IR 05000318/1987007

From kanterella
Jump to navigation Jump to search
Occupational Radiation Protection Insp Rept 50-318/87-07 on 870323-27.No Violations Noted.Major Areas Inspected:External Exposure & Personnel Dosimetry,Internal Exposure Control & Assessment & Control of Radioactive Matl & Contamination
ML20209D013
Person / Time
Site: Calvert Cliffs Constellation icon.png
Issue date: 04/20/1987
From: Mcfadden J, Shanbaky M
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I)
To:
Shared Package
ML20209D000 List:
References
50-318-87-07, 50-318-87-7, NUDOCS 8704290147
Download: ML20209D013 (7)


Text

.

.

U.S. NUCLEAR REGULATORY COMMISSION

REGION I

Report No. 50-318/87-07 Docket N License No. DPR-69 Priority---- Category C Licensee: Balticore Gas and Electric Company P.O. box 1475 Baltimore, Maryland 21203

' Facility Name: Calvert Cliffs Nuclear Power Plant, Unit 2 Inspection At: Lusby, Maryland Inspection Conducted: March 23-27, 1987 Inspectors: , f)? f6 // .2p - FF J.'McFadden, Senior Radiaion Specialist date Approved by: ##-

M. Shanbaky, Chief d/r /

Mu//7 date Facilities Radiation Protection Section Inspection Summary: Inspection on March 23-27, 1987 (Inspection Report No. 50-318/87-07)

Areas Inspected: An unannounced occupational radiation protection inspection at Unit 2 during an outage including: external exposure and personnel dosim-etry, internal exposure control and assessment, control of radioactive mater-tals and contamination, surveys, and monitoring, and ALARA. One regionally-based inspector was onsite for the inspectio Results: No violations were identifie $

PDR ADDCK 05000318 g PDR

.

.

DETAILS 1.0 Persons Contacted During the course of this inspection, the following personnel were contacted or interviewe .1 Licensee Personnel

  • R. Bodin, Supervisor-QC-Operations J. Brown,-Instructor-Training J. Carlson, Plant Health Physicist
  • S. Cowne, Sr. Engineer-licensing B. Dansberger, ALARA Coordinator-Radiation Control /ALARA T. Koranek, Shift Supervisor-Radiation Control / Operations
  • J. Lemons, Manager-Nuclear Operations Department
  • J. Lenhart, Supervisor-Radiation Control / Operations
  • N. Millis, General Supervisor-Radiation Safety
  • G. Phair, Supervisor-Radiation Control /ALARA E. Reimer, Plant Health Physicist
  • L. Smialek, Sr. Plant Health Physicist J. Tiernan, Vice President-Nuclear Energy B. Watson, Asst. General Supervisor-Radiation Control and Support R. Woods, Technician-Radiation Control / Operations R. Wyvill, ALARA Coordinator-Radiation Control /ALARA 1.2 NRC Personnel T. Foley, Senior Resident Inspector D. Trimble, Resident Inspector

Additional licensee personnel were contacted during this inspection or intervie .0 Purpose The purpose of this inspection was to review the licensee's occupational radiation protection program with respect to the following elements:

External occupational exposure control and personal dosimetry

Internal exposure control and assessment

Control of radioactive materials and contamination, surveys, and monitoring

Maintaining occupational exposures ALARA

__ .. _

,__ _ . _ , . .

-~ . _ _ s 7- ,

3.0 External Occupational Exposure Control and Personnel Dosimetry The licensee's program for external occupational exposure control and personnel dosimetry was reviewed against criteria contained in:

10 CFR 20, Standards for Protection Against Radiation

Licensee's Technical Specification 6.0, Administrative Controls

Licensee's Radiological Safety Procedure Manual The licensee's performance relative to these criteria was determined by:

-

discussions with licensee personnel

-

observations of the performance of radiation safety activities

-

tours of the reactor containment and of the auxiliary building

-

reviews of procedures and documentation The following aspects of external exposure control and personnel dosimetry were reviewed and appeared adequate and effective: the special radiation work permit (SWP) program, tracking of cumulative dose for each worker and dissemination of same on a twice daily basis, individual access and ex-posure control, use of special control point watch stations (SCPWs) (in containment) and level HP stations (in auxiliary building), pre-job brief-ings, ALARA reviews (pre-and post-job), ALARA field service inspection reports, special dosimetry, surveys for SWPs, use of temporary, local shielding, of closed circuit television (CCTV) systems, and of remote man-ipulators on steam generator (S/G) work, dosimetry records, and skin dose evaluations for contamination incident An SWP for diving in the spent fuel pool and the associated requirements generated by an ALARA review were inspected. The inspector noted that there was no detailed guidance for underwater surveys as to the number and spacing of measurement points in the dive path and dive work area / Underwater surveys were reviewed by the inspector and appeared to be adequate and effective. The licensee stated that the importance of under-water surveys is recognized, that thorough initial surveys, consuming several hours, are conducte Followup surveys, after potential changes

, in underwater radiological conditions, are mad The licensee also stated i

that consideration will be given to documenting the details of their current practice for conducting underwater surveys prior to diving opera-tion Within the scope of this review, no violations were identifie .0 Internal Exposure Control and Assessment The licensee's program for internal occupational exposure control and assessment was reviewed against criteria contained in:

'

_

l

.

.

