MONTHYEARML24278A2832024-11-0707 November 2024 Letter to E. Carr Environmental Impact Statement Scoping Summary Report for Virgil C. Summer Nuclear Station Unit 1 ML24305A1302024-10-31031 October 2024 Submittal of 30 Day Report Per 10 CFR 26.719(c) Blind Performance Testing ML24308A0052024-10-28028 October 2024 10-28-24 NRC V.C. Summer Nuclear Station SLR Cherokee Nation Letter to USNRC ML24308A0062024-10-25025 October 2024 Subsequent License Renewal Application Area of Potential Effect (Ape) Clarification Fairfield County, South Carolina SHPO Project No. 22-EJ0147 ML24302A1442024-10-24024 October 2024 Update to Subsequent License Renewal Application (SLRA) Supplement 4 and Requested Information Formation in Response to Limited Aging Management Audit ML24255A3152024-10-22022 October 2024 Relief Request RR-5-V2 Regarding Pressure Isolation Valves ML24256A2322024-10-22022 October 2024 Relief Request RR-5-P1 Charging/Safety Injection Pumps ML24250A0782024-10-22022 October 2024 Relief Request RR-5-V1 Regarding Service Water Return Header Check Valves 05000395/LER-2024-002, Loss of Control Room Emergency Filtration System2024-10-15015 October 2024 Loss of Control Room Emergency Filtration System ML24290A1052024-10-0707 October 2024 Core Operating Limits Report VCSNS Unit 1 Cycle 29, Revision 0 IR 05000395/20244042024-09-26026 September 2024 Cyber Security Inspection Report 05000395-2024404 - Public ML24274A1942024-09-26026 September 2024 (Vcsns), Unit 1 Subsequent License Renewal Application (SLRA) First 10 CFR 54.21(b) Annual Amendment ML24267A0642024-09-23023 September 2024 Clarification Regarding Area of Potential Effect for the Subsequent Operating License Renewal for Virgil C. Summer Nuclear Station Fairfield County, South Carolina (SHPO Project Number: 22-EJ0147) (Docket Number: 50-395) ML24267A0592024-09-23023 September 2024 Clarification Regarding Area of Potential Effect for the Subsequent Operating License Renewal for Virgil C. Summer Nuclear Station Fairfield County, South Carolina (SHPO Project Number: 22-EJ0147) (Docket Number: 50-395) ML24221A2112024-09-23023 September 2024 Clarification Regarding Area of Potential Effect for the Subsequent Operating License Renewal for Virgil C. Summer Nuclear Station Fairfield County, South Carolina (SHPO Project Number: 22-EJ0147) (Docket Number: 50-395) ML24267A0552024-09-23023 September 2024 Clarification Regarding Area of Potential Effect for the Subsequent Operating License Renewal for Virgil C. Summer Nuclear Station Fairfield County, South Carolina (SHPO Project Number: 22-EJ0147) (Docket Number: 50-395) ML24267A0542024-09-23023 September 2024 Clarification Regarding Area of Potential Effect for the Subsequent Operating License Renewal for Virgil C. Summer Nuclear Station Fairfield County, South Carolina (SHPO Project Number: 22-EJ0147) (Docket Number: 50-395) IR 05000395/20244022024-09-10010 September 2024 Security Baseline Inspection Report 05000395/2024402 IR 05000395/20240052024-08-22022 August 2024 Updated Inspection Plan for Virgil C. Summer Nuclear Station - Report 05000395/2024005 ML24190A4012024-08-19019 August 2024 Request for Withholding Information from Public Disclosure Regarding the Subsequent License Renewal Application - Dominion Energy Letter Dated May 30, 2024 IR 05000395/20240022024-08-12012 August 2024 Integrated Inspection Report 05000395/2024002 ML24180A0062024-08-0505 August 2024 Issuance of Amendment No. 227 to Modify Technical Specification 3.8.3.1 to Increase Completion Time for 120-Volt A.C. Vital Busses ML24218A3002024-08-0101 August 2024 Environmental Review Response to NRC Requests for Additional Information and Response to NRC Requests for Confirmation of Information Set 1 ML24158A3882024-07-31031 July 2024 Issuance of Amendment No. 226 to Change Emergency Plan Staff Augmentation Times and Relocate Emergency Operations Facility ML24162A3292024-07-0505 July 2024 Letter to E Carr - V.C. Summer Unit 1 - Summary of the May 2024 Audit Regarding the Environmental Review of the Subsequent License Renewal Application ML24177A1382024-06-25025 June 2024 Aging Management Audit Report- VC Summer, Unit 1 - Subsequent License Renewal Application ML24178A1192024-06-25025 