MONTHYEARIR 05000395/20244042024-09-26026 September 2024 Cyber Security Inspection Report 05000395-2024404 - Public IR 05000395/20244022024-09-10010 September 2024 Security Baseline Inspection Report 05000395/2024402 IR 05000395/20240052024-08-22022 August 2024 Updated Inspection Plan for Virgil C. Summer Nuclear Station - Report 05000395/2024005 IR 05000395/20240022024-08-12012 August 2024 Integrated Inspection Report 05000395/2024002 IR 05000395/20240012024-05-10010 May 2024 Integrated Inspection Report 05000395/2024001 IR 05000395/20240402024-05-0101 May 2024 95001 Supplemental Inspection Report 05000395/2024040 and Follow-Up Assessment Letter IR 05000395/20230062024-02-28028 February 2024 Annual Assessment Letter for Virgil C. Summer Nuclear Station - Report 05000395/2023006 IR 05000395/20244032024-02-27027 February 2024 Security Baseline Inspection Report 05000395/2024403 IR 05000395/20244012024-02-0808 February 2024 Security Baseline Inspection Report 05000395/2024401 IR 05000395/20230042024-01-31031 January 2024 Integrated Inspection Report 05000395/2023004 IR 05000395/20240112024-01-17017 January 2024 Notification of VC Summer Station Comprehensive Engineering Team Inspection - U.S. Nuclear Regulatory Commission Inspection Report 05000395/2024011 IR 05000395/20230912023-12-21021 December 2023 Final Significance Determination of a White Finding and Notice of Violation and Assessment Followup Letter–Nrc Inspection Report 05000395/2023091 IR 05000395/20234032023-11-0101 November 2023 – Material Control and Accounting Program Inspection Report 05000395/2023403 Cover IR 05000395/20230032023-11-0101 November 2023 – Integrated Inspection Report 05000395/2023003 IR 05000395/20230902023-10-0404 October 2023 NRC Inspection Report 05000395/2023090 and Preliminary Yellow Finding and Apparent Violation IR 05000395/20230112023-09-27027 September 2023 Focused Engineering Inspection Report 05000395/2023011 IR 05000395/20234012023-08-30030 August 2023 Security Baseline Inspection Report 05000395/2023401 IR 05000395/20230052023-08-23023 August 2023 Updated Inspection Plan for Virgil C. Summer Nuclear Station (Report 05000395 2023005) IR 05000395/20230022023-08-14014 August 2023 Integrated Inspection Report - Integrated Inspection Report 05000395/2023002 and Apparent Violation IR 05000395/20230102023-08-12012 August 2023 Biennial Problem Identification and Resolution Inspection Report 05000395/2023010 IR 05000395/20234412023-07-17017 July 2023 95001 Supplemental Inspection Report 05000395/2023441 and Follow Up Assessment Letter ML23131A3512023-05-12012 May 2023 Integrated Inspection Report 05000395/2023001 IR 05000395/20230012023-05-12012 May 2023 Integrated Inspection Report 05000395/2023001 IR 05000395/20230402023-05-0101 May 2023 – 95001 Supplemental Inspection Supplemental Report 05000395/2023040 and Follow-Up Assessment Letter ML23075A1702023-03-21021 March 2023 – Security Baseline Inspection Report 05000395/2023420 IR 05000395/20234202023-03-21021 March 2023 Letter - Virgil C. Summer Nuclear Station, Unit 1 – Security Baseline Inspection Report 05000395/2023420 IR 05000395/20220062023-03-0101 March 2023 Annual Assessment Letter for Virgil C. Summer Nuclear Station (Report 05000395/2022006) IR 05000395/20220042023-02-10010 February 2023 Integrated Inspection Report 05000395/2022004 IR 05000395/20234402023-02-0202 February 2023 Final Significance Determination for a Security-Related Greater than Green Finding, Notice of Violation and Assessment Follow-up Letter, NRC Security Inspection Report 05000395/2023440 ML22314A1832022-11-14014 November 2022 Triennial Inspection of Evaluation of Changes, Tests and Experiments Baseline Inspection Report 05000395/ 2022012 IR 05000395/20220032022-10-31031 October 2022 Integrated Inspection Report 05000395/2022003 IR 05000395/20220912022-10-18018 October 2022 Final Significance Determination of a White Finding and Notice of Violation and Assessment Follow-up Letter; NRC Inspection Report 05000395/2022091 IR 05000395/20220112022-09-29029 September 2022 Fire Protection Team Inspection Report 05000395/2022011, Summer Report Final IR 05000395/20220052022-08-26026 