August 6, 1997

SUBJECT:

NRC RESTART ACTION PLAN - REVISION 4

Dear Mr. Eliason:

Enclosed is the Revision 4 to NRC's Restart Action Plan (RAP) for Salem Units 1 and 2.

The RAP was originally published on February 23, 1996 to describe NRC's planned monitoring activities for restart of the Salem units. Revision 1, 2, and. 3 of NRC's RAP were sent to you on August 3, 1996, December 26, 1996, and June 4, 1 997, respectively. The enclosed revision was reviewed and approved by the Salem Assessment Panel (SAP) in SAP meetings 97-07 & 97-08 and includes the following:

A continuation of the line-by-line review of all restart items which originally began in SAP meeting 96-11, dated December 6, 1996. This included special focus on open restart issues and other issues that had the potential to impact on Salem Unit 2 restart. Although additional corrective actions may be necessary, the SAP is satisfied that adequate performance improvement has been achieved to support restart of Salem Unit 2.

  • A technical item was added to address a Containment Fan Cooler Modification (CFCU) that was installed to prevent water hammer. Your actions on this matter have been reviewed and found acceptable. See item 11.45.
  • The entire RAP was reviewed and updated, where appropriate. You should also note that a number of items remain open for Salem Unit 1 restart and will have to*

be addressed in the future. If no unit designator is provided, the SAP considers the matter closed for both units.

The status of the restart items reflects inspections up to and including 50-311 /97-12.

If you have any questions or comments on our restart plan, please contact Mr. G. S. Barber (610-337-5232).

9708180215 970806 PDR ADOCK 05000272 P

PDR

Sincerely, Original Signed By:

James C. Linville, Chief Projects Branch 3 Division of Reactor Projects 1111111111111111111111111111111111111111

  • &B5F19 111

Enclosure:

NRC Restart Action Plan Docket Nos. 50-272; 50-311 cc w/encl:

L. Storz, Senior Vice President - Nuclear Operations E. Simpson, Senior Vice President - Nuclear Engineering E. Salowitz, Director - Nuclear Business Support A. F. Kirby, Ill, External Operations - Nuclear, Delmarva Power & Light Co.

D. Garchow, General Manager - Salem Operations J. McMahon, Director - Quality Assurance & Nuclear Safety Review D. Powell, Manager, Licensing and Regulation R. Kankus, Joint Owner Affairs A. Tapert, Program Administrator J. J. Keenan, Esquire M. Wetterhahn, Esquire J. A. Isabella, Manager, Joint Generation Atlantic Electric Consumer Advocate, Office of Consumer Advocate William Conklin, Public Safety Consultant, Lower Alloways Creek Township Public Service Commission of Maryland State of New Jersey State of Delaware