|
---|
Category:Inspection Report
MONTHYEARIR 05000390/20240032024-11-13013 November 2024 Integrated Inspection Report 05000390/2024003, 05000391/2024003 & 07201048/2024001 IR 05000390/20250102024-11-0404 November 2024 Notification of an NRC (FPTI) (NRC Inspection Report 05000390/2025010 0500039/ 2025010) (RFI) IR 05000390/20243012024-10-17017 October 2024 Operator Licensing Examination Approval 05000390/2024301 and 05000391/2024301 IR 05000390/20240052024-08-28028 August 2024 Updated Inspection Plan and Assessment Follow-Up Letter for Watts Bar Nuclear Plant, Units 1 and 2 - Report 05000390-2024005 and 05000391-2024005 IR 05000390/20244022024-08-20020 August 2024 – Security Baseline Inspection Report 05000390-2024402 and 05000391/2024402 - Public IR 05000390/20240022024-08-0707 August 2024 Integrated Inspection Report 05000390/2024002 and 05000391/2024002 Rev IR 05000390/20244402024-07-12012 July 2024 95001 Supplemental Inspection Supplemental Report 05000390-2024440 and 05000391-2024440 and Follow-Up Assessment Letter IR 05000390/20240012024-05-14014 May 2024 Integrated Inspection Report 05000390/2024001 and 05000391/2024001 IR 05000391/20240072024-04-30030 April 2024 Assessment Follow-up Letter for Watts Bar Nuclear Plant, Unit 2 – Report 05000391/2024007 IR 05000390/20244012024-04-0202 April 2024 – Security Baseline Inspection Report 05000390/2024401 and 05000391/2024401 - (Public) IR 05000390/20240102024-03-0808 March 2024 Age-Related Degradation Inspection Report 05000390/2024010 and 05000391/2024010 IR 05000390/20230062024-02-28028 February 2024 Annual Assessment Letter for Watts Bar Nuclear Plant Units 1 and 2 - Report 05000390/2023006 and 05000391/2023006 IR 05000390/20230042024-02-13013 February 2024 Integrated Inspection Report 05000390/2023004 and 05000391/2023004 and Apparent Violation IR 05000390/20234412023-12-21021 December 2023 Plant–Final Significance Determination for a Security-Related Greater than Green Finding, Nov, and Assessment Follow-up, 05000390-2023441 and 05000391-2023441-Public IR 05000390/20234042023-12-14014 December 2023 – Security Baseline Inspection Report 05000390/2023404 and 05000391/2023404 IR 05000390/20230102023-11-30030 November 2023 RE-Issue Watts Bar Nuclear Plant - Biennial Problem Identification and Resolution Inspection Report 050000390/2023010 and 05000391/2023010 and Apparent Violation IR 05000390/20230032023-11-13013 November 2023 Integrated Inspection Report 05000390/2023003 and 05000391/2023003 and Apparent Violation ML23296A0242023-10-24024 October 2023 Biennial Problem Identification and Resolution Inspection Report and Preliminary Greater than Green Finding and Apparent Violation IR 05000390/20230052023-08-30030 August 2023 Updated Inspection Plan for Watts Bar Nuclear Plant, Units 1 and 2 - Report 05000390/2023005 and 05000391/2023005 IR 05000390/20230022023-08-16016 August 2023 Reissue - Watts Bar Nuclear Plant - Integrated Inspection Report 05000390/2023002 and 05000391/2023002 ML23220A1582023-08-0909 August 2023 Integrated Inspection Report 05000390/2023002 and 05000391/2023002 IR 05000390/20230112023-07-24024 July 2023 Quadrennial Focused Engineering Inspection (FEI) Commercial Grade Dedication Report 05000390 2023011 and 05000391 2023011 IR 05000390/20234032023-05-30030 May 2023 Cyber Security Inspection Report 05000390/2023403 and 05000391/2023403 IR 05000390/20220032023-05-0909 May 2023 Reissue Watts Bar Nuclear Plant - Integrated Inspection Report 05000390/2022003 and 