|
---|
Category:Inspection Report Correspondence
MONTHYEARML18158A4792018-05-17017 May 2018 Independent Spent Fuel Storage Installation Security Inspection Report 07201035/2018401 (Cover Letter Only) ML1112501592011-05-0505 May 2011 Notice of Inspection and Request for Information 05000302/2011003 IR 05000302/20104032010-07-29029 July 2010 IR 05000302-10-403 on 07/13/2010 for Crystal River - NRC Material Control and Accounting IR 05000302/20094032009-08-0404 August 2009 Nuclear Generating Plant - NRC Security Inspection Report 05000302/2009403 IR 05000302/20074012007-04-27027 April 2007 NRC Physical Security Baseline Inspection Report 05000302/2007401 - Safeguards Information Removed IR 05000302/20070012007-03-0101 March 2007 Annual Assessment Letter - Crystal River Unit 3 (NRC Inspection Report 05000302/2007001) IR 05000302/20060102006-06-0202 June 2006 IR 05000302-06-010; 04/24-28/2006; Crystal River Unit 3; Emergency Preparedness ML0400902182003-12-22022 December 2003 Undated, Inspector Post-Inspection Debrief to Region II DRS Managers Briefing Summary of Crystal River Triennial Fire Protection Baseline Inspection on 06/24-28 and 07/08-12/2002 ML0304403332003-02-10010 February 2003 IR 05000302-03-002, Notification of Crystal River - Safety System Design & Performance Capability Inspection on 05/05-19/2003 ML0223907192002-08-23023 August 2002 IR 05000302-02-005, on 06/24/2002 - 07/12/2002, Crystal River Unit 3, Triennial Baseline Inspection of Fire Protection Program. No Violations Noted IR 05000302/20010042002-01-28028 January 2002 IR 05000302/2001-004, on 09/30/2001 - 12/29/2001, Florida Power Corporation, Crystal River Unit 3, Event Followup and Refueling Outage 2018-05-17
[Table view] Category:Letter
MONTHYEARIR 05000302/20240012024-09-23023 September 2024 Accelerated Decommissioning Partners (ADP) CR3, LLC, Crystal River Unit 3, NRC Inspection Report No. 05000302/2024001 ML24240A1692024-09-18018 September 2024 Cy 2023 Summary of Decommissioning Trust Fund Status ML24226B2392024-08-27027 August 2024 Application for License Amendment Request to Add License Condition to Include License Termination Plan Requirements – Acknowledgement of Withdrawal ML24179A0702024-07-26026 July 2024 SHPO S106 Completion Crystal River Unit 3 ML24205A2192024-07-24024 July 2024 Tribal S106 Completion Crystal River Unit 3: Muscogee Nation ML24205A2182024-07-24024 July 2024 Tribal S106 Completion Crystal River Unit 3: Seminole Nation of Oklahoma ML24179A0912024-07-24024 July 2024 Tribal S106 Completion Crystal River Unit 3: Seminole Tribe of Florida ML24205A2202024-07-24024 July 2024 Tribal S106 Completion Crystal River Unit 3_Miccosukee Tribe of Florida ML24190A1912024-07-0808 July 2024 Fws Concurrence for Crystal River Unit 3 ML24172A2552024-06-20020 June 2024 Fws to NRC Species List: Florida Ecological Services Field Office 06/20/2024 ML24170A9242024-06-18018 June 2024 024-0023697 Crystal River License Termination Plan Unit 3 ML24151A6482024-06-0303 June 2024 Changes in Reactor Decommissioning Branch Project Management Assignments for Some Decommissioning Facilities ML24114A2262024-04-24024 April 2024 Amended Special Package Authorization for the Cr3 Middle Package (Crystal River 3 Middle Package - Docket No. 71-9393) IR 05000302/20230022024-04-17017 April 2024 Accelerated Decommissioning Partners (ADP) CR3, LLC, Crystal River Unit 3 - NRC Inspection Report No. 05000302/2023002 ML24054A0612024-04-0202 April 2024 Request to Initiate Section 106 Consultation Regarding the License Termination Plan for Crystal River Unit 3 in Citrus County, Florida ML24079A2492024-04-0202 April 2024 Tribal S106 Initiation Crystal River Unit 3-Johnson, Lewis Johnson ML24054A0582024-04-0202 