MONTHYEARIR 05000334/20240052024-08-29029 August 2024 Updated Inspection Plan for Beaver Valley Power Station, Units 1 and 2 (Reports 05000334/2024005 and 05000412/2024005) IR 05000334/20244022024-08-22022 August 2024 Security Baseline Inspection Report 05000334/2024402 and 05000412/2024402 (Cover Letter Only) IR 05000334/20240102024-08-20020 August 2024 Comprehensive Engineering Team Inspection - Inspection Report 05000334/2024010 and 05000412/2024010 IR 05000334/20240022024-08-0505 August 2024 Integrated Inspection Report 05000334/2024002 and 05000412/2024002 IR 05000334/20245012024-07-0808 July 2024 Emergency Preparedness Biennial Exercise Inspection Report 05000334/2024501 and 05000412/2024501 IR 05000334/20244012024-06-26026 June 2024 Material Control and Accounting Program Inspection Report 05000334/2024401 and 05000412/2024401 (Cover Letter Only) ML24135A1702024-05-29029 May 2024 – Steam Generator Tube Inspection - Review of the Spring 2023 Tube Inspection Reports ML24135A2282024-05-29029 May 2024 Review of the Spring 2023 Outage Generic Letter 95-05 Voltage-Based Alternate Repair Criteria and Steam Generator F Star Reports IR 05000334/20240012024-05-0808 May 2024 Integrated Inspection Report 05000334/2024001 and 05000412/2024001 IR 05000334/20230062024-02-28028 February 2024 Annual Assessment Letter for Beaver Valley Power Station, Units 1 and 2 (Reports 05000334/2023006 and 05000412/2023006) IR 05000334/20230042024-02-12012 February 2024 Integrated Inspection Report 05000334/2023004 and 05000412/2023004 IR 05000334/20230112023-12-0404 December 2023 Age-Related Degradation Inspection Report 05000334/2023011 and 05000412/2023011 IR 05000334/20233012023-11-27027 November 2023 Initial Operator Licensing Examination Report 05000334/2023301 IR 05000334/20230032023-11-0606 November 2023 Integrated Inspection Report 05000334/2023003 and 05000412/2023003 IR 05000334/20234022023-09-29029 September 2023 Security Baseline Inspection Report 05000334/2023402 and 05000412/2023402 (Cover Letter Only) IR 05000334/20234012023-09-21021 September 2023 Cybersecurity Inspection Report 05000334/2023401 and 05000412/2023401 (Cover Letter Only) ML23243A9272023-09-19019 September 2023 Review of the Fall 2022 Steam Generator Tube Inspection Report IR 05000334/20230052023-08-31031 August 2023 Updated Inspection Plan for Beaver Valley Power Station Units 1 and 2 (Report 05000334/2023005 and 05000412/2023005) IR 05000334/20230022023-08-0909 August 2023 Integrated Inspection Report 05000334/2023002 and 05000412/2023002 ML23157A1072023-06-0707 June 2023 Request for Information and Notification of Conduct of IP 71111.21.N.04, Age-Related Degradation, Reference Inspection Report 05000334/2023011 and 05000412/2023011 IR 05000334/20230012023-05-0808 May 2023 Integrated Inspection Report 05000334/2023001 and 05000412/2023001 L-23-058, 180-Day Steam Generator Tube Inspection Report2023-03-27027 March 2023 180-Day Steam Generator Tube Inspection Report IR 05000334/20230102023-03-0808 March 2023 Biennial Problem Identification and Resolution Inspection Report 05000334/2023010 05000412/2023010 IR 05000334/20220062023-03-0101 March 2023 Annual Assessment Letter for Beaver Valley Power Station, Units 1 and 2 (Reports 05000334/2022006 and 05000412/2022006) IR 05000334/20220042023-02-0909 February 2023 Integrated Inspection Report 05000334/2022004 and 05000412/2022004 IR 05000334/20224012023-01-0909 January 2023 Security Baseline Inspection Report 05000334/2022401 and 05000412/2022401 (Cover Letter Only) ML22314A2682022-12-16016 December 2022 Review of the Fall 2021 2R22 Steam Generator Tube Inspection 180 