05000391/2022003 IR 05000390/20230012023-05-0404 May 2023 Integrated Inspection Report 05000390/2023001 and 05000391/2023001 IR 05000390/20234012023-03-13013 March 2023 – Security Baseline Inspection Report 05000390 2023401 and 05000391 2023401 IR 05000390/20220062023-03-0101 March 2023 Annual Assessment Letter for Watts Bar Nuclear Plant, Units 1 and 2 - Report 05000390/2022006 and 05000391/2022006 IR 05000390/20220042023-02-10010 February 2023 – Integrated Inspection Report 05000390/2022004 and 05000391/2022004 IR 05000390/20224202022-12-0101 December 2022 Security Baseline Inspection 05000390/2022420 and 05000391/2022420 Cover Letter ML22318A0072022-11-14014 November 2022 Integrated Inspection Report 05000390/2022003 and 05000391/2022003 IR 05000390/20220102022-10-28028 October 2022 Design Basis Assurance Inspection (Teams) Inspection Report 05000390/2022010 and 05000391/2022010 ML22256A2952022-09-14014 September 2022 Operation of an Independent Spent Fuel Storage Installation Report 07201048/2022001 IR 05000390/20220052022-08-31031 August 2022 Updated Inspection Plan for Watts Bar Nuclear Plant, Units 1 and 2 - Report 05000390/2022005 and 05000391/2022005 - Final IR 05000390/20220022022-08-12012 August 2022 Integrated Inspection Report 05000390/2022002 and 05000391/2022002 and Exercise of Enforcement Discretion IR 05000390/20224012022-08-0303 August 2022 Security Baseline Inspection Report 05000390/2022401 and 05000391/2022401 ML22123A2412022-05-11011 May 2022 Review of the Fall 2021 Mid-Cycle Steam Generator Tube Inspection Report IR 05000390/20220012022-05-11011 May 2022 Integrated Inspection Report 05000390/2022001 and 05000391/2022001 IR 05000390/20210062022-03-0202 March 2022 Annual Assessment Letter for Watts Bar Nuclear Plant, Units 1 and 2 (Report No. 05000390/2021006 and 05000391/2021006) IR 05000390/20210042022-02-10010 February 2022 Integrated Inspection Report 05000390/2021004 and 05000391/2021004 IR 05000390/20223012022-01-0707 January 2022 Notification of Licensed Operator Initial Examination 05000390/2022301 and 05000391/2022301 IR 05000390/20210032021-11-10010 November 2021 Integrated Inspection Report 05000390/2021003 and 05000391/2021003 IR 05000390/20214022021-11-0202 November 2021 Security Baseline Inspection Report 05000390/2021402 and 05000391/2021402 IR 05000390/20214032021-10-26026 October 2021 Material Control and Accounting Program Inspection Report 05000390/2021403 and 05000391/2021403 (OUO Removed) ML21263A0042021-09-24024 September 2021 Review of the Fall 2020 Steam Generator Tube Inspection Report IR 05000390/20214012021-08-31031 August 2021 Security Baseline Inspection Report 05000390/2021401 and 05000391/2021401 IR 05000390/20210052021-08-24024 August 2021 Updated Inspection Plan for Watts Bar Nuclear Plant, Units 1 & 2 Report 05000390/2021005 and 05000391/2021005 IR 05000390/20210022021-08-0404 August 2021 Integrated Inspection Report 05000390/2021002 and 05000391/2021002 IR 05000390/20210122021-07-0101 July 2021 Biennial Problem Identification and Resolution Inspection Report 05000390/2021012 and 05000391/2021012 IR 05000390/20210102021-05-0606 May 2021 NRC Inspection Report 05000390/2021010 and 05000391/2021010 IR 05000390/20210012021-05-0505 May 2021 Integrated Inspection Report 05000390/2021001 and 05000391/2021001 2024-08-07
[Table view] Category:Letter