April 2024 Achp S106 Initiation Crystal River Unit 3 - Letter 1 ML24079A2472024-04-0202 April 2024 Tribal S106 Initiation Crystal River Unit 3-Cypress, Talbert ML24079A2482024-04-0202 April 2024 Tribal S106 Initiation Crystal River Unit 3-Hill, David Hill ML24054A0812024-04-0202 April 2024 Tribal S106 Initiation Crystal River Unit 3-Osceola, Marcellus ML24089A0362024-03-29029 March 2024 Response to Audit Plan in Support of Accelerated Decommissioning Partners and Request to Add License Condition to Include License Termination Plan Requirements. W/Enclosures 1 to 5 ML24073A1922024-03-11011 March 2024 Fws to NRC, List of Threatened and Endangered Species That May Occur in Your Proposed Project Location or May Be Affected by Your Proposed Project ML24054A6452024-02-29029 February 2024 Letter - Reply to Request for RAI Extension Related to the Crystal River License Termination Plan ML24030A7482024-02-12012 February 2024 Audit Report Cover Letter and Report - Crystal River Unit 3 Nuclear Generating Plant LTP ML23342A0942024-01-0909 January 2024 – Independent Spent Fuel Storage Installation Security Inspection Plan ML23354A0632023-12-22022 December 2023 Cover Letter - Crystal River License Termination Plan Request for Additional Information ML23345A1882023-12-0606 December 2023 Fws to NRC Crystal River Species List of Threatened and Endangered Species That May Occur in Your Proposed Project Location or May Be Affected by Your Proposed Project ML23320A2592023-11-17017 November 2023 STC-23 077 Notification of the Crystal River Unit 3 Generating Plant License Termination Plan Public Meeting and Federal Register Notice ML23313A1322023-11-15015 November 2023 Request for Additional Information for the Environmental Assessment of the License Termination Plan for Crystal River Unit 3 Nuclear Generating Plant ML23310A0712023-11-0707 November 2023 Audit Plan Cover Letter - Crystal River Unit 3 Nuclear Generating Plant LTP ML23187A1112023-07-25025 July 2023 Acceptance of Requested Licensing Action License Request to Add License Condition to Include License Termination Plan Requirements ML23107A2722023-06-13013 June 2023 Letter Transmitting NRC Survey Results for East Settling Pond ML23160A2962023-06-0909 June 2023 Response to Crystal River, Unit 3 – Supplemental Information Needed for Acceptance on the Application for a License Amendment Regarding Approval of the License Termination Plan ML23107A2732023-06-0707 June 2023 Orise Independent Survey Report Dcn 5366-SR-01-0 IR 05000302/20220032023-05-25025 May 2023 Accelerated Decommissioning Partners (ADP) CR3, LLC, Crystal River Unit 3 - NRC Inspection Report No. 05000302/2022003 ML23103A1902023-04-19019 April 2023 Request for Supplemental Information Cover Letter ML23058A2532023-03-22022 March 2023 Accelerated Decommissioning Partners (ADP) CR3, LLC, Crystal River, Unit 3 - NRC Inspection Report No. 05000302/2022003 ML22361A1022023-02-24024 February 2023 Reactor Decommissioning Branch Project Management Changes for Some Decommissioning Facilities and Establishment of Backup Project Manager for All Decommissioning Facilities ML22265A0192022-09-26026 September 2022 Nuclear Generating Plant - U.S. Nuclear Regulatory Commissions Analysis of ADP CR3, LLCs Decommissioning Funding Status Report (License No. DPR-72, Docket Nos. 50-302 and 72-1035) IR 05000302/20220022022-08-0909 August 2022 Accelerated Decommissioning Partners (ADP) CR3, LLC, Crystal River Unit 3 - NRC Inspection Report 05000302/2022002 IR 05000302/20220012022-05-0303 May 2022 Accelerated Decommissioning Partners (ADP) CR3, LLC, Crystal River Unit 3 - NRC Inspection Report 05000302/2022001 ML22116A1752022-04-27027 April 2022 Accelerated Decommissioning Partners (ADP) CR3, LLC, Crystal River Unit 3- Independent Spent Fuel Storage Installation Security Inspection Report 07201035/2022401 ML22105A3992022-04-18018 April 2022 Nuclear Generating Plant - Change in NRC Project Manager ML22011A1362022-01-31031 January 2022 Independent Spent Fuel Storage Installation Security Inspection Plan ML22024A2142022-01-24024 January 2022 Nuclear Generating Plant - NMFS NRC Letter - Crystal River Energy Complex Biological Opinion Status (License No. DPR-72, Docket Nos. 50-302 and 72-1035) IR 05000302/20210042022-01-24024 January 2022 Accelerated Decommissioning Partners (ADP) CR3, LLC, Crystal River Unit 3 - NRC Inspection Report No. 05000302/2021004 ML21351A0052021-12-20020 December 2021 NRC Analysis of ADP CR3, LLC Decommissioning Funding Status Report for the Crystal River Unit 3 Nuclear Generating Plant (License No. DPR-72, Docket Nos. 50-302 and 72-1035) ML21322A2702021-11-24024 November 2021 Nuclear Generating Plant - Issuance of Amendment No. 260 Approving the Independent Spent Fuel Storage Installation Only Security Plan, Rev 3 IR 05000302/20210032021-11-0909 November 2021 Accelerated Decommissioning Partners (ADP) CR3, LLC, Crystal River Unit 3 - NRC Inspection Report Nos. 05000302/2021003 and 07201035/2021001 ML21288A4292021-10-18018 October 2021 Letter - Crystal River Unit 3 Nuclear Generating Plant - Correction to Safety Evaluation Related to the Issuance of Amendment No. 259 Approving the Independent Spent Fuel Storage Installation Only Emergency Plan 2024-09-23
[Table view] |
Text
ril 27, 2007
SUBJECT:
CRYSTAL RIVER NUCLEAR PLANT - NRC PHYSICAL SECURITY BASELINE INSPECTION REPORT 05000302/2007401
Dear Mr. Young:
On March 30, 2007, the U. S. Nuclear Regulatory Commission (NRC) completed a security baseline inspection at your Crystal River Nuclear Plant. The inspection covered one or more of the key attributes of the security cornerstone of the NRCs Reactor Oversight Process. The enclosed report documents the inspection results, which were discussed with you and other members of your staff on March 30, 2007. A re-exit was conducted on April 18, 2007, with Mr. M. Widner and other staff personnel.
This inspection examined activities conducted under your license as they relate to security and compliance with the Commissions rules and regulations and with the conditions of your license.
The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel.
This report documents one licensee-identified finding of very low security significance (i.e.,
Green as determined by the Physical Protection Significance Determination Process). The deficiency was promptly corrected or compensated for, and the plant was in compliance with applicable physical protection and security requirements within the scope of this inspection before the inspectors left the site. The finding was licensee identified. The NRC is treating this violation as a non-cited violation consistent with Section VI.A.1 of the NRCs Enforcement Policy because of the very low safety significance of the violation and because it is entered into your corrective action program. If you contest this non-cited violation, you should provide a response within 30 days of the date of this inspection report, with the basis for your denial, to DOCUMENT CONTAINS ENCLOSURE CONTAINS UPON SEPARATION THIS PAGE IS DECONTROLLED
Progress Energy 2 DOCUMENT CONTAINS the U.S. Nuclear Regulatory Commission, ATTN.: Document Control Desk, Washington, D. C.
20555-0001, with copies to the Regional Administrator, Region II; the Director, Office of Enforcement, United States Nuclear Regulatory Commission, Washington, D. C. 20555-0001; and the NRC Resident Inspector at the Crystal River Nuclear Plant.
