|
---|
Category:Letter
MONTHYEARIR 05000346/20240032024-11-14014 November 2024 Integrated Inspection Report 05000346/2024003 ML24303A3282024-10-29029 October 2024 Information Request for the Cyber Security Baseline Inspection Identification to Perform Inspection ML24281A0662024-10-0404 October 2024 EN 57363 - MPR Associates, Inc. Report in Accordance with 10 CFR Part 21 on Incomplete Dedication of Contactors Supplied as Basic Components IR 05000346/20244032024-09-27027 September 2024 Security Baseline Inspection Report 05000346/2024403 ML24269A0552024-09-25025 September 2024 Submittal of the Updated Final Safety Analysis Report, Revision 35 05000346/LER-2021-001-01, Emergency Diesel Generator Speed Switch Failure Due to Direct Current System Ground2024-09-19019 September 2024 Emergency Diesel Generator Speed Switch Failure Due to Direct Current System Ground ML24134A1522024-09-17017 September 2024 Exemption from the Requirements of 10 CFR 50.71(e)(4) Final Safety Analysis Report Update Schedule (EPID L-2024-LLE-0005) - Letter ML24260A2382024-09-16016 September 2024 Notification of an NRC Biennial Licensed Operator Requalification Program Inspection and Request for Information ML24255A8032024-09-11011 September 2024 Technical Specification 5.6.6 Steam Generator Tube Inspection 180-Day Report ML24255A8642024-09-0606 September 2024 Rscc Wire & Cable LLC Dba Marmon Industrial Energy & Infrastructure - Part 21 Retraction of Final Notification ML24249A1602024-09-0505 September 2024 Information Request to Support Upcoming Material Control and Accounting Inspection at Davis-Besse Nuclear Power Station L-24-188, Submittal of Quality Assurance Program Manual, Revision 302024-08-27027 August 2024 Submittal of Quality Assurance Program Manual, Revision 30 ML24239A3972024-08-23023 August 2024 Rssc Wire & Cable LLC Dba Marmon - Part 21 Final Notification - 57243-EN 57243 IR 05000346/20240052024-08-22022 August 2024 Updated Inspection Plan for Davis-Besse Nuclear Power Station (Report 05000346/2024005) L-24-186, Response to RAI for Exemption Request from 10 CFR 50.71(e)(4) Final Safety Analysis Update Schedule2024-08-15015 August 2024 Response to RAI for Exemption Request from 10 CFR 50.71(e)(4) Final Safety Analysis Update Schedule IR 05000346/20240022024-08-0101 August 2024 Integrated Inspection Report 05000346/2024002 IR 05000346/20244012024-07-30030 July 2024 Security Baseline Inspection Report 05000346/2024401 ML24208A0962024-07-25025 July 2024 57243-EN 57243 - Rssc Wire & Cable LLC, Dba Marmon - Part 21 Notification L-24-032, Cycle 23 and Refueling Outage 23 Inservice Inspection Summary Report2024-07-15015 July 2024 Cycle 23 and Refueling Outage 23 Inservice Inspection Summary Report L-24-063, License Amendment Request to Remove the Table of Contents from the Technical Specifications2024-07-0808 July 2024 License Amendment Request to Remove the Table of Contents from the Technical Specifications L-24-024, Annual 10 CFR 50.46 Report of Changes to or Errors in Emergency Core Cooling System Evaluation Models2024-06-19019 June 2024 Annual 10 CFR 50.46 Report of Changes to or Errors in Emergency Core Cooling System Evaluation Models L-23-214, Submittal of Relief Request for Impractical American Society of Mechanical Engineers Boiler and Pressure Vessel Code Section XI Examination Requirements2024-06-0505 June 2024 Submittal of Relief Request for Impractical American Society of Mechanical Engineers Boiler and Pressure Vessel Code Section XI Examination Requirements L-24-019, Unit No.1 - Report of Facility Changes, Tests, and Experiments2024-05-22022 May 2024 Unit No.1 - Report of Facility Changes, Tests, and Experiments ML24142A3532024-05-21021 May 2024 Station—Information Request to Support the NRC Annual Baseline Emergency Action Level and Emergency Plan Changes Inspection L-24-072, Combined Annual Radiological Environmental Operating Report and Radioactive Effluent Release Report - 20232024-05-15015 May 2024 Combined Annual Radiological Environmental Operating Report and Radioactive Effluent Release Report - 2023 L-24-111, Response to Regulatory Issue Summary 2024-01, Preparation and Scheduling of Operator