IR 05000373/2025003

From kanterella
Jump to navigation Jump to search
County Station - Integrated Inspection Report 05000373/2025003; 05000374/2025003 07200070/2025001 and Exercise of Enforcement Discretion
ML25349A053
Person / Time
Site: LaSalle  Constellation icon.png
Issue date: 12/15/2025
From: Robert Ruiz
NRC/RGN-III/DORS/RPB1
To: Mudrick C
Constellation Energy Generation, Constellation Nuclear
References
EA-NMSS-2023-0002, EAF-NMSS-2025-0226 IR 2025003
Download: ML25349A053 (0)


Text

SUBJECT:

LASALLE COUNTY STATION - INTEGRATED INSPECTION REPORT 05000373/2025003; 05000374/2025003; 07200070/2025001 AND EXERCISE OF ENFORCEMENT DISCRETION

Dear Christopher H. Mudrick:

On September 30, 2025, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at LaSalle County Station. On November 17, 2025, the NRC inspectors discussed the results of this inspection with John VanFleet, Site Vice President, and other members of your staff. The results of this inspection are documented in the enclosed report.

Due to the temporary cessation of government operations, which commenced on October 01, 2025, the NRC began operating under its Office of Management and Budget-approved plan for operations during a lapse in appropriations. Consistent with that plan, the NRC operated at reduced staffing levels throughout the duration of the shutdown. However, the NRC continued to perform critical health and safety functions and make progress on other high-priority activities associated with the ADVANCE Act and Executive Order 14300. On November 13, 2025, following the passage of a continuing resolution, the NRC resumed normal operations. However, due to the 43-day lapse in normal operations, the Office of Nuclear Reactor Regulation granted the Regional Offices an extension on the issuance of the calendar year 2025, 3rd quarter integrated inspection reports normally issued by November 15, 2025, to December 31, 2025. The NRC will resume the routine cycle of issuing inspection reports on a quarterly basis beginning with the calendar year 2025, 4th quarter integrated inspection reports, which will be issued 45 days after the 4th quarter ends on December 31, 2025.

The NRC-identified a violation of 10 CFR 72.48 (c)(1), (c)(2), and (d)(1) and 10 CFR 72.212(b)(3) that resulted from a CoC holders failure to comply with 10 CFR 72.48 for a CoC holder-generated change to the multi-purpose canister fuel basket, known as the continuous basket shim variant. However, an Interim Enforcement Policy (IEP) issued in August 2025 is applicable to this violation. Specifically, Enforcement Policy section 9.4, Enforcement Discretion December 15, 2025 for General Licensee Adoption of Certificate of Compliance (CoC) Holder-Generated Modifications under 10 CFR Part 72.48, provides enforcement discretion to not issue an enforcement action for this violation. The licensee will be expected to comply with 10 CFR 72.212 provisions after the NRC dispositions the noncompliance for a CoC holder-generated change that affects the General Licensee.

This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations 2.390, Public Inspections, Exemptions, Requests for Withholding.

Sincerely, Robert Ruiz, Chief Reactor Projects Branch 1 Division of Operating Reactor Safety Docket Nos. 05000373; 05000374; 07200070 License Nos. NPF-11 and NPF-18

Enclosure:

As stated

Inspection Report

Docket Numbers:

05000373; 05000374; 07200070

License Numbers:

NPF-11 and NPF-18

Report Numbers:

05000373/2025003; 05000374/2025003; 07200070/2025001

Enterprise Identifier:

I-2025-003-0055; I-2025-001-0134

Licensee:

Constellation Nuclear

Facility:

LaSalle County Station

Location:

Marseilles, IL

Inspection Dates:

July 01, 2025, to September 30, 2025

Inspectors:

N. Audia, Reactor Inspector

J. Benjamin, Senior Resident Inspector

J. Cassidy, Senior Health Physicist

J. Hoang, Reactor Technology Instructor

T. Hooker, Health Physicist

B. Lin, Senior Health Physicist

A. Muneeruddin, Resident Inspector

R. Zuffa, Illinois Emergency Management Agency

Approved By:

Robert Ruiz, Chief

Reactor Projects Branch 1

Division of Operating Reactor Safety

SUMMARY

The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees performance by conducting an integrated inspection at LaSalle County Station, in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information.