In accordance with 10 CFR 2.390 of the NRCs Rules of Practice, a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRCs document system, ADAMS. ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room). However, because of the security-related concerns contained in the enclosure, and in accordance with 10 CFR 2.390 a copy of this letters enclosure will not be available for public inspection.
In accordance with 10 CFR 2.390(b)(1)(ii), the NRC is waiving the affidavit requirements for your response, if any. This practice will ensure that your response will not be made available electronically for public inspection in the NRC Public Document Room or from the NRCs document system, ADAMS. If Safeguards Information is necessary to provide an acceptable response, please provide the level of protection described in 10 CFR 73.21. Otherwise, mark your entire response Security Related Information-Withhold Under 10 CFR 2.390" and follow the instructions for withholding in 10 CFR 2.390 (b)(1).
Sincerely,
/RA/
Joel T. Munday, Chief Plant Support Branch 2 Division of Reactor Safety Docket No.: 50-302 License No.: DPR-72 Enclosure: NRC Inspection Report No. 05000302/2007401 w/Attachment: Supplemental Information cc w/encl:
Daniel L. Roderick Director Site Operations Crystal River Nuclear Plant (NA2C)
15760 West Power Line Street Crystal River, FL 34428-6708 (cc w/encl contd - See page 3)
DOCUMENT CONTAINS ENCLOSURE CONTAINS UPON SEPARATION THIS PAGE IS DECONTROLLED
Progress Energy 3 DOCUMENT CONTAINS (cc w/encl contd)
Jon A. Franke Plant General Manager Crystal River Nuclear Plant (NA2C)
15760 West Power Line Street Crystal River, FL 34428-6708 Terry D. Hobbs Manager Nuclear Assessment Crystal River Nuclear Plant (NA2C)
15760 West Power Line Street Crystal River, FL 34428-6708 Michael J. Annacone Engineering Manager Crystal River Nuclear Plant (NA2C)
15760 West Power Line Street Crystal River, FL 34428-6708 R. Alexander Glenn Associate General Counsel (MAC - BT15A)
Florida Power Corporation P. O. Box 14042 St. Petersburg, FL 33733-4042 Steven R. Carr Associate General Counsel - Legal Dept.
Progress Energy Service Company, LLC P. O. Box 1551 Raleigh, NC 27602-1551 cc w/o encl:
Attorney General Department of Legal Affairs The Capitol Tallahassee, FL 32304 (cc w/o encl contd - See page 4)
DOCUMENT CONTAINS ENCLOSURE CONTAINS UPON SEPARATION THIS PAGE IS DECONTROLLED
Progress Energy 4 DOCUMENT CONTAINS (cc w/o encl contd)
William A. Passetti Bureau of Radiation Control Department of Health 2020 Capital Circle, SE, Bin #C21 Tallahassee, FL 32399-1741 Craig Fugate, Director Division of Emergency Preparedness Department of Community Affairs 2740 Centerview Drive Tallahassee, FL 32399-2100 Chairman Board of County Commissioners Citrus County 110 N. Apopka Avenue Inverness, FL 36250 Jim Mallay Framatome ANP 1911 North Ft. Myer Drive, Suite 705 Rosslyn, VA 22209 Distribution w/encl:
D. Riffle, NSIR Distribution w/o encl:
B. Mozafari, NRR RIDSNRRDIRS PUBLIC DOCUMENT CONTAINS ENCLOSURE CONTAINS UPON SEPARATION THIS PAGE IS DECONTROLLED
_________________________
OFFICE RII:DRS RII:DRS SIGNATURE RA RA RA RA NAME KDAVIS IHALL JSHEHEE JMUNDAY MERNSTES DATE 4/24/07 4/27/07 4/27/07 4/ /07 4/24/07 E-MAIL YES NO YES NO YES NO YES NO YES NO PUBLIC YES w/o SGI YES w/o SGI YES w/o SGI YES w/o SGI YES w/o SGI