Licensing Examinations2024-05-15015 May 2024 Response to Regulatory Issue Summary 2024-01, Preparation and Scheduling of Operator Licensing Examinations L-24-031, Unit No.1 - Steam Generator Tube Circumferential Crack Report - Spring 2024 Refueling Outage2024-05-14014 May 2024 Unit No.1 - Steam Generator Tube Circumferential Crack Report - Spring 2024 Refueling Outage IR 05000346/20240012024-05-0303 May 2024 Integrated Inspection Report 05000346/2024001 L-24-069, Occupational Radiation Exposure Report for Year 20232024-04-30030 April 2024 Occupational Radiation Exposure Report for Year 2023 L-24-018, Submittal of Core Operating Limits Report, Cycle 24, Revision 02024-04-16016 April 2024 Submittal of Core Operating Limits Report, Cycle 24, Revision 0 ML24089A2582024-04-0101 April 2024 Request for Information for the NRC Quuadrennial Comprehensive Engineering Team Inspection: Inspection Report 05000346/2024010 L-24-013, Annual Notification of Property Insurance Coverage2024-03-26026 March 2024 Annual Notification of Property Insurance Coverage ML24036A3472024-03-0707 March 2024 Exemption from Select Requirements of 10 CFR Part 73 (EPID L-2023-LLE-0076 (Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting)) ML24057A0752024-03-0101 March 2024 The Associated Independent Spent Fuel Storage Installations IR 05000346/20230062024-02-28028 February 2024 Re-Issue Annual Assessment Letter for Davis-Besse Nuclear Power Station (Report 05000346/2023006) ML24057A3362024-02-28028 February 2024 Annual Assessment Letter for Davis-Besse Nuclear Power Station (Report 05000346/2023006) L-23-264, Request for Exemption from 10 CFR 50.71(e)(4) Final Safety Analysis Report Update Schedule2024-02-23023 February 2024 Request for Exemption from 10 CFR 50.71(e)(4) Final Safety Analysis Report Update Schedule CP-202300502, Notice of Planned Closing of Transaction and Provision of Documents to Satisfy Order Conditions2024-02-23023 February 2024 Notice of Planned Closing of Transaction and Provision of Documents to Satisfy Order Conditions L-24-050, Retrospective Premium Guarantee2024-02-22022 February 2024 Retrospective Premium Guarantee IR 05000346/20243012024-02-0202 February 2024 NRC Initial License Examination Report 05000346/2024301 IR 05000346/20230042024-01-31031 January 2024 Integrated Inspection Report 05000346/2023004 ML23313A1352024-01-17017 January 2024 Authorization and Safety Evaluation for Alternative Request RP 5 for the Fifth 10 Year Interval Inservice Testing Program ML23353A1192023-12-19019 December 2023 Operator Licensing Examination Approval Davis Besse Nuclear Power Station, January 2024 L-23-260, Corrections to the 2022 Combined Annual Radiological Environmental Operating Report and Radioactive Effluent Release Report for the Davis-Besse Nuclear Power Station2023-12-0707 December 2023 Corrections to the 2022 Combined Annual Radiological Environmental Operating Report and Radioactive Effluent Release Report for the Davis-Besse Nuclear Power Station L-23-243, Independent Spent Fuel Storage Installation - Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation2023-12-0606 December 2023 Independent Spent Fuel Storage Installation - Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation ML23338A3172023-12-0606 December 2023 Notification of NRC Baseline Inspection and Request for Information; Inspection Report 05000346/2024001 IR 05000346/20234032023-11-0202 November 2023 Security Baseline Inspection Report 05000346/2023403 ML23293A0612023-11-0101 November 2023 Letter to the Honorable Marcy Kaptur, from Chair Hanson Responds to Letter Regarding Follow Up on Concerns Raised by Union Representatives During the June Visit to the Davis-Besse Nuclear Power Plant ML24045A0322023-10-26026 October 2023 L-23-221 Proposed Exam Submittal Cover Letter L-23-215, Changes to Emergency Plan2023-10-19019 October 2023 Changes to Emergency Plan 2024-09-06
[Table view] Category:Inspection Report