List of Findings and Violations

No findings or violations of more than minor significance were identified.

Additional Tracking Items

Type Issue Number Title Report Section Status URI 05000373,05000374/2023003-01 Continuous Basket Shim Design Change for HI-STORM 100 60855 Closed EDG EAF-NMSS-2025-0226 Continuous Basket Shim - General Licensee Adoption of Certificate of Compliance Holder-Generated Changes under 10 CFR 72.48 (IEP 9.4)60855 Closed

PLANT STATUS

Unit 1 began the inspection period at rated thermal power. On September 6, 2025, the unit down powered to approximately 78 percent to perform main turbine control valve testing, control rod scram time testing, and a control rod sequence exchange and was returned to full power on September 7, 2025. The unit operated at or near full power for the remainder of the inspection period.

Unit 2 began the inspection period at rated thermal power. On September 27, 2025, the unit down powered to approximately 63 percent to perform main turbine control valve testing, a main control rod sequence exchange and scram time testing. The unit was restored to full power on September 28, 2025, and operated at full power for the remainder of the inspection period.

INSPECTION SCOPES

Inspections were conducted using the appropriate portions of the inspection procedures (IPs) in effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with their attached revision histories are located on the public website at http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html. Samples were declared complete when the IP requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter (IMC) 2515, Light-Water Reactor Inspection Program - Operations Phase. The inspectors performed activities described in IMC 2515, Appendix D, Plant Status, observed risk significant activities, and completed on-site portions of IPs. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess licensee performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards.

REACTOR SAFETY

71111.04 - Equipment Alignment

Partial Walkdown Sample (IP Section 03.01) (2 Samples)

The inspectors evaluated system configurations during partial walkdowns of the following systems/trains:

(1) Unit 2 spent fuel pool cooling on July 7, 2025
(2) Unit 2B train service water pump with Unit 2A train service water pump out of service for maintenance on July 23, 2025

71111.05 - Fire Protection

Fire Brigade Drill Performance Sample (IP Section 03.02) (2 Samples)

(1) The inspectors evaluated the onsite fire brigade training and crew performance during an unannounced fire drill on August 21, 2025.
(2) The inspectors evaluated the onsite fire brigade training and crew performance during an unannounced fire drill on August 22, 2025.

71111.11Q - Licensed Operator Requalification Program and Licensed Operator Performance

Licensed Operator Requalification Training/Examinations (IP Section 03.02) (1 Sample)

(1) The inspectors observed and evaluated license operator requalification training: out-of-the-box evaluation on July 8, 2025.

71111.12 - Maintenance Effectiveness

Maintenance Effectiveness (IP Section 03.01) (2 Samples)

The inspectors evaluated the effectiveness of maintenance to ensure the following structures, systems, and components (SSCs) remain capable of performing their intended function:

(1)1A standby liquid control pump

(2) Unit 1 SCRAM discharge volume drain valve, 1C11-F381

71111.13 - Maintenance Risk Assessments and Emergent Work Control

Risk Assessment and Management Sample (IP Section 03.01) (3 Samples)

The inspectors evaluated the accuracy and completeness of risk assessments for the following planned and emergent work activities to ensure configuration changes and appropriate work controls were addressed:

(1)planned elevated Unit 2 on-line risk the week of July 7, 2025, during the Unit 2A train service water system work window (2)unplanned elevated Unit 1 on-line risk on September 2, 2025, following the Common emergency diesel generator Unit 1 output breaker closure failure during testing (3)planned elevated Unit 2 on-line risk from September 2 through September 4, 2025, during Unit 2A train residual heat removal (RHR) system maintenance window

71111.15 - Operability Determinations and Functionality Assessments

Operability Determination or Functionality Assessment (IP Section 03.01) (4 Samples)

