IR 05000373/2025002

From kanterella
Jump to navigation Jump to search
County Station Integrated Inspection Report 05000373/2025002 and 05000374/2025002
ML25223A298
Person / Time
Site: LaSalle  Constellation icon.png
Issue date: 08/11/2025
From: Robert Ruiz
NRC/RGN-III/DORS/RPB1
To: Rhoades D
Constellation Energy Generation
References
IR 2025002
Download: ML25223A298 (1)


Text

SUBJECT:

LASALLE COUNTY STATION - INTEGRATED INSPECTION REPORT 05000373/2025002 AND 05000374/2025002

Dear David Rhoades:

On June 30, 2025, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at LaSalle County Station. On July 9, 2025, the NRC inspectors discussed the results of this inspection with John VanFleet, Site Vice President, and other members of your staff. The results of this inspection are documented in the enclosed report.

No findings or violations of more than minor significance were identified during this inspection.

This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations 2.390, Public Inspections, Exemptions, Requests for Withholding.

Sincerely, Robert Ruiz, Chief Reactor Projects Branch 1 Division of Operating Reactor Safety Docket Nos. 05000373 and 05000374 License Nos. NPF-11 and NPF-18

Enclosure:

As stated

Inspection Report

Docket Numbers:

05000373 and 05000374

License Numbers:

NPF-11 and NPF-18

Report Numbers:

05000373/2025002 and 05000374/2025002

Enterprise Identifier:

I-2025-002-0055

Licensee:

Constellation Nuclear

Facility:

LaSalle County Station

Location:

Marseilles, IL

Inspection Dates:

April 01, 2025, to June 30, 2025

Inspectors:

M. Abuhamdan, Reactor Inspector

J. Benjamin, Senior Resident Inspector

J. Hoang, Reactor Technology Instructor

R. Zuffa, Illinois Emergency Management Agency

Approved By:

Robert Ruiz, Chief

Reactor Projects Branch 1

Division of Operating Reactor Safety

SUMMARY

The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees performance by conducting an integrated inspection at LaSalle County Station, in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information.

List of Findings and Violations

No findings or violations of more than minor significance were identified.

Additional Tracking Items

Type Issue Number Title Report Section Status LER 05000373/2024-004-01 LER 2024-004-01,

Supplement to Emergency Diesel Generator Auto-Start and Load due to Loss of System Auxiliary Transformer 71153 Closed

PLANT STATUS

Unit 1 began the inspection period at rated thermal power. On April 4, 2025, the unit down powered to approximately 60 percent to perform a reactor control rod pattern adjustment and main turbine control valve testing. The unit returned to full power on April 7, 2025. On June 28, 2025, the unit derated to approximately 90 percent power to ensure adequate main condenser vacuum margin during hot weather conditions coupled with degraded main condenser performance. The unit operated at approximately 90 to 95 percent for the remainder of the inspection period.

Unit 2 began the inspection period at rated thermal power. On May 17, 2025, the unit down powered to approximately 76 percent to perform control rod testing. The unit returned to full power on May 18, 2025, and operated at full power for the remainder of the cycle.

INSPECTION SCOPES

Inspections were conducted using the appropriate portions of the inspection procedures (IPs) in effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with their attached revision histories are located on the public website at http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html. Samples were declared complete when the IP requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter (IMC) 2515, Light-Water Reactor Inspection Program - Operations Phase. The inspectors performed activities described in IMC 2515, Appendix D, Plant Status, observed risk significant activities, and completed on-site portions of IPs. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess licensee performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards.