MONTHYEARIR 05000346/20240032024-11-14014 November 2024 Integrated Inspection Report 05000346/2024003 IR 05000346/20244032024-09-27027 September 2024 Security Baseline Inspection Report 05000346/2024403 IR 05000346/20240052024-08-22022 August 2024 Updated Inspection Plan for Davis-Besse Nuclear Power Station (Report 05000346/2024005) IR 05000346/20240022024-08-0101 August 2024 Integrated Inspection Report 05000346/2024002 IR 05000346/20244012024-07-30030 July 2024 Security Baseline Inspection Report 05000346/2024401 IR 05000346/20240012024-05-0303 May 2024 Integrated Inspection Report 05000346/2024001 IR 05000346/20230062024-02-28028 February 2024 Re-Issue Annual Assessment Letter for Davis-Besse Nuclear Power Station (Report 05000346/2023006) IR 05000346/20243012024-02-0202 February 2024 NRC Initial License Examination Report 05000346/2024301 IR 05000346/20230042024-01-31031 January 2024 Integrated Inspection Report 05000346/2023004 ML23338A3172023-12-0606 December 2023 Notification of NRC Baseline Inspection and Request for Information; Inspection Report 05000346/2024001 IR 05000346/20234032023-11-0202 November 2023 Security Baseline Inspection Report 05000346/2023403 IR 05000346/20234012023-09-13013 September 2023 Security Baseline Inspection Report 05000346/2023401 (Public) IR 05000346/20230112023-08-30030 August 2023 Biennial Problem Identification and Resolution Inspection Report 05000346/2023011 IR 05000346/20230052023-08-24024 August 2023 Updated Inspection Plan for Davis-Besse Nuclear Power Station (Report 05000346/2023005) IR 05000346/20230502023-08-0303 August 2023 Special Inspection Report 05000346/2023050 IR 05000346/20230902023-08-0101 August 2023 EA-23-002 Davis-Besse Nuclear Power Station - NRC Inspection Report No. 05000346/2023090 (Public) IR 05000346/20230022023-07-27027 July 2023 Integrated Inspection Report 05000346/2023002 IR 05000346/20234022023-07-13013 July 2023 Information Request for the Cyber-Security Baseline Inspection, Notification to Perform Inspection 05000346/2023402 IR 05000346/20235012023-06-13013 June 2023 Emergency Preparedness Biennial Exercise Inspection Report 05000346/2023501 IR 05000346/20230102023-05-0909 May 2023 Commercial Grade Dedication Inspection Report 05000346/2023010 IR 05000346/20230012023-05-0101 May 2023 Integrated Inspection Report 05000346/2023001 and 07200014/2022001 ML23096A1382023-04-11011 April 2023 Review of the Spring 2022 Steam Generator Tube Inspection Report IR 05000346/20220062023-03-0101 March 2023 Annual Assessment Letter for Davis-Besse Nuclear Power Station, Unit 1 (Report 05000346/2022006) IR 05000346/20220912023-02-10010 February 2023 NRC Inspection Report 05000346/2022091 and Apparent Violation IR 05000346/20220042023-02-0909 February 2023 Integrated Inspection Report 05000346/2022004 and 07200014/2022001 IR 05000346/20224042023-02-0808 February 2023 Material Control and Accounting Program Inspection Report 05000346/2022404 IR 05000346/20224032023-01-23023 January 2023 – Security Baseline Inspection Report 05000346/2022403 IR 05000346/20220112023-01-0505 January 2023 Triennial Fire Protection Inspection Report 05000346/2022011 IR 05000346/20220032022-11-10010 November 2022 Integrated Inspection Report 05000346/2022003 IR 05000346/20220402022-11-10010 November 2022 95001 Supplemental Inspection Report 05000346/2022040 and Follow-Up Assessment Letter IR 05000346/20220102022-11-0202 November 2022 Design Basis Assurance Inspection (Programs) Inspection Report 05000346/2022010 IR 05000346/20224402022-10-0404 October 2022 NRC Supplemental Inspection (95001) Interim Report 05000346/2022440 IR 05000346/20220052022-08-25025 August 2022 Updated Inspection Plan for Davis-Besse Nuclear Power Station (Report 05000346/2022005) IR 05000346/20220022022-08-11011 August 2022 Integrated Inspection Report 05000346/2022002 ML22208A0652022-07-27027 July 2022 Notification of NRC Fire Protection Team Inspection Request for Information: Inspection Report 05000346/2022011 IR 05000346/20220122022-06-30030 June 2022 Phase III 71003 License Renewal Report 05000346/2022012 IR 05000346/20224012022-05-17017 May 2022 Security Baseline Inspection Report 05000346/2022401 IR 05000346/20220012022-05-12012 May 2022 Integrated Inspection Report 05000346/2022001 IR 05000346/20223012022-04-12012 April 2022 NRC Initial License Examination Report 05000346/2022301 IR 05000346/20210062022-03-0202 