Day Report IR 05000334/20220032022-11-10010 November 2022 Integrated Inspection Report 05000334/2022003 and 05000412/2022003 and Independent Spent Fuel Storage Installation Inspection Report 07201043/2022001 IR 05000334/20220052022-08-31031 August 2022 Updated Inspection Plan for Beaver Valley Power Station, Units 1 and 2 (Report 05000334/2022005 and 05000412/2022005) IR 05000334/20220022022-08-12012 August 2022 Integrated Inspection Report 05000334/2022002 and 05000412/2022002 IR 05000334/20224022022-08-12012 August 2022 Cyber Security Problem Identification and Resolution Inspection Report 05000334/2022402 and 05000412/2022402 (Cover Letter Only) IR 05000334/20225012022-06-29029 June 2022 Emergency Preparedness Biennial Exercise Inspection Report 05000334/2022501 and 05000412/2022501 IR 05000334/20220112022-06-29029 June 2022 Temporary Instruction 2515/194 Inspection Report 05000334/2022011 and 05000412/2022011 IR 05000412/20223012022-06-14014 June 2022 Initial Operator Licensing Examination Report 05000412/2022301 IR 05000334/20220102022-05-12012 May 2022 Design Basis Assurance Inspection (Programs) Inspection Report 05000334/2022010 and 05000412/2022010 IR 05000334/20224202022-05-11011 May 2022 Security Baseline Inspection Report 05000334/2022420 and 05000412/2022420 - Cover Letter IR 05000334/20220012022-05-10010 May 2022 Integrated Inspection Report 05000334/2022001 and 05000412/2022001 IR 05000334/20210062022-03-0202 March 2022 Annual Assessment Letter for Beaver Valley Power Station, Units 1 and 2 (Reports 05000334/2021006 and 05000412/2021006) IR 05000334/20210042022-02-14014 February 2022 Integrated Inspection Report 05000334/2021004 and 05000412/2021004 L-22-054, Steam Generator Inspection Report- Fall 2021 Refueling Outage2022-02-10010 February 2022 Steam Generator Inspection Report- Fall 2021 Refueling Outage IR 05000334/20210032021-11-0909 November 2021 Integrated Inspection Report 05000334/2021003 and 05000412/2021003 IR 05000334/20210112021-10-19019 October 2021 Temporary Instruction 2515/194 Inspection Report 05000334/2021011 and 05000412/2021011 IR 05000334/20210102021-09-29029 September 2021 Triennial Fire Protection Inspection Report 05000334/2021010 and 05000412/2021010 IR 05000334/20210052021-09-0101 September 2021 Updated Inspection Plan for the Beaver Valley Power Station, Units 1 and 2 (Report 05000334/2021005 and 05000412/2021005) IR 05000334/20214022021-08-18018 August 2021 Security Baseline Inspection Report 05000334/2021402 and 05000412/2021402 IR 05000334/20214012021-08-12012 August 2021 Material Control and Accounting Program Inspection Report 05000334/2021401 and 05000412/2021401 (Cover Letter Only) IR 05000334/20210022021-08-11011 August 2021 Integrated Inspection Report 05000334/2021002 and 05000412/2021002 IR 05000334/20214032021-05-13013 May 2021 Cyber Security Problem Identification and Resolution Inspection Report 05000334/2021403 and 05000412/2021403 (Cover Letter Only) IR 05000334/20210012021-05-13013 May 2021 Integrated Inspection Report 05000334/2021001 and 05000412/2021001 ML21097A1142021-04-19019 April 2021 Review of Steam Generator Tube Inspection Report for the Spring 2020 Refueling Outage 2024-08-05
[Table view] Category:Letter