REACTOR SAFETY

71111.01 - Adverse Weather Protection

Seasonal Extreme Weather Sample (IP Section 03.01) (1 Sample)

(1)station summer readiness: Unit 1 main condenser performance and Unit 2A train emergency diesel generator (EDG) jack water heat exchanger

71111.04 - Equipment Alignment

Partial Walkdown Sample (IP Section 03.01) (3 Samples)

The inspectors evaluated system configurations during partial walkdowns of the following systems/trains:

(1) Unit Common EDG following 2-year planned preventative maintenance out of service on May 9, 2025
(2) Unit 1 residual heat removal (RHR) service water system following system outage window on June 5, 2025
(3) Unit 1 switchgear heat removal system (VX) on June 9, 2025

Complete Walkdown Sample (IP Section 03.02) (1 Sample)

The inspectors evaluated system configurations during complete walkdowns of the following systems/trains:

(1) Unit 2 hardened containment vent system (HCVS) on June 11, 2025

71111.05 - Fire Protection

Fire Area Walkdown and Inspection Sample (IP Section 03.01) (7 Samples)

The inspectors evaluated the implementation of the fire protection program by conducting a walkdown and performing a review to verify program compliance, equipment functionality, material condition, and operational readiness of the following fire areas:

(1) Fire Zone (FZ) 3H4, reactor building, elevation 694'-6", Unit 2 reactor core isolation cooling (RCIC)/low-pressure core spray (LPCS) cubicle on June 3, 2025
(2) FZ 4E2, auxiliary building, elevation 731'-0", Unit 2 auxiliary equipment room on June 4, 2025
(3) FZ 2I, reactor building, elevation 673'-4", Unit 1 LPCS/RCIC pump cubicle on June 4, 2025
(4) FZ 4D3, auxiliary building, elevation 749'-0", Unit 1 electrical equipment room on June 4, 2025
(5) FZ 4D4, auxiliary building, elevation 749'-0", Unit 2 electrical equipment room on June 4, 2025
(6) FZ 2E, reactor building, elevation 761'-0", Unit 1 general area on June 5, 2025
(7) FZ 3F, reactor building, elevation 740'-0", Unit 2 general area on June 6, 2025

71111.06 - Flood Protection Measures

Flooding Sample (IP Section 03.01) (2 Samples)

The inspectors evaluated internal flooding mitigation protections in the:

(1) Unit 1 AB core standby cooling system (CSCS) pump rooms on June 16, 2025
(2) Unit 2 AB CSCS pump rooms on June 17, 2025

71111.11Q - Licensed Operator Requalification Program and Licensed Operator Performance

Licensed Operator Performance in the Actual Plant/Main Control Room (IP Section 03.01) (1 Sample)

(1) The inspectors observed and evaluated licensed operator performance in the control room during power ascension following an unplanned downpower due to high condenser backpressure on June 30, 2025.

Licensed Operator Requalification Training/Examinations (IP Section 03.02) (1 Sample)

(1) The inspectors observed and evaluated an out-of-the-box training activity on April 22, 2025.

71111.12 - Maintenance Effectiveness

Maintenance Effectiveness (IP Section 03.01) (3 Samples)

The inspectors evaluated the effectiveness of maintenance to ensure the following structures, systems, and components (SSCs) remain capable of performing their intended function:

(1) Unit 2A train EDG
(2) Action Request (AR) 4846342, Rising 2A Reactor Recirculation Pump #2 Seal Pressure Trend
(3) Unit 2A and 'B' trains EDG cooling water pumps

71111.13 - Maintenance Risk Assessments and Emergent Work Control

Risk Assessment and Management Sample (IP Section 03.01) (5 Samples)

The inspectors evaluated the accuracy and completeness of risk assessments for the following planned and emergent work activities to ensure configuration changes and appropriate work controls were addressed:

(1)elevated Unit 1 risk on April 1, 2025, during division 1 work window with RHR system and low-pressure coolant injection inoperable (2)elevated Unit 2 risk on April 8, 2025, during Unit 2B train RHR system planned work window (3)elevated Unit 2 risk on April 21, 2025, during Unit 2 division 3 125 Vdc battery performance testing (4)elevated Unit 1 and Unit 2 risk from May 5, 2025, through May 7, 2025, during unit Common EDG planned work window (5)elevated Unit 2 risk from May 19, 2025, through May 20, 2025, during Unit 2 division 3 work window

71111.15 - Operability Determinations and Functionality Assessments

Operability Determination or Functionality Assessment (IP Section 03.01) (8 Samples)

