Similar Documents at Fermi |
---|
Category:License-Operator Examination Report
MONTHYEARIR 05000341/20213012021-07-13013 July 2021 NRC Initial License Examination Report 05000341/2021301 IR 05000341/20203022021-03-18018 March 2021 NRC Initial License Examination Report 05000341/2020302 IR 05000341/20173012017-05-31031 May 2017 NRC Initial License Examination Report 05000341/2017301 (Meb) IR 05000341/20153012015-10-0707 October 2015 Examination Report 05000341/2015301; 08/24/2015 - 09/03/2015; DTE Energy Company, Fermi Power Plant, Unit 2, Initial License Examination Report; (Meb) IR 05000341/20133012013-10-29029 October 2013 Er 05000341-13-301(DRS); 09/09/2013 - 09/24/2013; Detroit Edison Company, Fermi Power Plant, Unit 2, Initial License Examination Report IR 05000341/20123012012-04-12012 April 2012 Er 05000341-12-301(DRS); 03/19/2012-03/30/2012; Detroit Edison Company, Fermi Power Plant, Unit 2. Initial License Examination Report IR 05000341/20103012010-10-29029 October 2010 Er 05000341-10-301(DRS), on 08/30/2010 - 09/17/2010, Fermi Power Station, Unit 2, Initial License Exam Report IR 05000341/20093012009-04-29029 April 2009 Er 05000341-09-301(DRS), on 3/16/2009 - 3/26/2009, Detroit Edison Company, Fermi Power Plant, Unit 2, Initial License Examination Report IR 05000341/20063022006-09-0606 September 2006 Er 05000341/2006302(DRS); 08/16/2006; Fermi Power Plant; Initial License Written Retake Examination Report IR 05000341/20063012006-05-0101 May 2006 Er 05000341-06-301(DRS); Fermi Power Plant, Unit 2; Initial License Examination Report IR 05000341/20043012004-11-0505 November 2004 Er 05000341-04-301(DRS); 09/20/2004-09/24/2004; Fermi Power Plant, Unit 2; Initial License Examination Report IR 05000341/20033022003-08-20020 August 2003 Er 05000341/2003-302(DRS); Detroit Edison Company; 07/07/03; Fermi 2 Nuclear Power Station. Initial License Examination Report NRC-02-0059, Preparation and Scheduling of Operator Licensing Examinations2002-07-10010 July 2002 Preparation and Scheduling of Operator Licensing Examinations 2021-07-13
[Table view] Category:License-Operator
MONTHYEARIR 05000341/20233012023-08-16016 August 2023 NRC Initial License Examination Report 05000341/2023301 ML23213A0302023-08-11011 August 2023 Form 5.1-1 Postexamination Check Sheet ML23212A8732023-07-31031 July 2023 Form 1.3-1 Examination Security Checklist ML23200A2182023-06-28028 June 2023 Form 3.4-1 Scenario Events & Evolutions Checklist RO & SRO Final ML23200A2552023-06-28028 June 2023 Post-Exam Letter with Comments and Exam Analysis ML23200A2572023-06-19019 June 2023 Form 2.1-1 Examination Prep Checklist ML23200A2562023-06-19019 June 2023 IP 21 Operator Licensing Exam Schedule ML23166A0892023-06-15015 June 2023 Operator Licensing Examination Approval Fermi Power Plant, June 2023 ML23200A1852023-06-0202 June 2023 Form 2.3-2 Operating Test Quality Checklist ML23200A1862023-06-0202 June 2023 Form 2.3-4 Written Exam Quality Checklist ML23200A1842023-04-0606 April 2023 Proposed Exam Submittal Letter ML23074A1972023-03-16016 March 2023 Confirmation of Initial License Examination February 2024 ML23200A2212023-02-0808 February 2023 Form 2.3-1 Outline Quality Checklist ML23200A2162023-01-20020 January 2023 Outline Submittal Letter ML23200A2172023-01-20020 January 2023 Form 3.4-1 Scenario Events & Evolutions Checklist RO & SRO Draft ML22322A1082022-11-18018 November 2022 Confirmation of Initial License Examination ML21258A0602021-09-15015 September 2021 Notification of an NRC Biennial Licensed Operator Requalification Program Inspection and Request for Information ML21327A1702021-06-16016 June 2021 ES-401-6 ML21327A4272021-06-16016 June 2021 Post Exam Submittal Letter ML21327A4252021-06-16016 June 2021 ES-403-1 ML21327A4242021-06-16016 June 2021 ES-201-3 ML21327A4212021-06-16016 June 2021 ES-201-1 ML21327A1062021-06-16016 June 2021 Proposed Exam Submittal Letter ML21327A1042021-06-16016 June 2021 ES-301-4 ML21327A0952021-06-16016 June 2021 ES-301-3 ML21327A0922021-06-16016 June 2021 ES-301-6 ML21326A1242021-06-16016 June 2021 Licensee Outline Submittal Letter ML21326A1212021-06-16016 June 2021 ES-301-5 ML21326A1202021-06-16016 June 2021 ES-201-2 ML21327A3362021-06-16016 June 2021 Handouts to Applicants (Summary) ML21327A3262021-06-16016 June 2021 Administered Written Exam with Answer Key ML21328A1382021-06-16016 June 2021 Proposed Admin JPMs ML21327A3212021-06-16016 June 2021 Administered Scenarios ML21328A1622021-06-16016 June 2021 Proposed Control Room and In-Plant JPMs ML21328A1642021-06-16016 June 2021 Proposed Scenarios ML21328A1662021-06-16016 