IR 05000335/1987026

From kanterella
Jump to navigation Jump to search
Insp Repts 50-335/87-26 & 50-389/87-25 on 871026-30.No Violation or Deviation Noted.Major Areas inspected:safety- Related Pipe Supports & Pipe Support Base Plate Design Using Concrete Expansion Bolt(Ie Bulletin 79-02)
ML17221A575
Person / Time
Site: Saint Lucie  
Issue date: 12/29/1987
From: Blake J, Chou R
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
To:
Shared Package
ML17221A574 List:
References
50-335-87-26, 50-389-87-25, IEB-79-02, IEB-79-2, NUDOCS 8801110367
Download: ML17221A575 (13)


Text

~

~y,g RQgI (g C

UNITED STATES NUCLEAR REGULATORY COMMISSION

REGION II

101 MARIETTASTREET, N.W.

ATLANTA,GEORGIA 30323 Report Nos.:

50-335/87-26 and 50-389/87-25 Licensee:

Florida Power and Light Company 9250 West Flagler Street Miami, FL 33102 Docket Nos.:

50-335 and 50-389 Facility Name:

St. Lucie 1 and

Inspection Conducted:

October 26-30, 1987 Inspector:

R.

.

Ch License Nos.:

DPR-67 and NPF-16 (p y

f~g'ate Sign Approved

. J.

Bla e, Chief Materials and Processes Section Division of Reactor Safety D terSigned SUMMARY Scope:

This routine, announced inspection was in the areas of safety-related pipe supports and pipe support base plate design using concrete expansion anchor bolt (IEB 79-02).

Results:

No violations or. deviations were identified.

880iii0367 87i23i PDR ADOCK 05000335

DCD

REPORT DETAILS 1.

Persons Contacted Licensee Employees

  • J. H. Barrow, Operations Superintendent W. R. Bloor, Supervisor, Civil and Structural Engineering, JPE
  • G. J. Boissy, Plant Manager W. Brannin, Manager, Civil and Structural Engineering, JPE
  • K. N. Harris, Vice President, St. Lucie Nuclear Plant M. 'Hoskins, QC Inspector
  • K. P.

Hughes, Site Lead Civil Engineer

  • J. Krumins, Site Engineering Supervisor
  • L. McLaughlin, Technical Staff Engineer
  • B. Parks, QA
  • N. G. Roos, gC Supervisor
  • M. J.

Snyder, Technical Staff Engineer

  • D. H. West, Technical Staff Supervisor Other licensee employees contacted included engineers, technicians, mechanics, and office personnel.

Other Organization

  • R. Russo, Principal Structural Engineer, Ebasco Services Inc.

NRC Resident Inspector

  • R. V. Crlenjak, Senior Resident Inspector
  • Attended exit interview 2.

Exit Interview The inspection scope and findings were summarized on October 30, 1987, with those persons indicated in paragraph

above.

The inspector described the areas inspected and discussed in detail the inspection findings.

No dissenting comments were received from the licensee.

The following new items were identified during this inspection:

Unresolved Items (UNR) 50-335/87-26-01 and 50-389/87-25-01, Pipe Support Discrepancies between Field Conditions and Drawings UNR 50-335/87-26-02 and 50-389/87-25-02, Base Plate and Anchor Bolt Deficiencies UNR 50-389/87-25-03, Base Plate and Anchor Bolt Calculation Problems

Qe UNR 50-389/87.-25-04, Support Not Found in Field UNR 50-335/87-26-03 and 50-389/87-25-05, Installation and Inspection Records for Pipe Supports Inspector Followup Item (IFI) 50-335/87-26-04 and 50-389/87-25-06, Structural Members, Connections and Pipe Support Maintenance The licensee did not identify as proprietary any of the materials provided to or reviewed by the inspector during this inspection.

3.

. Licpnsee Action on Previous Enforcement Matters This subject was not addressed in the inspection.

4.

Unresolved, Items Unresolved items are matters about which more information is required to determine whether they are acceptable or may involve violations or deviations.

Five unresolved items identified during this inspection are discussed in paragraph 5.

5.