The inspectors evaluated the licensee's justifications and actions associated with the following operability determinations and functionality assessments:

(1) Action Request (AR) 4879420, Reactor Core Isolation Cooling Turbine Trip Pushbutton Broke
(2) Unit 1 emergency cooling water system operability during routine fill and vent activities
(3) AR 4836829, 'C' Vacuum Breaker, 2PC001C, Failed Force Check
(4) AR 4865523 and AR 4865896, NRC Identified U-1 250V Battery Discrepancies

71111.24 - Testing and Maintenance of Equipment Important to Risk

The inspectors evaluated the following testing and maintenance activities to verify system operability and/or functionality:

Post-Maintenance Testing (PMT) (IP Section 03.01) (3 Samples)

(1) Unit 1B train spent fuel pooling cooling water pump replacement, WO 5181459
(2) Unit 2B train RHR service water pump seal replacement, WO 1927593
(3) Unit Common emergency diesel generator Unit 1 output breaker relay replacement on October 30, 2025

Surveillance Testing (IP Section 03.01) (2 Samples)

(1) Unit Common emergency diesel generator fuel oil transfer pump test per LOS-DG-Q1, Attachment A1 on July 2, 2025
(2) Unit 2B train RHR pump run per LOS-RH-Q1 2B RHR on August 11, 2025

Inservice Testing (IST) (IP Section 03.01) (1 Sample)

(1) Unit 2 reactor core isolation cooling water pump operability and inservice test on August 26, 2025

Diverse and Flexible Coping Strategies (FLEX) Testing (IP Section 03.02) (1 Sample)

(1)diverse and flexible coping strategy hale pump A functional surveillance on July 8, 2025

71114.06 - Drill Evaluation

Additional Drill and/or Training Evolution (1 Sample)

The inspectors evaluated:

(1) emergency response organization full-scale exercise on August 19,

RADIATION SAFETY

71124.06 - Radioactive Gaseous and Liquid Effluent Treatment

Walkdowns and Observations (IP Section 03.01) (3 Samples)

The inspectors evaluated the following radioactive effluent systems during walkdowns:

(1)main vent stack sample skid and radiation monitor (2)standby gas treatment sample skid and radiation monitor (3)cooling pond blowdown effluent release point

Sampling and Analysis (IP Section 03.02) (3 Samples)

Inspectors evaluated the following effluent samples, sampling processes and compensatory samples:

(1)particulate and iodine sampling of Unit 0 main vent stack (2)noble gas grab sample of Unit 0 main vent stack (3)cooling pond blowdown composite sampling

Dose Calculations (IP Section 03.03) (2 Samples)

The inspectors evaluated the following dose calculations:

(1) Permit Number G-20250527-1232-C
(2) Permit Number G-20221025-925-C

71124.07 - Radiological Environmental Monitoring Program

Environmental Monitoring Equipment and Sampling (IP Section 03.01) (1 Sample)

(1) The inspectors evaluated environmental monitoring equipment and observed collection of environmental samples.

Radiological Environmental Monitoring Program (IP Section 03.02) (1 Sample)

(1) The inspectors evaluated the implementation of the licensees radiological environmental monitoring program.

GPI Implementation (IP Section 03.03) (1 Sample)

(1) The inspectors evaluated the licensees implementation of the groundwater protection initiative (GPI) program to identify incomplete or discontinued program elements.

OTHER ACTIVITIES - BASELINE

===71151 - Performance Indicator Verification The inspectors verified licensee performance indicators submittals listed below:

MS06: Emergency AC Power Systems (IP Section 02.05)===

(1) Unit 1 (July 1, 2024, through June 30, 2025)
(2) Unit 2 (July 1, 2024, through June 30, 2025)

MS07: High Pressure Injection Systems (IP Section 02.06) (2 Samples)

(1) Unit 1 (July 1, 2024, through June 30, 2025)
(2) Unit 2 (July 1, 2024, through June 30, 2025)