June 2024 Update to License Amendment Request- Inverter Allowed Outage Time (AOT) Extension ML24185A1902024-06-25025 June 2024 Submittal of Updated Final Safety Analysis Report, Revision 24 ML24178A2422024-06-25025 June 2024 2023 Annual Report of Emergency Core Cooling System (ECCS) Model, Changes Pursuant to the Requirements of 10 CFR 50.46 ML24177A2792024-06-20020 June 2024 Preparation and Scheduling of Operator Licensing Examinations ML24171A0152024-06-17017 June 2024 Update to Subsequent License Renewal Application (SLRA) Response to NRC Request for Additional Information Set 2 Safety Review ML24157A3352024-06-0606 June 2024 – Notification of an NRC Cybersecurity Baseline Inspection (NRC Inspection Report 05000395-2024404 and Request for Information ML24155A2042024-05-31031 May 2024 Proposed Alternative Request RR-24-123, Containment Unbonded Post-Tensioning System Inservice Inspection Requirements ML24155A1462024-05-30030 May 2024 Update to Subsequent License Renewal Application (SLRA) -Response to NRC Request for Additional Information Set 1 Response to NRC Request for Confirmation of Information Set 1 and Supplement 3 ML24143A1792024-05-22022 May 2024 Special Report 2024-001-01 for Virgil C. Summer Nuclear Station (Vcsns), Unit 1, Waste Gas System Inoperability ML24141A2822024-05-20020 May 2024 (Vcsns), Unit 1 - License Amendment Request - Emergency Response Organization (ERO) Augmentation Time Change, Emergency Operations Facility Relocation and Other Emergency Plan Changes IR 05000395/20240012024-05-10010 May 2024 Integrated Inspection Report 05000395/2024001 ML24129A2002024-05-0606 May 2024 Update to Subsequent License Renewal Application, Supplement 2 IR 05000395/20240402024-05-0101 May 2024 95001 Supplemental Inspection Report 05000395/2024040 and Follow-Up Assessment Letter ML24121A1002024-04-29029 April 2024 Response to Request for Additional Information Regarding Alternative Request RR-5-V2 ML24120A2072024-04-29029 April 2024 Submittal of Annual Radiological Environmental Operating Report ML24116A2052024-04-23023 April 2024 Annual Radioactive Effluent Release Report ML24109A1792024-04-19019 April 2024 Aging Management Audit Plan Regarding the Subsequent License Renewal Application Review ML24108A0392024-04-18018 April 2024 Letter to E Carr-V.C. Summer Unit 1- Regulatory Audit Regarding the Environmental Review of the Subsequent License Renewal Application 05000395/LER-2024-001, (Vcsns), Unit 1, Automatic Actuation of B Emergency Diesel Generator2024-04-17017 April 2024 (Vcsns), Unit 1, Automatic Actuation of B Emergency Diesel Generator ML24108A0672024-04-17017 April 2024 Submittal of Summary for Condition of the Service Water Intake Structure Provided in Accordance with License Condition 2.C.5.d ML24100A7312024-04-0909 April 2024 Personnel Exposure and Monitoring Annual Report ML24095A2072024-04-0101 April 2024 Update to Subsequent License Renewal Application (SLRA) Supplement 1 ML24087A2182024-03-26026 March 2024 (Vcsns), Unit 1 - License Amendment Request - Emergency Response Organization (ERO) Augmentation Time Change, Emergency Operations Facility Relocation and Other Emergency Plan Changes - Response to Request. ML24087A2262024-03-26026 March 2024 License Amendment Request - Inverter Allowed Outage Time Extension Response to Request for Additional Information 2024-09-26
[Table view] |
Text
UNITED STATES NUCLEAR REGULATORY COMMISSION
REGION II
245 PEACHTREE CENTER AVENUE NE, SUITE 1200 ATLANTA, GEORGIA 30303-1257 July 24, 2018 Mr. George A. Lippard, III Vice President, Nuclear Operations South Carolina Electric & Gas Company Virgil C. Summer Nuclear Station P.O. Box 88, Mail Code 800 Jenkinsville, SC 29065 SUBJECT: V.C. SUMMER NUCLEAR STATION, UNIT 1 - NRC SECURITY INSPECTION REPORT 05000395/2018411
Dear Mr. Lippard:
On June 20, 2018, the U.S. Nuclear Regulatory Commission (NRC) completed a security inspection at your V.C. Summer Nuclear Station, Unit 1. The NRC inspectors discussed the results of the inspection with Mr. Robin R. Haselden, General Manager Organizational Development & Effectiveness, and other members of your staff. The results of this inspection are documented in the enclosed report.