(Open)

Pipe Support Base Plate Design Using Concrete Expansion. Anchor Bolt (IEB 79-02) - Units I and

'a ~

Briefing This inspection was conducted to verify licensee compliance with IE Bulletin 79-02 requirements and licensee commitments.

Dur ing 1977, an extensive inspection similar to the requirements of IEB 79-02 was performed on all Unit I Seismic Category I Pipe Supports utilizing concrete expansion anchors.

The following installation parameters were verified:

bolt diameter and length, embedment depth, thread engagement length, sleeve recess in concrete and presence of the conical plug.

Various supports, based on the as-built information, were reanalyzed to demonstrate the ability to withstand design loads.

Prying forces were not considered in qualification of anchor bolts and base plates.

There were 13 cases where structural shapes were attached directly to concrete in Unit I and they were not reported to NRC, Region II.

These cases had been reviewed and the designs were found to be adequate by the licensee.

The licensee's response on Unit 2 for IEB 79-02; dated July 2, 1979 (L-79-180),

stated that prying forces would be calculated and accounted for in the design.

The design criteria for expansion anchor applications would use safety factors of four for static loading, five for impactive loading and 15 for vibratory and seismic loading.

Subsequently after a meeting between the NRC, FPL, and Ebasco, the licensee submitted a

response concerning Base Plate

Flexibility Action Items to NRC, dated September.21, 1982 (L-82-408),

and stated that the use of a safety factor of 15 for all types of loading precludes the necessity of a prying calculation or, if the use of a safety factor of 15 is impractical and the presence of large loads results in a significant prying effect, base plates would be analyzed using the ANSYS finite element computer program.

b.

Walkdown Check The inspector reviewed previous inspection reports and found that only a few pipe supports were walked down previously for IEB 79-02.

Therefore, the inspector decided to walkdown pipe supports particularly for IEB 79-02.

The inspector randomly selected the following 13 supports, in the area of dynamic pipe supports and component support structures, which included anchor bolts and baseplates, that had been gC final inspected, to see if they complied with IEB 79-02 requirements.

The supports were reinspected with the assistance of the licensee's gC inspector and engineer.

Table 1 is the list of supports reinspected.

TABLE 1 FIELD WALKDOWN SUPPORTS AND COMMENTS 1.

Mark No. BF-2-9, Rev. 3, Feed Water System, Unit 1 a.

A 5" x 2" x 3/8" plate between the bracing and base plate was not shown on the drawing.

b.

2-3/8" edge distance for anchor bolt at south side of the base plate for bracing was different from the drawing which showed an 1-1/2" edge distance.

c.

1-1/4" edge distances for three anchor bolts in the base plate for the vertical post (3"d standard pipe)

was different from the 1" shown on drawing.

d.

1'-l-l/2" x 0'-10-1/2" base plate for bracing was different from 10-1/2" x 10-1/2" shown on drawing.

2.

Mark No. CW-64-51, Rev. 0, ICW Lube Water System, Unit 1 (Gange Support CW-63-52)

1-3/4" edge distances for three anchor bolts were different from the 1-1/2" shown on the drawing.

3.

Mark No. CW-58-62, Rev.

1, ICW Lube Water System, Unit

(Gang Support CW-59-61)

a.

Base plate bent and 1/4" max gap between base plate and concrete

b.

Lower bolt on south side bent at an angle of 12'.

Mark No. CW-53-72, Rev.

1, ICW Lube Water System, Unit

(Gang Support CW-54-71)

Base plate bent and 1/4" max gap between base plate and concrete 5.

Mark No. CC-2074-44, Rev. 4, Component Cooling System, Unit 2 a.

1-3/8" to 2-3/4". edge distances for anchor bolts instead of the 3/4" shown on drawing.

b.

1/4" Gap between top of pipe and 3" x "3" tube steel exceeded the 1/16" CLR.

shown on drawing.

6.

Mark No. FS-2138-17, Rev. 8, Fuel Pool System, Unit 2 2-1/4" edge distance for anchor bolt at North-East corner exceeded the 2" shown on drawing 7.

Mark No. FS-2137-143, Rev.