MONTHYEARCNL-24-080, Response to Request for Additional Information Regarding Application to Revise Updated Final Safety Analysis Report Regarding Changes to Hydrologic Analysis (WBN-19-011)2024-11-20020 November 2024 Response to Request for Additional Information Regarding Application to Revise Updated Final Safety Analysis Report Regarding Changes to Hydrologic Analysis (WBN-19-011) IR 05000390/20240032024-11-13013 November 2024 Integrated Inspection Report 05000390/2024003, 05000391/2024003 & 07201048/2024001 CNL-24-021, Application to Revise Technical Specification Limiting Condition of Operation 3.5.2, ECCS – Operating, Note 1 to Include Residual Heat Removal Pump Flow Paths (SQN-TS-23-04 and WBN-TS-23-020)2024-11-12012 November 2024 Application to Revise Technical Specification Limiting Condition of Operation 3.5.2, ECCS – Operating, Note 1 to Include Residual Heat Removal Pump Flow Paths (SQN-TS-23-04 and WBN-TS-23-020) IR 05000390/20250102024-11-0404 November 2024 Notification of an NRC (FPTI) (NRC Inspection Report 05000390/2025010 0500039/ 2025010) (RFI) CNL-24-014, License Amendment Request to Revise the Sequoyah Nuclear Plant, Units 1 and 2 and Watts Bar Nuclear Plant, Units 1 and 2 Technical Specifications to Use Online Monitoring Methodology (SQN-TS-24-02 and WBN-TS-23-22)2024-11-0404 November 2024 License Amendment Request to Revise the Sequoyah Nuclear Plant, Units 1 and 2 and Watts Bar Nuclear Plant, Units 1 and 2 Technical Specifications to Use Online Monitoring Methodology (SQN-TS-24-02 and WBN-TS-23-22) CNL-24-064, Response to Request for Additional Information Regarding the Watts Bar Nuclear Plant, Unit 2 Steam Generator Tube Inspection Report for U2R52024-11-0404 November 2024 Response to Request for Additional Information Regarding the Watts Bar Nuclear Plant, Unit 2 Steam Generator Tube Inspection Report for U2R5 CNL-24-074, Tennessee Valley Authority - Central Emergency Control Center Emergency Plan Implementing Procedure Revisions2024-10-23023 October 2024 Tennessee Valley Authority - Central Emergency Control Center Emergency Plan Implementing Procedure Revisions IR 05000390/20243012024-10-17017 October 2024 Operator Licensing Examination Approval 05000390/2024301 and 05000391/2024301 ML24282B0412024-10-15015 October 2024 Request for Withholding Information from Public Disclosure for Sequoyah Nuclear Plant, Units 1 and 2 and Watts Bar Nuclear Plant, Units 1 and 2 ML24261C0062024-10-0404 October 2024 Correction to Amendment No. 134 to Facility Operating License No. NPF-90 and Amendment No. 38 to Facility Operating License No. NPF-96 ML24260A1682024-10-0404 October 2024 Regulatory Audit Summary Related to Request to Add and Revise Notes Related to Technical Specification Table 3.3.2-1, Function 5 ML24284A1072024-09-26026 September 2024 Affidavit for Request for Withholding Information from Public Disclosure for Sequoyah Nuclear Plant, Units 1 and 2, and Watts Bar Nuclear Plant, Units 1 and 2 CNL-24-060, Supplement to Request for Approval of the Tennessee Valley Authority Nuclear Quality Assurance Program Description2024-09-24024 September 2024 Supplement to Request for Approval of the Tennessee Valley Authority Nuclear Quality Assurance Program Description CNL-24-047, Decommitment of Flood Mode Mitigation Improvement Systems2024-09-24024 September 2024 Decommitment of Flood Mode Mitigation Improvement Systems ML24262A0602024-09-23023 September 2024 Summary of August 19, 2024, Meeting with Tennessee Valley Authority Regarding a Proposed Supplement to the Tennessee Valley Authority Nuclear Quality Assurance Plan CNL-24-065, Tennessee Valley