October 4, 2018
SUBJECT:
CALVERT CLIFFS NUCLEAR POWER PLANT - NRC BASELINE SECURITY INSPECTION REPORT 05000317/2018410, 05000318/2018410, AND INDEPENDENT SPENT FUEL STORAGE SECURITY INSPECTION REPORT 07200008/2018401
Dear Mr. Hanson:
On September 13, 2018, the U.S. Nuclear Regulatory Commission (NRC) completed a security inspection at the Calvert Cliffs Nuclear Power Plant. The NRC inspectors discussed the results of this inspection with Mr. Mark Flaherty, Site Vice President, and other members of your staff.
Inspectors documented the results of this inspection in the enclosed inspection report.
NRC inspectors documented one finding of very low security significance (Green) in this report.
This finding involved a violation of NRC requirements. The NRC is treating this violation as non-cited violation (NCV) consistent with Section 2.3.2.a of the Enforcement Policy.
One cross-cutting aspect was assigned to a finding in the area of Human Performance.
Specifically, Exelon failed to recognize and plan for the possibility of mistakes, latent issues, and inherent risk [H.12].
If you contest this violation or the significance, you should provide a response within 30 days of the date of this inspection report, with the basis for your denial, to the U.S. Nuclear Regulatory Commission, ATTN: Document Control Desk, Washington DC 20555-0001; with copies to the Regional Administrator, Region I; the Director, Office of Enforcement; the Director, Office of Nuclear Security and Incident Response; and the NRC resident inspector at the Calvert Cliffs Nuclear Power Plant.
If you disagree with the cross-cutting aspect assignment in this report, you should provide a response within 30 days of the date of this inspection report, with the basis for your disagreement, to the U.S. Nuclear Regulatory Commission, ATTN: Document Control Desk, Washington DC 20555-0001; with copies to the Regional Administrator, Region I; and the NRC resident inspector at the Calvert Cliffs Nuclear Power Plant.
Enclosure contains Sensitive Unclassified, Non-Safeguards Information. When separated from Enclosure, the transmittal document is decontrolled. This letter will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRCs Public Document Room in accordance with Title 10 of the Code of Federal Regulations (10 CFR) 2.390, Public Inspections, Exemptions, Requests for Withholding.
However, the enclosed report contains Security-Related Information; it will not be made publically available in accordance with 10 CFR 2.390(d)(1). If you choose to provide a response that contains Security-Related Information, please mark your entire response Security-Related Information-Withhold from public disclosure under 10 CFR 2.390, in accordance with 10 CFR 2.390(d)(1) and follow the instructions for withholding in 10 CFR 2.390(b)(1). The NRC is waiving the affidavit requirements for your response in accordance with 10 CFR 2.390(b)(1)(ii).
Sincerely,
/RA/
Raymond R. McKinley, Chief Plant Support Branch Division of Reactor Safety
Docket Nos.
50-317, 50-318, and 72-08 License Nos. DPR-53, DPR-69, and SNM-2505
Enclosure:
Inspection Report 05000317/2018410, 05000318/2018410, and 07200008/2018401
cc w/o encl; w/o OUO-SRI: Distribution via ListServ
cc w/encl; w/OUO-SRI:
T. Young, Manager, Site Security M. Griffen, State Liaison Officer, Emergency Preparedness Planning
ML18277A261 (Cover letter)
ADAMS ACCESSION NUMBER: ML18277A265 (Cover letter w/OUO-SRI)
Cover Letter:
SUNSI Review Non-Sensitive Sensitive
Publicly Available Non-Publicly Available Cover Letter w/rpt.
SUNSI Review Non-Sensitive Sensitive
Publicly Available Non-Publicly Available OFFICE RI/DRS RI/DRS RI/DRS RI/DRP RI/DNMS RI/DRS NAME SMcCarver JBream JRey DCaron CCahill RMcKinley DATE 09/24/18 09/24/2018 09/24/2018 09/24/2018 09/24/2018 10/4/2018