IR 05000311/1997007

From kanterella
Jump to navigation Jump to search
Forwards Rev 3 to NRC Restart Action Plan for Plant,Units 1 & 2.Status of Restart Items Reflects Insp Up to & Including 50-311/97-07 & Includes Insp Rept 50-311/97-11
ML18102B377
Person / Time
Site: Salem  
Issue date: 06/04/1997
From: Linville J
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I)
To: Eliason L
Public Service Enterprise Group
References
50-311-97-07, 50-311-97-11, 50-311-97-7, NUDOCS 9706100277
Download: ML18102B377 (26)


Text

June 4, 1997

SUBJECT:

NRC RESTART ACTION PLAN - REVISION 3

Dear Mr. Eliason:

Enclosed is the Revision 3 to NRC's Restart Action Plan (RAP) for Salem Units 1 and 2.

The RAP was originally published on February 23, 1996 to describe NRC's planned monitoring activities for restart of the Salem units. Revision 1 and Revision 2 of NRC's RAP were sent to you on August 3, and December 26, 1996, respectively. The enclosed revision was approved by the Salem Assessment Panel (SAP) in SAP meeting 97-07 and includes the following:

A technical item was added to address NRC concerns with the adequacy of of ECCS Swapover methodology, available Residual Heat Removal Pump Net Position Suction Head, and Technical Specification changes for hot leg injection valve 2RH26.

  • The entire RAP was reviewed and updated, where appropriate.

. The status of the restart items reflects inspections up to and including 50-311197-07. It also includes inspection report 50-311197-11.

If you have any questions or comments on our restart plan, please contact Mr. G. S. Barber (610-337-5232).

Enclosure:

NRC Restart Action Plan Docket Nos. 50-272; 50-311

  • --

9706100277 970604 PDR ADOCK 05000272 P

PDR l"\\. *., -

10 ni1 *.,)

) v

~*._.

ORIGINAL SIGNED BY:

James C. Linville, Chief Projects Branch 3 Division of Reactor Projects

.

,