The inspectors evaluated the licensee's justifications and actions associated with the following operability determinations and functionality assessments:

(1) AR 4853964, MOV [motor-operated valve] 2E12-F003B As-Found Under Thrust
(2) AR 4846342, Rising 2A Reactor Recirculation Pump Seal #2 Adverse Trend
(3) AR 4857391, 'B' Diesel-Driven Fire Pump Failure to Start on Remote Start Signal from the Main Control Room
(4) AR 4861597, Unit 1 'B' Train Residual Heat Removal Heat Exchange Service Water Side Through Wall Leak
(5) AR 4861260, LOA-WL-001 Entry Due to Low Lake Level
(6) AR 4868809, Unit 2 Reactor Core Isolation Cooling Water Pump Suction Pressure Higher Than Normal
(7) AR 4868178, U1 RBM [rod-block monitor] Recorder Reading Low
(8) AR 4875675, ADS [automatic depressurization system) Valve Solenoid Lights Out 2B21C-S013A (Continuity Lights on Panel 2H13-P628)

71111.24 - Testing and Maintenance of Equipment Important to Risk

The inspectors evaluated the following testing and maintenance activities to verify system operability and/or functionality:

Post-Maintenance Testing (PMT) (IP Section 03.01) (5 Samples)

(1) Unit Common 'B' train diesel driven fire pump after upgrade during the week of February 3, 2025
(2) Unit 1B train RHR service water leak repair on May 4, 2025
(3) Unit Common EDG cooling water pump planned maintenance on May 7, 2025
(4) Unit Common EDG 2-year maintenance work on May 7, 2025
(5) Unit 2 division 3 work window May 19 through May 20, 2025

Surveillance Testing (IP Section 03.01) (5 Samples)

(1) Work Order (WO) 4745806, Motor Operated Valve 2E12-F003B Diagnostic Testing
(2) Unit 2 division 3 125 Vdc battery performance testing on April 21, 2025
(3) Unit 1B train EDG run on April 24, 2025
(4) Unit 1 division 2 RHR service water system operability and inservice testing on June 1, 2025
(5) Unit 1 RHR 'B' train pump operability on June 27, 2025

Inservice Testing (IST) (IP Section 03.01) (1 Sample)

(1) Unit 1 RCIC valve inservice test on June 10, 2025

71114.06 - Drill Evaluation

Required Emergency Preparedness Drill (1 Sample)

(1) April 18, 2025, drill and exercise performance (DEP) drill

Additional Drill and/or Training Evolution (1 Sample)

The inspectors evaluated:

(1) April 24, 2025, DEP drill

OTHER ACTIVITIES - BASELINE

===71151 - Performance Indicator Verification The inspectors verified licensee performance indicators submittals listed below:

BI02: RCS Leak Rate Sample (IP Section 02.11)===

(1) Unit 1 (April 1, 2024, through March 31, 2025)
(2) Unit 2 (April 1, 2024, through March 31, 2025)

71152A - Annual Follow-Up Problem Identification and Resolution Annual Follow-Up of Selected Issues (Section 03.03)

The inspectors reviewed the licensees implementation of its corrective action program related to the following issues:

(1) AR 4853657, Second Fuel Defect Suppressed at LaSalle
(2) AR 4849266, 2A RR [reactor recirculation] Pump Seal Cavity #2 Pressure Trend
(3) AR 4867317, Rosemount Transmitters Static Shift Concern

71152S - Semiannual Trend Problem Identification and Resolution Semiannual Trend Review (Section 03.02)

(1) The inspectors reviewed the licensees corrective action program to identify potential trends in human performance that might be indicative of a more significant safety issue. No potential adverse trends were identified.

71153 - Follow Up of Events and Notices of Enforcement Discretion Event Report (IP Section 03.02)

The inspectors evaluated the following licensee event reports (LERs):

(1) LER 05000373/2024-004-01, Supplement to Emergency Diesel Generator Auto-Start and Load due to Loss of System Auxiliary Transformer (Agencywide Document Access and Management System (ADAMS) Accession No. ML24235A178). The inspectors determined that the cause of the condition described in the LER was not reasonably within the licensees ability to foresee and correct and therefore was not reasonably preventable. No performance deficiency nor violation of NRC requirements was identified. This LER is closed.