August 2022 Updated Inspection Plan for Virgil C. Summer - Report 05000395/2022005 ML22216A1202022-08-0404 August 2022 IR2022002 Summer for Workflow IR 05000395/20220902022-07-14014 July 2022 NRC Inspection Report 05000395/2022090 and Preliminary White Finding and Apparent Violation IR 05000395/20220012022-05-12012 May 2022 Integrated Inspection Report 05000395/2022001 and Apparent Violation IR 05000395/20224012022-03-16016 March 2022 V.C. Summer Nuclear Station - Information Request for the Cyber-Security Baseline Inspection, Notification to Perform Inspection 05000395/2022401 IR 05000395/20220102022-03-10010 March 2022 NRC Inspection Report 05000395 2022010 IR 05000395/20210062022-03-0202 March 2022 Annual Assessment Letter for Virgil C. Summer Unit 1 (Report No 05000395/2021006) IR 05000395/20224022022-02-15015 February 2022 Security Baseline Inspection Report 05000395/2022402 IR 05000395/20210042022-01-21021 January 2022 Integrated Inspection Report 05000395/2021004 IR 05000395/20213012021-11-0303 November 2021 NRC Operator License Exam Report 05000395/2021301 IR 05000395/20210032021-10-28028 October 2021 Integrated Inspection Report 05000395/2021003 IR 05000395/20210052021-08-24024 August 2021 Updated Inspection Plan for Virgil C.Summer Nuclear Station, Unit 1 (Report 05000395/2021005) IR 05000395/20214022021-08-0505 August 2021 Security Baseline Inspection Report 05000395/2021402 IR 05000395/20210022021-08-0404 August 2021 Integrated Inspection Report 05000395/2021002 IR 05000395/20210102021-08-0202 August 2021 Design Basis Assurance Inspection (Programs) Inspection Report 05000395/2021010 IR 05000395/20214032021-07-0808 July 2021 Target Set Inspection Report 05000395/2021403 IR 05000395/20210112021-06-0101 June 2021 Biennial Problem Identification and Resolution Inspection Report 05000395/2021011 2024-09-26
[Table view] Category:Letter
MONTHYEARML24278A2832024-11-0707 November 2024 Letter to E. Carr Environmental Impact Statement Scoping Summary Report for Virgil C. Summer Nuclear Station Unit 1 ML24305A1302024-10-31031 October 2024 Submittal of 30 Day Report Per 10 CFR 26.719(c) Blind Performance Testing ML24308A0052024-10-28028 October 2024 10-28-24 NRC V.C. Summer Nuclear Station SLR Cherokee Nation Letter to USNRC ML24308A0062024-10-25025 October 2024 Subsequent License Renewal Application Area of Potential Effect (Ape) Clarification Fairfield County, South Carolina SHPO Project No. 22-EJ0147 ML24302A1442024-10-24024 October 2024 Update to Subsequent License Renewal Application (SLRA) Supplement 4 and Requested Information Formation in Response to Limited Aging Management Audit ML24250A0782024-10-22022 October 2024 Relief Request RR-5-V1 Regarding Service Water Return Header Check Valves ML24256A2322024-10-22022 October 2024 Relief Request RR-5-P1 Charging/Safety Injection Pumps ML24255A3152024-10-22022 October 2024 Relief Request RR-5-V2 Regarding Pressure Isolation Valves 05000395/LER-2024-002, Loss of Control Room Emergency Filtration System2024-10-15015 October 2024 Loss of Control Room Emergency Filtration System ML24290A1052024-10-0707 October 2024 Core Operating Limits Report VCSNS Unit 1 Cycle 29, Revision 0 IR 05000395/20244042024-09-26026 September 2024 Cyber Security Inspection Report 05000395-2024404 - Public ML24274A1942024-09-26026 September 2024 (Vcsns), Unit 1 Subsequent License Renewal Application (SLRA) First 10 CFR 54.21(b) Annual Amendment ML24221A2112024-09-23023 September 2024 Clarification Regarding Area of Potential Effect for the Subsequent Operating License Renewal for Virgil C. Summer Nuclear Station Fairfield County, South Carolina (SHPO Project Number: 22-EJ0147) (Docket Number: 50-395) ML24267A0552024-09-23023 September 2024 Clarification Regarding Area of Potential Effect for the Subsequent Operating License Renewal for Virgil C. Summer Nuclear Station Fairfield County, South Carolina (SHPO Project Number: 22-EJ0147) (Docket Number: 50-395) ML24267A0642024-09-23023 September 2024 Clarification Regarding Area of Potential Effect for the Subsequent Operating License Renewal for Virgil C. Summer Nuclear Station Fairfield