MS09: Residual Heat Removal Systems (IP Section 02.08) (2 Samples)

(1) Unit 1 (July 1, 2024, through June 30, 2025)
(2) Unit 2 (July 1, 2024, through June 30, 2025)

71152A - Annual Follow-up Problem Identification and Resolution Annual Follow-up of Selected Issues (Section 03.03)

The inspectors reviewed the licensees implementation of its corrective action program related to the following issues:

(1)extent-of-condition review based upon AR 4865896, Unit 1 250 VDC Battery Spacing Discrepancies

OTHER ACTIVITIES

- TEMPORARY INSTRUCTIONS, INFREQUENT AND ABNORMAL

60855 - Operation of an Independent Spent Fuel Storage Installation Operation of an Independent Spent Fuel Storage Installation

(1) The inspectors evaluated the licensee's use of the Holtec multi-purpose canister (MPC) continuous basket shim (CBS) variant during a previous independent spent fuel storage installation (ISFSI) loading.

INSPECTION RESULTS

Enforcement Discretion Enforcement Action EAF-NMSS-2025-0226: Continuous Basket Shim - General Licensee Adoption of Certificate of Compliance Holder-Generated Changes under 10 CFR 72.48 (IEP 9.4)60855

Description:

Holtec International implemented a design change to its multi-purpose canister (MPC) fuel basket, known as the continuous basket shim (CBS) variant, which altered the structural configuration from welded to bolted shims. This change resulted in a departure from the method of evaluation (MOE) described in the final safety analysis report (FSAR) used to establish the design basis for tip-over events. Holtec did not fully evaluate the cumulative impact of the MOE changes or apply them consistently with the licensing basis. As a result, the NRC issued three Severity Level IV violations to Holtec for noncompliance with 10 CFR 72.48 requirements (see U.S. Nuclear Regulatory Commission Inspection Report 07201014/2022-201, Holtec International, Agency wide Documents Access and Management System (ADAMS) Accession No. ML23145A175 and Holtec International, Inc. - Notice of Violation; The U.S. Nuclear Regulatory Commission Inspection Report No. 07201014/2022-201, ADAMS Accession No. ML24016A190).

When the licensee (also referred to as a general licensee) chooses to adopt a change the Certificate of Compliance (CoC) holder made pursuant to a CoC holders change authority under 10 CFR 72.48 (referred to herein as a CoC holder-generated change,), the General Licensee (GL) must perform a separate review using the requirements of 10 CFR 72.48(c).

Accordingly, when the licensee chooses to adopt a CoC holder-generated change, and that change results in a non-conforming cask, there is a violation of 10 CFR 72.48 and certain provisions of 10 CFR 72.212 by the licensee, in addition to a CoC holder violation of 10 CFR 72.48. The licensee failed to recognize the noncompliance with 10 CFR 72.48 requirements made by the CoC holders design change and subsequently loaded the CBS variant casks.

Corrective Actions: The licensee entered this into its corrective action program to restore compliance with the 10 CFR 72.212 provisions that require each cask to conform to the terms, conditions, and specifications of a CoC or an amended CoC listed in 10 CFR Part 72.214.

Corrective Action References:

AR 4683011, Potential NRC Concern Regarding HOLTEC DCS System, dated June 6, 2023 AR 4746833, Holtec Level IV Violations for CBS Design Change, dated February 6, 2024

Enforcement:

Significance/Severity: Consistent With the guidance in Section 1.2.6.D of the NRCs Enforcement Manual, if a violation does not fit an example in the enforcement policy violation examples, it should be assigned a severity level:

(1) commensurate with its safety significance; and
(2) informed by similar violations addressed in the violation examples. The violation was evaluated to be similar to a Severity Level IV violation in Enforcement Policy Section 6.1.d.2. Since this violation meets the criteria of Section 9.4, Enforcement Discretion for General Licensee Adoption of CoC Holder-Generated Changes Under 10 CFR 72.48, of the NRC Enforcement Policy (ML25224A097), and the licensee has taken actions to restore compliance, the NRC is exercising enforcement discretion by not issuing an enforcement action for this violation.

