March 24, 2020

SUBJECT:

COLUMBIA GENERATING STATION - NRC TEMPORARY INSTRUCTION 2515/193, IMPLEMENTATION OF RELIABLE HARDENED CONTAINMENT VENTS - NRC INSPECTION REPORT 05000397/2020010

Dear Mr. Sawatzke:

On March 12, 2020, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at Columbia Generating Station and discussed the results of this inspection with Mr. H. G. Hettel, Chief Nuclear Officer, and other members of your staff. The results of this inspection are documented in the enclosed report.

No findings or violations of more than minor significance were identified during this inspection.

This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations 2.390, Public Inspections, Exemptions, Requests for Withholding.

Sincerely,

/RA/

Jeffrey E. Josey, Chief Reactor Projects Branch A Division of Reactor Projects Docket No. 05000397 License No. NPF-21

Enclosure:

As stated

Inspection Report

Docket Number: 05000397 License Number: NPF-21 Report Number: 05000397/2020010 Enterprise Identifier: I-2020-010-0048 Licensee: Energy Northwest Facility: Columbia Generating Station Location: Richland, WA Inspection Dates: March 9, 2020, to March 12, 2020 Inspectors: R. Alexander, Senior Emergency Preparedness Inspector G. Kolcum, Senior Resident Inspector Approved By: Jeffrey E. Josey, Chief Reactor Projects Branch A Division of Reactor Projects Enclosure

SUMMARY

The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees performance by conducting an NRC inspection at Columbia Generating Station, in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information.

List of Findings and Violations

No findings or violations of more than minor significance were identified.

Additional Tracking Items

None.

INSPECTION SCOPES

Inspections were conducted using the appropriate portions of the inspection procedures (IPs) in effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with their attached revision histories are located on the public website at http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html.

Samples were declared complete when the IP requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter (IMC) 2515, Light-Water Reactor Inspection Program - Operations Phase. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess licensee performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards.

OTHER ACTIVITIES

- TEMPORARY INSTRUCTIONS, INFREQUENT AND ABNORMAL 2515/193 - Inspection of the Implementation of EA-13-109: Order Modifying Licenses with Regard to Reliable Hardened Containment Vents Capable of Operation under Severe Accident Conditions Inspection of the Implementation of EA-13-109: Order Modifying Licenses with Regard to Reliable Hardened Containment Vents Capable of Operation under Severe Accident Conditions (1 Sample)

(1) The inspectors evaluated licensee implementation of the appropriate elements of the reliable hardened containment wetwell vent as described in the plant specific submittal (ADAMS Accession No. ML19232A448) and the associated NRC safety evaluation (ADAMS Accession No. ML19350B579). Specifically, the inspectors evaluated licensee implementation of hardened containment vent system (HCVS)functional requirements, design features, maintenance and testing, quality standards, and programmatic requirements as described in Appendix A of TI 2515/193.

Further, the inspectors evaluated licensee implementation of the appropriate elements of the reliable wetwell venting strategy as described in the plant specific submittal (ADAMS Accession No. ML19232A448) and the associated NRC safety evaluation (ADAMS Accession No. ML19350B579). Specifically, the inspectors evaluated licensee implementation of the severe accident water addition and management (SAWA/SAWM) functional requirements, installed instrumentation, maintenance and testing, and programmatic requirements as described in Appendix B of TI 2515/193.

INSPECTION RESULTS

No findings were identified.

EXIT MEETINGS AND DEBRIEFS

The inspectors verified no proprietary information was retained or documented in this report.

  • On March 12, 2020, the inspectors presented the NRC inspection results to Mr. H. G. Hettel, Chief Nuclear Officer, and other members of the licensee staff.