INSPECTION RESULTS

No findings were identified.

EXIT MEETINGS AND DEBRIEFS

The inspectors verified that no proprietary information was retained or documented in this report.

  • On July 9, 2025, the inspectors presented the integrated inspection results to John VanFleet, Site Vice President, and other members of the licensee staff.

DOCUMENTS REVIEWED

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

71111.01

Procedures

LOS-ZZ-A2

Preparation for Winter Summer Operation

AR 4423492

U1 Div 1 Supply Fan Trip

05/13/2021

Corrective Action

Documents

AR 4857602

U1 Div 1 VX Abnormal Noise

04/16/2025

1E-1-4081ZF

Schematic Diagram Hardened Containment Vent System

(HCVS)

A

1E-1-4081ZG

Schematic Diagram Hardened Containment Vent System

(HCVS)

A

M-138, Sheet 3

P&ID Primary Containment Vent and Purge

B

M-5092, Sheet 1

Logic Block Diagram Primary Containment Vent and Purge

System "PC"

G

M-959, Sheet 4

Primary Containment and Reactor Vessel Isolation Piping

System

A

Drawings

P&ID M-134

CSCS Equipment Cooling Water System

BH

LOP-DG-03M

Unit 0 Diesel Generator Mechanical Checklist

LOP-PC-04E

Unit 2 Hardened Containment Vent System Electrical

Checklist

LOP-PC-04M

Unit 2 Hardened Containment Vent System Mechanical

Checklist

LOP-RH-05

Operation of the RHR Service Water System

LOP-VX-01

Switchgear Heat Removal System Startup

71111.04

Procedures

LOP-VX-01E

Unit 1 Switchgear Heat Removal System Electrical Checklist

PFP AUX BLDG

731-0, Fire Zone

4E2

Pre-Fire Plan U2 Auxiliary Equipment Room

PFP AUX BLDG

749-0, Fire Zone

4D3

Pre-Fire Plan U1 Electrical Equipment Room

71111.05

Fire Plans

PFP AUX BLDG

749-0, Fire Zone

4D4

Pre-Fire Plan U2 Electrical Equipment Room

PFP RX BLDG

673-4, Fire Zone

2I

Pre-Fire Plan U1 LPCS /RCIC Pump Cubicle

PFP RX BLDG

694-6, Fire Zone

3H4

Pre-Fire Plan U2 RCIC/LPCS Cubicle

PFP RX BLDG

740-0, Fire Zone

3F

Pre-Fire Plan U2 General Area & CRD Repair Room

Fire Plans

PFP RX BLDG

761-0, Fire Zone

2E

Pre-Fire Plan U1 General Area & RWCU Pump Cubicles

ER-AA-600-1069

High Risk Fire Area Identification

LOP-FP-02M

Unit 2 Fire Protection System Mechanical Checklist

MA-AA-716-025,

Scaffold Installation, Modification, and Removal Request

Process

OP-AA-201-009

Control of Transient Combustible Material

OP-AA-201-103

Fire Drill Performance

71111.05

Procedures

OP-LA-201-012-

1001

LaSalle On-Line Fire Risk Management

Corrective Action

Documents

AR 4866742

U1 D3 CSCS Sump - Neither Sump Pump Removes Water,

Equipment Deficiency Tag (EDT) 151905

05/18/2025

Engineering

Changes

EC 625825

LaSalle Mitigating Strategies Flood Hazard Assessment

(MSFHA) and Supporting Documents, L-004286

DBD-LS-M11

Topical Design Basis Document Flood Protection

F

LS-PRA-012

LaSalle County Generating Station Probabilistic Risk

Assessment Internal Flood Analysis Volume 1 of 2:

Summary and Notebook

71111.06

Miscellaneous

LS-PRA-012

LaSalle County Generating Station Probabilistic Risk

Assessment Internal Flood Analysis Volume 2 of 2: Flood

Walkdown Notebook

UFSAR Appendix

J

J.4 Effects of Flooding

UFSAR Chapter

03, Section 04

Figures

UFSAR Chapter

2.4

Hydrologic Engineering

Miscellaneous

UFSAR Chapter

3.4

Water Level (Flood) Design

CC-AA-201

Plant Barrier Control Program

CC-LA-201-1001

Plant Barrier Control Program Implementation

ER-LA-450

LaSalle Structures Monitoring Program

LOA-FLD-001

Operating Abnormal Procedure - Flooding

71111.06

Procedures

TRM 3.5.a

ECCS Corner Room Watertight Doors

Miscellaneous

LORT Simulator

Scenario - April

2, 2025

LORT Training Performed on April 22, 2025 in Simulator

71111.11Q

Procedures

REMA L1C21-03

Reactivity Maneuver LaSalle Unit 1 Cycle 21-03

06/30/2025

AR 4556777

2A DG Cooling Water Strainer Found Continuously

Backwashing

2/23/2023

AR 4561537

LOS-DG-M1 DG Engine Cooling Water to Oil Cooler Limit

03/13/2023

AR 4666885

2PM01J-B206 2A DG Trouble Alarm

04/01/2023

AR 4669892

2A DG Starting Air Pressure PPC D825 Alarm

04/13/2023

AR 4670248

2A DG CWP d/p Outside Surveillance Criteria

04/15/2023

AR 4670248

2A DG CWP d/p Outside Surveillance Criteria

04/15/2023

AR 4683216

2A DG Cooling Water Strainer DP High Alarm

06/07/2023

AR 4809919

2A DG Exciter Diode Replacement

10/16/2024

Corrective Action

Documents

AR 4846342

Raising Pressure Trend on RR Pump Seals

03/18/2025

ER-AA-310-1002

Maintenance Rule Functions - Safety Significance

Classification

ER-AA-310-1008

Exelon Maintenance Rule Process Map

ER-AA-320

Maintenance Rule Implementation Per NEI 18-10

ER-AA-320-1003

Maintenance Rule 18-10 Failure Definition

71111.12

Procedures

ER-AA-320-1004

Maintenance Rule - (A)(1) and (A)(2) Requirements

ER-AA-320-1006

Maintenance Rule 18-10 - Expert Panel Roles and

Responsibilities

Procedures

ER-AA-600-1044

Maintenance Rule Support

71111.12

Work Orders

ACMP Unit 2 RR

Pump Seal

Issues

2A Reactor Recirculation Pump Seal Cavity #2 Adverse

Pressure Trend

03/26/2025

AD-AA-3000

Nuclear Risk Management Process

ER-AA-600-1012

Risk Management Documentation

ER-AA-800-1042

On-Line Risk Management

OP-AA-107

Integrated Risk Management

OP-AA-201-012

Operations On-Line Fire Risk Management

OP-LA-201-012

LaSalle On-Line Fire Risk Management

71111.13

Procedures

WC-AA-101-1006

On-Line Risk Management and Assessment

AR 2493439

During LIS-NR-105B, Found RBM 'B' Not Functioning

Properly

04/30/2025

AR 4853964

MOV 2E12-F003B As-Found Underthrust

04/07/2025

AR 4857391

'B' DFP Failure to Start on a Remote Start Signal

04/15/2025

AR 4861597

Through Wall Leak, WS Side of Outlet Piping of U1 B RHR

HX

04/29/2025

AR 4868178

U1 RBM Recorder Reading Low

05/23/2025

AR 4868809

U2 RCIC Pump Suction Pressure Indicated High

05/28/2025

Corrective Action

Documents

AR 4875675

ADS Valve Solenoid Lights Out 2B21C-S013A

06/24/2025

Corrective Action

Documents

Resulting from

Inspection

AR 4846342

Raising Pressure Trend on RR Pump Seals

03/18/2025

Drawings

1E-2-4201AG

Schematic Diagram Auto Depressurization System NB B21C

Part 7

R

LOA-WL-001

River Screen House and Lake Abnormal

OP-AA-108-104

Technical Specification Compliance

OP-AA-108-115

Operability Determination

OP-AA-108-115

Operability Determinations (CM-1)