The inspection examined activities conducted under your license as they relate to security and compliance with the Commissions rules and regulations and with the conditions of your license.
The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel.
The NRC inspectors documented one finding of very low security significance (Green) in this report. This finding involved a violation of NRC requirements. The NRC is treating this violation as non-cited violations (NCVs) consistent with Section 2.3.2.a of the Enforcement Policy.
If you contest this violation or the significance, you should provide a response within 30 days of the date of this inspection report, with the basis for your denial, to the U.S. Nuclear Regulatory Commission, ATTN: Document Control Desk, Washington DC 20555 0001; with copies to the Regional Administrator, Region II; the Director, Office of Enforcement, U.S. Nuclear Regulatory Commission, Washington, DC 20555 0001; and the NRC resident inspector at the V.C.
Summer Nuclear Station. OFFICAL USE ONLY One cross-cutting aspect was assigned to a finding in the area of Human Performance, Consistent Process [H.13]. If you disagree with the cross-cutting aspect assignment in this report, you should provide a response within 30 days of the date of this inspection report, with the basis for your disagreement, to the Regional Administrator, Region II; and the NRC resident inspector at the V.C. Summer Nuclear Station.This letter will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRCs Public Document Room in accordance with 10 CFR 2.390, Public Inspections, Exemptions, Requests for Withholding.
However, the enclosed report contains Security-Related Information, so the enclosed report will not be made publically available in accordance with Title 10 of the Code of Federal Regulations (10 CFR) 2.390(d)(1). If you choose to provide a response that contains Security-Related Information, please mark your entire response Security-Related Information-Withhold from public disclosure under 10 CFR 2.390 in accordance with 10 CFR 2.390(d)(1) and follow the instructions for withholding in 10 CFR 2.390(b)(1).
The NRC is waiving the affidavit requirements for your response in accordance with 10 CFR 2.390(b)(1)(ii).
Sincerely,
/RA/
Scott M. Shaeffer, Chief Engineering Branch 2 Division of Reactor Safety Docket Nos.: 50-395 License Nos.: NPF-12 Enclosure:
Inspection Report 05000395/2018411 w/Attachment: Supplemental Information OFFICAL USE ONLY cc:
Mr. Michael S. Moore, Manager Nuclear Licensing South Carolina Electric & Gas Company Virgil C. Summer Nuclear Station Bradham Blvd & Hwy 215 Post Office Box 88, Mail Code 830 Jenkinsville, SC 29065 Mr. Gregg Douglass Manager, Nuclear Protection Services Virgil C. Summer Nuclear Station Bradham Blvd & Hwy 215 Post Office Box 88, Mail Code 505 Jenkinsville, South Carolina 29065 _________________________ SUNSI REVIEW COMPLETE FORM 665 ATTACHED OFFICE RII:DRS RII:DRS RII:DRS SIGNATURE LJJ EMAIL ETC1 EMAIL SMS NAME L. JONES E/ COFFMAN S. SHAEFFER DATE 7/23/2018 7/23/2018 7/24/2018 E-MAIL COPY? YES NO YES NO YES NO YES NO YES NO YES NO YES NO