MONTHYEARIR 05000334/20240052024-08-29029 August 2024 Updated Inspection Plan for Beaver Valley Power Station, Units 1 and 2 (Reports 05000334/2024005 and 05000412/2024005) L-24-188, Submittal of Quality Assurance Program Manual, Revision 302024-08-27027 August 2024 Submittal of Quality Assurance Program Manual, Revision 30 IR 05000334/20244022024-08-22022 August 2024 Security Baseline Inspection Report 05000334/2024402 and 05000412/2024402 (Cover Letter Only) IR 05000334/20240102024-08-20020 August 2024 Comprehensive Engineering Team Inspection - Inspection Report 05000334/2024010 and 05000412/2024010 IR 05000334/20240022024-08-0505 August 2024 Integrated Inspection Report 05000334/2024002 and 05000412/2024002 ML24208A0462024-07-26026 July 2024 NRC Office of Investigations Case No. 1-2023-005 L-24-182, Discharge Monitoring Report (NPDES) Permit No. PA00256152024-07-23023 July 2024 Discharge Monitoring Report (NPDES) Permit No. PA0025615 L-24-161, Discharge Monitoring Report (NPDES) Permit No. PA00256152024-07-19019 July 2024 Discharge Monitoring Report (NPDES) Permit No. PA0025615 L-24-014, Annual 10 CFR 50.46 Report of Changes to or Errors in Emergency Core Cooling Svstem Evaluation Models2024-07-16016 July 2024 Annual 10 CFR 50.46 Report of Changes to or Errors in Emergency Core Cooling Svstem Evaluation Models ML24193A2912024-07-16016 July 2024 Revision to Reactor Vessel Surveillance Capsule Withdrawal Schedule IR 05000334/20245012024-07-0808 July 2024 Emergency Preparedness Biennial Exercise Inspection Report 05000334/2024501 and 05000412/2024501 L-24-164, BV-2, Post Accident Monitor Report2024-06-27027 June 2024 BV-2, Post Accident Monitor Report IR 05000334/20244012024-06-26026 June 2024 Material Control and Accounting Program Inspection Report 05000334/2024401 and 05000412/2024401 (Cover Letter Only) L-24-094, Reactor Vessel Surveillance Capsule Withdrawal Schedule2024-06-24024 June 2024 Reactor Vessel Surveillance Capsule Withdrawal Schedule L-24-152, Response to NRC Regulatory Issue Summary 2024-01 Preparation and Scheduling of Operator Licensing Examinations2024-06-17017 June 2024 Response to NRC Regulatory Issue Summary 2024-01 Preparation and Scheduling of Operator Licensing Examinations ML24135A1702024-05-29029 May 2024 – Steam Generator Tube Inspection - Review of the Spring 2023 Tube Inspection Reports ML24135A2282024-05-29029 May 2024 Review of the Spring 2023 Outage Generic Letter 95-05 Voltage-Based Alternate Repair Criteria and Steam Generator F Star Reports L-24-021, Cycle 30 Core Operating Limits Report2024-05-23023 May 2024 Cycle 30 Core Operating Limits Report L-24-121, Discharge Monitoring Report (NPDES) Permit No. PA00256152024-05-23023 May 2024 Discharge Monitoring Report (NPDES) Permit No. PA0025615 ML24141A1052024-05-20020 May 2024 Senior Reactor and Reactor Operator Initial License Examinations L-24-107, CFR 50.55a Request 1-TYP-5-RRP-l, for Alternative Method of Nondestructive Examination for River Water Outlet Piping Weld Repair2024-05-13013 May 2024 CFR 50.55a Request 1-TYP-5-RRP-l, for Alternative Method of Nondestructive Examination for River Water Outlet Piping Weld Repair IR 05000334/20240012024-05-0808 May 2024 Integrated Inspection Report 05000334/2024001 and 05000412/2024001 L-23-269, Application to Revise Technical Specifications to Adopt TSTF-569, Revision of Response Time Testing Definitions2024-05-0707 May 2024 Application to Revise Technical Specifications to Adopt TSTF-569, Revision of Response Time Testing Definitions L-24-054, Submittal of 2023 Annual Radioactive Effluent Release Report 2023 Annual Radiological Environmental Operating Report and 2023 Annual Environmental Operating Report (Non-Radiological)2024-04-29029 April 2024 Submittal of 2023 Annual Radioactive Effluent Release Report 2023 Annual Radiological Environmental Operating Report and 2023 Annual Environmental Operating Report (Non-Radiological) L-24-089, Emergency Preparedness Plan2024-04-23023 April 2024 Emergency Preparedness Plan L-24-088, Discharge Monitoring