2, Fuel Pool System, Unit 2 3-1/4" edge distance for anchor bolt exceeded the 3" shown on drawing 8.

Mark No. CW-3000B-187, Rev. 8, Circulating Water System, Unit 2 Support could not be located in field.

9.

Mark No. CS-2012-8015, Rev. 5, Fuel Pool System, Unit 2 a.'-3/4" to 4-1/2" edge distances for anchor bolts were different from 3" (TYP.) shown on drawing b.

Center lines of Item No.

6 (2" d pipe)

were 6" from left edge and 7-3/4" from top edge of base plate which were different from 9" (TYP.)

as shown in Section A-A of drawing.

10.

Mark No. BF-4001-190, Rev. 9, Feed Water System, Unit 2 Weld around in field between Item No.

(TS 4" x 4") and base plate was not shown on drawing.

The above supports were partially reinspected against their detail drawings particularly for anchor bolts and base plates with a

few exceptions on configuration, identification, dimensions, bolt edge distances, base plate thicknesses, bolt size, installation, rust, maintenance, and damage/protectio c.

Calculations Review Design calculations were partially reviewed and evaluated for thoroughness, clarity, consistency and accuracy for anchor bolts and base plates.

The prying forces, safety factors and allowables were reviewed particularly to see if they meet the requirements of IEB 79-02 and the licensee commitment.

Table 2 showed the 32 support calculations reviewed, with comments.

d.

Other Documents Reviewed The following documents were reviewed for the support walkdown reinspection and calculation review.

Expansion Anchors, Construction guality Control Technical Sheet, TS 10. 13, Rev. I, FPL (iii)

For expansion anchor inspection.

Drilled-In Expansion Type Anchors in Concrete, FL0-2998.469, Rev. 3, Ebasco For procurement, installation and testing requirement of anchoring devices.

Control of Nondestructive Examination, Appendix C, Non-Destructive Examination Manual, gI9-PR/PSL-2, Rev.

12, FPL e.

For visual inspection on welds, castings, wrought and forged components, hangers, supports, pumps, valves, and other piping and structured components.

(iv)

Concrete Expansion Anchor Design, Final Safety Analysis Report (FSAR), Unit 2 For design criteria for expansion anchor bolts.

Documentation Availability The following documents were requested by the inspector for references or review during the inspection, but they were not available.

The licensee stated that they had completed IEB 79-02 a

long time ago and it was not easy to collect all the information/documents requested in such a short period of time.

(i)

A set of pipe support drawings made from final control drawing for supports shown on Table 2.

(ii) Installation and inspection records including anchor bolts and base plates for supports shown on Table (iii) Copies of pipe support installation, inspection, evaluation and design procedures or criteria.

(iv) Copy of walkdown, inspection, evaluation, and design criteria or procedures for IEB 79-14 with the cover titles which related to I EB 79-02.

Findings and Conclusions During the calculation review of Unit 2, Support No. CC-2074-44, which was performed by Bergen-Paterson appeared to have a safety factor below two for anchor bolts due to the safety factor of 1.33 being used with the final interaction ratio of 0.75.

Also, the prying forces were not considered in the above calculation.

Therefore, the inspector requested that the licensee to evaluate the anchor bolts for the system operability.

If the safety factor of anchor bolt is

'below two, the system should be declared inoperable.

If the safety factor is between two and four, the support meets the interim operability requirement, but it requires modification to meet the long term requirements.

The licensee engineers, after searching documents, replied that this support was one of the worst examples in guestion No. 210A.61, SL2-FSAR, and in separate correspondence to Base Plate Flexibility Action Items to NRC, dated September 21, 1982, (L-82-408)

was approved by NRC without question.

The inspector reviewed the submitted FSAR and correspondence (they are identical).

It appeared that the input loads were not the worst case for the analysis.

Therefore, during the exit meeting, the inspector requested that the licensee perform the evaluation of two supports for the system operability; Support no.

CV-58-62 in Unit 1, with the warped baseplate, plus one bolt bent 12',

and the support listed above, using computer analysis, with current loads and field as-built conditions, due to the field conditions differing from the detail dr awing.