Authority – Central Emergency Control Center Emergency Plan Implementing Procedure Revisions2024-09-18018 September 2024 Tennessee Valley Authority – Central Emergency Control Center Emergency Plan Implementing Procedure Revisions 05000390/LER-2024-002, Automatic Reactor Trip Due to Main Generator Protection Relay Actuation2024-09-0505 September 2024 Automatic Reactor Trip Due to Main Generator Protection Relay Actuation IR 05000390/20240052024-08-28028 August 2024 Updated Inspection Plan and Assessment Follow-Up Letter for Watts Bar Nuclear Plant, Units 1 and 2 - Report 05000390-2024005 and 05000391-2024005 ML24218A1442024-08-27027 August 2024 Issuance of Amendment Nos. 169 and 75 Regarding Technical Specification Surveillance Requirement 3.9.5.1 to Reduce the Residual Heat Removal Flow Rate IR 05000390/20244022024-08-20020 August 2024 – Security Baseline Inspection Report 05000390-2024402 and 05000391/2024402 - Public CNL-24-061, Supplement to Application to Revise Function 5 of Technical Specification Table 3.3.2-1, ‘Engineered Safety Feature Actuation System Instrumentation,’ for the Sequoyah and Watts Bar (SQN-TS-23-02 and WBN-TS-23-08),2024-08-19019 August 2024 Supplement to Application to Revise Function 5 of Technical Specification Table 3.3.2-1, ‘Engineered Safety Feature Actuation System Instrumentation,’ for the Sequoyah and Watts Bar (SQN-TS-23-02 and WBN-TS-23-08), ML24219A0262024-08-12012 August 2024 Request for Withholding Information from Public Disclosure IR 05000390/20240022024-08-0707 August 2024 Integrated Inspection Report 05000390/2024002 and 05000391/2024002 Rev ML24204A2652024-07-25025 July 2024 Regulatory Audit Summary Related to Request to Revise Technical Specification Surveillance Requirement 3.9.5.1 to Reduce the Residual Heat Removal Flow Rate ML24199A0012024-07-22022 July 2024 Clarification and Correction to Exemption from Requirement of 10 CFR 37.11(c)(2) ML24170A8002024-07-15015 July 2024 Issuance of Amendment Nos. 168 and 74 Regarding Revision to Technical Specification Table 1.1-1 for Required Number of Fully Tensioned Reactor Pressure Vessel Head Closure Bolts ML24172A1342024-07-15015 July 2024 Exemptions from 10 CFR 37.11(C)(2) (EPID L-2023-LLE-0024) - Letter IR 05000390/20244402024-07-12012 July 2024 95001 Supplemental Inspection Supplemental Report 05000390-2024440 and 05000391-2024440 and Follow-Up Assessment Letter 05000391/LER-2024-003, Inoperability of Both Trains of Unit 2 Low Head Safety Injection2024-07-11011 July 2024 Inoperability of Both Trains of Unit 2 Low Head Safety Injection ML24131A0012024-07-0202 July 2024 Issuance of Amendment Nos. 167 and 73 Regarding Adoption of Technical Specification Task Force Traveler TSTF-427-A, Revision 2 CNL-24-052, Response to Request for Additional Information Regarding Application to Modify the Technical Specification Surveillance Requirement 3.9.5.1 (WBN-TS-21-14)2024-06-27027 June 2024 Response to Request for Additional Information Regarding Application to Modify the Technical Specification Surveillance Requirement 3.9.5.1 (WBN-TS-21-14) CNL-24-018, License Amendment Request for Adoption of Technical Specification Task Force Traveler TSTF-276-A, Revision 2, Regarding TS 3.8.1 AC Sources – Operating to Clarify Requirements for Diesel Generator Testing (WBN-TS2024-06-25025 June 2024 License Amendment Request for Adoption of Technical Specification Task Force Traveler TSTF-276-A, Revision 2, Regarding TS 3.8.1 AC Sources – Operating to Clarify Requirements