County, South Carolina (SHPO Project Number: 22-EJ0147) (Docket Number: 50-395) ML24267A0542024-09-23023 September 2024 Clarification Regarding Area of Potential Effect for the Subsequent Operating License Renewal for Virgil C. Summer Nuclear Station Fairfield County, South Carolina (SHPO Project Number: 22-EJ0147) (Docket Number: 50-395) ML24267A0592024-09-23023 September 2024 Clarification Regarding Area of Potential Effect for the Subsequent Operating License Renewal for Virgil C. Summer Nuclear Station Fairfield County, South Carolina (SHPO Project Number: 22-EJ0147) (Docket Number: 50-395) IR 05000395/20244022024-09-10010 September 2024 Security Baseline Inspection Report 05000395/2024402 IR 05000395/20240052024-08-22022 August 2024 Updated Inspection Plan for Virgil C. Summer Nuclear Station - Report 05000395/2024005 ML24190A4012024-08-19019 August 2024 Request for Withholding Information from Public Disclosure Regarding the Subsequent License Renewal Application - Dominion Energy Letter Dated May 30, 2024 IR 05000395/20240022024-08-12012 August 2024 Integrated Inspection Report 05000395/2024002 ML24180A0062024-08-0505 August 2024 Issuance of Amendment No. 227 to Modify Technical Specification 3.8.3.1 to Increase Completion Time for 120-Volt A.C. Vital Busses ML24218A3002024-08-0101 August 2024 Environmental Review Response to NRC Requests for Additional Information and Response to NRC Requests for Confirmation of Information Set 1 ML24158A3882024-07-31031 July 2024 Issuance of Amendment No. 226 to Change Emergency Plan Staff Augmentation Times and Relocate Emergency Operations Facility ML24162A3292024-07-0505 July 2024 Letter to E Carr - V.C. Summer Unit 1 - Summary of the May 2024 Audit Regarding the Environmental Review of the Subsequent License Renewal Application ML24185A1902024-06-25025 June 2024 Submittal of Updated Final Safety Analysis Report, Revision 24 ML24177A1382024-06-25025 June 2024 Aging Management Audit Report- VC Summer, Unit 1 - Subsequent License Renewal Application ML24178A1192024-06-25025 June 2024 Update to License Amendment Request- Inverter Allowed Outage Time (AOT) Extension ML24178A2422024-06-25025 June 2024 2023 Annual Report of Emergency Core Cooling System (ECCS) Model, Changes Pursuant to the Requirements of 10 CFR 50.46 ML24177A2792024-06-20020 June 2024 Preparation and Scheduling of Operator Licensing Examinations ML24171A0152024-06-17017 June 2024 Update to Subsequent License Renewal Application (SLRA) Response to NRC Request for Additional Information Set 2 Safety Review ML24157A3352024-06-0606 June 2024 – Notification of an NRC Cybersecurity Baseline Inspection (NRC Inspection Report 05000395-2024404 and Request for Information ML24155A2042024-05-31031 May 2024 Proposed Alternative Request RR-24-123, Containment Unbonded Post-Tensioning System Inservice Inspection Requirements ML24155A1462024-05-30030 May 2024 Update to Subsequent License Renewal Application (SLRA) -Response to NRC Request for Additional Information Set 1 Response to NRC Request for Confirmation of Information Set 1 and Supplement 3 ML24143A1792024-05-22022 May 2024 Special Report 2024-001-01 for Virgil C. Summer Nuclear Station (Vcsns), Unit 1, Waste Gas System Inoperability ML24141A2822024-05-20020 May 2024 (Vcsns), Unit 1 - License Amendment Request - Emergency Response Organization (ERO) Augmentation Time Change, Emergency Operations Facility Relocation and Other Emergency Plan Changes IR 05000395/20240012024-05-10010 May 2024 Integrated Inspection Report 05000395/2024001 ML24129A2002024-05-0606 May 2024 Update to Subsequent License Renewal Application, Supplement 2 IR 05000395/20240402024-05-0101 May 2024 95001 Supplemental Inspection Report 05000395/2024040 and Follow-Up Assessment Letter ML24121A1002024-04-29029 April 2024 Response to Request for Additional Information Regarding Alternative Request RR-5-V2 ML24120A2072024-04-29029 April 2024 Submittal of Annual Radiological Environmental Operating Report ML24116A2052024-04-23023 April 2024 Annual Radioactive Effluent Release Report ML24109A1792024-04-19019 April 2024 Aging Management Audit Plan Regarding the