Violation: Title 10 CFR 72.48(c)(1) states, in part, a licensee may make changes in the facility or spent fuel storage cask design as described in the FSAR (as updated), without obtaining:

(ii) a CoC amendment submitted by the certificate holder pursuant to § 72.244 if: (C) the change, test, or experiment does not meet any of the criteria in paragraph (c)(2) of this section.

Title 10 CFR 72.48(c)(2) states, in part, a GL shall request that the certificate holder obtain a CoC amendment, prior to implementing a proposed change, if the change would: (viii) result in a departure from a MOE described in the FSAR (as updated) used in establishing the design bases or in the safety analyses.

Title 10 CFR 72.48(d)(1) states, in part, that the licensee shall have a written evaluation which provides the basis for the determination that the change does not require a CoC amendment pursuant to § 72.48(c)(2).

Title 10 CFR 72.212(b)(3) states, in part, a GL must ensure that each cask used by the GL conforms to the terms, conditions, and specifications of a CoC or an amended CoC listed in

§ 72.214.

Contrary to the above, prior to December 20, 2024, the licensee failed to:

(1) request that the certificate holder obtain a CoC amendment for a change in the cask design that resulted in a departure from an MOE described in the FSAR;
(2) have a written evaluation providing the bases for the determination that the adopted change did not require a CoC Amendment; and
(3) ensure that the affected casks conformed to the terms, conditions, and specifications of the applicable CoC. Specifically, the licensee failed to identify that the CBS variant design change resulted in a departure from a MOE described in the FSAR used in establishing the design bases. The licensee did not request that the certificate holder, Holtec, obtain a CoC amendment pursuant to 10 CFR 72.244. The licensee also failed to ensure that each cask conformed to the terms, conditions, and specifications of a CoC or an amended CoC listed in 10 CFR 72.214, prior to using the CBS variant design.

Basis for Discretion: The NRC exercised enforcement discretion in accordance with Section 9.4 of the Enforcement Policy, titled Enforcement Discretion for General Licensee Adoption of Certificate of Compliance Holder-Generated Changes under 10 CFR 72.48, (ML25224A097), because the licensee met the criteria within this section. Specifically, this section states that the NRC will exercise enforcement discretion and not issue an enforcement action to a GL, for a noncompliance with the requirements of paragraphs (c)(1)and

(2) and (d)(1) of 10 CFR 72.48 and with the provisions of 10 CFR 72.212 that require GLs to ensure use of casks that conform to the terms, conditions and specifications of a CoC listed in 10 CFR 72.214, when the noncompliance results from a CoC holders failure to comply with 10 CFR 72.48 for a CoC holder-generated change. In support of the 2023 loading campaign, the licensee adopted a generic CoC holder design change (the CBS basket variant) and subsequently loaded the casks. On January 30, 2024, the NRC issued a notice of violation, identifying the noncompliance, for the generic design change associated with the CBS basket variant (ML24016A190). As a result, the licensee became noncompliant due to the CoC holders failure to comply with 10 CFR 72.48 for the CoC holder-generated change. Since this violation has been determined to be more than minor and it meets the criteria of Section 9.4 of the policy, the NRC is exercising enforcement discretion by not issuing an enforcement action for this violation.

The disposition of this violation closes URI: 05000373,05000374/2023003-01.

EXIT MEETINGS AND DEBRIEFS

The inspectors verified that no proprietary information was retained or documented in this report.

  • On November 17, 2025, the inspectors presented the integrated inspection results to John VanFleet, Site Vice President, and other members of the licensee staff.
  • On August 21, 2025, the inspectors presented the radiation protection inspection results to John VanFleet, Site Vice President, and other members of the licensee staff.
  • On September 29, 2025, the inspectors presented the ISFSI inspection results to John VanFleet, Site Vice President, and other members of the licensee staff.