Report (NPDES) Permit No. PA0025615 for March 20242024-04-22022 April 2024 Discharge Monitoring Report (NPDES) Permit No. PA0025615 for March 2024 ML24101A2752024-04-10010 April 2024 Response to Request for Additional Information Regarding Spring 2023 180-Day Steam Generator Tube Inspection Report L-24-082, Withdrawal of Exemption Request2024-04-0303 April 2024 Withdrawal of Exemption Request L-24-013, Annual Notification of Property Insurance Coverage2024-03-26026 March 2024 Annual Notification of Property Insurance Coverage L-24-064, Submittal of Discharge Monitoring Report (NPDES) Permit No. PA00256152024-03-13013 March 2024 Submittal of Discharge Monitoring Report (NPDES) Permit No. PA0025615 ML24044A0662024-03-0404 March 2024 Exemption from Select Requirements of 10 CFR Part 73 (EPID L-2023-LLE-0083 (Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting ML24057A0752024-03-0101 March 2024 the Associated Independent Spent Fuel Storage Installations IR 05000334/20230062024-02-28028 February 2024 Annual Assessment Letter for Beaver Valley Power Station, Units 1 and 2 (Reports 05000334/2023006 and 05000412/2023006) CP-202300502, Notice of Planned Closing of Transaction and Provision of Documents to Satisfy Order Conditions2024-02-23023 February 2024 Notice of Planned Closing of Transaction and Provision of Documents to Satisfy Order Conditions L-24-050, Retrospective Premium Guarantee2024-02-22022 February 2024 Retrospective Premium Guarantee IR 05000334/20230042024-02-12012 February 2024 Integrated Inspection Report 05000334/2023004 and 05000412/2023004 ML24025A0922024-01-25025 January 2024 Requalification Program Inspection L-23-267, Submittal of Discharge Monitoring Report (Npdes), Permit No. PA00256152023-12-18018 December 2023 Submittal of Discharge Monitoring Report (Npdes), Permit No. PA0025615 IR 05000334/20230112023-12-0404 December 2023 Age-Related Degradation Inspection Report 05000334/2023011 and 05000412/2023011 L-23-229, Request for Additional Information Regarding the Spring 2023 Generic Letter 95-05 Voltage-Based Alternate Repair Criteria and Steam Generator F-Star Reports2023-11-29029 November 2023 Request for Additional Information Regarding the Spring 2023 Generic Letter 95-05 Voltage-Based Alternate Repair Criteria and Steam Generator F-Star Reports IR 05000334/20233012023-11-27027 November 2023 Initial Operator Licensing Examination Report 05000334/2023301 L-23-247, Discharge Monitoring Report (NPDES) Permit No. PA00256152023-11-17017 November 2023 Discharge Monitoring Report (NPDES) Permit No. PA0025615 IR 05000334/20230032023-11-0606 November 2023 Integrated Inspection Report 05000334/2023003 and 05000412/2023003 L-23-227, Discharge Monitoring Report (NPDES) Permit No. PA0025615 for Third Quarter 20232023-10-20020 October 2023 Discharge Monitoring Report (NPDES) Permit No. PA0025615 for Third Quarter 2023 ML23279A0612023-10-0505 October 2023 Paragon Energy Solutions LLC, Part 21 Final Report Re Potential Defect with Eaton Jd and Hjd Series Molded Case Circuit Breakers (Mccbs) ML23198A3592023-10-0202 October 2023 Issuance of Amendment Nos. 322 and 212 Analytical Methodology to the Core Operating Limits Report for a Full Spectrum Loss of Coolant Accident (EPID L-2022-LLA-0129) - Nonproprietary IR 05000334/20234022023-09-29029 September 2023 Security Baseline Inspection Report 05000334/2023402 and 05000412/2023402 (Cover Letter Only) ML23237B4222023-09-28028 September 2023 Energy Harbor Nuclear Corp. - Vistra Operations Company LLC - Letter Regarding Order Approving Transfer of Licenses and Draft Conforming License Amendments ML23269A1242023-09-27027 September 2023 Request for Withholding Information from Public Disclosure IR 05000334/20234012023-09-21021 September 2023 Cybersecurity Inspection Report 05000334/2023401 and 05000412/2023401 (Cover Letter Only) 2024-08-05