Subsequent License Renewal Application Review ML24108A0392024-04-18018 April 2024 Letter to E Carr-V.C. Summer Unit 1- Regulatory Audit Regarding the Environmental Review of the Subsequent License Renewal Application ML24108A0672024-04-17017 April 2024 Submittal of Summary for Condition of the Service Water Intake Structure Provided in Accordance with License Condition 2.C.5.d 05000395/LER-2024-001, (Vcsns), Unit 1, Automatic Actuation of B Emergency Diesel Generator2024-04-17017 April 2024 (Vcsns), Unit 1, Automatic Actuation of B Emergency Diesel Generator ML24100A7312024-04-0909 April 2024 Personnel Exposure and Monitoring Annual Report ML24095A2072024-04-0101 April 2024 Update to Subsequent License Renewal Application (SLRA) Supplement 1 ML24088A2062024-03-26026 March 2024 Annual Operating Report ML24087A2182024-03-26026 March 2024 (Vcsns), Unit 1 - License Amendment Request - Emergency Response Organization (ERO) Augmentation Time Change, Emergency Operations Facility Relocation and Other Emergency Plan Changes - Response to Request. 2024-09-26
[Table view] |
Text
ber 29, 2007
SUBJECT:
VIRGIL C. SUMMER NUCLEAR STATION - NRC EMERGENCY PREPAREDNESS INSPECTION REPORT 05000395/2007501
Dear Mr. J. Archie:
On October 5, 2007, the U.S. Nuclear Regulatory Commission (NRC) completed an Emergency Preparedness inspection at your V. C. Summer Nuclear Station. The enclosed inspection report documents the inspection results, which were discussed on October 5, 2007, with you, and other members of your staff.
The inspection examined activities conducted under your license as they relate to safety and compliance with the Commissions rules and regulations and with the conditions of your license.
The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel. Based on the results of this inspection, no findings of significance were identified.
In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter and its enclosure will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
Sincerely,
/RA/
Brian R. Bonser, Chief Plant Support Branch 1 Division of Reactor Safety Docket Nos. 50-395 License Nos. NPF-12
Enclosure:
NRC Inspection Report No. 05000395/2007501 w/Attachment: Supplemental Information
REGION II==
Docket No.: 50-395 License No.: NPF-12 Report No: 05000395/2007501 Licensee: South Carolina Electric and Gas Facility: Virgil C. Summer Nuclear Station Location: 576 Stairway Road Jenkinsville, SC 29065 Dates: October 1 - 5, 2007 Inspectors: Lee Miller, Senior Emergency Preparedness Inspector John Zeiler, Senior Resident Inspector James Polickoski, Resident Inspector Carl Moore, Operations License Examiner Approved by: Brian R. Bonser, Chief Plant Support Branch 1 Division of Reactor Safety Enclosure
SUMMARY OF FINDINGS
IR 05000395/2007501; 10/01-05/2007; Virgil C. Summer Nuclear Station; Exercise and
Baseline Inspection.
The report covered an announced inspection by one emergency preparedness inspector, one senior resident inspector, one resident inspector and one operations license examiner. The NRCs program for overseeing the safe operation of commercial nuclear power reactors is described in NUREG-1649, Reactor Oversight Process.
NRC-Identified and Self-Revealing Findings
None
Licensee-Identified Violations
.
None
REPORT DETAILS
REACTOR SAFETY
Cornerstone: Emergency Preparedness
1EP1 Exercise Evaluation
a. Inspection Scope
Prior to the inspection activity, the inspector conducted an in-office review of the exercise objectives and scenario submitted to the NRC to determine if the exercise would test major elements of the emergency plan as required by 10 CFR 50.47(b)(14).
This inspection activity represents one sample on a biennial cycle.
The onsite inspection consisted of the following review and assessment:
- The adequacy of the licensees performance in the biennial exercise conducted on October 2, 2007, was reviewed and assessed regarding the implementation of the Risk Significant Planning Standards (RSPSs) in 10 CFR 50.47 (b)(4), (5), (9), and (10), which address emergency classification, offsite notification, radiological assessment, and protective action recommendations, respectively.
