SUBJECT:
JOSEPH M. FARLEY NUCLEAR PLANT, UNITS 1&2 - SECURITY BASELINE INSPECTION REPORT 05000348/2024403 AND 05000364/2024403
Dear Jamie M. Coleman:
On November 7, 2024, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at Joseph M. Farley Nuclear Plant, Units 1&2 and discussed the results of this inspection with Edwin Dean and other members of your staff. The results of this inspection are documented in the enclosed report.
No findings or violations of more than minor significance were identified during this inspection.
This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations 2.390, Public Inspections, Exemptions, Requests for Withholding.
Sincerely, Jannette G. Worosilo, Chief Nuclear Security Branch Division of Fuels, Radiological Safety, and Security Docket Nos. 05000348 and 05000364 License Nos. NPF-2 and NPF-8
Enclosure:
As stated
Inspection Report
Docket Numbers:
05000348 and 05000364
License Numbers:
Report Numbers:
05000348/2024403 and 05000364/2024403
Enterprise Identifier:
I-2024-403-0033
Licensee:
Southern Nuclear Operating Co., Inc.
Facility:
Joseph M. Farley Nuclear Plant, Units 1&2
Location:
Columbia, AL
Inspection Dates:
November 04, 2024 to November 07, 2024
Inspectors:
J. Justice, Senior Physical Security Inspector
Approved By:
Jannette G. Worosilo, Chief
Nuclear Security Branch
Division of Fuels, Radiological Safety, and Security
SUMMARY
The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees performance by conducting a security baseline inspection at Joseph M. Farley Nuclear Plant,
Units 1&2, in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors.
Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information.
List of Findings and Violations
No findings or violations of more than minor significance were identified.
Additional Tracking Items
None.
INSPECTION SCOPES
Inspections were conducted using the appropriate portions of the inspection procedures (IPs) in effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with their attached revision histories are located on the public website at http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html. Samples were declared complete when the IP requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter (IMC) 2201, Security Inspection Program for Commercial Nuclear Power Reactors. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess licensee performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards.
SAFEGUARDS
71130.02 - Access Control
The inspectors evaluated the access control program through completion of the following
inspection elements: Access Control
(1)
- Tier I: All Requirements
- Tier II: 02.06(a-c), 02.07(a), 02.08(a,b,c,e,i)
- Tier III: 02.10(a)
71130.09 - Security Plan Changes
The inspectors evaluated the security plan changes through completion of the following
procedure elements: Security Plan Changes
- (1) Since the last NRC baseline inspection of this program area, Security Plan Revision 18-FNP-3 was implemented, based on Southern Nuclear Operating Company's evaluation, and in accordance with 10 CFR 50.54(p)(2), that the changes resulted in no decrease in safeguards effectiveness of the security plan and the revised security plan continues to meet the requirements of 10 CFR 73.55(b). The inspector conducted a review of the security plan changes to evaluate for a potential decrease in safeguards effectiveness of the security plan; however, this review does not constitute formal NRC approval of those changes. Therefore, the changes remain subject to future NRC inspection in their entirety.
OTHER ACTIVITIES - BASELINE
71151 - Performance Indicator Verification The inspectors verified licensee performance indicators submittals listed below:
PP01: Protected Area Security Equipment Performance Index Sample (IP Section 02.17) (1 Sample)
- (1) August 2023 - October
INSPECTION RESULTS
No findings were identified.
EXIT MEETINGS AND DEBRIEFS
The inspectors verified no proprietary information was retained or documented in this report.
- On November 7, 2024, the inspectors presented the security baseline inspection results to Edwin Dean and other members of the licensee staff.
DOCUMENTS REVIEWED
Inspection
Procedure
Type
Designation
Description or Title
Revision or
Date
Corrective Action
Documents
11125737
11125736
11125732
11125021
11125041
11125830
FNP-0-SP-37.0
Threat Assessment and Security Force Protection
Recommendations
Rev 14
FNP-0-SP-9.0
Lock and Key Control Procedures
Rev 21
NMP-AD-013
Control of Safeguards Information - (SGI)
Rev 5.2
NMP-EP-144
Protective Actions
Rev 11
NMP-SE-021
Security Search Processes
Rev 16
NMP-SE-021-001
Security Sealing Operations Instruction
Rev 2
Procedures
NMP-SE-023
Personnel Authorization and Badging Program
Rev 6
Fleet-SEC-2024
24 Nuclear Oversight Security Audit
05/03/2024
Self-Assessments
TE# 1113774
Pre-NRC Routine Baseline Inspection Readiness (Access
Control, Security Plan Changes, PI Verification, and
Protective Strategy)
03/21/2024
Farley Nuclear Plant, Units 1&2, Physical Security Plan
Rev 18-FNP-
Procedures
FNP-0-SP-34.0
FNP Security Response
Rev 30
71151
Self-Assessments NMP-AD-034
Key Performance Indicators
Rev 13.2