The licensee agreed, and called the Region II office to state that both of the two supports met the system operability.

The input loads on FSAR and response for support no.

CC-2074-44 were different from the calculation reviewed by the inspector.

It appeared that this support has double calculations existing since the Bergen-Paterson calculation was revised on August 3, 1983, after the response sent to NRC on September 21, 1982.

The inspector held discussions with the licensee engineers and gC inspector about the discrepancies found in Table 1.

gC Inspector stated that the supports should be inspected per the detail drawings without any tolerances except those stated in the detail drawings.

Any dimensions or items which deviated from the detail drawings should be recorded and sent to

.,the engineering department for evaluation.

The licensee engineers did not know processes and location of document for evaluation after the gC inspector wrote the deviation reports.

The licensee engineers also did not know the procedure for correcting the detail drawings after the deviated items were identified.

The A/E, Ebasco, was not available at the tim Table 2 shows the summary of the calculations reviewed.

The safety factor for anchor bolts ranged from 1.33 to 15; Ebasco used safety factors of 4, 5, and 15.

and Bergen-Paterson used 1.33, 2, and 4.

The safety factor for anchor bolts should be more than four for wedge and sleeve type anchor bolts and five for shell type anchor bolts after considering base plate flexibility or prying forces.

Prying

'orces were not considered in most calculations.

The allowables for anchor bolts were also different even with the same size of bolt and the same safety factor.

Per the licensee FSAR and response to NRC as stated above, the licensee committed to use a safety factor of 15 for anchor bolts in all load cases without considering the prying forces or base plate flexibility.

Based on all the findings in field walkdown, calculation review, and document request, the inspector summarized the results as follows:

UNR 50-335/87-26-01 and 50-389/87-25-01, Pipe Support Discrepancies between Field Conditions and the Drawings Examples such as Items 1(a),

1(d), 5(b), 9(b),

and

on Table 1.

UNR 50-335/87-26-02 and 50-389/87-25-02, Base plate and Anchor bolt Deficiencies Examples such as Items l(b), 1(c), 2, 3(a), 3(b), 4, 5(a),

6, 7 and 9(a)

on Table

UNR 50-389/87-25-03, Base plate and Anchor Bolt Calculation Problems Examples such as the generic problems for the different safety factor and allowables used on Table 2.

Particularly, the safety factor of 1.33 and

used by Bergen-Paterson Support No. CC-2074-44, Unit 2 appeared to have double calculations existing All the notes on Table

UNR 50-389/87-25-04, Support not Found in Field Support No. CW-3000B-187 could not be found in field as shown on Item 8 of Table I UNR 50-335/87-26-03 and 50-389/87-25-05, Installation and Inspection Records Request for Pipe Supports The document listed in paragraph 5(e)

were requested for review or references

IFI 50-335/87-26-04 and 50-389/87-25-06, Structural Members, Connections and Pipe Supports Maintenance During the field walkdown in the intake structure area on Units I and 2, the inspector observed heavy rust on the structural beams, connections, anchor bolts, baseplate etc.,

due to'he water leakage.

The licensee should evaluate the significant of this condition.

In summary, Bergen-Paterson performed the large bore support calculations for Unit 2.

Table 2, shows that five out of eight support calculatio'ns performed by Bergen-Paterson may have used a safety factor of 1.33 and

with no consideration of the prying forces.

Therefore, before this Bulletin can be closed the licensee must evaluate all safety-related large bore support calculations performed by Bergen-Paterson.