- The overall adequacy of the licensees emergency response facilities with regard to NUREG-0696, Functional Criteria for Emergency Response Facilities and Emergency Plan commitments. The facilities assessed were the Control Room simulator, Technical Support Center (TSC), Operations Support Center (OSC) and Emergency Operations Facility (EOF).
- Other performance areas besides the RSPS, such as the emergency response organizations (ERO) recognition of abnormal plant conditions, command and control, intra- and inter-facility communications, prioritization of mitigation activities, utilization of repair and field monitoring teams, interface with offsite agencies, and the overall implementation of the emergency plan and its implementing procedures.
- The post-exercise critique process and the presentation to the licensee's senior management conducted on October 4, 2007, to evaluate the licensees self-assessment of its ERO performance during the exercise and to ensure compliance with 10 CFR 50 Appendix E.IV.F.2.g.
The inspector reviewed various documents which are listed in the Attachment to this report.
b. Findings
No findings of significance were identified.
1EP4 Emergency Action Level (EAL) and Emergency Plan Changes
a. Inspection Scope
The inspectors review of revisions to the emergency plan, implementing procedures, and EAL changes was performed to determine that changes had not decreased the effectiveness of the plan. The inspector also evaluated the associated 10 CFR 50.54(q)reviews associated with non-administrative emergency plan, implementing procedures, and EAL changes. The Summer Emergency Plan Procedures changes were reviewed for the period from July 1, 2006 to October 1, 2007.
The inspection was conducted in accordance with NRC Inspection Procedure 71114, 04, Emergency Action Level and Emergency Plan Changes. The applicable planning standard (PS), 10 CFR 50.47(b)(4) and its related 10 CFR 50, Appendix E requirements were used as reference criteria. The criteria contained in NUREG-0654, Appendix 1, Emergency Action Level Guidelines for Nuclear Power Plants, Revision 1 and Regulatory Guide 1.101 were also used as references. This inspection activity represents one sample on an annual basis.
The inspector reviewed various documents which are listed in the Attachment to this report.
b. Findings
No findings of significance were identified.
OTHER ACTIVITIES
4OA1 Performance Indicator (PI) Verification
a. Inspection Scope
The inspector sampled licensee submittals for the three Performance Indicators (PIs)listed below. For each of the submittals reviewed, the inspector looked at the period from April 1, 2006 to June 30, 2007. To verify the accuracy of the PI data reported during that period, PI definitions and guidance contained in NEI 99-02, Regulatory Assessment Indicator Guideline, Revision 4, were used to verify the basis in reporting for each data element.
- Emergency Response Organization Drill/Exercise Performance (DEP)
- Emergency Response Organization Readiness (ERO)
- Alert and Notification System Reliability (ANS)
The inspector reviewed portions of the raw PI data developed from monthly performance indicator reports and discussed the methods for compiling and reporting the PIs with cognizant emergency preparedness personnel. The inspector also independently screened drill and exercise opportunity evaluations, drill participation reports, and drill evaluations. Selected reported values were calculated to verify their accuracy. The inspector compared graphical representations from the most recent PI report to the raw data to verify that the data was correctly reflected in the report.
The inspection was conducted in accordance with NRC Inspection Procedure 71151, Performance Indicator Verification.
The inspector reviewed various documents which are listed in the Attachment to this report. This inspection satisfied three inspection samples for PI verification on an annual basis.
b. Findings
No findings of significance were identified.
4OA6 Meetings, including Exit
On October 5, 2007, the lead inspector for the emergency preparedness inspection presented the inspection results to Mr. J. Archie, and other members of his staff. The inspector confirmed that proprietary information was not provided or taken during the inspection.
ATTACHMENT:
SUPPLEMENTAL INFORMATION
KEY POINTS OF CONTACT
Licensee personnel
- S. Byrne, Senior Vice President - Generation and CNO
- J. Archie, Vice-President Nuclear Operations
- D. Gatlin, General Manager Nuclear Plant Operations
- R. Haselden, Manager, Organizational Development and Performance
- J. Nesbitt, Manager Materials and Procurement
- L. Bennett, Manager Plant Support and Engineering
- B. Williamson, Supervisor Emergency Preparedness
- D. Lavigne, General Manager Organization Effectiveness
- R. Fowlkes, General Manager Engineering
- G. Lippard, Manager Operations
- S. Zarandi, General Manager Nuclear Support Services
- B. Thompson, Manager Nuclear Licensing
LIST OF DOCUMENTS REVIEWED