for Diesel Generator Testing (WBN-TS ML24089A1152024-06-21021 June 2024 Transmittal Letter, Environmental Assessments and Findings of No Significant Impact Related to Exemption Requests from 10 CFR 37.11(c)(2) ML24141A0482024-05-17017 May 2024 EN 56958_1 Ametek Solidstate Controls, Inc ML24100A7642024-05-16016 May 2024 Issuance of Amendment No. 166 Regarding Revision to Technical Specification 3.8.2, AC Sources-Shutdown, to Remove Reference to C-S Diesel Generator (CNL-23-062) IR 05000390/20240012024-05-14014 May 2024 Integrated Inspection Report 05000390/2024001 and 05000391/2024001 CNL-24-040, Tennessee Valley Authority - Central Emergency Control Center Emergency Plan Implementing Procedure Revisions2024-05-0808 May 2024 Tennessee Valley Authority - Central Emergency Control Center Emergency Plan Implementing Procedure Revisions 05000391/LER-2024-002, Re Automatic Reactor Trip Due to Steam Generator 3 Level LO-LO2024-05-0606 May 2024 Re Automatic Reactor Trip Due to Steam Generator 3 Level LO-LO IR 05000391/20240072024-04-30030 April 2024 Assessment Follow-up Letter for Watts Bar Nuclear Plant, Unit 2 – Report 05000391/2024007 ML24120A1182024-04-29029 April 2024 – Notification of NRC Supplemental Inspection (95001) and Request for Information CNL-24-037, Clinch River, Sequoyah, Units 1 and 2, Watts Bar, Unit 1 and 2, Nuclear Quality Assurance Plan, TVA-NQA-PLN89-A, Revision 422024-04-22022 April 2024 Clinch River, Sequoyah, Units 1 and 2, Watts Bar, Unit 1 and 2, Nuclear Quality Assurance Plan, TVA-NQA-PLN89-A, Revision 42 ML24087A1912024-04-18018 April 2024 Exemption from Select Requirements of 10 CFR Part 73, Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting CNL-24-033, Central Emergency Control Center Emergency Plan Implementing Procedure Revisions2024-04-17017 April 2024 Central Emergency Control Center Emergency Plan Implementing Procedure Revisions CNL-24-010, License Amendment Request to Recapture Low-Power Testing Time (WBN-TS-23-19)2024-04-17017 April 2024 License Amendment Request to Recapture Low-Power Testing Time (WBN-TS-23-19) CNL-24-024, Hydrologic Engineering Center River Analysis System Project Milestone Status Update2024-04-17017 April 2024 Hydrologic Engineering Center River Analysis System Project Milestone Status Update ML24072A0052024-04-15015 April 2024 Issuance of Amendment Nos. 165 and 72 Regarding Increase in the Maximum Number of Tritium Producing Burnable Absorber Rods and Supporting Changes, and Revision to the Updated Final Safety Analysis Report CNL-24-004, Application to Modify the Watts Bar Nuclear Plant, Unit 1 and Unit 2 Technical Specifications for Main Control Room Chiller Completion Time Extension (WBN-TS-23-13)2024-04-0404 April 2024 Application to Modify the Watts Bar Nuclear Plant, Unit 1 and Unit 2 Technical Specifications for Main Control Room Chiller Completion Time Extension (WBN-TS-23-13) IR 05000390/20244012024-04-0202 April 2024 – Security Baseline Inspection Report 05000390/2024401 and 05000391/2024401 - (Public) 2024-09-05
[Table view] |
Text
UNITED STATES une 22, 2015
SUBJECT:
WATTS BAR NUCLEAR PLANT UNITS 1 AND 2 - NRC TEAM INSPECTION REPORT 05000390/2015009 AND 05000391/2015616
Dear Mr. Shea:
On April 3, 2015, the U. S. Nuclear Regulatory Commission (NRC) completed an inspection at your Watts Bar Nuclear Plant, Units 1 and 2. The enclosed report documents the inspection results, which were discussed on April 3, 2015, with Mr. Walsh and other members of your staff.