No violations or deviations were identifie J'

CALCULATIONS REVIEWED FOR AtlCIIOR BOLTS AHD BASE PLATES WITII CONNEIITS I tern No I~lark In Of-2-9 CS"678-157 CS-2000-45 CS-2000-47 CSII"15

~Rev e

~eni r e

1 Bol t

~e<ze in 3/8 3/4 5/8 5/8 5/8 3/4 Sa I'ety Factor Used A I Iovab les L ~bi Ta=1190 Va=768 Ta=2900 Ta=2962 Ta=2500 Ta=2457 Va=2713 tlo tlo tlo Yes No No tonsion on bolt No tension on bolt Prying forces Considered Comments I

'IO 12" 13%

14%

CI(-64-51 CW-58-62 CW-53-72 CW-54-71 SIN-15 BF-4001-190 CC-2074-44 CC-2074-7288 CII-2081-14 5/8 5/8 5/8 5/8 3/4 5/8 1/2 1/2

a4

1.33 1.33 Ta =361 Va=747 Ta=2080 Vs=3054 Ta=2080 Va=3054 Ta=361 Vs=747 Ta=2900 Va-3700 Ta"-5150 Va=4800 Ta=5325 Vs=4500 Ta=16350 Vs=17700 Ta=3550 Va=3000 tlo tlo Yes tlo tlo tlo tlo No No Note

Note

Note

Note

Note

Hote 4 Note 5

C-IA-6-R4 Note 6

TA

CALCULATIONS REVIEWED FOR ANCIIOR BOLTS AND BASE PLATES WITII COHHEtITS item ILo

~Hark i o

~Bev o

~un i o

Bol t

~size in Sa fety Factor Used A I I owab Ies

~lb Prying Forces Considered

~Common s

C" IA"6-R27

Ta=773 Va=987 No

18

20

22

24" 25%

C-RC-98-R9 C-RC"98-R10 C-RC-99-Rl C-RC-99-R9 C-Rc-100-Rl C-RC-103-R1 C-RC-103-R2 CS-2012-8015 CW-30008-187 3/4 3/4 3/4 3/4 3/4 3/4

15 Ta=773 Ye=987 Ta=773 Va=987 Ta=18800 Va=17800 Ta=2900 Ye=3700 Ho tlo tlo tlo tlote 7 tlote 7 Note

Hote

Note

Note 8

27,

29 C-SA-4-RI C-SA->>-RIO FS-2137-1>>3 FS-2138-17 3/4 3/4 3/4 3/4

Ta=773 Note 7 Hote 7 Ho tension on bolt

31%

32" S I -2>l01->>003 SPS->>27 Wth-2092-76 3/>>

3/8 3/4 Ta=2900 Va=3700 Ta=1150 Va=800 Ta=2900 Va=3700 Yes tlo

"These calculations were performed by Bergen-Paterson Pipe Support Corp.

It~e remaining of calculations were performed by Ebasco Sercices Inc.

Ta

= Tens i on Al Iowa b Ie, Va = Shea r A I I owab I e

TABLE 2 CALCULATIONS REVIEWEO FOR ANCHOR BOLTS ANO BASE PLATES WITH COMMENTS NOTES:

1.

Calculation used one support load to qualify anchor bolts and base plate.

Actually, two supports acted at same bolts and base plate.

2.

Disposition of "use as is" for base plate warped with 1/8" to 1/4" gaps at all four anchor bolts was not adequate.

Shim plates should be considered to be used.

3.

a.

Oouble anchor bolt spacing reduction factors should be used since existing spacings of 6.25" were.less thatn the minimum requirement of 7 5 II 6 25" x

6 25" =

0 694

~7. 50

~7. 50'

4.

a.

Using safety factor of two to qualify anchor bolts is not allowed.

Requal jfication or modifications is required for anchor bolt safety factor between two and four.

This calc.

was initiated on May 10, 1982 by Bergen-Paterson and the final revision was perf'ormed on August 3, 1983.

b.

Using safety factor of 1.33 to qualify anchor bolts is not allowed.

For anchor bolt safety factor below 2, the immediate evaluation of the system operability is required.

5.

Using safety factor of two to qualify anchor bolts is not allowed.

Aequalification or modification is required for anchor bolt safety factor between two and four.

6.

This calculation was referred to calc.

No. C-SA-4-Rll which was not attached or available for review.

7.

Anchor bolts and base plate were qualified by comparison with the standard calculations for the various type of base plate and anchor bolts.

The standard calculations were not available and wi 11 be reviewed later.

8.

a.

Same as note 3(b).

b.

Ta=18800 and Va=17800 are the ultimate allowables for 1-1/4" p, not for 1" g.