DOCUMENTS REVIEWED

Inspection Type Designation Description or Title Revision or

Procedure Date

2515/193 Calculations ME-02-14-02, Suppression Pool Freeboard Available During Extended 003

Appendix H Loss of AC Power (ELAP)

Corrective Action Action Requests 350650, 366752, 380025, 384464, 38210, 390256, 390257,

Documents (ARs) 395869, 397967, 403046, 403048

Corrective Action Action Requests 404947, 404961, 404962, 405021

Documents (ARs)

Resulting from

Inspection

Miscellaneous ER000260 Equipment Operator Requalification: Primary Containment 09/12/2019

(including HCVS)

ER000719 Equipment Operator Requalification: Hardened Containment 06/12/2017

Vent (HCV)

ER000759 Equipment Operator Requalification: Standards Updates 03/14/2019

(including SAWA/SAWM)

FLEX-01 FLEX Program Document 2&3

IC000725 JITT/Maintenance: Hardened Containment Vent (HCV) 12/22/2015

System

LDCN-15-033 EC 13094, Addition of Wetwell Hardened Containment Vent 000

(HCV) System

LDCN-17-005 Revise LCS Table 1.6.1.3-1, Primary Containment Isolation 000

Valves, to include new valves HCV-V-1 and HCV-V-2

LDCN-18-027 New LCS RFO 1.11.1 000

LR002303 LORQ: Cycle 16-1 Updates (including HCVS) 01/07/2016

LR002374 LORQ: Hardened Containment Vent (HCV) System 05/23/2017

LR002455 LORQ: Cycle 19-2 Updates (including SAWA/SAWM) 03/14/2019

Procedures ABN-FSG-002 Water Makeup Strategies for RPV, SFP, DW, WW During an 008, 009,

Extended Loss of AC Power or other Beyond Design Basis 010, and

Event 010.001

PPM 1.5.18 Managing B.5.b and FLEX Equipment Unavailability 009

PPM 5.1.1 RPV Control EOP 022

PPM 5.1.8 Alternate Level/Pressure Control EOP 000

PPM 5.2.1 Primary Containment Control EOP 028

Inspection Type Designation Description or Title Revision or

Procedure Date

PPM 5.5.14 Emergency Wetwell Venting 010

PPM 5.6.1 SBO/ELAP 030.001

PPM SAG1 RPV Control SAG 006

PPM SAG1-TAB- Core Debris Has Breached the RPV 003

B

SOP-FLEX- FLEX Equipment Refueling 005

EQUIPMENT-

REFUEL

SOP-HHGP- High Head Godwin Pump Start - Quick Card 001

START-QC

Self-Assessments XC-19007-N-R- Order EA-13-109 Compliance Assessment 01/09/2020

001

Work Orders WO 02082834-01 AOV Valve Testing, HCV-V-1 04/24/2017

WO 02082834-02 AOV Valve Testing, HCV-V-2 04/24/2017

WO 02082836-04 Valve Stroke Verification for HCV-V-1 and HCV-V-2 05/19/2017

WO 02082836-12 Final Walkdown Fukushima EC 13094 (HCV) 06/03/2017

WO 02083371-12 HCV - Calibrate/Test Radiation Detector 05/04/2017

WO 02083371-12 HCV - Calibrate/Test Temperature Indicator 05/08/2017

WO 02083371-24 Program and Test New Battery Charger E-C0-3 05/12/2017

WO 02118301-01 TSP-HCV/X58-C801: LLRT of HCV-V-1 and HCV-V-2 05/29/2019

WO 02128517-01 HCV-MV/I-1 Replacement 06/28/2018

WO 02136310-01 FLEX-P-1, Flow and Pressure Verification Test OSP-FLEX- 05/02/2019

A101

WO 02141336-01 HCVS NITROGEN BOTTLES, Verify pressure in Nitrogen 12/23/2019

Bottles

WO 02148863-01 FUNCTION TEST-HCVRDMN: Function Test for HCV Rad 11/02/2019

Monitor

WR 29135683 Perform LLRT on HCV-V-1 and 2 (post installation) 06/07/2017

WR 29142524 HCV-RI-1 reading E1 (10) R/hr, midscale 05/15/2018

5