A re-exit was conducted with Mr. ODell via telephone on May 15, 2015, to discuss the final results of the inspection.
The inspection examined activities conducted under your licenses as they relate to the implementation of mitigation strategies and spent fuel pool instrumentation orders (EA-12-049 and EA-12-051) and Emergency Preparedness Communication/Staffing/Multi-Unit Dose Assessment Plans, your compliance with the Commissions rules and regulations, and with the conditions of your operating license. Within these areas, the inspection involved examination of selected procedures and records, observation of activities, and interviews with plant personnel.
The NRC inspectors did not identify any findings or violations of more than minor significance.
In accordance with 10 CFR 2.390 of the NRCs Rules of Practice, a copy of this letter and its enclosure will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of the NRCs document system (ADAMS). Adams is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
Sincerely,
/RA/
Anthony D. Masters, Chief Reactor Projects Branch 7 Division of Reactor Projects Docket No.: 50-390, 50-391 License No.: NPF-90, CPPR-92
Enclosure:
05000390/2015009 AND 05000391/2015616 w/Attachment: Supplementary Information
REGION II==
Docket No.: 50-390, 50-391 License No.: NPF-90, CPPR-92 Report No.: 05000390/2015009, 05000391/2015616 Licensee: Tennessee Valley Authority (TVA)
Facility: Watts Bar Nuclear Plant Units 1 and 2 Location: Spring City, TN Dates: March 30 - April 3, 2015 Inspectors: R. Rodriguez, Senior Project Engineer (Team Leader)
S. Sanchez, Senior Emergency Preparedness Inspector J. Hamman, Resident Inspector (Watts Bar Unit 1)
J. Seat, Construction Project Inspector W. Cook, Senior Reactor Analyst, Region I (Observer)
J. Boettcher, Reactor Inspector, Region III (Observer)
R. Hagar, Senior Project Engineer, Region IV (Observer)
T. Brown, Project Manager, JLD (Observer)
J. Paige, Project Manager, JLD (Observer)
Approved by: Anthony D. Masters, Chief Reactor Projects Branch 7 Division of Reactor Projects ENCLOSURE
SUMMARY OF FINDINGS
IR 05000390/2015009 and 05000391/2015616; 3/30/2015 - 4/03/2015; Watts Bar Nuclear Plant
Units 1 and 2; Temporary Instruction 2515/191, Inspection of the Implementation of Mitigation Strategies and Spent Fuel Pool Instrumentation Orders and Emergency Preparedness Communication/Staffing/Multi-Unit Dose Assessment Plans issued October 06, 2014.
The inspection covered a one week inspection by one senior project inspector, a senior emergency preparedness inspector, a construction project inspector, and the resident inspector.
No findings of significance were identified. The significance of most findings is identified by their color (Green, White, Yellow, Red) using Inspection Manual Chapter (IMC) 0609, Significance Determination Process (SDP); cross-cutting aspects were determined using IMC 0310; Aspects Within Cross-Cutting Areas; and findings for which the SDP does not apply may be Green or be assigned a severity level after NRC management review. The NRCs program for overseeing the safe operation of commercial nuclear power reactors is described in NUREG-1649, Reactor Oversight Process, Revision 5.