-

10 CFR 20, Standards for Protection Against Radiation

-

Licensee's Technical Specification 6.0, Administrative Controls

-

Licensee's Radiological Safety Procedure Manual The licensee's performance relative to these criteria was determined by:

-

discussions with licensee personnel

-

observations of the performance of radiation safety activities

-

tours of the reactor containment and of the auxiliary building

-

review of procedures and documentation The following aspects of internal exposure control and assessment were reviewed and appeared adequate and effective: SWP requirements for HEPA-filtered exhaust units, air sampling, and respiratory protective equipment, the use of ventilation containments, exhaust units, and res-pirators, and record keeping (respirator use/ air activity worksheets, mpc-hours log, and air sampling results).

The inspector noted that, during this outage, there was an increased use of respirators and an increase in the number of individuals with tracked MPC-hours. These increases were caused by the fact that initial removable surface contamination levels in containment were higher than normal (due possibly to a leaking in-core instrumentation [ICI] flange) and to a short-term iodine degassing from the flooded-up refueling pool due to elevated containment temperatur The inspector also noted that the licensee's program for posting airborne radioactivity areas and for tracking intake is still more rigorous than regulatory requirements in that areas are posted at 0.1 MPC and quan-tities equal to and greater than 0.1 MPC-hour are tracked. Review of the MPC-hours log indicated that there were no recorded cumulative totals greater than 10 MPC-hours over any seven consecutive day Within the scope of this review, no violations were identifie .0 Control of Radioactive Materials and Contaminations, Surveys, and Monitoring The licensee's program for control of radioactive materials and contam-

,

ination, surveys, and monitoring was reviewed against criteria contained in:

-

10 CFR 20, Standards for Protection Against Radiction

-

Licensee's Technical Specification 6.0, Administrative Controls

-

Licensee's Radiological Safety Procedure Manual The licensee's performance relative to these criteria was determined by:

.

-

discussions with licensee personnel

-

observations of the performance of radiation safety activities

-

tours of the reactor containment and of the auxiliary building

-

review of procedures and documentation

-

f

_ ,. _ . - . . _ . , , - . _ - _. . - . _ _ _ _ . . _ . . . , . , . - - - - --

.

'

l 5 -

r The following aspects were reviewed and appeared adequate and effective:

numerical adequacy and use of frisking, surveying and counting equipment, provisions for surveying for release of materials or equipment from the radiologically controlled area (RCA), and posting of signs and survey During a tour of containment, the inspector noted several bags of radio-active material which did not appear to be marked and labeled in full compliance with the licensee's procedure RSP 1-111, " Identification and Control of Radioactive Material". The licensee stated that these bags were in transit and are properly labeled or posted with the words "Cau-tion-Radioactive Material" prior to exit from the RCA. Several bags were not marked in a readily visible fashion as to survey date or surveyor's identity. The licensee stated that this item would be reviewe During review of the air sampling records, the inspector observed that airborne tritium sampling in containment while the refueling pool was flooded up was not being performed. The licensee stated that airborne tritium sampling is not performed since theoretical calculations and historical data show that such sampling is not required when the tritium concentration in the refueling pool water is below a predetermined valu The licensee's calculation will be reviewed in a future inspectio The inspector also noted that approximately thirty air sampling results for March 4, 1987 had been documented as lost. The licensee stated that they had investigated this, that the lost surveys had been trending sur-veys, and that their loss had not resulted in a decrease in radiological protection on any SWP wor Within the scope of this review, no violations were identifie .0 Maintaining Occupational Exposures ALARA The licensee's program for maintaining occupational exposures ALARA was

,

reviewed against criteria contained in:

!

i

-

10 CFR 20.1, Purpose

-

Licensee's Technical Specification 6.0, Administrative Controls

-

Liensee's Radiological Safety Procedure Manual l The licensee's performance relative to these criteria was determined by:

l

-

discussions with licensee personnel

-

observations of the performance of radiological safety activities

-

tours of reactor containment

-

review of procedures and , documentation 1 - - - - -- -- . .- -.

.  !

.

The following SWP/ALARA packages among others were reviewed by the inspector

-

SWP 87-2319, Remove defective ICIs, transfer to SFP, and clean ICI guide tubes

-

SWP 87-2406, Entries into #21 and #22 S/G Primary side to install, remove, and repair nozzle dam equipment The inspector attended the pre-job briefing for SWP 87-2319, and this briefing appeared to thoroughly cover the possible hazards and pre-cautionary measures outlined in the ALARA review. The inspector noted that the conference room, used for pre-job SWP briefings, was equipped with a CCTV view of the work area and a videocassette re-corde The package for SWP 87-2406 was reviewed and contained the following:

The SWP, pre-job briefing attendance records, job / area acceptance inspection report (initial), surveys records, summary of special TLD, ALARA review (containing fifteen pages of detailed ALARA requirements),

and an ALARA Job Inspection Report. This SWP package appeared ex-ceptionally thorough and well don The licensee's actual 1986 person-rems for the site and Unit-1 outage were less than the goals. In addition, the licensee ste:ed that a third 1986 goal of less than two rem (plant dose) for each individual was also met. Person-rem goals for 1987 nave been set and are lower than those for 198 To have less than two rem (plant dose) for each individual is also a 1987 goal. Based on these numbers and on the ALARA inspection find-

, ings, this area is presently a licensee strong poin PERSON-REM Site Outage 1986 Goal 390 280 Actual 347 9245 1987 Goal 330 235 Within the scope of this review, no violations were identifie '

._ _ _ . _ _ . _ _ . _ . _ _ - . ~ . _ . _ . ._.-_ _ __ _ _ . _ _ _ . _ _ _ .

.

.

.

7.0 Exit Interview The inspector met with the personnel denoted in Section 1.0 at the con-clusion of the inspection on March 27, 1987. The scope and findings of the inspection were discussed at that time.