March 2022 Annual Assessment Letter for Davis-Besse Nuclear Power Station, Unit 1 (Report 05000346/2021006) IR 05000346/20210922022-03-0101 March 2022 EA-21-155 Davis Besse - Final Significance Determination of White Finding, Notice of Violation and Assessment Follow Up Letter, NRC Inspection Report 50000346/2021092 IR 05000346/20210042022-02-0909 February 2022 Integrated Inspection Report 05000346/2021004 and Exercise of Enforcement Discretion ML22032A3142022-02-0101 February 2022 Notification of NRC Design Bases Assurance Inspection (Programs) and Initial Request for Information Inspection Report 05000346/2022010 IR 05000346/20210912021-12-17017 December 2021 NRC Inspection Report (05000346/2021091) Preliminary Greater than Green Finding IR 05000346/20210902021-12-16016 December 2021 Reissue Davis-Besse NRC Inspection Report (05000346/2021090) Preliminary White Finding ML21340A2212021-12-0909 December 2021 NRC Inspection Report (05000346/2021090) Preliminary White Finding IR 05000346/20214042021-12-0909 December 2021 Security Baseline Inspection Report 05000346/2021404 IR 05000346/20210502021-11-19019 November 2021 Special Inspection Reactive Report 05000346/2021050 and Apparent Violation IR 05000346/20210032021-11-10010 November 2021 Integrated Inspection Report 05000346/2021003 IR 05000346/20210112021-11-0101 November 2021 Design Basis Assurance Inspection (Teams) Inspection Report 05000346/2021011 2024-09-27
[Table view] |
Text
ber 29, 2009
SUBJECT:
DAVIS-BESSE NUCLEAR POWER STATION NRC SUPPLEMENTAL INSPECTION REPORT 05000346/2009406(DRS)
Dear Mr. Allen:
On September 17, 2009, the U. S. Nuclear Regulatory Commission (NRC) completed a supplemental inspection at your Davis-Besse Nuclear Power Station. The inspection examined activities conducted under your license as they relate to safety and compliance with the Commission's rules and regulations, and with the conditions of your license. The enclosed inspection report documents the inspection results, which were discussed at the exit meeting on September 17, 2009, with Mr. V. Kaminskas and other members of your staff. The NRC was informed of your readiness for the inspection on August 13, 2009.
As required by the NRC Reactor Oversight Process Action Matrix, this supplemental inspection was conducted to provide assurance that the root causes and contributing causes of the events resulting in a Greater than Green finding were understood, to independently assess the extent of condition and extent of cause, and to provide assurance that the corrective actions for significant performance issues were sufficient to address the root causes and contributing causes, and to prevent recurrence. The inspection consisted of plant walkdowns, a selected examination of representative records, and interviews with personnel.
Based on the results of this supplemental inspection, no findings of significance were identified.
EXEMPT FROM PUBLIC DISCLOSURE May be exempt from public release under the Freedom of Information Act (5 U.S.C. 552)
Exemption number: 5___________
Nuclear Regulatory Commission review required before Enclosure transmitted herewith contains public release. Safeguards Information. When separated from enclosure, this transmittal document is Donald Funk, RIII/DRS/PSB___________ decontrolled.
Name and organization of person making determination.
Date of determination: 10/26/09______ In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records System (PARS) component of NRC's Agencywide Documents Access and Management System (ADAMS), accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room). However, because of the security-related concerns contained in the enclosure, and in accordance with 10 CFR 2.390, a copy of this letters enclosure will not be available for public inspection.
Sincerely,
/RA/
Anne T. Boland, Director Division of Reactor Safety Docket Nos. 50-346 License Nos. NPF-3 Nonpublic Enclosure: Inspection Report 05000346/2009406(DRS);
w/Attachment: Supplement Information ( )
cc w/encl ( ):
S. Coker, NSIR/DSO/DDSO/ST C. OClaire, State Liaison Officer Ohio Emergency Management Agency cc w/o encl: Distribution via ListServ ( )