NRC-Identified and Self-Revealing Findings
None
Licensee-Identified Violations
None
REPORT DETAILS
4. Other Activities
4OA5 Other Activities (TI 2515/191)
The objective of Temporary Instruction (TI) 2515/191 Inspection of the Implementation of Mitigation Strategies and Spent Fuel Pool Instrumentation Orders and Emergency Preparedness Communication/Staffing/Multi-Unit Dose Assessment Plans is to verify that licensees have adequately implemented the mitigation strategies as described in the licensees Final Integrated Plan (ADAMS Accession No. ML15072A116) and the NRCs plant safety evaluation (ADAMS Accession No. ML15078A193) and to verify that the licensees installed reliable water-level measurement instrumentation in their spent fuel pools. The purpose of this TI is also to verify that licensees have implemented emergency preparedness (EP) enhancements as described in their site-specific submittals and NRC safety assessments, including multi-unit dose assessment capability, enhancements to ensure that staffing is sufficient, and that communications can be maintained during beyond-design-basis external events.
The team verified that plans for complying with NRC Orders EA-12-049, Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (ADAMS Accession No. ML12229A174) and EA-12-051, Order Modifying Licenses With Regard to Reliable Spent Fuel Pool Instrumentation (ADAMS Accession No. ML12056A044) are in place and are being implemented by the licensee.
The team also verified that the licensee had implemented staffing and communications plans provided in response to the March 12, 2012, request for information letter and multi-unit dose assessment information provided per COMSECY-13-0010, Schedule and Plans for Tier 2 Order on Emergency Preparedness for Japan Lessons Learned, dated March 27, 2013 (ADAMS Accession No. ML12339A262).
The team discussed the plans and strategies with plant staff, reviewed documentation, and where appropriate, performed plant walk downs to verify that the strategies could be implemented as stated in the licensees submittals and the NRC staff prepared safety evaluation. For most strategies, this included verification that the strategy was feasible, procedures and/or guidance had been developed, training had been provided to plant staff, and required equipment had been identified and staged. Specific details of the teams inspection activities are described in the following sections.
1. Mitigation Strategies for Beyond-Design Basis External Events
a. Inspection Scope
The team examined the licensees established guidelines and implementing procedures for the beyond-design-basis mitigation strategies. The team assessed how the licensee coordinated and documented the interface/transition between existing off-normal and Emergency Operating Procedures with the newly developed mitigation strategies. The team selected a number of mitigation strategies and conducted plant walk downs with licensed operators and responsible plant staff to assess: the adequacy and completeness of the procedures; familiarity of operators with the procedure objectives and specific guidance; staging and compatibility of equipment; and the practicality of the operator actions prescribed by the procedures, consistent with the postulated scenarios.
The team verified that a preventive maintenance program had been established for the Diverse and Flexible Coping Strategies (FLEX) portable equipment and that periodic equipment inventories were in place and being conducted. Additionally, the team examined the introductory and planned periodic/refresher training provided to the Operations and Maintenance staff most likely to be tasked with implementation of the FLEX mitigation strategies. The team also reviewed the introductory and planned periodic training provided to the Emergency Response Organization personnel.
Documents reviewed are listed in the Attachment.
b. Assessment Based on samples selected for review, the team verified that the licensee satisfactorily implemented appropriate elements of the FLEX strategy as described in the plant specific submittal(s) and the associated safety evaluation. The team did not identify any issues of a more than minor significance concerning the licensees compliance with NRC Order EA-12-049. The team verified that the licensee satisfactorily:
- developed and issued FLEX Support Guidelines (FSGs) to implement the FLEX strategies for postulated external events
- integrated their FSGs into their existing plant procedures such that entry into and departure from the FSGs are clear when using existing plant procedures
- protected FLEX equipment from site-specific hazards
- developed and implemented adequate testing and maintenance of FLEX equipment to ensure their availability and capability
- trained their staff to assure personnel proficiency in the mitigation of beyond-design-basis events
- developed means to ensure that the necessary off-site FLEX equipment will be available from off-site locations.
The team verified that issues identified during the inspection were entered into the licensee's corrective action program.
2. Spent Fuel Pool Instrumentation
a. Inspection Scope
The team examined the licensees newly installed spent fuel pool (SFP) instrumentation.