June 2021 Proposed Written Exam with Answer Key ML21327A3082021-06-16016 June 2021 Administered Admin JPMs ML21327A3422021-06-16016 June 2021 Modified Question Source Information ML21327A3142021-06-16016 June 2021 Administered Control Room and In-Plant JPMs ML21120A0202021-05-0303 May 2021 Operator Licensing Examination Approval IR 05000341/20203022021-03-18018 March 2021 NRC Initial License Examination Report 05000341/2020302 ML22158A1462021-02-0505 February 2021 Fer 2020 Ile ES-301-7 Operating Test Review Worksheet-Final ML22158A1302021-02-0505 February 2021 Fer 2020 ES-201-1 Rev 11 ML22158A1332021-02-0505 February 2021 Fer 2020 Ile Final Es 201-3 ML22158A1382021-02-0505 February 2021 Fer 2020 Ile Es 403-1 RO-SRO Written Exam Grading Quality Checklist ML22158A1582021-02-0505 February 2021 Fer 2020 Ile NRC ES-401-4 Record of Rejected KAs Rev 11 2023-08-16
[Table view] Category:Part 55 Examination Related Material
MONTHYEARIR 05000341/20233012023-08-16016 August 2023 NRC Initial License Examination Report 05000341/2023301 ML23213A0302023-08-11011 August 2023 Form 5.1-1 Postexamination Check Sheet ML23212A8732023-07-31031 July 2023 Form 1.3-1 Examination Security Checklist ML23200A2182023-06-28028 June 2023 Form 3.4-1 Scenario Events & Evolutions Checklist RO & SRO Final ML23200A2552023-06-28028 June 2023 Post-Exam Letter with Comments and Exam Analysis ML23200A2572023-06-19019 June 2023 Form 2.1-1 Examination Prep Checklist ML23200A2562023-06-19019 June 2023 IP 21 Operator Licensing Exam Schedule ML23166A0892023-06-15015 June 2023 Operator Licensing Examination Approval Fermi Power Plant, June 2023 ML23200A1852023-06-0202 June 2023 Form 2.3-2 Operating Test Quality Checklist ML23200A1862023-06-0202 June 2023 Form 2.3-4 Written Exam Quality Checklist ML23200A1842023-04-0606 April 2023 Proposed Exam Submittal Letter ML23074A1972023-03-16016 March 2023 Confirmation of Initial License Examination February 2024 ML23200A2212023-02-0808 February 2023 Form 2.3-1 Outline Quality Checklist ML23200A2162023-01-20020 January 2023 Outline Submittal Letter ML23200A2172023-01-20020 January 2023 Form 3.4-1 Scenario Events & Evolutions Checklist RO & SRO Draft ML22322A1082022-11-18018 November 2022 Confirmation of Initial License Examination ML21258A0602021-09-15015 September 2021 Notification of an NRC Biennial Licensed Operator Requalification Program Inspection and Request for Information ML21327A1702021-06-16016 June 2021 ES-401-6 ML21326A1202021-06-16016 June 2021 ES-201-2 ML21326A1212021-06-16016 June 2021 ES-301-5 ML21326A1242021-06-16016 June 2021 Licensee Outline Submittal Letter ML21327A0922021-06-16016 June 2021 ES-301-6 ML21327A0952021-06-16016 June 2021 ES-301-3 ML21327A1042021-06-16016 June 2021 ES-301-4 ML21327A1062021-06-16016 June 2021 Proposed Exam Submittal Letter ML21327A4212021-06-16016 June 2021 ES-201-1 ML21327A4242021-06-16016 June 2021 ES-201-3 ML21327A4252021-06-16016 June 2021 ES-403-1 ML21327A4272021-06-16016 June 2021 Post Exam Submittal Letter ML21327A3362021-06-16016 June 2021 Handouts to Applicants (Summary) ML21327A3262021-06-16016 June 2021 Administered Written Exam with Answer Key ML21327A3212021-06-16016 June 2021 Administered Scenarios ML21327A3142021-06-16016 June 2021 Administered Control Room and In-Plant JPMs ML21327A3082021-06-16016 June 2021 Administered Admin JPMs ML21328A1662021-06-16016 June 2021 Proposed Written Exam with Answer Key ML21328A1642021-06-16016 June 2021 Proposed Scenarios ML21328A1622021-06-16016 June 2021 Proposed Control Room and In-Plant JPMs ML21327A3422021-06-16016 June 2021 Modified Question Source Information ML21328A1382021-06-16016 June 2021 Proposed Admin JPMs ML21120A0202021-05-0303 May 2021 Operator Licensing Examination Approval IR 05000341/20203022021-03-18018 March 2021 NRC Initial License Examination Report 05000341/2020302 ML22158A1582021-02-0505 February 2021 Fer 2020 Ile NRC ES-401-4 Record of Rejected KAs Rev 11 ML22158A1382021-02-0505 February 2021 Fer 2020 Ile Es 403-1 RO-SRO Written Exam Grading Quality Checklist ML22158A1332021-02-0505 February 2021 Fer 2020 Ile Final Es 201-3 ML22158A1302021-02-0505 February 2021 Fer 2020 ES-201-1 Rev 11 ML22158A1642021-02-0505 February 2021 Ile Outline Review Comments 2023-08-16
[Table view] |
Text
ust 20, 2003
SUBJECT:
FERMI 2 NUCLEAR POWER STATION NRC INITIAL LICENSE EXAMINATION REPORT 50-341/03-302(DRS)
Dear Mr. OConnor:
On July 7, 2003, the NRC completed an initial operator licensing reexamination at your Fermi 2 Nuclear Power Station. The enclosed report presents the results of the examination.