[Table view] |
Text
uly 20, 2016
SUBJECT:
BEAVER VALLEY POWER STATION - EVALUATED EMERGENCY PREPAREDNESS EXERCISE - INSPECTION REPORT 05000334/2016502 AND 05000412/2016502
Dear Mr. Richey:
On June 16, 2016, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection of the June 14, 2016 evaluated emergency preparedness exercise at the Beaver Valley Power Station, Units 1 and 2. The enclosed inspection report documents the inspection results, which were discussed on June 16, 2016, with you and other members of your staff.
The inspection examined activities conducted under your licenses as they relate to safety and compliance with the Commissions rules and regulations and with the conditions of your licenses. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel.
The NRC inspectors did not identify any findings or violations of more than minor significance.
In accordance with Title 10 of the Code of Federal Regulations (10 CFR) 2.390, Public Inspections, Exemptions, Requests for Withholding, of the NRCs Rules of Practice, a copy of this letter, its enclosure, and your response, (if any), will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of the NRCs document system, Agencywide Documents Access and Management System (ADAMS). ADAMS is accessible from the NRCs Website at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
Sincerely,
/RA/
Raymond McKinley, Chief Plant Support Branch 1 Division of Reactor Safety Docket No. 50-334 and 50-412 License No. DPR-66 and NPF-73
Enclosure:
NRC Inspection Report Nos. 05000334/2016502 and 05000412/2016502 w/Attachment:
Supplementary Information
REGION I==
Docket Nos. 50-334 and 50-412 License Nos. DPR-66 and NPF-73 Report Nos. 05000334/2016502 and 05000412/2016502 Licensee: FirstEnergy Nuclear Operating Company (FENOC)
Facility: Beaver Valley Power Station, Units 1 and 2 Location: Shippingport, PA 15077 Dates: June 13-17, 2016 Inspectors: S. Barr, Senior Emergency Preparedness Inspector, Division of Reactor Safety (DRS), Region I (Lead)
J. DeBoer, Emergency Preparedness Inspector, DRS E. Burket, Reactor Inspector, DRS T. Hedigan, Operations Inspector, DRS C. Hobbs, Reactor Inspector, DRS Approved By: Raymond McKinley, Chief Plant Support Branch 1 Division of Reactor Safety Enclosure
SUMMARY
IR 05000334/2016502 and 05000412/2016502; 06/13/2016 - 06/17/2016; Beaver Valley Power
Station, Units 1 and 2; Exercise Evaluation - Scenario Review - Performance Indicator Verification.
This report covers an announced inspection conducted by five Region I-based inspectors.
No findings were identified during the inspection. The NRCs program for overseeing the safe operation of commercial nuclear power reactors is described in NUREG-1649, Reactor Oversight Process, Revision 5.
Cornerstone: Emergency Preparedness
No findings were identified.
REPORT DETAILS
REACTOR SAFETY
1EP1 Exercise Evaluation (71114.01 - 1 Sample)
a. Inspection Scope
On June 14, 2016, FirstEnergy Nuclear Operating Company (FENOC) conducted a biennial Beaver Valley emergency preparedness exercise. The inspectors evaluated the adequacy of the licensees conduct of the exercise, the performance of the Beaver Valley emergency response organization (ERO) to respond to the simulated emergency, and FENOCs capability to assess their own staff performance via a formal critique process, as required by Title 10 of the Code of Federal Regulations (CFR) 50.47(b) (14).
