Partially Withheld Insp Rept 50-331/93-06 on 930322-26.No Violations Noted.Major Areas Inspected:Mgt Support,Plans & Audits,Protected & Vital area-barriers & Detection & Assessment Aids.Details Withheld Ref 10CFR2.790
ML20035C698
Person / Time
Site: Duane Arnold NextEra Energy icon.png
Issue date: 04/05/1993
From: Creed J, Madera T
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
To:
Shared Package
ML20035C697 List:
References
50-331-93-06, 50-331-93-6, NUDOCS 9304090011
Download: ML20035C698 (2)


Text

.

i U. S. NUCLEAR REGULATORY COMMISSION

REGION III

Report No. 50-331/93006(DRSS)

Docket No. 50-331 License No. DPR-49 Licensee:

Iowa Electric Light and Power Company P. O. Box 351

-

Cedar Rapids, IA 52406 q

Facility Name: Duane Arnold Energy Center, Palo, Iowa Inspection Dates: March 22-26, 1993

'

Type of Inspection: Announced, Routine Physical Security Inspection Date of Previous Physical Security Inspection: May 4 through June 8, 1992 l

/?n 44 Yf/'f3 Inspector:

%.

Terry f'. fiadeda Da'e t

i Physidal/ Security Inspector

Approved By:

C L Mfl /4 Y/O

!

M Jamss R. Creed, Chidf Date Safeguards Section i

.

Inspection Summary Inspection on March 22 - 26. 1993 (Report No. 50-331/93006(DRSS))

Areas Inspected:

Routine, announced physical security inspection involving:

Management Support, Plans and Audits; Protected and Vital Area - Barriers,

'

Detection and Assessment Aids; Protected and Vital Area Access Control - Personnel, Packages and Vehicles; and Followup on Previous Inspection Findings.

Results: The licensee was found to be in compliance with NRC requirements in the areas inspected. One plant safety issue relating to an inoperative emergency access door was identified.

Licensee corrective action was

!

implemented. All previously identified inspection findings were closed.

Inspection results showed positive improvement in management effectiveness for the security program as evidenced by continued senior plant management support and realignment of day-to-day security functions that resulted in improved

-

security management overview. Review of security audits showed that i 9304090011 930406 PDR ADOCK 05000331

PDR

,

t (\\r

,:l

-

I {

regulatory requirements ware being met and that the scope of audits was good.

Audit findings were corrected in a timely and effective manner.

Protected and vital area security. equipment showed a high level of effectiveness and performance.

Improvement was noted in the licensee's program to control personnel, packages and vehicle access to the protected area.

Security upgrade projects showed good planning and implementation.