Members of the Fermi 2 Nuclear Power Station Training staff administered the written examination on July 7, 2003, to one Reactor Operator (RO) applicant who had previously failed the written examination administered on March 17, 2003. The results of the examination were finalized on July 17, 2003, showing the applicant passed the written examination. The applicant passed the operating test administered the week of March 10, 2003, and therefore has now passed all sections of his examination.
In accordance with 10 CFR Part 2.790 of the NRC's Rules of Practice, a copy of this letter and its enclosure will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room). We will gladly discuss any questions you have concerning this examination.
Sincerely,
/RA/
Roger D. Lanksbury, Chief Operations Branch Division of Reactor Safety Docket No. 50-341 License No. NPF-43
Enclosures:
1. Operator Licensing Examination Report 50-341/03-302(DRS)
2. Written Examinations and Answer Key
REGION III==
Docket No: 50-341 License No: NPF-43 Report No: 50-341/03-302(DRS)
Licensee: Detroit Edison Company Facility: Enrico Fermi, Unit 2 Location: 6400 N. Dixie Highway Newport, MI 48166 Dates: July 7, 2003 Examiner B. Palagi, Chief Examiner Approved by: Roger Lanksbury, Chief Operations Branch Division of Reactor Safety
SUMMARY OF FINDINGS ER 05000341/2003-302(DRS); Detroit Edison Company; 07/07/03; Fermi 2 Nuclear Power Station. Initial License Examination Report.
The announced operator licensing initial examination was conducted in accordance with the guidance of NUREG-1021, Operator Licensing Examination Standards for Power Reactors, Draft Revision 9.
Examination Summary:
- A written examination was administered to one Reactor Operator (RO) applicant on July 7, 2003.
- The applicant passed the written examination.
- The applicant passed the operating test administered the week of March 10, 2003, and therefore has now passed all sections of his examination.
- The applicant was issued the applicable operator license on July 17, 2003.
REPORT DETAILS 4. OTHER ACTIVITIES (OA)
4OA5 Other
.1 Initial Licensing Examinations a. Examination Scope An announced operator licensing initial examination was conducted on July 7, 2003.
The facility's training staff used the guidance established in NUREG-1021, Operator Licensing Examination Standards for Power Reactors, Draft Revision 9, to prepare the examination outline and to develop the written examination. Members of the Fermi Training Department administered the written examination on July 7, 2003. One Reactor Operator (RO) applicant was examined.
b. Findings Written Examination The licensee developed the written examination. During their initial review, the NRC examiners determined that the examination, as submitted by the licensee, was within the range of acceptability expected for a proposed examination. During NRC review of the examination, changes agreed upon between the NRC and the licensee were incorporated according to the guidance contained in NUREG-1021.
Examination Results One RO applicant was administered the written examination. The RO applicant passed the examination.
The applicant had previously passed the operating test administered by NRC examiners the week of March 10, 2003 and was therefore issued the applicable operator license.
.2 Examination Security a. Inspection Scope The NRC examiner briefed the facility contact on the NRCs requirements and guidelines related to examination physical security and integrity. The examiner observed the implementation of examination security and integrity measures (e.g., security agreements, sampling criteria, bank use, and test item repetition)
throughout the examination process.
b. Findings The NRC examiner determined that the licensees examination security practices associated with the development and administration of the operator license examination were satisfactory.
4OA6 Meetings Exit Meeting The Training Manager was notified of the examination results via telephone on July 17, 2003. The licensee acknowledged the finding.
KEY POINTS OF CONTACT Licensee L. Sanders, Training Manager G. Strobel, Operations Training Supervisor S. Bollinger, Operations Training Instructor NRC B. Palagi, Chief Examiner ITEMS OPENED, CLOSED, AND DISCUSSED Opened None Closed None Discussed None
LIST OF ACRONYMS ADAMS Agency-Wide Document Access and Management System DRS Division of Reactor Safety NRC Nuclear Regulatory Commission PARS Publicly Available Records RO Reactor Operator
Enclosure 2 WRITTEN EXAMINATIONS AND ANSWER KEYS (RO/SRO)
RO Initial Examination ADAMS Accession #ML032180779.