This overall exercise inspection activity represented the completion of one sample on a biennial cycle.
The exercise evaluation consisted of the following review and assessment:
- The adequacy of FENOCs performance in the biennial full-participation exercise regarding the implementation of the risk-significant planning standards (RSPS)described in 10 CFR 50.47(b)(4), (5), (9), and (10), which are: emergency classification; offsite notification; radiological assessment; and protective action recommendations, respectively.
- The overall adequacy of FENOCs Beaver Valley emergency response facilities with regard to NUREG-0696, Functional Criteria for Emergency Response Facilities, and Emergency Plan commitments. The facilities assessed were the Control Room Simulator, Technical Support Center (TSC), and Emergency Operations Facility (EOF).
- A review of other performance areas, such as: the licensee emergency response organizations (EROs) recognition of abnormal plant conditions; command and control; intra- and inter-facility communications; prioritization of mitigating activities; utilization of repair and field monitoring teams; interface with offsite agencies; staffing and procedure adequacy; and the overall implementation of the emergency plan and its implementing procedures.
- A review of past performance issues from the last NRC Beaver Valley exercise inspection report and FENOCs EP drill reports, to determine the effectiveness of licensee corrective actions as demonstrated during the June 14, 2016, exercise and to ensure compliance with 10 CFR 50.47(b)(14).
- The licensees post-exercise critiques, to evaluate FENOCs self-assessment of its ERO performance during the June 14, 2016, exercise and to ensure compliance with 10 CFR Part 50, Appendix E, Section IV.F.2.g.
The inspectors reviewed the documents listed in the attachment to this report.
b. Findings
No findings were identified.
1EP8 Exercise Evaluation - Scenario Review (71114.08 - 1 Sample)
a. Inspection Scope
Prior to the June 14, 2016, emergency preparedness exercise, the NRC inspectors conducted an in-office review of the exercise objectives and scenario, FENOC had submitted to the U.S. Nuclear Regulatory Commission (NRC), to determine if the exercise would test major elements of the Beaver Valley Emergency Plan as required by Title 10 of the Code of Federal Regulations (10 CFR) 50.47(b)(14). This overall exercise inspection activity represented the completion of one sample on a biennial cycle.
The inspectors reviewed the documents listed in the attachment to this report.
b. Findings
No findings were identified.
OTHER ACTIVITIES (OA)
4OA1 Performance Indicator (PI) Verification (71151 - 3 Samples)
a. Inspection Scope
The inspectors reviewed data for the Beaver Valley EP PIs, which are:
- (1) Drill and Exercise Performance (DEP);
- (2) ERO Drill Participation; and,
- (3) Alert and Notification System (ANS) Reliability. The last NRC EP inspection at Beaver Valley was conducted in the second calendar quarter of 2015, so the inspectors reviewed supporting documentation from EP drills, training records, and equipment tests from the second calendar quarter of 2015 through the first quarter of 2016, to verify the accuracy of the reported PI data. The review of these PIs was conducted in accordance with NRC Inspection Procedure 71151, using the acceptance criteria documented in NEI 99-02, Regulatory Assessment Performance Indicator Guidelines, Revision 6.
This inspection activity represented the completion of three samples.
b. Findings
No findings were identified.
4OA6 Meetings, including Exit
On June 16, 2016, the inspectors presented the results of this inspection to Mr. M. Richey, Beaver Valley Site Vice President, and other members of the FENOC staff. No proprietary information was provided to the inspectors during this inspection.
ATTACHMENT
SUPPLEMENTAL INFORMATION
KEY POINTS OF CONTACT
Licensee Personnel
- M. Richey, Site Vice President
- S. Sawtschenko, Emergency Preparedness Manager
LIST OF ITEMS OPENED, CLOSED, AND DISCUSSED
None.
LIST OF DOCUMENTS REVIEWED