DOCUMENTS REVIEWED

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

AR 4683011

Potential NRC Concern Regarding Holtec DCS System

06/06/2023

60855

Corrective Action

Documents

AR 4746833

Holtec Level IV Violations for CBS Design Change

2/06/2024

Corrective Action

Documents

AR 4827698

Increase Vibration Trend on 2B FC Motor (2FC01PB)

PeaKVue

01/06/2025

LOP-FC-02E

Unit 2 Fuel Pool Cooling System Electrical Checklist

LOP-FC-02M

Unit 2 Fuel Pool Cooling Mechanical Checklist

LOP-WS-02

Service Water Pump and Service Water Jockey Pump

Startup and Operation

LOP-WS-02M

Unit 2 Service Water System Mechanical Checklist

Procedures

LOP-WS-05

Service Water Strainer Operations

71111.04

Work Orders

WO 5613920

2FC01PB Increase Vibe Trend - Lubrication

01/09/2025

AR 4893802

Delta Crew Unannounced Fire Drill

08/28/2025

Corrective Action

Documents

AR 4893811

Romeo Crew Unannounced Fire Drill

08/21/2025

Fire Plans

FZ 4E3

Aux. Bldg. 731'-0" Elev. U1 Division 2 Essential

Switchgear Room

Miscellaneous

Fire Drill Scenario

No. 23-21

Unit 1/2 SWGR - 731 AB

71111.05

Procedures

OP-AA-201-013

Fire Brigade

71111.11Q

Procedures

LOA-RD-201

Control Rod Drive Abnormal

AR 4843211

U1 SDV Drain Valve 1C11-F381 Failed to Move During

LOS-RD-Q1

03/06/2025

AR 4866951

1A SBLC Pump Flow in Alert Range During LOS-SC-Q1

05/19/2025

71111.12

Corrective Action

Documents

AR 4882941

1C11-F380 Low Margin to Stroke Time Warning Range

07/17/2025

Corrective Action

Documents

Resulting from

Inspection

AR 4888765

Missing Work Package

08/06/2025

M-100

P&ID CRD Hydraulic Piping Sheet 2

AF

Drawings

M-100

P&ID CRD Hydraulic Piping Sheet 4

N

Engineering

Changes

EC 644635

IST Pump Evaluation for Pump 1C41-C001A

Miscellaneous

ISSUE-2025-3570

Engage Health - 1C11-F381 Maintenance Rule

Determination

05/01/2025

Procedures

LOS-SC-Q1

SBLC Pump Operability/Inservice Test and Explosive

Valve Continuity Check

WO 1861931-18

Disassemble and Inspect Check Valve

03/14/2025

WO 5540422

Contingency Replace SBLC Flowmeter per LIP-SC-502

03/14/2025

WO 5599035-03

Replace IA Regulator 1C11-F415 for 1C11-F381 Valve

03/07/2025

WO 5599035-04

PMT Testing on 1C11-F381

03/07/2025

71111.12

Work Orders

WO 5643930

IST Comprehensive Pump Test for 1C41-C001A

05/19/2025

Corrective Action

Documents

AR 4894683

DG Output Breaker Failed to Close on Unit 1

09/02/2025

09.01.2025.18.20.41

Unit 2 'A' RHR Protected System/Pathway Checklist

09/01/2025

Miscellaneous

LAS-1937-LAS

Unit 1 '0' DG Output Breaker Support/Refute Matrix

09/02/2025

ER-AA-600-1014

Risk Management Configuration Control

ER-AA-600-1042

On-Line Risk Management

71111.13

Procedures

OP-AA-108-117

Protected Equipment Program

043604(CMED)

Seismic Qual of GNB NCX-17 and NCX-27 Battery Cells

05/16/1989

Calculations

043796(CMED)