71111.15

Procedures

Tech Spec 3.3.2.1

Control Rod Block Instrumentation

06/12/2025

WO 4745806

Perform EQ Inspection and Votes Test

04/07/2025

71111.15

Work Orders

WO 5540732

U1 B RBM Recorder Indication Erratic and Not Normal

06/12/2025

OP-AA-102-107-

1001

Operations On-Line Work Management

WC-AA-101

On-Line Work Control Process

Procedures

WC-AA-106

Work Screening and Processing

WO 4745806

MOV 2E12-F000B VOTES Diagnostic Testing

04/07/2026

WO 5255030

Disassemble, Inspect 0 DG Heat Exchanger

05/05/2025

WO 5371978

Unit 2 Division 3 Battery Charger Inspection and Cleaning

05/25/2025

WO 5515524

Unit 2 Division III 125VDC Battery Performance Testing

04/21/2025

WO 5591064

1B DG 24-HR Run Surveillance

04/24/2025

WO 5634076

LOS-RH-Q1 1B RHR WS Operability & Inservice Testing

06/26/2025

WO 5636250

LOS-RI-Q1 U1 RCIC Valves

06/10/2025

WO 5649219

LOS-RH-Q1 1B RHR Att. 1B - Unit 1 RHR B Quarterly

Surveillance Run

06/27/2025

71111.24

Work Orders

WO 5658583

1B RHR-WS Leak Repair and Drain

05/01/2025

April 18, 2025 EP

Drill Package

Drill Package 4/18/2025

71114.06

Miscellaneous

April 25, 2025

LaSalle DRP Drill

Package

DEP Drill 4/25/2025

71151

Procedures

SP-AA-3000

Exelon Nuclear Performance Monitoring and Management

Implementation Guide

Calculations

L-001345

Average Power Range Monitor (APRM), Rod Block Monitor

(RBM), and Recirculation Flow Monitor (RFM) Bistable Loop

Accuracy for Rod Block and Scram Functions

AR 4849266

2A RR Pump Seal Cavity #2 Pressure Trend

03/27/2025

AR 4853657

Second Fuel Defect Suppressed at LaSalle

04/06/2025

AR 4853657

RM - Second Fuel Defect Suppressed in LaSalle Unit 1

04/06/2025

Corrective Action

Documents

AR 4867317

Pressure Transmitter Static Shift Concern

05/20/2025

Engineering

Evaluations

NES-EIC-20.04

Analysis of Instrument Channel Setpoint and Instrument

Loop Accuracy

07/18/2011

Miscellaneous

R369-0297

Binder J-0223

Rosemont Transmitters

71152A

Procedures

LIS-RR-101A

Unit1 Recirculation Flow Converter A Calibration

LIS-RR-201A

Recirculation Flow Converter A Calibration

NF-AB-140

BWR Fuel Conditioning

OP-AB-300-1003

BWR Reactivity Maneuver Guidance

PI-AA-125

Corrective Action Program (CAP) Procedure

WO 1629301

Replace Electrolytic Capacitors in ABB Flow Units

2/19/2025

Work Orders

WO 5556815

Recirculation Flow Converter 'A' Calibration

01/15/2025

AR 4673746

Operations Trending in Human Performance

04/28/2023

AR 4680675

Operations Trend in Communications

05/25/2023

AR 4684120

Maintenance Trend: MMD Attention to Detail

06/12/2023

AR 4684729

Operations Trend - Place Keeping Behaviors

06/14/2023

AR 4694181

Trend in Self-Check Behaviors

08/02/2023

AR 4710907

Ops Trend: Attention to Detail Less than Adequate

10/19/2023

AR 4719308

Maintenance Trend in Maintenance Work Preparations

11/22/2023

AR 4722841

Trend in Control of CDA

2/11/2023

AR 4752387

Emerging Trend - At Risk Safety Behaviors

2/22/2024

71152S

Corrective Action

Documents

AR 4854404

Operations MRM Trend IR

04/08/2025