.

December 27, 1985

CEI requested extension of CPPR-148 to

March 3, 1986.

January 30, 1986

NRC Commissioner Bernthal toured

plant.

January 31, 1986

Magnitude 5.0 earthquake occurs near

Perry plant site. As a result of the

earthquake, a Confirmatory Action

Letter (CAL) 86-01 was issued.

CEI requested extension of CPPR-148 to

April 15,1986.

February 6,1986

Board Notification 86-03 issued

regarding Perry earthquake.

I

February 12/13, 1986

NRC/CEI briefing of ACRS on

preliminary findings regarding the

January 31, 1986, earthquake.

l

March 10, 1986

CEI formally certified Perry 1

technical specifications.

March 14, 1986

CEI requested extension of CPPR-148 to

May 15, 1986.

!

-

_

.

March 17, 1986

ACRS report to Chairman NRC on NRC

findings and confirmatory action items

regarding the January 31, 1986,

,

earthquake.

March 18, 1986

NRC issued a low power operating

license for Perry 1.

March 20, 1986

ASLAB ordered exploratory hearings

on seismic event.

March 21, 1986

Fuel load commenced.

April 15, 1986

Full Scale Emergency Plan Exercise was

conducted.

April 18, 1986

Commission Order vacated ASLAB Order

cancelling exploratory hearings.

!

April 24, 1986

Fuel load complete.

June 6, 1986

Initial Criticality achieved.

i

i

!

r

!

!

,

39