Seismic Qual of Battery Racks 1DC01E and 1&2DC14E

Due to Material Changes of Racks

05/23/1990

AR 4836829

2PC001C, C Vacuum Breaker Failed Force Check

2/12/2025

AR 4865523

NRC Identified U-1 250V Battery Discrepancies

05/13/2025

AR 4865896

NRC Identified U-1 250V Battery Discrepancies

05/14/2025

71111.15

Corrective Action

Documents

AR 4871337

Missing Seismic Test Reports for 250V Batteries

06/06/2025

AR 4880491

NRC Question - Were All SRs Met after RCIC Failure to

Trip

07/10/2025

Corrective Action

Documents

AR 4887321

Results of U2 250V Battery EOC Walkdown

07/31/2025

Corrective Action

Documents

Resulting from

Inspection

AR 4888765

Missing Work Package

08/06/2025

Drawings

1E-2-4232AL

Primary Containment & Reactor Vessel Isolation System

Part 11

Engineering

Evaluations

TE-BATT-2025-02

Evaluation of NRC-Identified Rack Issues for LaSalle

25V and 250V Batteries

Miscellaneous

J-2554

Storage Batteries and Accessories Purchase Order

08/20/1976

LOP-HP-01

Filling and Venting the High Pressure Core Spray System

LOP-LP-01

Filling and Venting, Draining the Low Pressure Core Spray

System

Procedures

LOP-RH-04

Filling, Venting, and Flushing the RHR Service Water

System

WO 5344972-13

Primary Containment Vacuum Breaker PMT

2/24/2025

WO 5577480

OP LOS-PC-Q3 D/W to S/P Vacuum Brks Test Att 2A

2/13/2024

71111.15

Work Orders

WO 5625169-02

MM Troubleshoot the 2PC001C Valve

2/24/2025

Calculations

NED-I-EIC-0158

Determination of Optimal RCIC Keep Filled Alarm Setpoint

and Associated TS Allowable Value

AR 4809723

2B RHR Service Water Pump Leak

10/16/2024

AR 4864460

2B RHR SW Pump Leak Degraded

05/09/2025

Corrective Action

Documents

AR 4879778

FLEX Hale Pump A Submersible Pipe Elbow has

Damaged End

07/08/2025

M-147

P&ID RCIC

BL

Drawings

M-85

P&ID Diesel Oil System

AE

Engineering

Changes

EC 399482

Provide M&TE Requirements for Comprehensive Pump

Tests

Miscellaneous

LOS-RI-Q3/Q5

LaSalle IST Surveillance Acceptance Criteria Manual

LOS-DG-Q1, Att. 1

DG Fuel Oil Transfer Pump Test

LOS-RI-Q5

RCIC System Pump Operability Valve Inservice Tests and

Cold Quick Start

71111.24

Procedures

MA-AA-716-230-

1002

Vibration Analysis/Acceptance Guideline

WO 1458120

Refurbish Operating Mechanism

10/13/2016

WO 1927593

Replace 2B RHR WS Pump Inboard and Outboard Seals

09/03/2025

WO 1927593-02

PMT - Perform a Functional and Leak Check for 2B RHR

WS Pump

09/04/2025

WO 5181459

EWP EM Replace 1B FC Motor

08/11/2025

WO 5181459-02

OP PMT 1FC01PB Runs Sat

08/11/2025

WO 5181459-10

MS - PMT Fuel Pool Cooling 1B Pump Motor Vibes

08/11/2025

WO 5428842

Refurbish Operating Mechanism

05/25/2025

WO 5535715

FLEX MISC EQUIPMENT ANNUAL FUNCTIONAL

SURVEILLANCE

07/09/2025

WO 5671334

Unit 2 'B' Train Residual Heat Removal Quarterly Pump

Run

08/11/2025

Work Orders

WO 5677689

LRA LOS-DG-M1 0 DG Idle Start Att 0 - Idle

07/01/2025

71114.06

Miscellaneous

08/19/2025 LaSalle

DEP Drill Package

DEP Drill Package 08/19/2025

CY-LA-170-301

Offsite Dose Calculation Manual

DTSQA

classification log ID:

EX0008268

OpenEMS

1.1

RA24-009

23 Annual Radioactive Effluent Release Report

04/26/2024

Miscellaneous

RA25-011

24 Annual Radioactive Effluent Release Report

04/25/2025

LCP-310-14

Sampling and Compositing Cooling Pond Makeup and

Blowdown Samples

Procedures

LCP-310-52

Wide Range Gas Monitor Normal Noble Gas, Iodine, and

Particulate Sampling

71124.06

Self-

Assessments

04855562

Self Assessment: Radioactive Gaseous and Liquid

Effluent

Treatment (RETS)

05/12/2025

AR 4695163

SVS WRGM Aux Sample Pump Loss

08/08/2023

AR 4734879

WWTF EQ Tank not Sampled During Week of 1/15/24

01/23/2024

AR 4736650

Fleet Gap in ANSI N13.37 Environmental Dosimetry

01/26/2024

AR 4747903

Q1 2020 Field Dosimeter Data Readings Lower than

Expected

2/07/2024

AR 4749521

Field Dosimeter Extent-of-Condition Review

2/12/2024

71124.07

Corrective Action

Documents

AR 4792598

REMP Control Dairy Location Permanently Unavailable

08/08/2024

AR 4803967

Request WR/WO to Calibrate 0XI-EM007 for 375' Wind

Direction

09/24/2024

AR 4837825

Typographical Errors in 2022 and 2023 AREOR

2/16/2025

AR 4886385

Missed ODCM Sample Required per LOP-VQ-04/ODCM

2.4.1

Land Use Census

22

Land Use Census

23

Land Use Census

24

Monthly Report on the Meteorological Monitoring Program

at the LaSalle County Nuclear Generating Station

06/17/2025

Results of Radiochemistry Cross Check Program

07/03/2025

Results of Radiochemistry Cross Check Program

05/28/2025

RA23-029

22 Annual Radiological Environmental Operating Report

05/12/2023

RA24-011

23 Annual Radiological Environmental Operating Report

05/03/2024

Miscellaneous

RA25-012

24 Annual Radiological Environmental Operating Report

05/09/2025

EN-AA-408

Radiological Groundwater Protection Program

EN-AA-408-4000

Radiological Groundwater Protection Program

Implementation

EN-LA-408-4160

RGPP Reference Material for LaSalle County Generating

Station

Procedures

LCP-140-1

Radioactivity Measurements and Corrective Action

Schedule

04750740

Self Assessment: Radiological Environmental Monitoring

Program (REMP)

10/15/2024

Self-

Assessments

NOSA-LAS-23-03

Chemistry, Radwaste, Effluent and Environmental

Monitoring Audit Report

04/05/2023

Miscellaneous

LS-MSPI-001

ROP MSPI Basis Document

ER-AA-2008

MSPI Monitoring and Margin Evaluation

71151

Procedures

ER-AA-600-1047

Mitigating Systems Performance Index Basis Document

71151

Procedures

LS-AA-2200

Mitigating System Performance Index Data Acquisition &

Reporting

AR 4865896

NRC Identified U-1 250 V Battery Discrepancies

05/14/2025

AR 4867124

EOC Walkdown for Unit 2 Div 3 Battery

05/20/2025

AR 4867154

EOC Walkdown for Unit 1 Div 1 125 V Battery

05/20/2025

AR 4867155

EOC Walkdown for Unit 1 Div 2 125 V Battery

05/20/2025

AR 4867156

EOC Walkdown for Unit 2 Div 1 125 V Battery

05/20/2025

AR 4867157

EOC Walkdown for Unit 2 Div 2 125 V Battery

05/20/2025

AR 4867159

EOC Walkdown for Unit 2 250 V Battery

05/20/2025

AR 4867160

EOC Walkdown for Unit 1 Div 3 125 V Battery

05/20/2025

Corrective Action

Documents

AR 4894683

DG Output Breaker Failed to Close on Unit 1

09/02/2025

ER-AA-200

Preventative Maintenance Program

ER-AA-200-1001

Equipment Classification

Procedures

LEP-DC-106

Installation of 250 Volt Batteries

71152A

Work Orders

WO 4917327

Replace Unit 1 250VDC Battery 1DC01E

05/06/2024