Specifically, the team verified the sensors were installed as described in the plant specific submittals and the associated safety evaluation, and that the cabling for the power supplies and the indications for each channel are physically and electrically separated. Additionally, environmental conditions and accessibility of the instruments were evaluated.
The team verified that the licensee has approved procedures for maintenance, testing, calibration, and use of the primary and backup SFP instrumentation channels. And that the procedures follow the guidance contained in Nuclear Energy Institute (NEI) 12-02 and that these procedures are part of an existing licensee process to be maintained.
Documents reviewed are listed in the attachment.
b. Assessment Based on samples selected for review, the team determined that the licensee satisfactorily installed and established control of the SFP instrumentation as described in the plant specific submittal(s) and the associated safety evaluation. The team did not identify any issues of a more than minor significance concerning the licensees compliance with NRC Order EA-12-051. The team verified that the licensee satisfactorily:
- installed the SFP instrumentation sensors, cabling, and power supplies to provide physical and electrical separation as described in the plant specific submittal(s) and safety evaluation
- installed the SFP instrumentation display in the accessible location, and environmental conditions as described in the plant specific submittal(s)
- trained their staff to assure personnel proficiency with the maintenance, testing, and use of the SFP instrumentation
- developed and issued procedures for maintenance, testing, and use of the reliable SFP instrumentation.
The team verified that issues identified during the inspection were entered into the licensee's corrective action program.
3. Staffing and Communication Request for Information
a. Inspection Scope
Through discussions with plant staff, review of documentation and plant walk downs, the team verified that the licensee has implemented required changes to staffing, communications equipment, and facilities to support a multi-unit extended loss of all AC power (ELAP) scenario as described in the licensees staffing assessment and the NRC safety evaluation. The team also verified that the licensee has implemented multi-unit dose assessment (including releases from spent fuel pools) capability using the licensees site-specific dose assessment software and approach as described in the licensees multi-unit dose assessment submittal. Documents reviewed are listed in the
.
b. Assessment The team reviewed information provided in the licensees multi-unit dose submittal and in response to the NRCs March 12, 2012, request for information letter, and verified that the licensee satisfactorily implemented enhancements pertaining to Near-Term Task Force Recommendation 9.3 response to a large scale natural emergency event that results in an extended loss of all AC power to all site units and impedes access to the site. The team verified the following:
- Licensee satisfactorily implemented required staffing change(s) to support a multi-unit ELAP scenario
- EP communications equipment and facilities are sufficient for dealing with a multi-unit ELAP scenario
- Implemented multi-unit dose assessment capabilities (including releases from spent fuel pools) using the licensees site-specific dose assessment software and approach.
The team verified that issues identified during the inspection were entered into the licensee's corrective action program.
4OA6 Exit
Exit Meeting Summary
On April 3, 2015, the team presented the inspection results to Mr. Walsh and other members of the site staff. The team confirmed that proprietary information was not provided or examined during the inspection. A re-exit was conducted with Mr. ODell via telephone on May 15, 2015, to discuss the final results of the inspection.
ATTACHMENT:
SUPPLEMENTARY INFORMATION
KEY POINTS OF CONTACT
Licensee personnel
- S. Duncan, Performance Improvement Manager
- K. Walsh, Site VP
- S. Conners, Plant Manager
- J. ODell, Regulatory Compliance
- D. Charlton, Regulatory Compliance
- J. Harvey, FLEX Engineer
- T. Dutchemendy, Emergency Preparedness Manager
- W. Smith, Operations Training Manager
- J. Reidy, Operations
- R. Proffitt, Regulatory Compliance
NRC personnel
- C. Kontz, Senior Project Engineer
- S. Rose, Chief, Projects Branch 5
- T. Nazario, Senior Resident Inspector Watts bar Unit 2
- E. Patterson, Resident Inspector Watts Bar Unit 2
- V. McCree, Regional Administrator
LIST OF REPORT ITEMS
Opened and Closed
None
Discussed
None ATTACHMENT
LIST OF DOCUMENTS REVIEWED